Académique Documents
Professionnel Documents
Culture Documents
HM-LE-PRWIDE-M0201-DOC-MA-STC-00-001
CLIENT: CONSULTANT:
L&T METRO RAIL (HYDERABAD) LIMITED LARSEN & TOUBRO CONSTRUCTION LIMITED
Building & Factories
PROJECT:
HYDERABAD METRO RAIL PROJECT
SUPPLIER / CONTRACTOR:
LARSEN & TOUBRO CONSTRUCTION LIMITED
TITLE :
Document Control
List of Tables
Table 1: Reference, Standards & Codes .............................................................................................................. 8
Table 2: Station numbering ............................................................................................................................... 19
Table 3: Look At For ........................................................................................................................................... 21
Table 4: Minimum Sightline Distances and the Minimum Size of the Signs ..................................................... 23
Table 5: Sign boards during Maintenance ......................................................................................................... 24
Table 6 Maintenance Guidelines ....................................................................................................................... 40
Table 7: Common defects remedial measures .................................................................................................. 43
Table 8 Proforma for inspection of station ....................................................................................................... 44
Table 9 Proforma for Structural Steel Inspection Register ................................................................................ 47
Table 10: Maintenance periodicity .................................................................................................................... 48
List of Figures
Figure 1 Typical Station Cross Section ............................................................................................................... 10
Figure 2 Cross Sectional details of Stations Spine & Wing and Pier arm .......................................................... 11
Figure 3 General Block Diagram of Stations ...................................................................................................... 12
Figure 4: Street Level plan ................................................................................................................................. 13
Figure 5: Concourse level plan .......................................................................................................................... 13
Figure 6: Platform level plan ............................................................................................................................. 14
Figure 7: Organogram........................................................................................................................................ 15
Figure 8 Hand Signs ........................................................................................................................................... 25
Figure 9: Station traffic management ............................................................................................................... 27
Figure 10 Cross Section at Concourse level of Station ...................................................................................... 29
Figure 11: Spine end-sections near pier ............................................................................................................ 30
Figure 12: Spine section at centre ..................................................................................................................... 30
Figure 13: Spine & Wing cross section near pier ............................................................................................... 30
Figure 14: Spine 7 Wing cross section at Centre ............................................................................................... 30
Figure 15 Isometric view of elastomeric bearing .............................................................................................. 31
Figure 16: Bearing pedestal detail at Concourse level ...................................................................................... 32
Figure 17 Cross Section at Platform level of Stations........................................................................................ 36
Figure 18 General arrangement of station roof structure ................................................................................ 38
Figure 19 Typical Stations- Internal Staircase.................................................................................................... 41
Part-A Part-B
- INTRODUCTION - Types of Station
Abbreviations - General Arrangement
- List of Reference, Standards and Codes
Part-C
- Station General Block Diagram
Part-A Part-B
- Objectives - STATION BUILDINGS STRUCTURES
- Roles & Responsibilities - STATION BOX STRUCTURE
- Chief Station Maintenance Engineer - ROOF STRUCTURE
- Inspection Officer - STREET LEVEL STRUCTURE
- Assistant Officer
- Knowledge of rules and regulations
Part-C Part–D
- ANNEXURE 1 Proforma for Inspection of Station ANNEXURE 8 Master Maintenance Schedule
- ANNEXURE 2 Proforma for Periodic Inspection
Report of Bearings Inspection
- ANNEXURE 3 Proforma for Structural Steel
Inspection Register
- ANNEXURE 4 Periodicity of Inspection and
Maintenance
- ANNEXURE 5 Routine Inspection Check List (for
Typical Station)
- ANNEXURE 6 Detailed Inspection Check List
- ANNEXURE 7 List of tools for Routine, Detailed &
Special Inspection
INTRODUCTION
The Hyderabad Metro Rail Project (HMRP) envisaged by the Government of Telangana covers three high
density traffic corridors of Hyderabad. This project is structured as a Public Private Partnership (PPP) Project
on design, build, and finance, operate and transfer (DBFOT) basis. The Metro consists of 3-Corridors (Lines)
The scope of work is operations and maintenance for the station civil that includes the station structures
which include Roof, Platform, Concourse, Entry & Exit staircases and retail areas based on ROW. This Manual
specifies the Technical Maintenance Plan (TMP) for different types of the station in HMRP. This Manual
covers the general construction issues and remedial measures and similarly the inspection maintenance of
the structures. It provides a general overview of the Station Structure as a System and includes essential
information relating to their maintenance.
Abbreviations
Abbreviations Description
AFC Automatic Fare System
ASS Auxiliary Sub Station
COM Communication
CSME Chief Station Maintenance Engineer
DB Distribution Board
DBFOT Design Build Finance Operate and Transfer
DG Diesel Generator
EFO Excess Fare Office
EPS Emergency Power Supply
FEA Fire Equipment Area
HMRP Hyderabad Metro Rail Project
IRS Indian Railway Standard
NDT Non Destructive Test
O&M Operation and Maintenance
PPP Public Private Partnership
PSS Power Supply and SCADA
PTFE Poly Tetra Fluoro Ethylene
S&TC Signalling and Train Control
SCR station control room
SER Signalling Equipment Room
SW Station Work
TER Telecom Equipment Room
UPS Uninterrupted Power supply
Typical station
There are 55 typical stations in this project. These consist of three levels – street level, concourse level and
platform level. Street level: There are total four entry-exits on both sides of each station for passengers to
enter station box from street level. All sump & pump rooms and DG are located at street level. Also there are
2 staircases at the street level and a lift on each side of station.
Concourse level: All technical rooms and retail areas are located in this level.
Platform level consists of DB, FEA shafts and the station roof. There are emergency exits at the four corners
of the Platform. The standard dimensions of the typical station:
station Length– 138.85m
station Width– 20.00m
station Height (with respective to road level) – Varies with site condition, min. 21.75m
Typical span of the station – 13.4m/17m
Interchange station
Interchange station connects two corridors. There are 3 interchange stations. Out of the three, 2 stations –
Ameerpet and MGBS stations consists of 2 platforms – lower platform and upper platform each connecting
one corridor.
Parade ground station consists of two independent stations (Corridor-2 & Corridor-3) connected through
sky-walk. Station in Corridor-2 is a multilevel station consisting of 3 levels namely Lower concourse, Upper
concourse and Platform level. Lower concourse further consists of 3 levels. Level 3 is the lower most level
and consists of toilets, food court, retail, auxiliary substation, emergency power supply and battery rooms.
Lower concourse level 2 and 1 consists of F&B outlet, retails, toilets and ticket office. Excess fare office is in
lower concourse level 2. Upper concourse level is similar to typical station except that the excess fare office
and ASS room are not at this level. Platform level is similar to typical station in all aspects.
Special station
There are 3 special stations in this project – Jubilee Check post, Punjagutta and Hi-tech city.
Jubilee Check post is a single level station with mezzanine covering part of the station. The technical rooms
like ASS, TER, SER, UPS, EPS and battery rooms are located at the mezzanine level. Ticket office, SCR and EFO
are located at platform level.
Punjagutta and Hi-tech city are multilevel stations. Hi-tech city station contains lower concourse covering
few spans of the total station. Punjagutta station contains lower concourse covering full station area. The
upper concourse and platform levels are similar to the typical stations.
2 General Arrangement
Roof
Platform
Concourse
Street Level
Every typical station consists of Street level, Concourse level, Platform level and Roof.
Street level: Houses the Sump & Pump room, DG set and Entry/Exit with Staircases, Elevators &
Escalators.
Concourse level: Typically houses technical rooms of all contractors like SW, PSS, AFC, O&M, COM and
S&TC. It is segregated in to paid and unpaid areas with unpaid areas having retail outlets. The spine and
wing arrangements for the station are shown in Figure 2. The grade of the concrete shall be M50. The
cables shall be 19K15 low relaxation stress relieved HTS strands conforming to Class-2 of IS: 141628.
Sheathing shall be HDPE (ID. = 17mm). Spines are joined together by longitudinal stressing, whereas
wings are stitched to spines through transverse stressing.
Platform level: Terminal stations / interchange stations have the train Crew room located in the platform
level. There are two DB closets at platform level which will house the electrical distribution boards and
earth terminals. There are 4 FEA shafts at the platform level of each station.
Roofing system – Structural steel supported with roof sheet
Figure 2 Cross Sectional details of Stations Spine & Wing and Pier arm
STATIONS
Concourse Platform
Street Level Roof Level
Level Level
Prestressed
Entry Exit Spine & Wing Structural Steel
Precast Girder
Bearing
UG Sump & Pump Bearing Roof Sheeting
Corbel
DG Foundation Slab (Composite) Solar Panel
Expansion Joint
Signage Expansion Joint
Mezzanine Slab Roof walkway
Lift pit Wicket Gate
Stair Case Gutter
Toilets
Handrails
Gutter
4.1. Objectives
The station inspection is done to ensure the safety and serviceability during the service life of the station civil
structures. The purpose of inspection of station can be classified as follows:
To ensure that the structure is safe and fit for the designed purpose. This relates to the gradual
deterioration of the station structure with time or due to any accidental occurrence;
To identify the actual and potential sources of trouble at the earliest possible stage;
To record systematically and periodically the condition of the structure. This enables the concerned
authorities to identify any significant structural changes and defects;
To provide necessary information on which decision can be taken for carrying out maintenance repairs,
strengthening and replacement of the structural components, if any;
To keep close coordination with operations team to record any abnormalities during operation stage
leading to requirement of any need based inspection (other than periodical);
Preventive maintenance of various elements of station/s.
Chief Station
Maintenance Engineer
Over all responsibility of the maintenance of the
Station Civil
Figure 7: Organogram
All personnel and equipment who may intend to use this manual for the maintenance of the station civil
assets must be suitably qualified and certified to be able to operate on the HMRP. The Operator shall be
responsible for ensuring that personnel are operating under safe systems of works. Part of this may include
undertaking tests, prior to working, to determine if there are any hazardous materials that may affect
personnel. Utmost care and safe working practices shall be observed while performing any activity on the
station civil of the Hyderabad Metro system by all Station Civil Maintenance personnel, as follows:
all personnel shall wear the appropriate Personal Protective Equipment (PPE) like safety shoes, high-
visibility vest, safety goggles, helmet, harness, gloves, mask etc. when working at site.;
a trained and competent member shall be the Person In Charge (PIC) for the duration of the preventive
or corrective maintenance;
coordinate with Roads Department and/or Traffic Police as necessary for works requiring lane closures
prior to commencement of work;
Special inspection is need based and should be carried out as and when required. However, special
inspection may require supplementary testing and structural analysis and may require detailed involvement
of CSME. It may be noted that the check list for Detailed Inspection can also be used for Special Inspections.
5.1. General
Maintenance of the buildings and other structures at station is undertaken to keep, restore or improve every
facility to a currently acceptable standard and to sustain the utility and value of the facility in an operational
condition. In order to achieve the above, the type of repairs as a follow up of inspection can be classified as:
Day-to-Day repairs;
Periodic repairs;
Special repairs.
STATION LOCATIONS
CORRIDOR - 1 CORRIDOR - 2 CORRIDOR - 3
Code Station Names Code Station Names Code Station Names
R1 Miyapur G1 Parade Grounds B1 Nagole
R2 JNTU College G2 Secunderabad B2 Uppal
R3 KPHB Colony G3 Gandhi Hospital B3 Survey of India
R4 Kukatpally G4 Musheerabad B4 NGRI
R5 Balanagar G5 R.T.C Cross Roads B5 Habsiguda
R6 Moosapet G6 Chikkadapally B6 Tarnaka
R7 Bharat Nagar G7 Narayanguda B7 Mettuguda
R8 Erragadda G8 Sultan Bazar B8 Secunderabad
R9 G9 MG BUS Station B9
ESI hospital (Interchange station) Parade Grounds
R10 S.R Nagar G10 Salarjung Museum B10 Paradise
R11 Ameerpet (Interchange G11 B11
station) Charminar Rasool Pura
R12 Punjagutta G12 Shalibanda B12 Prakash Nagar
R13 Irrum Manzil G13 Shamshergunj B13 Begumpet
R14 G14 B14 Ameerpet (Interchange
Khairatabad Falaknuma station)
R15 Lakdi-Ka-Pul B15 Madhura Nagar
R16 Assembly B16 Yusufguda
R17 Nampally B17 Road No.5 Jubilee Hills
R18 Gandhi Bhavan B18 Jubilee Hills Check Post
R19 Osmania Medical College B19 Pedamma Temple
R20 MG BUS Station B20
(Interchange station) Madhapur
R21 Malakpet B21 Durgam Cheruvu
R22 New Market B22 Hi Tec City
R23 Moosarambagh B23 Shilparamam
R24 Dilsukhnagar
R25 Chaitanyapuri
R26 Victoria Memorial
R27 L B Nagar
Table 2: Station numbering
LOOK
AT FOR
All over General condition of the structure and pre-stressed components;
Condition of concrete;
Cracks;
Corrosion signs;
Scaling of concrete;
Spalling of concrete;
Efflorescence;
Condition of construction joints.
Dampness At all the external wall through visual inspection;
During rainy season;
Check for leaks due to rains;
Leakage/crack in the PHE pipes;
False ceiling check for sagging through visual inspection;
fix the screws;
Check for any loading at that area over the false ceiling and replace;
For gypsum tile it should be replace with a new one;
For the metallic tile, the same can be used;
Inspection to be done by-yearly.
False floor If tiles will come up re-fix the supports replace the same and place it properly;
Inspection to be done 6 monthly.
Information signs
These signs are used to guide road users along routes, inform them about destination and distance, identify
points of geographical and historical interest, and provide other information that will make the road travel
easier, safe, and pleasant. They are usually rectangular in shape.
Delineators
The delineators are the elements of a total system of traffic control and have two distinct purposes:
To delineate and guide the driver to and along a safe path
As a taper to move traffic from one lane to another.
These channelizing devices such as cones, traffic cylinders, tapes and drums shall be placed in or adjacent to
the roadway to control the flow of traffic. These should normally be retro-reflectors complying with IRC: 79 -
Recommended Practice for Road Delineators.
Barricades
Full height fence, barriers, barricades etc. shall be erected around the site in order to prevent the
working area from the risk of accidents due to speedy vehicular movement. Same the way barricades
protect the road users from the danger due to construction equipment and other temporary structures.
All barricades shall be erected as per the requirements of the works being carried out and in line with
Traffic Management Plan and maintained in good condition.
All barricades shall be conspicuously seen in the dark/night time by the road users so that no vehicle hits
the barricade. Conspicuity shall be ensured by affixing retro reflective stripes of required size and shape
at appropriate angle at the bottom and middle portion of the barricade at a minimum gap of 1000mm.
In addition adequate light or red light blinker shall be placed at the barricades.
Cones
Traffic cones of 500mm, 750mm and 1000mm high and 300mm to 500mm in diameter or in square shape at
base and are often made of plastic or rubber and normally have retro-reflectorized red and white band shall
be used wherever required.
Drums
Drums about 800mm to 1000mm high and 300mm in diameter can be used either as channelizing or
warning devices. These are highly visible, give the appearance of being formidable objects, and therefore
command the respect of drivers.
Working space:
The space around the works area that will need to store tools, excavated material, equipment, and plant. It
is also the space to allow workmen, movement and operation of plant, (e.g. swing of jibs, excavator arms) to
move around to do the job. Materials and equipment must not be placed in the zone either. Workmen will
only need to enter the zone to maintain cones and other road sign.
Safety zone:
The zone that is provided to protect workmen from the traffic and to protect from the hazards at that site.
The maintenance zone will be barricaded by red-reflectorized cones with white band and tying red cloth
or warning tape top of safety cone.
Flagman (refer Figure 8 Hand Signs) will be appointed at both sides start and end of the transition zone.
Gap between barriers (cones) shall be closed to redirect errant vehicles inside the safety zone.
No personnel are allowed to come out of the safety zone, unless flagman guidance.
First aid kit, water bag, communication service must be carried along with.
Pedestrian Walkway
Separate walk way will be identified at the site and barricaded on both the sides to avoid the traffic
incidents for the pedestrians, Lighting shall be provided adequately in pedestrians footpath frequent
monitoring shall be done through inspections.
Spoil Removal
Only well maintained and licensed appropriate vehicles shall be allowed to be used for the removal of
excavated spoil from the sites.
All drivers operating the appropriate spoil removal vehicles shall be medically fit and in possession of a
valid and current driving licence.
No vehicles, which are overloaded, shall be allowed to leave the site.
Any vehicles leaving the sites carrying loads which are liable to produce airborne contaminants shall
prior to leaving the site securely sheet the load over in order to effectively prevent disbursement during
transportation on the public highway.
Vehicles exiting the site directly onto the live carriageway shall do so under the control of the clearly
identified Traffic Controller.
Any vehicles that are required to reverse whilst on the site shall do so under the control of a trained
banks man.
Any vehicles prior to leaving the site shall have their wheels washed and any loose material removed.
Any spoil that is removed from the work-sites shall be disposed of only at authorised dumping sites.
Deflection checks to be carried out as per routine / detailed inspection schedules. The spine and wing shall
be inspected every six months and any excessive deflection more than L/250 for spine and L/150 for wing
(where L is length of span) due to live load, shall be recorded and monitored. For overall load any excessive
deflection more than 20mm shall be further investigated. Future prestressing ducts shall be used if any
prestressing is required. The root cause analysis shall be determined by thoroughly inspecting joints
between the spine and wings, corrosion of reinforcement, deterioration of concrete etc.
In case of excessive deflection, actual deflection shall be measured and compared with design values. The
deflection can be recorded by using a levelling instrument or theodolite. The points where the camber is
measured should be clearly marked on the underside of the girders so that the reading taken on different
years are comparable.
Normally, stressing can proceed on the indication elongation. In case elongation is reached and
corresponding jack pressure is not reached, stressing shall be continued up to 5% in excess of prescribed
elongation. In case jack pressured is reached and elongation in snot reached, stressing can be continued up
to a maximum jack pressure of 1.05 times the calculated pressure. Even in case of variation more than the
prescribed limits, then the matter shall be referred to the
Grouting of strands shall be carried out as per Appendix 5 of IRC-18-2000, thoroughly flushing the sheathing
with water.
Anchorages: any corrosion and cracks and ducts seating arrangement shall be monitored.
Proper inspection of the bearing in terms of measurement of dimensions, physical condition and inspection
of the adjacent structure help to determine the condition of the bearing. It should be ensured that the
bearing is free of dust and any other deposits or any foreign debris. The bearing may be cleaned with clean
water. Tools like brush and lenin cloth may be used for cleaning of the elastomeric bearing.
The bearings shall be subjected to well planned maintenance;
The exposed bearing surface shall be maintained clean and free from contamination like grease, oil and
other dirt;
Damaged bearing shall be replaced immediately to avoid difference in stiffness. All adjacent bearings on
the same line of support shall also be inspected for uniform seating of the main girders over all the
bearings. The decision for replacement of other bearing shall be taken by CSME;
Routine annual maintenance inspection or special maintenance inspection for all bearings shall be made
to check for any surface cracking or signs of damage, deterioration or distress;
Following are some points which indicate that the bearing is not functioning properly either due to damage
in the bearing or inadequacy in design etc.:
Peeling of Skin of the Elastomer
Steel Laminate Exposure
Separation of Cover
Back Lift of Contact Edge
Bulging Overlap
Evidence of Cracks/Splits
Partial Loss of Contact
Evidence of Creep Walk
The condition and replaceability of a bearing can be best ascertained by Professional Inspection of bearings.
Note-1: At most care should be taken while bearing replacement+ to avoid any compounded effect on the
station block wall. The block walls have expansion joint in line with concourse level deck to nullify the effect
of lifting during bearing replacement.
Note-2: The Elastomeric bearings are tested as per the IRC83 Part-1 and IS3400 Part-1 and Part-2.
Cleaning
The inspection should be preceded by thorough and careful cleaning of the bearings, depending on the
actual condition surrounding the bearings e.g. deposit of salt, debris, dust or any other foreign material.
Elements of Inspection
The following are recommended inspection elements and actions, which are considered necessary to
monitor and maintain the bearing:
a. Functioning properly
During inspection at site, it should be checked whether all the components of the bearings are functioning
satisfactorily. This check is more a judgment than measurement and requires an experienced eye. However
the overall malfunctioning may be easily detected by any unusual characteristic or physical property of the
bearing such as excessive movement, leakage/ damage of the elastomer, excessive rotation etc.
b. Measurement of dimensions
Overall dimensions of the bearings are required to be measured and compared with the actual dimensions
to ascertain any excessive stress or strain on the bearing.
c. Condition of the adjacent structures
The adjacent structure of the bearings is also required to be inspected for any damage and if found,
necessary actions to repair the same should be taken immediately.
Maintenance
Bearings are maintenance free due to its unique features and supporting quality assurance system and
thereby eliminate undesirable effects caused by extreme atmospheric or adverse environmental
condition and/or unforeseen events.
The surrounding area of the bearings should be kept clean and dry to avoid damage to the bearings.
The bearings should be thoroughly and carefully cleaned at least once in every year to ensure that there
is no deposit of salt and accumulation of debris, dust or any other foreign material on or adjacent to the
bearings. If the grout is damaged and/or cracked it should be replaced.
The following checks should be carried out for the expansion joints
Check if the joints are free of stones and any other debris.
Are there tears or separation to the continuous water barrier?
Are there any leaks or cohesive failure of the expansion joint system?
Are there loose cover plates, hardware or components?
Is there evidence of underlying substrata failure?
Are cracks present in the base concrete?
Check the gap and compare the movement with design values. Movement should not be more than
±20mm. Procedure of replacement & supplier details can be traced from the Station AMS. It may be
noted that the supplier of Expansion Joint for the station is M/s. Construction Speciality for the station
box and M/s. Mageba for Station Entry/Exit.
Vertical Cracks
Vertical cracks may occur due to differential settlement of the foundation or excessive shearing stresses in
the sub structure. The crack should be monitored regularly. If these show sign of propagation, a detailed
study should be made to identify the cause before taking remedial measures.
Horizontal Cracks
These are more serious and could be due to inadequacy of section, defect in construction, failure of back fill
drainage or excessive horizontal loads etc. the remedial measure should be decided after identifying the
6.2.5. Gutter
Gutter is a narrow channel, or trough, forming the component of a roof system which collects and diverts
rainwater shed by the roof at platform level. Roof gutters in stations are fabricated from Galvalume colour
coated plain sheet with 4mm thick FRP coated, which collects water from roof and diverts it through a PHE
pipe on to the street level sewer manhole.
Routine inspection should be carried out as per routine inspection regime, preferably including the end of
autumn, end of spring and extreme weather conditions. In the case of extreme events, inspection should be
carried out and abnormal maintenance carried out as required. All gutters are to be inspected for the
deposition of any debris, dust, pollutants or organic growth. In particular, care is to be taken in the
inspection of gutters for these points.
Staining of gutter at possible ponding locations;
Built up of dust and debris at the high end of gutter;
Built up of debris at rain heads, water spouts, and overflow locations and in general around the down
pipe entry;
Metallic staining of the gutter surface rust.
Twigs, dust, leaves and fungal matter (debris) should be removed using the following recommended
procedure, taking care to ensure no damage occurs to the gutter during debris removal. We recommended
that the following procedure be adopted to remove the dust, debris and fungal matter
Sweep debris into a pile using a stiff , soft bristled brush (shovels or hard tools should not be used;
Place debris into a receptacle and lower to the ground;
The Gutter should then be washed down with a hose, including high ends of gutters, possibly protected
by overhangs, rain heads, water spouts and overflow locations.
6.2.6. Tactile
Tactile at station box are provided to assist visually impaired people to find their way to train door, lift etc.
Tactile should be checked regularly for any damage. Tactile shall be replaced just like replacing a floor tile.
Supplier details of tactile are H & R Johnson (India), (A Division of Prism Cement Limited), Hyderabad.
It should be noted that solar panel are installed on the roof of station from Stage-2 onwards. As part of
maintenance of the solar panel, a water supply arrangement through fixed pipe is provided. It should be
ensured that the water pipe is not chocked and flow if water is regular or not obstructed. There is a walkway
provided on the roof sheet to access each solar panel. It should be ensured that the walkway is in good
working condition.
Insure that all maintenance personnel are adequately trained in safety procedures and that all safety
equipment is in proper working condition. When walking on unprotected roofing, soft soled shoes should be
worn and walking on at least two ribs, as close to supports as possible is recommended. Point heel and toe
The area where the curving of sheets will take place, the curved sheets will be temporarily stacked and the
current fixing locations on the roof will be barricaded at platform level, by providing crash barriers the
barricades and placing them wherever required. Only Authorized personnel will be carrying / moving in the
area for erection of the building. The phase / area which are to be erected will be barricaded for movement
/personnel at the site.
Full body harness will be Double Lanyard (2.5m) will be fixed to the life line. A second line of protection is
safety net will be installed below while working on the roofs. After the above safety precautions are taken
the sheets will be laid from the eave to ridge bay wise and then continue to move on.
The rolling shutter, doors and locks at staircases are to be maintained regularly for comfortable operation.
Check regularly for cracks, debris or any damages in the staircase. It is always recommended to treat any
cracks on the staircase, major or minor, as soon as they occur to minimize accidents.
8.2. Signage
Signage plays a vital role in the efficient operation of the metro stations. The metal which is used for signage
shall be free from rust, scale and any other defects, the various shapes and sections shall be clearly rolled or
otherwise formed to uniform sections. All non-metal shall have uniform finished surface, machined and
buffed, free from defects and conform to the sizes and shapes required. This is further detailed in MEP
manual.
8.3. DG Foundations
DG foundation is located at street level of the station. Inspection needs to be carried out on regular basis to
check whether any differential settlement has happened. Observe the cracks formed on the pedestal and
rectify before it develops. And the same applies for entry/ exit.
The Escalator pit may be inspection once in 3 months. The main issues to be looked into are the
accumulation of water and/or debris. The water may be pumped out immediately, especially during the
rainy seasons. Check for cracks and dampness in the walls and followed the instruction mentioned in table
below.
# Condition of Building Nature of repair Details of repair Initial of Building In- Remarks
Roof Doors/ Flooring/ Others to be done done with date charge/ occupant
windows plastering
Breadth
Name of Station
Name of Inspection Officer
The following points (but not limited to) may be inspected as part of structural steel inspection:
3 DG Foundation
(a) Monitor for any deep excavations in vicinity.
CONCOURSE LEVEL
7 Spine and Wing
(a) Check for cracks, spalls and scaling
(b) Check the condition of recess filling at end anchorages
9 RCC Corbel
(a) Check for cracks, spalls and scaling
10 Expansion Joint
(a) Check if the joints are free of stones and debris
o Stair Case-1 / 2 /3 / 4
o Elevator Shaft-1 / 2
o Escalator Support-1 / 2 / 3/ 4
15 Bearing
Please refer Annexure 2
17 Expansion Joint
(a) Check if the joints are free of stones and debris
20 Others
(a) Door
Door key is locking properly;
Handle is rigidly connected to the door;
The door organiser is smoothly working.
(b) Check for cracks and dampness in the block work
(c) Check for cracks and dampness in the RCC upstand wall
(d) Flooring, coping stone, tactile and skirting
- Check for breakage, cracks;
- Check for bulges in the tiles;
- Check for stain marks;
(e ) Cladding:
- Loose cladding;
- Crack in the cladding material;
- Sharp edges and stain marks
ROOF LEVEL
21 Structural steel elements:
- Check for corrosion and peeling of paint;
- Check for any loose member including nuts & bolts
or swaying of structure;
(a) Structural Steel roof member
(b) Roof sheeting
(c) Solar Panel
(d) Gutter
3 DG Foundation
(a) Check for settlement wrt floor levels
(b) Monitor any deep excavations in the vicinity
CONCOURSE LEVEL
7 Spine and Wing
(a) Check for cracks, spalls and scaling
(b) Check the condition of recess filling at end anchorages
(c) Monitor the propagation and expansion of cracks by
using Tell-tale pads or by measuring gauges (if any)
(d) Take floor levels & compare with actual readings
(e) Check for deflection for excessive deflection more than
L/250 for spine and L/150 for wing (where L is length of
span) due to live load, shall be recorded & monitored.
(For spine check at mid of span; whereas for wings
check at free ends)
8 Bearing
Please refer Annexure 2
9 RCC Corbel
(a) Check for cracks, spalls and scaling
(b) Monitor the propagation and expansion of cracks by
using Tell-tale pads or by measuring gauges (if any)
10 Expansion Joint
(a) Check if the joints are free of stones and debris
(b) Check the width of Gap at expansion joint with respect
to the tolerance limits (50mm + 20mm) preferably
during extreme weather conditions
(c ) Check for acts of vandalism
(d) Check for any missing parts
o Stair Case-1 / 2 /3 / 4
o Elevator Shaft-1 / 2
o Escalator Support-1 / 2 / 3/ 4
14 Others
(a) Windows:
Ensure the window frame is rigidly fixed to the
wall;
Ensure the glass of window is not cracked;
Ensure there are not protruding sharp edges;
Ensure the window organiser is working smoothly;
(b) Ventilators
Check the louvers are free of dust and rigidly
connected with its frame;
Ensure there are not protruding sharp edges;
Replace any broken louver.
PLATFORM LEVEL
15 Prestressed precast girder
(a) Check for cracks, spalls and scaling
(b) Check the condition of recess filling at end anchorages
(c) Take platform levels and compare with actual readings
(d) Monitor the propagation and expansion of cracks by
using Tell-tale pads or by measuring gauges (if any)
17 Slab (composite)
Check for cracks, spalls and scaling
Monitor the propagation and expansion of cracks by
using Tell-tale pads or by measuring gauges (if any)
18 Expansion Joint
(a) Check the width of Gap at expansion joint with respect
to the tolerance limits (50mm + 20mm) preferably
during extreme weather conditions
(b) Check for acts of vandalism
(c) Check for any missing parts
(d) Check if the joints are free of stones and debris
21 Others
(a) Door
Door key is locking properly;
Handle is rigidly connected to the door;
The door organiser is smoothly working.
(b) Check for cracks and dampness in the block work
(c) Check for cracks and dampness in the RCC upstand wall
(d) Flooring, coping stone, tactile and skirting
- Check for breakage, cracks;
- Check for bulges in the tiles;
- Check for stain marks;
(e ) Cladding:
- Loose cladding;
- Crack in the cladding material;
- Sharp edges and stain marks
ROOF LEVEL
22 Structural steel elements:
Entry/exits slabs,
Annexure-5, item- Annexure-6,
2 beams (Stair case Record P P P Visual/Detailed Length - 1320 - 10 132 15 E 0.25 0.5 - 33 66 - G
1b item-1 b
steps), column.
Details are mentioned in separate document for tools and plants (Annexure 7)
Annexure-5, item- Annexure-6,
4 DG foundation Record P P P Visual/Detailed Number of units 66 - - 10 7 15 E 0.25 0.5 - 2 4 - G
3 item-3
Maintenance W ork Instruction Routine Inspection Total Sample Required Man-hours per unit or per m Total Man-hours for
Detailed Special Tolerance
Title 1st 2nd Year Sample Basis of (1 = 60 minutes, 0.5 = 30 minutes) (1 cycle of Inspection) Personnel Source of
Inspection Inspection Maintenance Unit of Units / of
# Name Reference for Year onwards Number Length Area size Required category Tools Data [Hazard
Action Codes measure Length / Inspection Routine Detailed Special Routine Detailed Special
Inspection Item Routine Detailed Action Half Unusual of units (m) (m2) (%) Manhours (G, M.E) Analysis]
Area (± days) Inspection Inspection Inspection Inspection Inspection Inspection
Inspection Inspection Required year ly Year ly 5 Year s occur r ence
Details are mentioned in separate document for tools and plants (Annexure 7)
Annexure-5, item- Annexure-6,
21 Hand railings Record P P P Visual/Detailed Length - 11220 - 10 1122 15 E 0.25 0.5 - 281 561 - G
13 b item-13 b
Maintenance W ork Instruction Routine Inspection Total Sample Required Man-hours per unit or per m Total Man-hours for
Detailed Special Tolerance
Title 1st 2nd Year Sample Basis of (1 = 60 minutes, 0.5 = 30 minutes) (1 cycle of Inspection) Personnel Source of
Inspection Inspection Maintenance Unit of Units / of
# Name Reference for Year onwards Number Length Area size Required category Tools Data [Hazard
Action Codes measure Length / Inspection Routine Detailed Special Routine Detailed Special
Inspection Item Routine Detailed Action Half Unusual of units (m) (m2) (%) Manhours (G, M.E) Analysis]
Area (± days) Inspection Inspection Inspection Inspection Inspection Inspection
Inspection Inspection Required year ly Year ly 5 Year s occur r ence
Details are mentioned in separate document for tools and plants (Annexure 7)
Upstand wall on viaduct Annexure-5, item- Annexure-6,
38 Record P P P Visual/Detailed Length - 17820 - 10 1782 15 E 0.25 0.5 - 446 891 - G
deck 20 c item-21 c