Académique Documents
Professionnel Documents
Culture Documents
2. WBS only
3. Contract
4. Scope baseline
Question 2: Perform Integrated Change Control process requires coordinating changes
across knowledge areas. When a proposed schedule change occurs, which of the following
will not be affected?
1. Cost
2. Quality
3. Staffing
4. Communications
Question 3: As a project manager, you are aware that the best way to resolve conflicts is to
face the conflict directly. This involves an problem-solving approach, whereby affected
parties work through their disagreements. In this context, the sources of conflict with the
least intensity are:
1. Bottom-up estimating
2. Analogous estimating
3. Parametric modeling
4. Top-down estimating
Question 5: The scope of your project is very well defined and you have completed all the
work described in the contract to your satisfaction, but you think your buyer is not happy
with the work. What should you do?
3. Ask the customer for input and get her advice on changes that need to be made
A. The buyer structures the bid documents to facilitate an accurate and complete response
from prospective sellers.
C. With government contracting, some or all of the content and structure of procurement
documents can be defined by regulation.
D. The term “proposal” is usually used when the seller selection decision will be based on
price.
1. B, C and D
2. Only B and C
4. A, B and C
Question 7: In your project, your subcontracting requirements of the machining of high-
value equipment are very demanding. Hence, you have determined the technical criteria to
evaluate the sellers. This is an example of:
3. Statement of work
1. Allow increase in cost of quality but ensure that the root cause of the problem is fixed
1. Executing
2. Initiating
3. Planning
1. Identify the operations manager as a valid stakeholder and review his requests and
possibly take them through change control.
2. Tell the team members to confront their issue and work it out among themselves.
3. Tell the team members you will advise the operations manager that the team will discuss
his requests and get back to him.
4. Tell the team members to stop wasting time arguing and get back to work since the
project is behind schedule.
Question 12: In your project, you are formalizing acceptance of the completed project
deliverables. This is done during:
2. Validate Scope
3. Control Scope
4. Control Communications
Question 13: What contains a predetermined list of risk categories that might give rise to
individual project risks and that could also act as sources of overall project risk?
1. Risk strategies
3. Risk register
4. Risk report
Question 14: In your project, you are using the Control Communications process to
organize and summarize the information gathered. Later, you present the results of the
analysis as a comparison to the performance measurement baseline. Some common
formats for performance reports that you could use are:
1. Regulations
2. Best practices
3. Assumptions
4. Constraints
Question 16: Your project sponsor has specified that you have to complete your project
within 3 months with a funding limit of $250,000. This is an example of:
2. Constraint
3. Assumption
4. Laissez-faire management
Question 17: You are the project manager of an IT company. You are creating a collection
and filing structure that details methods used to gather and store various types of
information, and also procedures to collect and disseminate updates and corrections to the
concerned stakeholders. Where will you include this information?
4. Project records
Question 18: You are a project manager and have just discovered a risk in your project
that requires an immediate corrective action. During which Project Risk Management
Process is this action performed?
2. Identify Risks
4. Monitor Risks
Question 19: Which of the following decision-making techniques used in the Plan Quality
Management process?
2. Mind mapping
3. Marginal analysis
1. Procrastination
2. Delaying tactics
3. Futuristic planning
Tasks A, B, C and D are in the critical path of a project, all the tasks are estimated to
required similar effort of 5 days each and cost $5,000 per task
At the end of day, task A and B are complete, task C is 50% complete, and $13,000 has
already been spent.
1. $5,000
2. $10,000
3. $11,000
4. $12,500
Question 22: At what stage of the project are factors like probability of successfully
completing the project, cost of changes, and cost of error correction, the highest?
1. Beginning
2. End
3. Executing
1. The activity list must include all activities that will be performed on the project
2. The activity list should include descriptions of major activities in sufficient detail
3. The activity list should include activity duration estimates and scope of work description
for each activity
3. The decomposition of the upper level WBS components requires subdividing the work
for each of the deliverables or subprojects into its fundamental components.
4. Audits
Question 26: It is important to gather and analyze all relevant information to determine all
project stakeholders and what their respective interests, expectations, and influences are.
It is also useful to identify stakeholder relationships that might enhance the project's
success. This information is documented in the:
1. Stakeholder Directory
3. Stakeholder Register
1. Project manager
1. Observation technique
2. Prototype
3. Requirement documentation
2. Change requests
1. Withdraw/Avoid
2. Force/Direct
3. Smooth/Accommodate
4. Compromise/Reconcile
Question 31: If there is a fire, the risk response plan developed is to use a fire extinguisher.
If the fire extinguisher cannot take care of the fire, you call in a fire engine. Calling in the
fire engine is an example of:
1. Secondary risk
2. Residual risk
3. Fallback Plan
4. Work around
Question 32: Which of the following statements about stakeholders are correct?
A. Project manager must try to satisfy even the implicit requirements of stakeholders.
B. Only those stakeholders who are project team members should be involved in the
creation of project plan.
1. B, C and D
2. A, C and D
3. Only C
4. Only D
Question 33: You are the project manager for an initiative to release a new product in the
market. But because of government regulations, you will have to make some changes to the
requirements documentation and the WBS. The changes made in the requirements
documentation are reflected in the:
3. Project plan
4. Project charter
Question 34: The customer was not satisfied with the finished product’s quality. The cost
of poor quality can also be referred to as:
1. Cost of conformance
2. Failure cost
3. Rework cost
4. Opportunity cost
Question 35: Which of the following items is not included in schedule data?
2. Cash-flow projections
3. Resource histograms
4. Cost baseline
Question 36: A project manager is responsible for managing project costs and human
resources. Factors like cost and staffing level for a project:
3. Are low at the start, peak as the work is carried out, and drop rapidly as the project
draws to a close
1. Three-point estimates
2. Parametric estimating
3. Quantitative estimating
4. Analogous estimating
Question 39: Please refer to the following diagram:
Tasks A, B, C and D are in the critical path of a project, all the tasks are estimated to
required similar effort of 5 days each and cost $5,000 per task
At the end of day 11, task A and B are complete, task C is 50% complete, and $13,000 has
already been spent.
1. Preferred price
2. Independent Estimate.
1. Process groups are non-overlapping activities that occur with varying intensity
throughout the project.
2. If the project is divided into phases, the process groups interact within a project phase
and may also cross over to other phases.
3. Not all processes will be needed on all projects and not all of the interactions will apply
to all the projects or process groups.
4. Among the process groups and their processes, the process outputs are related and have
an impact on the other process groups.
Question 42: Frequent heated discussions with your colleague over an issue are creating a
hostile environment. To ease this situation, you agree with your colleague`s point of view.
The conflict resolution mode that you are using is:
2. Withdraw or Avoid
3. Force or Direct
4. Smooth or Accommodate
Question 43: Which of the following is a hybrid type of contractual arrangement?
2. Fixed-price contracts
3. Cost-reimbursable contracts
2. Project files
3. Historical information
2. Work schedule
3. Risk responses
4. Activity duration
Question 47: A flow chart is a diagram, which shows how various elements of a system
relate and includes tools like "cause and effect diagrams" and "flowcharting". As a project
manager, you find "cause and effect diagrams" a useful tool for:
2. Identifying which factors may influence specific variables of a product or process under
development or in production
1. 0 weeks
2. 1 week
3. -1 week
4. Cannot be determined
Question 49: Project Integration Management includes the processes and activities needed
to identify, define, combine, unify and coordinate the various processes and project
management activities within the Project Management Process Groups. When a project is
initiated, one of the processes taken up early on in the project initiation stage is:
1. Identify Stakeholders
2. Define Scope
1. Constraint
2. Assumption
3. Discretionary dependency
4. Mandatory dependency
Question 51: In your project, as part of the Manage Communications process, you have
created an information retrieval system, which helps team members and stakeholders to
share information. What will you do next?
2. Cost of quality
3. Benchmarking
4. Design of experiments
Question 53: Inspection includes activities such as measuring, examining, and testing
undertaken to determine whether results conform to requirements. Which of the following
terms does not refer to inspection?
1. Product review
2. Audit
3. Walkthrough
4. Stage-gate
Question 54: Which of the following processes identifies the relationship among project
activities?
1. Sequence Activities
3. Define Activities
4. Control Schedule
Question 55: In your project, you identified disaster situations (e.g. floods, earthquakes,
etc.) as potential risks. The project sponsor suggested that, at the project level, no steps
could be taken to deal with such risks and recommended creation of a contingency reserve
(with 5% of the project budget) which could be used in case of disaster situations. This is
an example of:
1. Risk mitigation
2. Risk acceptance
3. Risk avoidance
2. Performance reports
2. Project plan
3. Organization chart
1. Cost variance
2. Schedule variance
1. Insist that the customer verify the deliverables at the end of each phase
2. Ask your senior management to review the deliverables at the end of each phase to
ensure that the deliverables satisfy customer requirements
3. Complete the product as per specifications and provide the completed product to the
customer as requested
4. Provide project deliverables to the customer at the end of each phase, even if the
customer does not review them
Question 61: The customer communicates a request for a change in your project plan.
What should be your first step towards addressing the change request?
2. Business need
3. Strategic plan
C. Convenience of the seller, if they cannot deliver as per the contract statement of work
1. A, B and C
2. Only A and B
3. A, B and D
1. A critical resource went on sick leave for a long period of time, which had not been
anticipated earlier.
2. The cost of raw materials required for construction increased by 10%. You had
anticipated a cost increase of 12% in your project plans.
4. There was four days waiting time in the curing of concrete, and work could not be done
during that time.
Question 65: In your project, you have completed the Identify Risks process to determine
which risks may affect the project, and a risk register has been prepared. What should you
do NEXT?
4. Risk audits
Question 66: In your project, you wish to include certain significant events in the
milestone list for the project based on historical information. Such milestones are:
1. Optional
2. Mandatory
3. Statutory
4. Authorized
Question 67: Given the current and desired engagement levels of stakeholders in the
following Stakeholder Engagement Assessment Matrix, which would be the most important
gap to be addressed by the project manager as soon as possible?
1. CEO
2. Team member
4. Sponsor
Question 68: You have recently joined as a project manager of an equipment
manufacturing company. Your project sponsor stresses the importance of obtaining
stakeholders` formal acceptance of completed deliverables. This should be done:
A. Cost-benefit analysis
B. Quality checklists
C. Cost of quality
D. Benchmarking
1. B, C and D
2. A, C and D
3. A, B and D
4. A, B and C
Question 70: You are managing the construction project of a highway overpass. The
project is critical, and must stay on schedule in order to not cause delays in subsequent
projects being planned. Your sponsor has placed a lot of pressure on you to ensure that you
do a good job of planning the schedule for this project so it can be submitted to the project
managers of those subsequent projects to be taken into account during their planning
processes. You would like to use the best practices in the road construction industry to help
you in your project. Which of the following tools of Sequence Activities process are based
on these best practices?
1. Mandatory dependencies
2. Discretionary dependencies
3. Industry norms
3. Let the customer know about the impact of the change in project scope and ask for
additional funding.
1. Create a scope management plan to document project scope definition, verification, and
control
4. Used for periodic risk reviews to identify risk ratings and prioritization
Question 75: You are the project manager for a high-priority project that involves the
creation of a new product that is expected to bring the company out of debt within one year
of the product's release. At least half of the company's employees have played a significant
role in the project. The project team is currently creating deliverables and everyone in the
company is excited to see the project moving along as per the project management plan.
The wife of the company's CEO often comes into the office and loves to visit and socialize
with company employees. She is very interested in the project and often asks you and other
team members specific details about the project and how things are going. One day, she
presents an innovative idea to you for an additional product feature that she thinks
customers will love. What should be your NEXT step?
3. Talk to the CEO about his wife & acutes suggestion and see what he thinks
4. Tell her you & acute’ll speak with some customers and see what they think about the
new feature’
Question 76: If you would like to compare different suppliers and rate their proposals for
the purpose of procurements, you should use:
1. Bidder conferences
2. Selected sellers
3. Procurement documents
1. Document analysis, SWOT analysis, Root cause analysis, and Assumption and constraint
analysis
2. Assumptions analysis, risk probability and impact assessment, interviewing, and Delphi
technique
3. Expected monetary value, root cause analysis, influence diagrams, and documentation
reviews
4. Contingent response strategies, assumptions analysis, influence diagrams, and Delphi
technique
Question 78: In your project, you are now interested in determining the cause of variance
relative to the scope baseline and deciding whether corrective action is required. You
should use:
2. Variance analysis
3. Re-planning
1. Training
2. Rework
3. Loss of reputation
4. Warranty
Question 81: You are working on a project that your company recently won through a
bidding process. It is still very early in the project, but the project charter is complete and
you are now creating the stakeholder register. Which of the following would be useful to
help you identity the project stakeholders?
2. Agreements
3. Business case
1. Lead and perform the work defined in the project management plan and implement
approved changes to achieve the project`s objectives.
2. Define, prepare, and coordinate all subsidiary plans and integrate them into a
comprehensive project management plan.
3. Track, review, and report the progress to meet the performance objectives defined in the
project management plan.
4. Review all change requests, approve changes, and manage changes to the deliverables,
organizational process assets, project documents, and the project management plan and
communicating their disposition.
Question 83: A conflict resolution technique that emphasizes areas of agreement is also
called:
2. Force or Direct
3. Compromise or Reconcile
4. Smooth or Accommodate
Question 84: A contract which includes features of cost reimbursable and fixed price types
of contract is a:
1. Project exclusions
3. Project deliverables
1. Negotiation
2. Change request
4. Litigation in courts
Question 88: In your project, you are coordinating people and resources as well as
integrating and performing activities of the project in accordance with the project
management plan. This is performed during:
1. Smooth
2. Escalate
3. Force
4. Collaborate
Question 91: During the Sequence Activities process, you realize that several tasks have
conditional branches (e.g., a design update is only needed if the inspection detects errors).
For this purpose, you may use Precedence diagramming method (PDM), which is also
referred to as:
1. GERT
2. AOA
3. AON
2. PERT
3. System dynamics
4. Templates
Question 93: In your project, you are preparing the requirements management plan to
define and document stakeholders` needs to meet the project`s objectives. Which of the
following is not a component of the requirements management plan?
1. Traceability structure
2. WBS
4. Product metrics
Question 94: The dictionary meaning of authority is "power to influence or command
thought, opinion, or behavior." Your authority as a project manager is greatly dependent
on:
4. Organizational structure
Question 95: Managing stakeholders allows the project manager to increase support and
decrease resistance from stakeholders with the ultimate goal of project success. Which of
the following are outputs of the Manage Stakeholder Engagement process?
1. Project Charter
2. Business Case
3. Deliverables
2. Cost of rework
3. Communication skill
4. Industry experience
Question 102: Project performance must be monitored and measured regularly to identify
variances from the plan. Which of the following processes does not belong to the
Monitoring and Controlling Process Group?
1. Validate Scope
2. Control Risks
3. Control Communications
4. Manage Quality
Question 103: You are the managing a complicated ERP implementation project. The
following provides information about one activity: deployment in your project:
1. Basis of estimates
2. Resource requirements
4. Activity attributes
Question 105: Motivating your team members is important for the success of the project.
You understand from the HR manager that employees are motivated by self-esteem,
recognition, and self-actualization. To which theory is the HR manager referring?
1. Theory Y
3. Herzberg`s theory
4. Maslow`s theory
Question 106: Items at the lowest level of a Work Breakdown Structure are called:
1. Work Packages
2. WBS Dictionaries
3. Work Components
1. Talk to your team and if they agree that it is the best response, implement the response.
2. Determine who should be notified about the threat and communicate the details to that
person.
3. In exceptional situations, a project manager can go beyond his authority. So, you can
implement the risk response if it is urgent.
4. As risk is an uncertainty, it may or may not happen. So, flag the risk and leave the
decision until it happens.
Question 109: Please refer to the following diagram:
Tasks A, B, C and D are in the critical path of a project, all the tasks are estimated to
required similar effort of 5 days each and cost $5,000 per task
At the end of day 11, task A and B are complete, task C is 50% complete, and $13,000 has
already been spent.
You know that current variances are typical, i.e., similar variances will not occur in future.
What is the cost performance index (CPI) for the project?
1. 0.96
2. 1.04
3. 1.00
4. 1.20
Question 110: You are a principal at an architecture firm which has made you the Project
Manager in charge of building four new apartment and office towers on a larger waterfront
construction. The project has a critical path of twenty-three weeks. What is the impact on
the duration of the critical path if the management wants you to complete the project in
twenty weeks?
4. Cannot be determined.
Question 111: As a project manager, you have created a document that describes the
procurement item in sufficient detail to provide a basis for the sellers to determine if they
can provide the item. This document is referred to as:
1. Statement of work
2. Contract
3. Procurement document
1. Soft logic
2. Hard logic
3. Mandatory logic
4. Optional dependency
Question 114: Your company has implemented ISO standards for quality. In this context,
which of the following statements regarding quality is accurate?
B. Manage Quality process increases the probability of meeting the quality objectives as
well as identifying ineffective processes and causes of poor quality.
C. Control Quality is the process of monitoring and recording results of executing the
quality activities to assess performance.
D. The Quality management plan describes how the project management team will
implement the performing organization`s quality policy.
1. B, C and D
2. C and D
3. B and D
4. A, B and C
Question 115: Which of the following statements relating to product-oriented processes
and project management processes is accurate?
1. Initiating
2. Planning
3. Executing
4. Controlling
Question 117: In your project, you have used valuable inputs to capture quality control
measurements. The inputs used for this purpose are:
A. Risk register
1. B, C and D
2. A, C and D
3. A, B and D
4. A, B and C
Question 118: You are managing a complicated software development project with several
deliverables. To be effective and to be alert to potential future problems, you monitor the
status of completion of the project deliverables. This information will be available to you in
the:
1. Initiating
2. Executing
4. Planning
Question 120: You are the project manager for a new software development project. A
previously unidentified risk is discovered when the project is nearing completion. You
realize that this risk may adversely impact the project`s overall ability to deliver. As a
project manager, what step do you take FIRST?
3. Project manager takes the anticipated changes through the change control process.
2. Either prior to or at the same time the project charter is developed and approved
2. You are happy, because the project will `exceed customer expectations`
3. You are worried that this is going to increase the project size
4. You are undecided about the increase in the quality metrics of the project
Question 124: You are the project manager in a software company. As an output of the
Plan Resource Management process, you have developed the Resource Management Plan.
In this context, which of the following actions is NOT documented as a part of the Resource
Management Plan?
2. Team performance assessment criteria are be determined by all appropriate parties and
incorporated in the Develop Project Team inputs.
3. Proper responsibility (work that a team member is expected to perform in order to
complete the project`s activities) is assigned to all the team members.
4. Mismatches between competencies and skills required to complete the assigned
activities and the competencies and skills of team members are identified.
Question 125: Which of the following is NOT a characteristic of external dependencies?
4. They are identified by the project team during the process of sequencing the activities
Question 126: You work for a company which executes heavy engineering contracts. While
performing risk response planning for your project, you determine a risk that there is a
"Possibility of getting new orders in the future which are beyond the current capacity of
our production facilities." What should you do?
1. Risk exploitation
2. Risk sharing
3. Risk enhancing
4. Risk mitigating
Question 128: What is the factor that helps a project manager gain maximum support
from the assigned project personnel?
1. Expertise
2. Work challenge
2. The ability to inspire the team members when faced with tough deadlines.
4. The ability to manage the personal emotions of oneself and other people
Question 130: While doing a cost-benefit analysis, you determine that a new project has
60% probability of earning a profit of $1,000,000 or 30% probability of incurring a loss of
$500,000. What is the expected monetary value of the decision?
1. $400,000
2. $600,000
3. $450,000
4. $200,000
Question 131: You are managing a small project with five team members working part-
time. At the beginning of every week, you orally allocate work to all the team members.
This is an example of:
2. Agreements can be amended till before the seller starts the work.
3. Agreements can be amended at any time prior to contract closure by mutual consent, in
accordance with the change control terms of the agreement. Such amendments are
typically captured in writing.
4. Agreements can be amended as when the buyer feels the need to amend it.
Question 134: You are in the process of selecting an appropriate type of contract for your
project. In this context, which of the following statements related to fixed price, cost
reimbursable, and time and material contracts is NOT correct?
What is the opportunity cost if the project manager decides to build instead of buy?
1. - $1,500
2. $3,500
3. $1,500
4. $5,000
Question 137: Please refer to the following diagram:
Tasks A, B, C and D are in the critical path of a project, all the tasks are estimated to
required similar effort of 5 days each and cost $5,000 per task
At the end of day 11, task A and B are complete, task C is 50% complete, and $13,000 has
already been spent.
You know that current variances are atypical, i.e., similar variances will not occur in the
future. What is the Estimate at Completion (EAC)?
1. $15,000
2. $20,000
3. $20,500
4. $22,000
Question 138: As the project manager of a project intended to mask stench from a gas
pipeline, you create the following Network Schedule Diagram (duration in weeks):
What is the effect on the project if the duration of task J is increased to 9 weeks?
3. The overall time-frame required to complete the project will increase by 1 week
1. Prepare and distribute the agenda stating the objectives of the meeting
2. Ensure that the meetings start and finish at the published time
4. Allow members to discuss an important topic even if it is not part of the agenda
Question 140: You have recently appointed a project manager to handle a critical project
in your organization. You want to give her the authority to apply organizational resources
to project activities. Which document should you use?
3. Project charter
1. Resource leveling
1. Team-building activities
2. Team charter
3. Interpersonal skills
4. Rules of conduct
Question 143: The following are the details of a project:
Payback: $2,000
Profit: $1,000
1. 2.50
2. 1.25
3. 1.67
4. 0.83
Question 144: In your project, you would like to conduct a lesson learned session to
identify project successes and failures, as well as make recommendations to improve future
project performance. This is done during:
1. Project closure
2. Project initiation
1. Market need
2. Business need
3. Social need
4. Legal requirement
Question 146: Which of the following statements about "Quality" and "Grade" is correct?
A. Grade is a rank given to entities having the same functional use but different technical
characteristics.
D. It is always a problem for the customers if the product is of high quality and low grade.
1. A and B
2. Only B
4. A, B and C
Question 147: In which of the following cases is a contract NOT legally binding?
1. Fast track the project to ensure that the project schedule is not delayed.
1. S-curve
2. Histogram
3. Control chart
4. Pareto diagram
Question 151: Careful and explicit risk management planning ensures possibility of
success of the other risk management processes. In this context, you use sensitivity
analysis to:
2. Determine which risks have the most potential impact on the project
1. Functional Manager
2. Program Manager
4. Portfolio Sponsor
Question 153: Your current project has very limited information on activity durations. You
wish to use the actual duration of a previous, similar activity as a basis for estimating the
current activity duration. Once you have estimated the durations for the activities on the
project, what would be your next step?
2. Calculate early and late start and finish dates for the unfinished project activities.
4. Subdivide project work packages into smaller more manageable components for better
management control.
Question 154: Which of the following cannot be considered a benefit of a well-constructed
scope statement?
1. Dispute log
2. Issue log
3. Change log
4. Problem log
Question 157: As part of Project Communications Management, you are monitoring
communications throughout the entire project life cycle to ensure the information needs of
the project and its stakeholders are met. This is done as part of:
2. Manage Communications
3. Monitor Communications
4. Administrative closure
Question 158: A project manager intends to identify and document interactivity
dependencies. Which of the following inputs can the project manager use for this purpose?
B. Activity list
D. Activity attributes
1. B, C and D
2. A, C and D
3. A, B and D
4. A, B and C
Question 159: Which of the following should be determined during the Plan Quality
Management process, so the cost of quality will include the number of tests, expected scrap,
etc.?
1. Sample frequency
2. Sample size
3. Sample time
3. You should select this project from all other competing alternatives.
4. You should not select this project from all other competing alternatives
Question 161: You and your sponsor are in an important meeting to select a project from
among other projects having similar investments. In this context, you select the project
with:
1. Planned Value
2. Earned Value
3. Actual Cost
1. Historical information
1. Discount Rate
3. Negotiate for the best price and protect interests of the buyer
1. Operational definitions
3. Checklists
4. Quality policy
Question 167: In the closure stage of your project, you are interacting with your team to
create lessons learned documentation, which will include recommendations to improve
performance of future projects. Which of the following will you NOT include in the lessons
learned documentation?
1. Cause of variances
3. Only positive aspects of the project which can be used by others in the company
1. Theory X
3. Learning curve
4. Economics of scale
Question 169: You are the project sponsor for a reputed company, and you work with the
project management team in certain matters concerned with the project. Which of the
following is an area where you would NOT assist?
1. Project funding
3. Clarifying scope
4. Monitoring progress
Question 170: You are trying to identify the type, quantity, and characteristics of resources
required to complete the project. In which process you would do this?
1. Acquire resources
4. Control resources
Question 171: Project Risk Management helps in maximizing the likelihood and impact of
positive events, and minimizing the likelihood and impact of negative events in the project.
In this context, Plan Risk Responses process:
3. Determines which risks may affect the project and documents their characteristics
4. Monitors residual risks, identifies new risks, and evaluates risk process effectiveness
Question 172: You are monitoring and recording results of assessing performance and
recommending necessary changes. What do you get from this exercise?
3. Quality metrics
4. Quality checklists
Question 173: As a project manager, you would identify risks in which of the following
processes?
1. Identify Risks
1. Define Activities
3. Sequence Activities
4. Develop Schedule
Question 176: In the Control Schedule process, changes to project schedule can result in
change requests to:
1. Schedule baseline
3. Activity attributes
1. Define Activities
3. Define Activities
4. Sequence Activities
Question 178: In the Control Procurements process, you are responsible to complete each
project procurement to support the Close Project or Phase process. In this context, the final
equitable settlement of all outstanding issues, claims, and disputes by negotiation is done
through:
1. Procurement Negotiations
2. Procurement audits
3. Litigation
4. Claims administration
Question 179: The project scope statement consists of the product scope description and
project deliverables. It also defines the:
1. Scope Baseline
2. WBS
4. WBS dictionary
Question 180: In your project, you have conducted a communication requirements
analysis to determine the total number of possible communication channels in the project.
While conducting the analysis, you learn that the number of communication channels:
2. Analytical forecasts
4. Stakeholder register
Question 182: Your project is very critical for the company and must be completed within
six months. The project charter has been signed, but the scope statement is not yet
prepared. The management asks you to go ahead with the project without the scope
statement being approved. What should you do?
1. Refuse to work on the project, because the management is not following standard project
management practices.
2. To save time, you should start the project with inputs from the project charter.
3. Meet the management and explain the problems you may face if you start a project
without a scope statement.
4. Escalate the issue to the project sponsor and issue a risk memo.
Question 183: From a project management perspective, which of the following BEST
describes activity attributes?
3. They provide a basis for determining how effectively performing organization supports
the project.
4. They provide primary data source for use in estimating team and physical resources
required for each activity on the activity list.
Question 184: In your project, you want to define variance thresholds at the designated
time points over the duration of a project. So, you should use:
1. Units of measure
2. Precision level
4. Control thresholds
Question 185: Which of the following processes, sometimes, is called 'quality assurance'?
1. Manage Quality
3. Control Quality
3. Provided by the buyer to the seller at the end of the project if defined performance
criteria are met
1. Facilitated workshops
2. Focus Groups
They also want the product development to be rushed as they are running low on current
inventory and want their next order to consist of the new pen. Since the product is a new
concept and the customer is an important one, you decide to create a prototype of the pen
during the design phase.
After reviewing the prototype, PM study's CEO advises that he is not happy with the design
and the size of the logos. The Quality and Marketing Directors and other PM study
stakeholders are happy with the prototype and feel that all their requirements were met.
What could be the most likely cause of this situation?
4. All of the requirements approved for the prototype were not implemented.
Question 190: As a project manager, you realize the importance of team development for
resource management. Which of the following is NOT a tool/technique for the Acquire
Resources process?
2. Pre-assignment
3. Virtual teams
4. Expert judgment
Question 191: What are the basic types of phase-to-phase relationships?
1. Create WBS
2. Scope verification
4. Product analysis
Question 193: Engagement levels of stakeholders can be classified as follows:
A. Bidder conference
B. Procurement documentation
C. Advertising
D. Negotiation
1. B, C and D
2. A, C and D
3. C and D
4. Only A
Question 195: You are a Project Manager in charge of building a school that will open next
month in the middle of a state-funded housing project. In your project, you are reviewing
and maintaining realistic start and finish dates for project activities. This should be done as
part of:
1. Sequence Activities
3. Develop Schedule
4. Define Activities
Question 196: The buyer has clearly specified that only companies that have revenues
greater than $300 million and profitability of more than $30 million over the past 3 years
can bid for the contract. This can also be referred to as:
1. Procurement negotiation
3. Independent estimate
1. Physiological need
2. Safety need
3. Social need
4. Self-esteem need
Question 198: You are the project manager for the construction of a shopping mall. As the
location is prone to earthquakes, you plan to construct a building that is resistant to
earthquakes. This is an example of:
1. Risk mitigation
2. Risk transfer
3. Risk avoidance
4. Risk acceptance
Question 199: Which of the following statements about stakeholders is INCORRECT?