ID Task Name Duration Start Finish 14 Jun '15 21 Jun '15 28 Jun '15 05 Jul '15 12 Jul '15

Start Finish 14 Jun '15 21 Jun '15 28 Jun '15 05 Jul '15 12 Jul '15 19 Jul '15 26 Jul '15 02 Au
S M TW T F S S M TW T F S S M TW T F S SM TW T F S SM TW T F S S M TW T F S S M TW T F S S M T
1 JD 1306 CONVEYOR STRUCTURE REPLACEMENT (RMH) 35 days? Tue 16-06-15 Mon 03-08-15
2 PROCUREMENT 14 days? Tue 16-06-15 Fri 03-07-15
3 BILL OF MATERIAL REPARATION 1 day? Tue 16-06-15 Tue 16-06-15
4 PURCHASE REQUSTION 1 day Thu 18-06-15 Thu 18-06-15
5 PURCHASE ORDER 1 day? Mon 22-06-15 Mon 22-06-15
6 MATERIAL DISPATCH TIME 9 days Tue 23-06-15 Fri 03-07-15
7 MOBILIZATION 2 days? Mon 06-07-15 Tue 07-07-15
8 MAN POWER ARRANGEMENT 1 day? Mon 06-07-15 Mon 06-07-15
9 MATERIAL SHIFTING TO SITE FROM YARD 2 days Mon 06-07-15 Tue 07-07-15
10 PRE FABRICATION 10 days? Wed 08-07-15 Tue 21-07-15
11 MATERIAL CUTTING & FABRICATING FRAMES & DECK PLATES 10 days Wed 08-07-15 Tue 21-07-15
12 FABRICATING HEAD DRUM STRUCTURE 5 days Wed 08-07-15 Tue 14-07-15
13 FABRICATING DRIVE BASE ,SNUB BASE SUPPORTED STRUCTURE 3 days Wed 08-07-15 Fri 10-07-15
14 SHIFTING FOR SAND BLASTING & PAINTING 2 days Mon 13-07-15 Tue 14-07-15
15 JOB INSPECTION 1 day? Wed 15-07-15 Wed 15-07-15
16 CONVEYOR DISMANTELING WORK 8 days? Mon 13-07-15 Wed 22-07-15
17 REMOVAL OF ELECTRICAL & CABLES , LIGHTS 1 day Mon 13-07-15 Mon 13-07-15
18 INSTRUMENTATION , PULL CORDS 1 day? Tue 14-07-15 Tue 14-07-15
19 CONVEYOR BELT REMOVAL 1 day? Wed 15-07-15 Wed 15-07-15
20 CONVEYOR STRUCTURE , DECK PLATES ,FRAMES & ROLLERS REMOVAL 4 days Thu 16-07-15 Tue 21-07-15
21 REMOVING HEAD DRUM STRUCTURE 3 days Mon 20-07-15 Wed 22-07-15
22 CONVEYOR ERECTION 9 days? Wed 22-07-15 Mon 03-08-15
23 ERECTION OF CHANNELS , VERTICAL ANGLES WELDING , DECK PLATES FIXING 3 days Wed 22-07-15 Fri 24-07-15
24 FRAMES FIXING , ROLLERS FIXING & COMPLETE BOLTING WORK 2 days Mon 27-07-15 Tue 28-07-15
25 ERECTION OF HEAD DRUM STRUCTURE , DRIVE BASE SNUB BASE SUPPORT STRUC 2 days Wed 29-07-15 Thu 30-07-15
26 CONVEYOR BELT ERECTION 1 day? Thu 30-07-15 Thu 30-07-15
27 TRAIL RUN OF CONVEYOR 1 day? Fri 31-07-15 Fri 31-07-15
28 FULL LOAD RUNNING 1 day? Mon 03-08-15 Mon 03-08-15

Project: Project1 Task Progress Summary External Tasks Deadline


Date: Fri 03-07-15 Split Milestone Project Summary External Milestone