Table of Contents
TABLE OF CONTENTS ................................................................................................................. 2
7.0 APPROVAL...................................................................................................................... 13
ANNEXURE-A.1 .................................................................................................................................... 32
ANNEXURE-A.2 .................................................................................................................................... 34
ANNEXURE-A.3 .................................................................................................................................... 35
ANNEXURE-A.4 .................................................................................................................................... 36
ANNEXURE-A.5 .................................................................................................................................... 37
Page | 2
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Definitions”
1.0 DEFINITIONS.
For the purpose of this document, the expressions mentioned hereunder shall have the
meaning specified against them unless there is anything repugnant in the subject or context:
(b) „Tender‟ Shall mean the tender submitted by the tenderer for
acceptance by the Owner.
(g) „Managing Director‟ Shall mean the Managing Director (MD) of HPGCL,
or his successors in office as designated by the
Owner.
(e) „Contract‟ Shall mean the agreement between the Owner and
the Consultant for execution of the contract
including therein all documents such as the
invitation to Tender, instructions to tenderer,
Special Conditions of Contract, Scope of Work,
agreed Variations if any etc.
Page | 3
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Definitions”
(l) „Appointing Authority‟ Shall be the Managing Director or any other person
so designated by him for the purpose of arbitration.
(o) Total Value of Contract‟ Shall mean the total consultancy price including all
applicable taxes in accordance with the prices
accepted in tender as payable to the consultant for
providing the consulting services
Page | 4
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Definitions”
(s) „Functional experts‟ or Shall mean persons with at least 5 years experience
„Infrastructure expert‟ in respective functional areas, having worked in
ERP Program management engagement of similar
type. Infrastructure expert should have at least five
years of experience in hardware, networking and
related areas.
(t) „Energy (Power Generation) Shall mean persons with at least 10 years experience
Domain expert‟ in power Generation sector (Govt/PSU)
In the event of any doubts arising with respect to the provisions of the rules and inadequacy
in the scope of its coverage, the final authority of interpretation shall vest with the MD whose
decision shall be final.
Page | 5
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Introduction”
2.0 INTRODUCTION
2.1 Haryana Power Generation Corporation Ltd. came into existence on 14.08.98 after
the restructuring of Haryana State Electricity Board into Haryana Power Generation Corporation
Ltd. (HPGCL), Haryana Vidyut Prasaran Nigam Ltd. (HVPNL), Uttar Haryana Bijli Vidyut Nigam
Ltd.(HPGCLL) & Dakshin Haryana Bijli Vidyut Nigam Ltd. (DHBVNL) under the Reform
Programme.
The main objectives of HPGCL are as under: -
To generate power from its existing Generating Stations in the most efficient manner on
commercial lines and to sell the same to distribution companies.
To set up new Power Generation Projects.
2.2 HPGCL owns & operates the following power plants in the state:
Sr.No Name of Power Station Unit Details Total Capacity
(MW)
i. Panipat Thermal Power Station, 1x117.8MW+3x110MW+ 1367.8 MW
Panipat. 2x210MW+2x250MW
ii. Deen Bandhu Chhotu Ram 600 MW
Thermal Power Project, Yamuna 2x300 MW
Nagar.
iii. Rajiv Gandhi Thermal Power 1200 MW
2x600 MW
Project, Khedar, Hisar
iv. WYC Hydro Electric Station, 62.4 MW
6x8MW+2x7.2MW
Yamuna Nagar
2.3 Apart from the above power projects following new projects are planned to be set-up in
12th/13th five Year Plan:
a) 1x660 MW Thermal Unit based on Super Critical Technology at Yamunanagar.
b) 1500 MW Gas based Project planned at Faridabad.
c) Development of Coal block at Mara-II-Mahan in MP with estimated coal reserves of
956 Million Tonnes allocated jointly to HPGCL and Delhi Govt.
d) Capacity expansion planned at PTPS Panipat.
2.5 An Application i.e Computerized Integrated Plant Management System (CIPMS) has
already implemented at PTPS, Panipat consist of modules i.e OPMS (Operation & Performance
Monitoring System) , MMS (Maintenance Management System) & Financial Accounting System.
Under CIPMS Finance & Accounting Systems (FAS) at corporate office Panchkula, RGTPP Hisar,
DCRTPP Yamunanagar & WYC Hydel has also been implemented however; none of the FAS
module at above said locations is integrated with each other.
Page | 6
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Objective for ERP Implementation in HPGCL”
Page | 7
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Scope of Work for the Consultant”
HPGCL would like to improve its organizational efficiency and effectiveness through
adoption of ERP and introduction of best practice business processes. To attain this goal,
HPGCL wants the Consultant to provide an implementation roadmap for ERP, through
the following:
Page | 8
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Scope of Work for the Consultant”
security practices.
5.1.7 Study of organization readiness at all levels of the organization to adopt
ERP.
5.1.8 Study of Real-Time operational Data capture in DCS, non-DCS & ABT
systems and recommend procedure to integrate them with ERP system.
5.2 Assessment of Existing IT infrastructure.
5.2.1 Study of existing IT infrastructure (including communication network) and
applications used by HPGCL across various locations.
5.2.2 Study of IT infrastructure and application management practices including
IT security measures deployed.
5.2.3 Study of user familiarity, expertise and satisfaction in using such
infrastructure and applications.
5.2.4 Study of existing IT infrastructure (including communication network
applications) used by HPGCL across various locations.
5.3 Preparation of Roadmap Blueprint & Detailed Project Report (DPR)
for ERP Implementation.
The activity and subsequent service delivery will consist of:
5.3.1 To-be Design:
Based on the detailed assessment conducted, the consultant should develop the
ERP Implementation roadmap, with the following objectives:
5.3.1.1 Meeting HPGCL's business specific requirements.
5.3.1.2 Meeting HPGCL's requirement to establish best-of-breed processes
through implementation of ERP.
5.3.1.3 Implementing leading standards in technology design and Power Sector
domain best-practices, addressing the need for scalability and flexibility
without undermining the data integrity and transparency required for
enabling the processes
Page | 9
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Scope of Work for the Consultant”
5.3.3.1 The Consultant will discuss and finalize the IT infrastructure (hardware,
software, network, facility) required for implementation of the ERP,
based on the implementation option selected by HPGCL and finalize the
IT architecture for ERP implementation in HPGCL.
5.3.3.2 The Consultant shall adopt the latest technology standards and practices
while developing the IT infrastructure. The Consultant shall undertake
due care and caution to ensure that the IT architecture and its
constituents are scalable to take care of future IT requirements of
HPGCL.
5.3.3.3 The Consultant shall evaluate the reusability of the existing IT hardware
infrastructure so as to optimize the procurement cost.
5.3.3.4 The Consultant shall advise on the retirement and integration
requirements of some of the legacy and existing applications, if required,
for successful implementation of ERP.
Page | 10
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Scope of Work for the Consultant”
5.3.3.5 The Consultant shall also suggest the measures to ensure business
continuity considering single-point-of-failures and disaster recovery
scenarios.
5.3.4 Preparation of Budget:
5.3.4.1 Keeping in view the IT infrastructure, IT architecture & other necessary
requirements for the implementation of ERP, the Consultant shall
prepare a detailed budget, highlighting the capital expenditure,
operational expenditure requirements & other miscellaneous
expenditure requirements.
5.3.4.2 The Consultant shall assist HPGCL in the preparation of such explanation
notes, as may be required, for justification of the proposed budget, for
obtaining administrative approval from authorities.
5.4 Selection of Vendor:
5.4.1 Based on the requirement of goods and services for ERP implementation
in HPGCL, the Consultant shall assist HPGCL in the preparation of a
Request for Proposal (RFP) document for the selection of a qualified
vendor(s) for the procurement of Services, Product & Infrastructure
required for implementation and management of the ERP solution. The
broad scope of work for this component shall be as follows:
5.4.1.1 Preparation of bid documents.
5.4.1.2 Assistance in bid process management including evaluation of
technical and financial proposals, assistance in discussions with
bidders, preparation of corrigendum‟s, preparation of final
evaluation report and assistance in contract finalization with
vendor(s) etc.
5.5 Program Management of ERP Implementation:
5.5.1 The Consultant shall assist HPGCL in Program Management of the ERP
solution implementation which will be for the duration of the Pilot go-live
as well as for the roll-out to all project locations. The Consultant shall
act as the liaison between the chosen vendor(s) and an internal ERP team
of HPGCL and facilitate quick resolution of any design and process issues
related to solution configuration, testing & other implementation related
tasks, that may come up during the implementation and rollout.
5.5.2 The Consultant shall also help with all UATs (User Acceptance Tests)
Page | 11
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Scope of Work for the Consultant”
Page | 12
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Deliverables of the Consultant & Approval”
Page | 13
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Location of Project”
Page | 14
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Service Delivery Timeline”
9.2 The consultant shall be provided with 15 days mobilization period from the date of
signing of contract with the consultant.
9.3 The consultant shall make presentation to Management regarding ERP Program
management plan during the Kick-off meeting which shall be held within 7
working days on or after the expiry of mobilization period, as per the date mutually
decided.
Page | 15
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Eligibility Criteria”
10.1 Consultancy firms should have minimum average annual consultancy Turnover
of INR 50 Crores, calculated as total certified consultancy payments received for
contracts in progress or completed, in the last three financial years.
10.2 Consultancy firms should have Positive Net Worth in the last three financial years.
10.3 Consultant, before deadline for submission of bids:
10.3.1 Should have successfully completed at least one ERP consultancy
engagement in large organization in which total consultancy fees
received by the consultant shall not be less than INR 1 crore, and;
10.3.2 Should have at least One ERP engagement during last six years,
completed or ongoing in State/Central Power Utility Company in India.
10.4 ERP OEM product vendors are not qualified to participate in this bid.
10.5 Consultancy firm that will be successful in this bid shall not be eligible to
participate in the ERP implementation bid.
10.6 Consultancy firms are not allowed to form consortium, JVs, partnerships or sub-
contracting arrangements at any stage of bid or subsequent consultancy
assignment.
Page | 16
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Evaluation Criteria”
Page | 17
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Evaluation Criteria”
Description %age
Successfully completed One ERP consulting assignment covering 75%
process study / BPR of Generation utility
Successfully completed Two ERP consulting assignments 90%
covering process study / BPR of Generation utility
Successfully completed Three ERP consulting assignments 100%
covering process study / BPR of Generation utility
Page | 18
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Evaluation Criteria”
HPGCL will determine if the financial proposals are complete and without
computational errors. Among the Financial offers (Total Consultancy fee as
mentioned in Annexure-A.4), the lowest bid “Bmin” will be given a financial score
“F” of 100 marks. The financial scores of all the bids will be computed as follows.
The bids will finally be ranked according to their combined technical (T) and
financial (F) scores using a weight of 25% for technical bids and 75% for price bids.
Overall Ranking (R) shall be calculated as under:
The bidders securing the highest ranking (R) shall be the first successful
bidder and so on. If bidders obtain same combined score, the contract shall be
awarded to the bidder whose technical score is highest.
Page | 19
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Terms of Payment & Facilities”
12.2 In case Go-Live at Last site will be achieved earlier than 20 months from the kick
off meeting date with ERP Vendor(s), the balance payment of Monthly Progress
Report will be made to consultant on submission of that month‟s progress report.
12.3 The Deliverable based Payment towards deliverables as mentioned above shall be
made only after its submission & acceptance of HPGCL.
Page | 20
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Terms of Payment & Facilities”
12.4 HPGCL reserves the right to stop payment towards deliverable if found
sub-standard or undervalued review.
12.5 Payment will be made against certified Bills for milestone payments as mentioned
above consultant will have to submit their Bills in triplicate to the Controlling
Officer which will be certified for release of payment.
12.6 If income tax or other taxes are deductible from the consideration payable to the
Consultants, HPGCL shall be entitled to deduct such taxes & pay the net amount.
13.0 Facilities:
At sites consultant will be provided with chargeable accommodation at our Guest House
subject to availability. Consultants shall be provided adequate office space for its team
members with table and chairs and required electric connections. Consultant shall be
required to arrange their own desktops/laptops.
Page | 21
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Instructions to Bidders”
Page | 22
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Instructions to Bidders”
Page | 23
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Instructions to Bidders”
14.4.2 Technical Bid must provide the information, using, but not limited to, the
formats attached as annexure in bid.
14.4.3 Bidder's understanding of the processes and the proposed solution is also
an elaboration of how the required tasks are proposed to be undertaken.
14.4.4 TECHNICAL BID MUST NOT INCLUDE ANY FINANCIAL
INFORMATION. IF FOUND SO THE BIDDER WILL BE
DISQUALIFIED.
14.5 Financial Bid.
14.5.1 The financial Bid must take into account the tax liability & cost of
insurances if any and any other statutory payouts as per the standard
guidelines.
14.5.2 The Bids should be submitted with a covering letter as per Annexure A.4.
14.6 Pre-Bid Discussion.
14.6.1 All questions regarding the NIT will be discussed in the Pre Bid Meeting.
14.6.2 The Pre Bid Discussion meeting will be held on 21.01.2013 at 11:00 hrs,
at Urja Bhawan, Panchkula. The points raised by the Bidders and any
other points required to be discussed further as desired by HPGCL shall
be clarified / modified in the Meeting.
14.6.3 Outcome of the meeting will be a part of the tender which has to be
followed by all bidders irrespective of their participation in the pre bid
discussion. The changes made, in the pre bid discussion, if any, will be
displayed on HPGCL's website www.hpgcl.gov.in.
14.7 Bid Opening.
14.7.1 Technical Bids will be opened on 28.01.2013 at 15.30 Hrs. Bidders are
requested to be present during Technical Bid opening.
14.7.2 On the basis of Technical evaluation, eligible Bids will be finalized.
Financial Bids for all eligible Technical Bids will be opened on a suitable
date, likely within 15 days of submission of Bids.
14.7.3 The Date of opening of the financial bid will be intimated to eligible
bidders and they are request to be present at the time of opening of
Financial Bid
14.8 Bid Evaluation & Selection.
14.8.1 Evaluation of the Technical Bids will be done by HPGCL on the basis of
Technical Evaluation criteria.
Page | 24
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Instructions to Bidders”
Page | 25
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Other Terms & Conditions of Contract”
Page | 26
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Other Terms & Conditions of Contract”
Page | 27
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Other Terms & Conditions of Contract”
15.11 Arbitration: -
15.11.1 All matters, questions, disputes, differences and/or claims arising out of
and/or concerning, and/or in connection with, and/or in consequence of,
and/or relating to any contract under these Regulations, whether or not
obligations of either or both the Supplier and the Corporation under that
contract be subsisting at the time of such dispute and whether or not the
contract has been terminated or purported to be terminated or
completed, shall be referred to the sole arbitration of Appointing
Authority. The award of the Arbitrator shall be final and binding on both
the parties to the contract.
15.11.2 The objection that the Arbitrator has to deal with matters, to which the
contract relates, in the course of his duties or, he has expressed his views
on any or all of the matters in dispute or difference, shall not be
considered as a valid objection.
15.11.3 The Arbitrator may, from time to time, with the consent of the parties to
the contract enlarge the time for making the award. The venue of the
arbitration shall be the place from which the acceptance of offer is issued
or such other place as the Arbitrator, in his discretion, may determine.
15.11.4 All arbitration proceedings under this Regulation shall be governed by
the provisions of the Arbitration and Conciliation Act, 1996 and the Rule
there under, with any statutory modifications thereof for the time being
in force.
15.12 Price, Taxes, Duties and Evaluation:-
15.12.1 Price offered in financial bid will be fixed throughout the contract period
and no escalation will be allowed.
15.12.2 Any variation, up or down, in taxes and duties or any new levy introduced
subsequent to bid opening will be considered applicable subject to
Bidders request and submission of necessary documents.
15.12.3 The Tax liability, if any, on deputation of the Consultant‟s personnel shall
be borne by the Consultant and shall be responsibility of the Consultant
as per Tax laws of India.
15.12.4 The Consultant shall pay taxes, duties, fees, and other impositions
(expect service tax) as may be levied under the applicable laws in India,
the amount of which is deemed to have been included in the quoted price.
Page | 28
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Other Terms & Conditions of Contract”
Page | 29
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Other Terms & Conditions of Contract”
Page | 30
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Schedule of Annexure”
Page | 31
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Schedule of Annexure”
Annexure-A.1
Cover Letter Format
We, the undersigned bidder, having read and examined in detail the
specifications and the NIT in respect of the Scope of Work do hereby propose to provide
services as specified in the NIT. We also declare that:
1. The prices mentioned in our Bid are in accordance with the terms as
specified in NIT. The prices and other terms and conditions of this Bid are
valid for the period of 90 days from the date of opening of financial bid.
2. We declare that all the services/works shall be performed strictly in
accordance with the NIT No. _______ dated [date].
3. We declare that our bid prices are for the entire scope of the work as
specified in the RFP. These prices have been submitted in the Financial Bid.
4. We further declare that the prices stated in our Bid are in accordance with
NIT & will not be subject to escalation for any reason whatsoever within the
period of project. A Bid submitted with an adjustable price quotation or
conditional Bid may be rejected as non-responsive.
5. Our Proposal is binding upon us and subject to the modifications resulting
from contract negotiations
Page | 32
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Schedule of Annexure”
This is to further certify that all the information contained in the Bid is to
the best of our knowledge and the bids submitted are completely unconditional.
Thanking you,
Yours faithfully,
(Signature)
Page | 33
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Schedule of Annexure”
Annexure-A.2
Technical Bid Format
Please ensure that every requirement has been answered in the technical bid
submission format. Failure to do so might lead to a rejection of the bid. The technical
bids submitted shall cover the following sections:
Sr. Section Instruction for Response
No
1 Understanding of Project Scope Describe your understanding of the scope
of work.
2 Description of the Project Details. Describe your Service Delivery
methodology with respect to the scope
3 Delivery Plan Share a Detailed Delivery Plan including
but not limited to Timelines, Important
milestones, Resource plan, Program
Management etc.
4 Roles and Responsibilities Matrix List out the Roles and responsibilities of
the Project team members
5 Resources and responsibilities List out the Resources and responsibilities
expected from HPGCL as expected from HPGCL.
6 Documentation Coverage Describe all the relevant system
documentation to be provided. This should
at least include all the documents as listed
in the deliverables section.
7 Project Team Details Include the details of the proposed project
team. Please include the resumes of the
relevant team members in the attached
format provided in Annexure-A.3. The
identified team should have to be a part of
the project throughout the duration of the
project otherwise penalty shall be levied as
per Clause No. 11.1.2.
Page | 34
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Schedule of Annexure”
Annexure-A.3
Format for Resume of Team Profile to be deployed.
(To be submitted with Technical Bid)
It may be noted that:
Person with at least 10 years of IT/ERP experience, having successfully managed at
least two ERP implementation projects in large organizations would be considered as
„Project Manager‟.
Persons with at least 5 years experience in their respective functional areas being part
of team managing similar kind of ERP engagement in large organization would be
considered as „Functional experts‟ , „Infrastructure expert‟.
Person with at least experience of 10 years in Large power Generation sector
(Govt/PSU) which has implemented at least core modules of ERP (Finance,
Procurement, Projects , HR and Payroll) in large organization would be considered as
„Energy (Power Generation) Domain expert‟.
The Consulting Team shall include Total Size of the Consulting Team in numbers with
Phase wise breakup as under:
(a) Project Manager.
(b) Infrastructure expert.
(c) Functional experts.
(d) Energy domain expert & Other experts etc.
Proforma of Proposed Team
Name
Proposed Position
Academic Details
Consulting Experience in years
Consulting areas
ERP Consulting Experience in years.
Project 1:
Industry Covered:
Modules Covered:
Organisation/Employer:
Project Description:
Specific Role played in ERP consultancy:
Duration of association:
Project 2:
Industry Covered:
Modules Covered:
Organisation/Employer:
Project Description:
Specific Role played in ERP consultancy:
Duration of association:
*Every team member profile shall be certified by Team Member and the proposed
Project Manager.
………………………..
(Signature)
Name of Authorized Signatory
Page | 35
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Schedule of Annexure”
Annexure-A.4
Financial Bid Proforma
Bid Reference No.:
From:
Bidders Name and Address:
Person to Be Contacted:
Designation:
To:
SE/Technical(HQ)
Haryana Power Generation Corporation Limited
Room No. 108, Urja Bhawan, C-7, Sector-6, Panchkula.
Haryana – 134109, India.
Yours sincerely,
………………………..
(Signature)
Name of Authorized Signatory
Page | 36
HPGCL – Appointment of Consultant for implementation of ERP Solution
“Schedule of Annexure”
Annexure-A.5
Proforma for Exceptions and Deviations
The bidder is required to stipulate the list of Exceptions and Deviations, if any, in the
Proforma given below:-
………………………..
(Signature)
Name of Authorized Signatory
Page | 37