6 BOILER
APH oulet flue gas temperature element checking and tapping
locatinon changing work if required.
7 BOILER Startup vent Control valve Inspection work.
8 BOILER MSSV motorized valve starter inspection and dressing work.
12 BOILER
Boiler furnaces thermocouple inspection and replacement if
required
BOILER/TURBI All Control Valves Checking along with Operation Person and
14 NE Calibration If Required.
Control Oil Pressure Transmitter Oil Line Leakage checking and
15 TURBINE arresting work if required.
Turbine Gauge Board panel Instruments Tubing Leakage checking and
16 TURBINE arresting work if required.
Lube Oil Pressure Transmitter Oil Line Leakage checking and tightness
17 TURBINE work if required.
ACOP no-1 auto ON/OFF pressure switch inspection, and
18 TURBINE replacement work if required.
19 TURBINE
Turbine Auxilary pump discharge pressure gauge checking work
and replacement if required.
20 TURBINE
Turbine Exchaust line temperature after desuperheating
Thermocouple checking and replacement
22 CCR DCS Cabinets Inspection along with its Bulbs/ Cooling Fans Checking.
SOV Available TL NO 1 1 0 0
Available TL NO
K-type thermocouple 1 1
Not Applicable Mechanical scope TL NO
1 1
NIL Not Applicable TL NO 2 1 0 0
Available TL NO
K-type thermocouple. 1 1
Indicator Lamps, Push Buttons, Available TL NO 2 1 0 0
NO/NC Elements.
R REQUIRED Quantity
1 2 3 4 Remarks Indent no Indent Date
indented
Helper
1 _ _ _ _
1 _ _ _ _
1 _ _ _ _
1
2 _ _ _ _
0 _ _ _ _
0 _ _ _ _
0 _ _ _ _
0 _ _ _ _
0 _ _ _ _
0 _ _ _ _
0 _ _ _ _
1 _ _ _ _
0
1x6.0 MW CPP, ABD SITE, THERMAX LT
Feed water control valve maintanace work and valve steam, seat
3 BOILER replacement.
Feed water control valve and feed water bypass control valve
8 BOILER instrument air line saparation work.
Ash handling system no-3,4 air filter cum lubricater unit changing
9 AHP work.
Ash handling system no-1,2 slide gate power cylinder seal kits
10 AHP checking and changing work.
11 CHP Belt sway switches installation and cable laying for BC-1,2,3,4.
12 CHP Zero speed switches installetion and cable laying work in CHP
14 CHP Emergency siren arrangement and cable laying work For CHP
1/2" GI pipe
4m,1/2"sockets,Welding Available TL NO 0 1 0 1
Electrodes
Juction box Not Available TL NO 1 0 1 1
SS fittings Not
6mm SS tube, SS tube fittings TL NO 2 1 0 0
available
Not Available TL NO 1 1 0 0
air filter cum lubricater unit
Available TL NO 1 1 0 0
Seal kits
TL NO 1 1 1 1
3C X 1.5 sqmm copper cable,16C
X 1.5 sqmm copper cable, BSS- Not Available
8no, ZSS-8no. TL NO 1 1 1 1
TL & Third
NIL Not Applicable Party YES 1 1 0 0
Support
REQUIRED
DAY
R REQUIRED Quantity
1 2 3 4 Remarks Indent no Indent Date
indented
Helper
1 _ _ _ _
1 _ _ _ _
1 _ _ _ _
1 _ _ _ _
1 _ _ _ _
0 _ _ _ _