National Consultative Workshop on Establishment of Caps on the

Recoverable Rate of Distribution System Losses

Segregation of
Distribution System Losses
Benguet Electric Cooperative (BENECO)

Engr. Melchor S. Licoben


Manager, CASD

A Technical Assistance Project of


the Asian Development Bank and the World Bank
to the Energy Regulatory Commission
PHILIPPINE MAP
CORDILLERA AUTONOMOUS REGION

KALINGA-APAYAO
BENGUET

Our Franchise
ABRA

PHILIPPINE MAP

MO UNTAIN PROVINCE

IFUGAO

BENGUET

National Consultative Workshop on Establishment of Caps on the


2
Recoverable Rate of Distribution System Losses
Scope of the Segregation study
BENGUET ELECTRIC COOPERATIVE COVERAGE BENGUET ELECTRIC COOPERATIVE COVERAGE

MANKAY AN MANKAY AN
BAKUN BAKUN
BULALACAO S/S

Substations KIB UNG AN


BUGUIAS
KIB UNG AN
BUGUIAS

ATOK S/S
KAPA NGAN KABA YAN KAPA NGAN KABA YAN

ATO K ATO K

TUBLAY TUBLAY
SABLAN LAMUT S/S SABLAN
IRISAN S/S LA TRINIDAD LA TRINIDAD
BOK OD BOK OD

BAG UIO CITY BAG UIO CITY


NPC BECKEL S/S

NSC S/S
ITOG O N ITOG O N

TUBA TUBA
Primary
NPC DALICNO LINE
Distribution

National Consultative Workshop on Establishment of Caps on the


3
Recoverable Rate of Distribution System Losses
BENECO STATISTICS (2003)
No. of
Customer Type % Sales
Customers
RESIDENTIAL + BAPA 92,956 89.784% 113,605,819
BIG COMMERCIAL 652 0.630% 30,753,566
SMALL COMMERCIAL 8,720 7.642% 35,599,451
HOSPITAL 31 0.027% 2,709,076
INDUSTRIAL 17 0.016% 2,717,678
WATER UTILITY 1 0.001% 6,298,923
MILITARY 118 0.113% 1,354,538
PUBLIC BUILDING 916 0.875% 23,027,146
STREETLIGHT 122 0.117% 1,743,550
TOTAL 103,533 217,809,747
National Consultative Workshop on Establishment of Caps on the
4
Recoverable Rate of Distribution System Losses
BENECO STATISTICS (2003)
Public
Residential Commercial Industrial Streetlights
Building
Average
Rate 4.0065 4.3665 4.2865 4.3065 4.3065
(P/kWh)
23 KV 13.2 KV 230 V
Total Circuit Kilometers
3645.8 1794.07 4600.96
Number of Employees 225
Sales per Employee 968043 kWh per year
Customer per Employee 460
System Loss 6.37%
(Underbilling Not yet Included)

National Consultative Workshop on Establishment of Caps on the


5
Recoverable Rate of Distribution System Losses
POWER SUBSTATIONS
 BENECO Owned
 Total Number of Substations -5
 Total Installed Capacity - 68.75 MVA
 Other Sources
 NPC/TRANSCO Owned S/S -2
 Total Installed Capacity - 50 MVA
 HEDCOR (Mini-Hydro)
 LUELCO (EC Distribution System)
 Total Installed Capacity - 128.75 MVA

National Consultative Workshop on Establishment of Caps on the


6
Recoverable Rate of Distribution System Losses
Total Technical
Segregated Losses
kWh % Loss
S/S Transformer Load Loss 107,240.10 0.0547
S/S Transformer No Load Loss 673.92 0.0003
Primary Line Losses 1,733,448.99 0.8836
Primary Service Drop Loss 176.46 0.0001
Distribution Transformer Load Losses 2,162,165.62 1.1022
Distribution Transformer No-Load
Losses 3,322,989.37 1.6939
Secondary Line Losses 3,855,401.95 1.9653
Service Drop Losses 1,807,622.89 0.9214
Total Losses 12,989,719.30 6.6214

Total Input Energy 196,176,943.42 (Tech)


National Consultative Workshop on Establishment of Caps on the
7
Recoverable Rate of Distribution System Losses
10 MVA Lamut Substation
kWh %loss
S/S Transformer Load Loss 21,055.11 0.0688
S/S Transformer No Load Loss 103.68 0.0003
Primary Line Losses 141,262.81 0.4613
Primary Service Drop Loss 0.00 0.0000
Distribution Transformer Load Losses 180,587.17 0.5898
Distribution Transformer No-Load
Losses 575,717.76 1.8802
Secondary Line Losses 543,713.52 1.7757
Service Drop Losses 135,410.36 0.4422
Total 1,597,850.41 5.2183

Input Energy 30,620,072.83


National Consultative Workshop on Establishment of Caps on the
8
Recoverable Rate of Distribution System Losses
10 MVA Irisan Substation
kWh %loss
S/S Transformer Load Loss 24,759.96 0.0734
S/S Transformer No Load Loss 103.68 0.0003
Primary Line Losses 328,143.91 0.9733
Primary Service Drop Loss 5.89 0.0000
Distribution Transformer Load Losses 321,259.82 0.9529
Distribution Transformer No-Load Losses 587,580.48 1.7429
Secondary Line Losses 609,552.62 1.8080
Service Drop Losses 142,670.14 0.4232
Total 2,014,076.50 5.9741

Input Energy 33,713,618.78

National Consultative Workshop on Establishment of Caps on the


9
Recoverable Rate of Distribution System Losses
20 MVA NSC SS T1
kWh % Loss
S/S Transformer Load Loss 17,582.62 0.0438
S/S Transformer No Load Loss 155.52 0.0004
Primary Line Losses 744,779.86 1.8566
Primary Service Drop Loss 147.40 0.0004
Distribution Transformer Load Losses 947,377.61 2.3617
Distribution Transformer No-Load
Losses 356,875.20 0.8896
Secondary Line Losses 511,385.35 1.2748
Service Drop Losses 267,775.58 0.6675
Total 2,846,079.15 7.0949

Input Energy 40,114,454.31

National Consultative Workshop on Establishment of Caps on the


10
Recoverable Rate of Distribution System Losses
20 MVA NSC SS T2

kWh % Loss
S/S Transformer Load Loss 39,087.59 0.0656
S/S Transformer No Load Loss 155.52 0.0003
Primary Line Losses 167,891.65 0.2819
Primary Service Drop Loss 23.18 0.0000
Distribution Transformer Load Losses 497,041.70 0.8345
Distribution Transformer No-Load Losses 876,994.56 1.4724
Secondary Line Losses 1,649,128.57 2.7688
Service Drop Losses 710,579.27 1.1930
Total 3,940,902.04 6.6165

Input Energy 59,561,483.41

National Consultative Workshop on Establishment of Caps on the


11
Recoverable Rate of Distribution System Losses
5 MVA Atok Substation
kWh % Loss
S/S Transformer Load Loss 3,434.31 0.0497
S/S Transformer No Load Loss 77.76 0.0011
Primary Line Losses 230,995.35 3.3399
Primary Service Drop Loss 0.00 0.0000
Distribution Transformer Load Losses 43,924.52 0.6351
Distribution Transformer No-Load Losses 284,886.72 4.1191
Secondary Line Losses 45,185.23 0.6533
Service Drop Losses 12,140.58 0.1755
Total 620,644.48 8.9736

Input Energy 6,916,318.08

National Consultative Workshop on Establishment of Caps on the


12
Recoverable Rate of Distribution System Losses
3.75 MVA Mankayan Substation

Total % Loss
S/S Transformer Load Loss 1,320.50 0.0368
S/S Transformer No Load Loss 77.76 0.0022
Primary Line Losses 7,455.90 0.2079
Primary Service Drop Loss 0.00 0.0000
Distribution Transformer Load Losses 25,354.69 0.7069
Distribution Transformer No-Load Losses 171,175.68 4.7725
Secondary Line Losses 14,822.58 0.4133
Service Drop Losses 9,311.99 0.2596
Total 229,519.10 6.3991

Input Energy 3,586,719.08

National Consultative Workshop on Establishment of Caps on the


13
Recoverable Rate of Distribution System Losses
20 MVA NPC Beckel Substation
kWh % Loss
S/S Transformer Load Loss 0.0000 0.0000

S/S Transformer No Load Loss 0.0000 0.0000


Primary Line Losses 112,414.95 0.5547
Primary Service Drop Loss 0.00 0.0000
Distribution Transformer Load Losses 133,708.20 0.6597
Distribution Transformer No-Load Losses 437,840.64 2.1604
Secondary Line Losses 393,572.70 1.9420
Service Drop Losses 523,866.67 2.5849
Total 1,601,403.16 7.9017

Input Energy 20,266,650.83

National Consultative Workshop on Establishment of Caps on the


14
Recoverable Rate of Distribution System Losses
30 MVA Dalicno Substation
kWh % Loss
S/S Transformer Load Loss 0.0000

S/S Transformer No Load Loss 0.0000


Primary Line Losses 504.55 0.0361
Primary Service Drop Loss 0.00 0.0000
Distribution Transformer Load Losses 12,911.90 0.9238
Distribution Transformer No-Load Losses 31,918.32 2.2838
Secondary Line Losses 88,041.38 6.2994
Service Drop Losses 5,868.32 0.4199
Total 139,244.46 9.9629

Input Energy 1,397,626.11


National Consultative Workshop on Establishment of Caps on the
15
Recoverable Rate of Distribution System Losses
Summary of Technical Losses
Rank Energy loss % loss Rank

20 MVA NSC SS T2 1 3,940,902.04 6.6165 5


20 MVA NSC SS T1 2 2,846,079.15 7.0949 4
10 MVA Irisan Substation 3 2,014,076.50 5.9741 7
20 MVA NPC Beckel
Substation 4 1,601,403.16 7.9017 3
10 MVA Lamut Substation 5 1,597,850.41 5.2183 8
5 MVA Atok Substation 6 620,644.48 8.9736 2
3.75 MVA Mankayan
Substation 7 229,519.10 6.3991 6
30 MVA NPC Dalicno
Substation 8 139,244.46 9.9629 1

National Consultative Workshop on Establishment of Caps on the


16
Recoverable Rate of Distribution System Losses
Segregated Distribution System Losses
(98% of System)
 Total Energy Input (Purchased)
 211,074,082 kWhr
 Total Energy Sales
 196,176,943 kWhr
 Total Distribution System Losses
 14,897,139 kWhr (7.06%)
 Total Technical Losses
 12,989,719 kWhr (6.15%)
 Total Non-Technical + Administrative Loss
 1,907,420 kWhr (0.91%)
National Consultative Workshop on Establishment of Caps on the
17
Recoverable Rate of Distribution System Losses
Lessons Learned

 Importance of Data Gathering, Encoding, Maintenance


 techniques in data gathering, encoding, correction and
maintenance are being developed as we go along
 importance of the utilization of the data gathered were
realized especially in the analysis of the distribution
system
 improved understanding of the distribution system
 The Segregation of Distribution System Loss should not
only be taken as a regulatory requirement but also as an
opportunity to further improve the DX system.
 Data requirements may be difficult at the beginning but
the expected output will bring positive results.

National Consultative Workshop on Establishment of Caps on the


18
Recoverable Rate of Distribution System Losses
Next Steps
 Complete the remaining areas not covered in the
study. We were only able to cover 98%.
 Go Back and validate the Distribution Database.
Check for inaccuracies.
 Submission of data requirements to the Energy
Regulatory Commission
 Implement a more detailed loss reduction
program based on the segregated DSL: i.e.
 Sizing of transformers
 Sizing of Secondary conductors
 Etc.

National Consultative Workshop on Establishment of Caps on the


19
Recoverable Rate of Distribution System Losses
Conclusion

 The Segregation of DSL must be pursued


especially for the Distribution Utilities so that the
operational efficiency envisioned by RA 9136 will
be achieved.

 BENECO is now comfortable that we can meet the


ERC requirements if the Guidelines will be
promulgated.

National Consultative Workshop on Establishment of Caps on the


20
Recoverable Rate of Distribution System Losses
A Technical Assistance Project of the Asian Development Bank
and the World Bank to the Energy Regulatory Commission

National Consultative Workshop on Establishment of Caps on the


21