Académique Documents
Professionnel Documents
Culture Documents
SBI 189
Insulation – moisture protection, acoustics, fire resistance, ventilation and strength.
2nd EDITION
SBI-DIRECTION 189 STATENS BVGGEFORSKNINGSINSTITUT 1999
Attic Attic
a) b)
c)
d) e)
f)
Figure 2. The stability of the house is ensured by anchoring the various structural elements to
each other. The roof trusses must be braced to prevent them from cascading (a) and anchored
against horizontal forces (b) and upward-acting forces (c). The walls must be supported at the
top by the ceiling diaphragm (d), and this must be able to transmit horizontal forces to the wind-
bracing walls. In ome cases, the walls must also be anchored at the bottom to prevent sliding (e)
and collapse or lifting (f)
Stabilising system
The central parts of the stabilising system are
the bracing walls and the so-called ceiling
diaphragm . Some important terms are
indicated on figures 3 and 4.
The ceiling diaphragm supports the external
Longitudinal
walls at the top and furthermore transmits wind action Facade
horizontal forces from the roof including the
gable triangles. The ceiling diaphragm must
be able to transmit these forces to the bracing Figure 4. Wind acting along the house: The
walls, which may be internal walls as well as facades and the internal longitudinal walls
external walls. Consequently, the ceiling may act as bracing walls.
diaphragm must be fixed to all external walls
and to the internal bracing walls. Further, the
ceiling diaphragm must be sufficiently stiff in
order to secure that forces can be distributed
to the braced walls without causing fatal
deformations, see figure 5.
The stabilising system must be able to
transmit the forces to the foundation or floor Wind
slab. This will often require a protection
against sliding and /or anchoring against
upward-acting forces on the walls
In addition, the roof construction itself must
be braced and anchored to prevent failure as Figure 5. The ceiling diaphragm shall be
shown in figures 2a-2c. Failure as shown in adequately strong and rigid in order to
figure 2c is caused by the considerable lifting distribute the wind action to the bracing
force occurring as a result of the longitudinal walls.
wind (along the roof).
SBI Direction 189
SBI Direction 189
KLJ 13
Translation KLJ
9
Dimensioning and design The chapters concerning the specific
The dimensioning of load bearing and construction elements give examples of
stabilising structures usually requires the designs with sufficient strength to transmit the
assistance of an engineer. Enclosures A and D forces.
can be used to assist when dimensioning. Enclosure D, Stabilising system describes
Enclosure A, Loads, gives loads used in how the stabilising system in 1-and 1½ storey
dimensioning structural elements affected by single length houses with pitched roof can be
vertical action perpendicularly to their plane. designed and dimensioned.
Level of topsoil
Level of topsoil Level of topsoil
excavation
excavation excavation
Excavation
trench
profile
Figure 6
Figure 7
Foundation at ground supported floor.
Foundation at crawl space. Often a concrete
Normally in situ cast concrete as a deep strip
pad is cast in situ (cross-hatched in the
foundation is used (cross-hatched in the
figure) and the crawl space wall is then
figure). The upper part is often built using
constructed using clinker concrete blocks or
clinker concrete blocks. Hollow concrete
hollow concrete blocks cast with concrete.
blocks may also be used especially where the
The wall can also be cast fully or partly in
topsoil excavation level is below the topside
situ, i.e. to the topsoil excavation level. The
of the deep strip foundation, thus avoiding the
foundation shall have at least the same width
use of formwork for casting the upper part of
as the wall above, and it should be
the foundation. The foundation shall have at
symmetrically placed below this.
least the same width as the wall above and
should be symmetrically placed below this.
The figure also shows the placement of a
perimeter drain and a branch drain, which
connect the capillary breaking layer beneath
the floor with the perimeter drain. It is not
necessary to connect the branch drain
directly to the perimeter drain.
SBI Direction 189 15
Translation KLJ
SBI Direction 189,
KLJ 11
Figure 8
Foundation at basement. Usually a concrete
pad is cast in situ (cross-hatched in the
figure) and the basement wall is then built
using clinker concrete blocks or using hollow
concrete blocks cast with concrete.
Alternatively, the entire wall can be cast in
situ. The foundation pad shall have at least
the same width as the basement wall and it
should be symmetrically placed below it.
The figure also shows the placement of a
perimeter drain and a branch drain which
connect the capillary breaking layer under
the floor with the perimeter drain.
Table 2 Dimensions of deep strip foundation under walls in small single length houses. The
dimensions given require that the width of the house is less than 9 m.
SBI Direction
SBI Direction189,
189 17
Translation KLJ
KLJ 13
The dimensions are valid for traditional single see paragraph on concrete. Internal wall
length houses that is, houses with load- foundations in houses with ground supported
bearing facades and possible load-bearing floor shall only be taken down to load bearing
longitudinal walls placed close to the centre subsoil, as they will not be exposed to frost
line of the house. (due to the temperature conditions under the
house).
Deep strip foundations shall have at least the If the oversite excavation level is lower than
same width as the wall above and should be the topside of the deep strip foundation the
placed symmetrically beneath this. In houses upper part of the foundation can be cast using
with basement where the foundation is used formwork. Alternatively hollow blocks of
as abutment for the concrete slab in the concrete or clinker concrete as well as
basement floor, the foundation shall be at massive clinker concrete blocks may be used..
least 0.10m wider than the basement wall. The hollow blocks are stacked on the strip
This will usually be fulfilled if the width is foundation with tight joints and bonding.
chosen to 0.50m. When casting no more than two courses must
Non load-bearing internal walls can usually be cast at one time using 5 or better. The
be founded directly at the floor deck concrete concrete is carefully compressed with
slab. The maximum linear and point loads, immersion vibrator. Horizontal construction
which can be transmitted, depend on the joints shall be placed along the centreline of
concrete slab and the insulating material. the blocks. Solid clinker concrete blocks are
Reference is made to product catalogues from laid with filled joints using mortar KC
the insulation manufacturers . Alternatively 20/80/550 or better according to the “Code of
non load-bearing internal walls can be practice for the Structural Use of Masonry”
founded on top of the capillary breaking (DS 414) .
layer, see figures 19 and 21 on pages 27 and When oversite excavation reaches deep down
28. it might be expedient to build the entire
If bracing walls are not founded as load- foundation of hollow blocks on top of a
bearing walls one must ensure that the vertical concrete blinding.
reaction can be absorbed by the bed on which The underside of the foundation shall be
the wall is resting (e.g. concrete slab). horizontal. Stepping shall be carried out as
shown in figure 9.
Workmanship Where service lines are taken across the
Foundation work starts by excavating an area foundation, the foundation must be carried out
similar to the geometry of the building - for according to figure 10.
example to a level corresponding to the upper
side of the deep strip foundations (see figures
6, 7 and 8). However, topsoil must be
Max.
removed to a depth where the stratum is no 0.60m
longer weak and compressible (removal of
layers containing organic material). Hereafter
commences the excavation of trenches for the
foundation according to dimensions (widths Max. Slope 1:1
SBI Directive
SBI Direction189
189 21
KLJ
Translation KLJ
17
(manholes) and inspection junctions (the latter the tools used for cleaning may have
with a diameter of minimum 300 mm) must difficulties in passing bends without the risk
be established at selected bends and on level of damaging the pipe. As a consequence all
stretches at intervals not exceeding 60 m. bends must be accessible for cleaning from
Figure 12 shows some examples of placement two sides via inspection junctions. Surface
of inspection junctions in a drainage system. water must not be drained directly to the
When placing inspection junctions drainage system. It is, however, permitted to
considerations must be given to the fact that drain the insignificant amount of rainwater
from light shafts or covered external
basement stairways directly to a perimeter
drain. It is not necessary to ventilate drainage
systems.
Drainage
Drained water is usually discharged to a waste
water installation. The connection shall be
made to a 300 mm gully at least 0.2 m above
the water level. The gully must have a sand
trap, a gully trap and a rain water inlet. Also,
the connection level must lay above the
highest damming level in the main sewer
system with the addition a safety factor of
Figure 12 Example of placements of 0.3m. This type of “direct” connection must
inspection junctions in a drainage system.
Plot
Filter cloth boundary
Figure 13 Fascines shall be placed inside the property boundary and at least 2 m away from any
boundary line. Furthermore, they shall be placed at least 25 m away from drinking water wells,
inspection chambers and the like. The distance from the centre line of the fascine (longitudinal axis)
and from the fascine extremities to domestic houses shall be at least 5 m. Fascines are build as 0.4-
0.5 m wide stone-filled trenches with a horizontal bottom. Stones to be used could be 32/64 mm
washed course gravel covered with filter cloth and a layer of soil of at least 0.3-0.4 m. The volume
of a fascine in clay soil can be determined at 1 m3 per 30 m2 rain area. When constructing fascines
of a considerable size it must be considered to establish a distribution pipe. Before connection to
the fascine the rainwater shall pass a sand trap. Maintenance of fascines is the sole responsibility of
the proprietor .
SBI Directive
SBI Direction189
189 22
KLJ
Translation KLJ
18
only be carried out provided the whole
drainage system is situated above the
maximum damming level of the waste water
installation in order to prevent pollution of the
drainage system. In cases where these
conditions can not be fulfilled the connection
must be made through a pump well. When the
outlet from the pump well is situated less then
0.2 m above maximum damming level it must
be supplied with a retention valve.
Fascines
Whenever building as well as soil conditions
are considered appropriate, the authorities
may approve the discharge of water from
roofs, smaller paved areas and drainage water
directly into a fascine for percolation. For
detailed design we refer to “Code of Practice
for smaller drainage disposal systems for
percolations into the ground” (DS 440)
SBI Directive
SBI Direction189
189 23
KLJ
Translation KLJ
19
Light weight clinker floor blocks or
Ground supported floors polystyrene insulation slabs resting on a
A ground supported floor is a floor
levelled gravel surface
construction resting directly on the ground.
The thickness of the capillary breaking layer
Ground supported floors shall be insulated
shall be at least 150mm.
against ingress of moisture and loss of heat.
Also they shall be sufficiently sealed in order
Heat insulating layers
to prevent the ingress of air containing radon
Insulating material shall be pressure-resistant
(from the subsurface). In the “Heat loss
and may consist of for example coated loose
frame” (see chapter on Thermal Insulation)
light clinkers, floor blocks, pressure-resistant
ground supported floors assume the U-value
mineral wool batts, or polystyrene slabs.
0.20 and in case of floor heating 0.15.
Concluding: Some materials can be both
A domestic ground floor is usually
capillary breaking and heat insulating.
constructed as follows: At the bottom a
capillary breaking layer preventing the
Concrete slab
absorption of ground moisture into the floor
The slab should be cast in minimum 100 mm
construction. This layer is followed by a heat-
thickness using concrete 15 or better, see
insulating layer and next a so-called load
page 19. Shrinkage reinforcement should be
distributing layer usually in the form of a
used, for example 5 mm reinforcement mesh
concrete slab cast in situ, and finally a floor
with 150 mm grid placed in the middle of the
finish. When the floor finish is a joist floor, a
slab.
minor part of the heat insulation can be placed
When casting the slab the concrete must
on top of the concrete slab. Apart from the
either have a plasticity which prevents it from
floor finish all materials used in the
penetrating the underlying layer, or it must be
construction of the domestic ground floor
cast on top of a diffusion open underlay for
must be non sensitive to moisture.
example filter cloth.
An extensive treatment of questions
Immediately upon casting the concrete shall
concerning moisture in ground supported
be protected against drying up by covering it
floors can be found in “SBI Directive 178 -
with a vapour tight membrane, for example
The moisture insulation of buildings”.
polyethylene foil. It should remain covered
for app. 8 days.
Ground conditions
Ground supported floors shall rest on a strata
Floor finishes
of subsoil which as a minimum fulfils the
When using moisture sensitive floor finishes,
requirements applying to the level of oversite
such as wooden floors on joists or floating
excavation, mentioned on p. 18. If this level is
floors containing wood, a damp proof
deeper than the underside of the capillary
membrane must always be placed on top of
breaking layer the remaining gap must be
the concrete slab as the slab will emit
filled with replacement material such as sand
construction moisture for a considerable
or gravel which is filled in gradually using
period of time after casting.
watering and compacting (with a plate
A 0.15 mm polyethylene foil is suitable as a
vibrator).
damp proof membrane. It must, however, be
laid with an overlap of at least 200-300 mm.
Capillary breaking layers
When using wooden floors on joists, the joists
Capillary breaking layers may consist of :
must rest on blocks preventing the rising of
Pebbles, shingles or gravel with a minimum
moisture, for example adjustable plastic
grain size of 4 mm;
wedges used in pairs of two. Part of the
Coated, loose light clinkers (expanded fired
insulation material can be placed on top of the
clay) with a grain size of 10-20 mm;
SBI Directive
SBI Direction189
189 24
KLJ
Translation KLJ
20
concrete slab. In doing so, a softer insulation
material may be used. This reduces cost and Concrete slab with wooden joist floor
also reduces the total thickness of the ground Wooden floor on joists. Damp proof
membrane
supported floor. In order to avoid Concrete 100 mm
condensation on the top side of the damp Loose light clinkers, coated
Loose light clinkers λ-class 80, 260 mm
proof membrane, the major part of the Loose light clinkers λ-class 100, 320 mm
insulating material must be placed below the
concrete slab.
Radon-proofing
When the atmospheric pressure decreases
radon rises from the soil together with air.
The pressure differences in question are up to
0.1 atmospheres and consequently the ingress
of radon can only be avoided by equalising
pressure in the capillary breaking layer with
the outside pressure. Simultaneously to this Figure 14 Ground supported floor:
the ground supported floor must be made as Concrete slab with wooden joist floor placed
airtight as possible. The concrete slab is on a capillary breaking and heat-insulating
considered airtight but it is necessary to layer of loose light clinkers. The layer
secure tightness along the foundation as thickness required to achieve the U-value
indicated in figures 18, 19, 20 and 21. 0.20 depends on the l-class of the light
Equalising pressure of the capillary breaking clinkers.
layer can be achieved by the use of a branch
drain connected to the perimeter drain, as
described in the chapter “Drainage”. Concrete slab with wooden joist floor
Wooden floor on joists. Damp proof membrane
Concrete 100 mm
Examples of ground supported floors Pressure resistant insulation, λ-class 39, 125 mm
The figures 14, 15, 16 and 17 show examples Shingels capillary breaking layer, 150 mm
SBI Directive
SBI Direction189
189 25
KLJ
Translation KLJ
21
bitumen felt as shown in figure 19.
Concrete slab with wooden joist floor Consequently, the constructions in figures
Wooden floor on joists. 18 and 20 are only radon proof provided
Mineral wool , λ-class 39, 50 mm the inner leaf is adequately airtight – also
Damp proof membrane
Concrete 100 mm where it meets the concrete slab.
Loose light clinkers, coated Figure 21 shows how a stud wall can be
Loose light clinkers λ-class 80, 150 mm
Loose light clinkers λ-class 100, 200 mm connected to a ground supported floor.
Tightness against radon ingress requires a
tight connection between concrete slab and
wall, for example by the use of bitumen felt
adhered to concrete slab and to internal
wall surface.
Alternative solutions, which differ
Figure 16 Ground supported floor: Concrete significantly from the ones shown here can
slab with wooden joist floor placed on a be found in SBI Directive 184 “The heat
capillary breaking and heat-insulating layer loos of buildings and U-values”
of loose light clinkers. The layer thickness The figures 18-21 show examples of the
required to achieve the U-value 0.20 depends construction of load-carrying and non
on the l-class of the light clinkers load-carrying internal walls on ground
A wooden floor is very sensitive to moisture supported floors. Figures 19 and 21 show
and a damp proof membrane must therefore non load-carrying internal walls founded
always be placed on top of the concrete slab, on the capillary breaking layer. Often it
as the concrete emits moisture in a will be possible to place these directly on
considerable period of time after casting. To the concrete slab as shown in figure 20 and
avoid condensation on the topside of the mentioned on page 18.
damp proof membrane the major part of the Foundations shall be so constructed that no
insulation material must be placed below the damage can occur as a result of ground
concrete slab. moisture. This is normally secured by
rendering foundation blockwork on the
Concrete slab with thin floor finish
outside (150 mm below ground level) and
Thin floor finish plastering the uppermost 150 mm (the
Concrete 100 mm
Pressure resistant insulation, λ-class 39, 75 mm
visible part).
Loose light clinkers, coated
SBI Directive
SBI Direction189
189 26
KLJ
Translation KLJ
22
Figure 18 The cold bridge through the upper part of the foundation (a) is broken by the use of
clinker concrete blocks with an insulating layer in the middle. Radon penetration is avoided by
suspending bitumen felt across the edge insulation groove and bonding it to the concrete slab. In
cases where the inner leaf will be treated with a surface coating making it radon tight the
bitumen felt can taken up along the wall - overlapping the surface coating- and bonded to this.
(shown with a dotted line). The figure also shows a load-carrying (b) and a non load-carrying
internal wall (c). Bitumen felt under the internal walls is bonded to the concrete slab.
Figure 19 The cold bridge through the upper part (a) of the foundation is broken by an insulating
layer between two clinker concrete blocks in the topmost course. Radon penetration is avoided by
suspending bitumen felt across the edge insulation groove and bonding it to the concrete slab. The
figure also shows a load-carrying (b) and a non load-carrying internal wall (c). The latter is founded
directly on the capillary breaking layer, see page 18. The foundation under the load-carrying internal
wall is taken to the topside of the concrete slab and the damp proof course is bonded to the concrete
slab.
SBI Directive
SBI Direction189
189 27
KLJ
Translation KLJ
23
Figure T1.
Placing of door at the
external foundation as in
figure 18 (p. 27).
The concrete slab in the
ground supported floor
must be extended and the
topmost clinker block must
be changed along the door
opening. Sealing against
radon penetration is done
by the use of bitumen felt,
which is extended into the
door opening. Additional
floor joists are added in the
door opening depending
on the orientation of the
joists
Figure T2
Placing of door at the
external foundation as in
figure 19(p. 27).
The concrete slab in the
ground supported floor must
be extended and the topmost
clinker block must be
changed along the door
opening. Sealing against
radon penetration is done by
the use of bitumen felt, which
is extended into the door
opening.
SBIDirection
SBI Directive189189 27A
KLJ
Translation KLJ
24
Figure 20 The cold bridge through the upper part of the foundation (a) is broken by the use of clinker
concrete blocks with an insulating layer in the middle. A damp proof membrane on the topside
protects moisture sensitive parts of the floor construction. Casting the concrete slab on top of the
foundation secures against the penetration of radon along the foundation. In case the internal leaf is
not radon tight , an additional layer of bitumen felt should be inserted (as indicated with a dotted
line). The figure also shows a load-carrying (b) and a non load-carrying internal wall (c). The latter is
founded directly on the capillary breaking layer, see page 18.
Figure 21 The cold bridge through the upper part of the foundation (a) is broken by the placing of an
insulating layer inside the foundation. In this way the insulation in wall and floor is connected. Radon
penetration along the foundation is avoided by bonding a strip of bitumen felt to the concrete slab and the
wall. The figure also shows a load-carrying (b) and a non load-carrying internal wall (c). The latter is not
always founded directly on the capillary breaking layer.
SBI Directive
SBI Direction189
189 28
KLJ
Translation KLJ
25
Crawl space Fire demands
The floor (deck) over the crawl space, be-
The normal height for a crawl space ranges cause it can be used for storage, must fulfill
from 0,6-0,8 m. The purpose of a crawl space the same fire demands for a floor over a
is to obtain a distance from the ground to the basement (BD 60 for 1 '/4 + 2 storey houses).
ground floor, to prevent contact with ground
moisture. See figure 22. A crawl space must U-value
be protected from ground moisture and sur- The deck over a crawl space must fulfill the
face water. heat frame demand of U-value 0,20.
Figure 22
Crawl space deck construction can be of prefabricated light weight slab with 100 mm insulation
bonded to the underside. The outside edge of the slabs by the external walls, should be insulated in
between the external leca blocks, to prevent thermal loss (cold bridge).
The timber floor construction over the slab must be protected from building component moisture
with a 0,15 mm polythylen DPM, laid on the slab. 75 mm extra insulation is laid on the DPM to
prevent condensation on the overside of the DPM.
80-100 80-100
Figure 24
The vents in the crawl space walls must be placed 80-100 mm over the ground and end under the
crawl spaces deck (under side floor). A horizontal vent channel through the external wall can
cause the ground floor level to lie too high over the ground. This distance can be reduced, if the
vent channel is bent down and inwards. If so the channels cross section should be increased min.
50%.
The casting of the wall should be done at one The rest of the external side of the wall mus'
time, the concrete must be compressed care- be coated with bitumen. The same for walls
fully with vibrator. cast in concrete 10.
Holes and indentations must be repaired with Filling out at the external wall must not be
cement mortar 1:3. started before the crawl spaces floor is cast
To be sure of the walls stability, because of and internal cross walls are constructed. If a
ground pressure, see max. wall size page 38. 4 sided supported wall is implemented then
The house must also be stabilized against the deck over the crawl space must be con-
wind suction, with casting of anchors in the structed.
crawl space external wall or foundation, if the
walls are constructedwith leca blocks. The Internal walls
crawl space's external walls must be moisture Internal walls in crawl spaces are normally
resistant. The walls of blocks must be rough constructed in concrete foundation blocks,
rendered in the full height and then fine leca blocks, light weight concrete. The walls
rendered on the visible part over ground level must be a minimum thickness of the load
and 150 mm under ground level. bearing walls above.
Timber joists
For joists dimensions, see page 41. To
obtain a U-value of 0,20, the joist con- Mineral wool 39, 150 mm between joists
struction must be insulated with approx. Stiff, wind resistant mineralwool boards 36, 75 mm
Fixed under joists
200 mm mineral wool. Approx. 1/3 of the
insulation shall be placed under the joists to U = 0,18
prevent moisture concentration. The insula-
tion must be fixed carefully so that air cur- Figure 25
rents do not penetrate the joints. The deck 1/3 of the insulation placed under the joists.
must be wind resistant so that draughts are Reduce the insulation thickness between the
prevented from the floor. This can be done joists to 125 mm, increases the U-value to
by placing a DPM under the floor boards 0,20.
and fixing it at the back of the skirting
board. This will also prevent radon expo-
Wet room with concrete slab cast in situ
sure. Floor tiles laid in mortar
The floor joist construction must be insu- Concrete slab with/without heated floor
lated against moisture at the walls by laying
a DPC of bitumen felt between the walls
and timber.
The ends of the joist in the external wall and
the joist sides by the external wall must be
coated 2 times with timber impregnation
paint.
Figure 25 shows an example of a timber
joist construction, and figure 26 shows an
example of a concrete slab under a wet
room.
Figures 27 and 28 show examples of con-
nections between joists and external walls.
To limit the joists height it is normal to use a
height of 150 mm as shown in figure 25. Pressure resistant insulation, 30 mm
This will reduce the max span of the joists, Concrete slab
therefore extra load bearing walls will be Insulation X-kl.36, 150 mm
fixed mechanically U = 0,19
constructed in the crawl space. Foundations
dimensions from table 2, page 17 can be
reduced to the half of the given sizes though Figure 26
min. 0,15 m. Crawl space deck constructed with timber
joists and concrete slab under a wet room.
To keep the timber joists from the wet room,
they are load bearing on brick piers.
For dimension of concrete slab cast in situ, In this case a layer of insulation max. 75 mm
see page 42. Leca concrete deck can be can be placed over the DPM to prevent
developed in standard size and load bearing condensation forming on the overside of the
capacity. DPM.
To obtain a U-value of 0,20 the concrete and Figure 29 is an example of a leca concrete
leca concrete must be constructed with with insulation cast on the underside. Figure
insulation, 175 - 200 mm depending on the 30 is an example of a wet room floor
slabs own insulation ability. construction on a leca beton slab. An example
With timber floor boards on battens or other of the connection between slab and wall is
sensitive floor coverings a DPM must always shown in figure 31. The figures 32 and 33 are
be laid on the overside of the concrete deck details of external door and slab construction.
for protection against building component
moisture.
Figure 29 Figure 31
Crawlspace deck of leca concrete Leca concrete component deck as show
component with insulation. Only a minor in
part of the insulation must lay over DPM. figure 22. The deck construction isplaa
as low as possible in connection to the
ground level, approx. 150 mm underflow
level.
If the level between in and out should be
reduced even more, a trench could be
established along the external wall.
Figure 30
Wet floor construction on leca
concrete components see page 29. If an
extra 50 mm insulation is fixed on the
underside of the deck a U-value ofO, 18
can be obtained.
Or to fulfill the heat loss frame the extra
50 mm insulation can be placed on another
building component.
Dimension
Figure 35 The soil pressures forces on the basements
Concrete slab basement floor with separate external walls, as a rule will only be sup-
insulation and capillary gravel layer ported along 3 sides, the bottom side and
two vertical sides, see figure 34; A basement
deck of light weight concrete with correct
construction detailing together with the
basement walls, for example with
reinforcement to compensate for the weak-
Concrete basement floor
100 mm concrete ened construction due to the cavity wall, can
Plastic membrane to prevent radon be classed as a 4-sided supported con-
250 mm Ieca modules Wcl.80 U = 0,20 struction. Basement walls or non-reinforced
concrete cast in situ (concrete norm 5.55)
can be constructed in sizes given in table 4.
3-sided 10 m2 13,3 m2
4-sided 15 m2 20,0 m2
I.,,
U = 0,28
Figure 37 Figure 38
For a 3-sided supported basement external External basement wall of concrete and ex-
walls the max area is decided with hxl where ternal insulation. Insulation with drain chan-
h is the height of the forces from the earth nels, if a non-drained insulation is imple-
pressure and I is the distance between the mented. The basement wall must be moisture
cross walls, t is the walls thickness. insulated.
overlapping the external insulation, see figure 34. Deck over the basement
External basement wall with internal thermal The deck over the basement is normally
insulation of mineral wool batts fixed constructed of timber joists or pre-fabricated
mechanically and clad with light weight concrete light weight concrete components. Under wet
components, see figure 40. This solution is the rooms, bathrooms, toilet with floor drain the
best considering moisture protection and internal timber joist will often be replaced by a concrete
insulation. slab.
SBI
SBIDirection
Direction189
189 40
Translation RHT
Translation RHT 38
D-floor partition 30 BD-floor partition 60
Min. 21 mm floor boards Min. 21 mm floor board Min. 95 x 170 mm
Min. 45 x 95 mm timber joists per max. 0,6 m timber joists max. 0,6 m Min. 98 mm fixed-
Min. 95 mm fixed mineral wool mineral wool in board form with density min.
30 kg/m3
Mineral wool in this example is fixed with: 2 mm steel wire per. min. Q,3 m
19 x 100 mm timber boards per max. 0,3 m 1 layer of min. class 2 cladding e.g. 13 mm
A class 2 cladding with thickness 12 m, plaster board
e.g. 13 mm plaster board 1 layer of min. class 2 cladding e.g. 15 mm
tongue-and-grooved timber boards
Figure 41 Figure 42
Example of a timber joist floor Example of a timber joist floor
constructed as a BD-building constructed as a BD-building
component 30. Instead of a 21 mm component 60. Instead of a 21 mm
floor board a 18 mm chip board floor board 18 mm chipboard or a
or a plywood board can be used. plywood board can be used.
SBI
SBI Direction
Direction 189189 43
Translation RHT
Translation RHT 41
External walls Further, the construction shall be so made that
any ingress of water can be lead out again. The
External walls include walls in facades and in insertion of damp proof courses and damp
gables. proof membranes can ensure this.
External walls must 1) be able to accept and A damp proof course is a layer, which apart
transfer load, 2) fulfil the requirements for heat from hindering diffusion also secures against
insulation, 3) be protected against moisture moisture transport via capillary rise
damages and 4) be fire resistant. When a A damp proof membrane is a layer, which
building is placed in noisy areas, external apart from hindering diffusion is at the same
walls shall furthermore fulfil requirements time airtight, that is, the joints between any
concerning acoustic insulation. lengths of barrier must not permit air leakage.
Diffusion is defined as “The transport of water
Heat insulation vapour through the pores of a material”.
The heat insulation requirements for heavy Insulation against moisture from the
external walls and for light external walls foundation or from a basement wall is
differ. Heavy external walls are defined as established by placing a bitumen felt damp
walls with a mass of more than 100 kg/m2. proof course at least 150 mm above ground
When calculating the mass, only the part of the level, see figure 46. The most appropriate
wall, which is placed inside any ventilated material is bitumen felt type PF 2000, which is
cavity, is included. polyester reinforced felt with a mass of
Heavy external walls are typically walls where 2000g/m2. Alternatively, type GF 2000 can be
the outer leaf is a masonry wall whereas the used which is a glass fibre reinforced bitumen
inner leaf is either a masonry wall or a felt.
lightweight concrete element wall. In the Bitumen felt is placed above all openings in
“Heat loss frame” (see Enclosure E) heavy the outer leaf, see figure 45. Other examples of
external walls assume the U-value 0.30. the placement of bitumen felt are described in
Light external walls are typically timber or “Tegl 17, Moisture barrier in masonry”,
metal stud walls with an external cladding of MURO, 1994.
wood, steel or fibre cement panels - or with In walls containing moisture sensitive
masonry outer leaf. Light external walls materials (such as wood, steel, gypsum and the
assume the U-value 0.20 in the “Heat loss like) a ventilated cavity shall be established
frame”. between the rain shield and heat insulation and
Windows, external doors, sky lights and glass the insulation shall be covered with a
walls all assume the U-value 1.80 in the Heat windproof layer. If the outer leaf is made of
loss frame and their total area must not bricks the width of the ventilated cavity should
exceed 22 per cent of the heated floor space. be at least 50 mm. Furthermore, the wall shall
Fulfilment of the requirements for heat be so constructed that any kind of
insulation is covered in detail in the chapter condensation is avoided. This is ensured by
“Heat insulation”. placing a damp proof membrane of e.g. 0.15
mm polyethylene foil on the warm side of the
Moisture conditions insulation or up to 1/3 of the total layer
External walls shall be so constructed that they thickness inside the insulation layer calculated
will not be damaged by moisture. from the warm side.
150
mm
Figure 45. Bitumen felt shall be inserted above openings or connections between outer leaf and
inner leaf. The felt is attached to the inner leaf. In masonry inner leafs the felt is embedded 2-
3 courses above the insertion in the outer leaf. If brick lintels are used above the openings (see
page 50), the felt shall be embedded above the last of the courses presumed to constitute part of
the lintel. When the inner leaf is constructed by the use of prefabricated elements, the felt is
bonded to a height of 150 mm.
Figure 46 External walls shall be secured against moisture from below. Bitumen felt is placed
securing against moisture from the foundation. At ground level the felt is at the same time
inserted and glued to the concrete slab to prevent air ingress (radon). Furthermore, bitumen
felt is inserted with the purpose of discharging penetrated water. If the wall is particularly
exposed to driving (horizontal) rain, mortar can be left out in every second head joint in the
first course above the bitumen felt. The felt is fixed to the inner leaf as described in figure 45.
Figure 48 Combination wall with brickwork in Figure 50.Combination wall with brickwork in
inner and outer leaf. outer leaf and clinker concrete in inner leaf.
Figure 51 Combination wall with brickwork in Figure 52 Wooden stud wall with brickwork as
outer leaf cellular concrete in inner leaf. outer leaf.
U = 0.18
is used – by two layers of class 2 covering,
each layer at least 12 mm thick and the
concealed layer in batt form. A ventilated
cavity is allowed between the two layers of
class 2 covering. In non load bearing walls
(typically gable walls) it is sufficient to use Figure 56 Inner leaf made of aerated concrete
one layer class 2 covering, provided rock wool with exterior wooden cladding. The density of
is used. the wall on the inner side of the ventilated
Steel frame walls are usually clad with cavity is less than 100 kg/ m2, consequently the
plasterboard. Load carrying steel parts shall be wall is classified as light external wall.
protected against corrosion. Due to strength,
fire and sound at least two layers of 13 mm
plaster boards should be used as internal
U = 0.27 U = 0.27
Figure 57. Inner leaf made of concrete with Figure 59 Inner leaf made of clinker concrete
exterior cladding in corrugated cement fibre with exterior cladding in plastered mineral
sheets. The density of the wall inside the wool batts (facade batts). The density of the
ventilated cavity is greater than 100 kg/m2, wall inside the ventilated cavity is greater 100
consequently the wall is classified as heavy kg/m2, consequently the wall is classified as
external wall. heavy external wall.
Sill
Sill
Jamb Jamb
Sill Sill
Jamb
Jamb
Figure 64. Fixing a window in a combination Figure 65. Fixing a window in an external
wall with concrete inner leaf. A 168 mm wide timber stud wall with wooden cladding. The
brick lintel is used above the window. The stud wall is constructed using 45 x 95 mm
outer leaf wall thickness is increased to 168 studs mounted with 45 x 45 mm horizontal
mm along the jambs and the sill. This battens on both sides. The construction is
construction constitutes a solid base for the supplemented with noggins and battens
fixing and sealing of the window and also around the window in order to establish a firm
constitutes a good basis for the fixing of the base for the fixing of the wind tight layer on
windowsill. The prefabricated inner leaf (wall the outside and, on the inside the fixing of a
element) is manufactured with a window damp proof membrane between the studs; for
opening. The reinforced lintel above the the fixing of battens, cladding, window,
window is an integrated part of the element. In window board, window reveal etc. The
this case a 70 mm gap is created between the unbroken wooden jambs in this construction
inner and outer leaf along the jambs, head and constitute a relatively insignificant thermal
sill. The gap is filled with insulation to avoid bridge and as such the solution can be
thermal bridging and is concealed by the considered satisfactory.
window board and the window reveals
Strength properties
Non-load bearing walls shall be so constructed
that they can resist randomly applied forces
etc. At the same time they must not be exposed
to any load from a possible storey partition
above.
SBI Direction
SBI Direction189
189 56-59
KLJ
61
Roofs
In this SBI directive roofs include the entire convection all joints in the dpm must be
attic consisting of the roof cover, the overlapped and jammed or taped. Also, joints
underlay, the load bearing construction (i.e must be in firm connection with any dpm in
rafters or roof elements) and the ceiling the external wall or the external wall itself
construction above the underlying storey. (when constructed without a dpm). In order to
Included are battens, distance slats, insulation, prevent damaging the dpm (for instance when
damp proof membranes etc. Arrangement of doing the electrical wiring) it is recommended
the attic is also included when the attic is used to place the dpm inside the insulation. When
for habitation doing so, the dpm must never be placed
Roofs must: 1) be able to accept and transmit further inside the insulation than a distance
load, 2) fulfil thermal insulation requirements, corresponding to 1/3 of the total thickness of
3) be secured against moisture damages and the insulation (calculated from the warm side)
4) be fire resistant. Non-heated cavities in roof structures must be
constructed in such a way that any
construction moisture or moisture which may
Thermal insulation
penetrate the roof from the outside or from
The ceiling construction and walls separating
below can be effectively removed. This is
habitable space from roof space assume the U-
usually done by ventilating the constructions.
value 0.15 in the “Heat loss frame”.
Flat roofs and sloping walls directly against
roof assume the U-value 0.20 in the “Heat loss Fire protection
frame”. For fire protection purposes, roof coverings
Insulation in roof and external walls must be shall be suitably fire-resistant class T roof
connected or overlapping in order to prevent coverings (i.e. they must be only moderately
cold bridges. fire spreading).
Examples of this are:
Moisture conditions • Roof covering of non-combustible
Roofs must be constructed in such a way that material for example roof tiles, fibre
they are adequately impermeable against cement sheets and metal roofing
ingress of snow, rain and melt-water. Also sheets on wood or steel battens.
they must be constructed with sufficient pitch • Bitumen felt on concrete, light weight
to secure the draining off of snow, rain and concrete, mineral wool, plywood or
melt-water. The necessary pitch depends on tongued and grooved boards. In this
the type of roof covering chosen. Flat roofs case bitumen felt is understood as a
covered with bitumen felt or other roofing felt roof covering made from oxidised
require a minimum slope of 1:40 (1.5o) bitumen or SBS modified bitumen
Moisture from heated rooms can penetrate the In non-habitable attics the ceiling construction
roof structure either due to diffusion or due to towards underlying rooms must, as a
air convection (the upward movement of hot minimum, be carried out as a class 2 covering
air) through cracks and crevices. Therefore, using class A insulation material, see
the ceiling construction must be made enclosure B, “Fire”.
adequately diffusion proof and airtight. When the attic is used for habitation the floor
Normally the transport of moisture is hindered deck between the attic and the underlying
by mounting a strong and durable damp proof rooms must be constructed as a BD-building
membrane (dpm) on the warm side of the component 30. All surfaces must be carried
insulation. In order to avoid air
Common rafters/joists
Common rafters/joists carry the roof covering, the
Ventilated cavity subroof and the ceiling construction of the rooms
Rafter, 75 x 225 mm per 1.0 m
Damp proof membrane below. In flat roof constructions the necessary
Battens, 50 x 50 mm height for placing the insulation and for
Mineral wool, cl. 39, 150 + 50 establishing sufficient slope can be achieved by
mm
Ceiling cladding adding additional joist laid to fall. An example of
U = 0.20 this is shown in figure 76.
Figure 76. Common joists with low roof pitch. Figure 78. Wood roofing elements with roof
Sufficient roof slope has been established by tile covering on battens. The underlay is not
adding additional joist laid to fall. ventilated.
The figures in the table have been calculated using the following criteria:: Construction timber is strength class
K18 according to the Code of Practice for the Structural use of Timber. Dead load of roof covering and
underlay: Light roof cover 0.25 kN/m2 (for example corrugated sheets or roofing felt), heavy roof cover 0.55
kN/m2 ( for example roof tiles). Dead load of insulation and ceiling cover: 0.25 kN/m2 (non-plastered ceilings).
Dead load of rafters/joists: 0.05 kN/m2 for dimensions up to and including 50 x 200 mm, above that 0.10 kN/m2.
The stated span corresponds a deflection for dead load and snow load of L/250 (L=span). Consequently the
deflection for dead load alone is less than L/400 .
The values in the table are applicable to flat roofs, but may be used directly for roof pitch up to 10o. At 20o roof
pitch the span (measured horizontally) shall be reduced to 90%, and at 30o to 83% of the stated value. Linear
interpolation is accepted.
Wooden roof elements must be produced in
Clinker concrete roofing elements accordance with regulations laid down by
Corrugated fibre cement boards on
battens “Tagelementkontrollen” (“The controlling
50 x 100 mm rafters (blocked up) board of roofing elements”)
Figure 79 shows a roof made of clinker
concrete elements spanning between
transverse walls.
When pressure resistant insulation is used the
roofing felt can be placed directly on top of
Mineral wool 39, 150 mm this. In this way the insulation is trapped
Damp proof membrane between the damp proof membrane (below)
Clinker concrete roofing
elements, sandwich and the roof cover (above). This may result in
construction, 200 mm, overpressure when the sun is heating the roof.
U = 0.20 density of middle layer 600
kg/m3 The pressure is equalised by the openings
along the roof edges.
Cantilever
Annular ring nails, anchored minimum 50 mm into the gable triangle and the rafter
Purlin anchors
2 pcs diagonally Slanted nailing
placed 2 pcs
Trimmer joist
Figure 80 Bracing of timber clad gable triangle. In order to counter horizontal wind action the gable
triangle is fixed to the battens along top edges. Likewise it is fixed to the gable truss along the bottom edge
for example by the use of short pieces of batten fixed to the tie beam. When using a light roofing material it is
imperative to anchor the gable triangle for example by the use of trimmings connecting the gable to the
outermost trusses. The trimmings are placed close to the facades. Using distances and dimensions as stated
on pages 61-62 the battens can be cantilevered up to 0.5 m.
Figure 81. Bracing of a brickwork gable triangle. At roof pitch up to 30o and in terrain
classes built-up and agricultural the gable triangle can be braced by mechanically
fixing it to 50 x 100 mm studs per 600 mm. The studs are bolted to the rafter and to the tie
beam. Noggins are inserted between the studs as shown. The brickwork is braced using wire
ties fixed to the studs at every fourth course. Along the topside of the gable triangle the wire
ties are placed at 300 mm intervals measured horizontally in 1st and 2nd joints or in the 2nd
and 3rd joints. The wall ties are fixed to the studs or to the noggins. The noggins are placed
at a level corresponding to that of a brick course. In this way a wire tie can be fixed on the
top side as well as on the bottom side of the noggin. Acceptable batten cantilever tolerances
are stated in the text below figure 82.
Rafter
Collar beam
Ceiling joists,
braced by ceiling
diaghpram
Figure 82. Bracing of gable triangle constructed as cavity wall. The inner leaf is
mechanically fixed to the ceiling diaphragm, the rafter and the collar beam for example by
the means of bolts. The collar beam must be braced for example by means of a duckrun or by
means of panelled cladding. When a heavy roof covering is applied and at a batten distance
of 0.35 m the accepted batten cantilever (calculated from the gable rafter) is maximum 0.9
m. When light roof coverings are applied using 50 x 62 mm battens per 1.1 m or 38 x 56 mm
per 0.55m the accepted cantilever is maximum 0.65 m. However, the cantilever, calculated
from the outer leaf, must never exceed 0.5 m. In the case of a light roof cover a cantilever of
maximum 0.9 m from the gable rafter and 0.7 m from the outer leaf is accepted - provided
the distance between the battens is halved within the cantilever section and the first two
rafters.
Type 2
Type 1
Width Width
Width
Type 3 Type 4
Width Width
Table T1. Maximum width of a brickwork gable triangle when the triangle is secured
along all three edges. The width is determined as a function of the roof pitch,
anchoring pattern (according to figure 81a) and the terrain class.
Anchoring may be carried out using wire stainless wire binders the space between the wall
ties, which under normal circumstances will and the timber construction must be between 100
have sufficient strength when placed at 300 and 200 mm and using 4 mm binders the distance
mm intervals. When using 3 mm must be between 120 and 300 mm
SBI
SBIDirection 189
Direction 189 69A
KLJ
Translation KLJ
Thermal insulation length of the thermal bridge. Linear loss occurs
principally along foundations and along joints
Single family houses shall be sufficiently insulated
around windows and doors. Spot loss occurs at
to avoid the unnecessary consumption of energy and
metal consoles and anchors penetrating the
to secure the achievement of satisfactory health
insulation. It should be noted that the spot losses
conditions.
from wall ties in cavity walls has always been
The insulation qualities of the construction elements
included in the calculation of the U-value of such
are described by their coefficients of transmission,
a wall.
the so-called U-values. These are calculated as
Requirements to insulation in floors with floor
described in DS 418: “Calculation of heat loss from
heating have also been tightened up.
buildings”. The U-value describes the heat loss in
Watt through 1 m2 of the construction element at an
Three possibilities
outdoor/indoor temperature difference of 1 Kelvin
The Building Regulations for Small Dwellings
(1K = 1oC). The U-value unit is W/m2 K and for
gives three possibilities for fulfilling the thermal
typical constructions the U-values can be found in
insulation requirements for single family houses
the previous chapters of this Direction and in “VIF,
heated to at least 18oC.
U-values’95 “.
An illustration: Let us assume that a certain • Observing the U-value demands as well as the
construction has the U-value 0.20. We increase the line loss demands for each construction
thickness of the insulation with 50 mm. This will element and at the same time reducing the
result in the reduction of the U-value to total area of windows and external doors to
approximately 0.16. maximum 22 percent of the building’s heated
Exterior construction elements, including windows floor area.
and external doors, must only contain cold bridges • Observing the so-called Heat Loss Frame
to a limited extend. This is due to the increased risk calculated for the house with changed U-
of condensation. The energy effect of cold bridges values for the constructions and also changing
must be taken into account when calculating the areas for windows and external doors.
thermal transmittance (the U-value) for the various • Observing the so-called Energy Frame, which
construction elements. Cold bridges may have a defines the heating requirements of the house
significant influence on the total transmission loss – including ventilation.
even in well-insulated buildings. Consequently it is In most cases the use of the Energy Frame results
essential to analyse and calculate the effect of cold in the best heating economy. Also, the use of the
bridges. Energy Frame gives more freedom in the choice of
Buildings and construction elements, including U-values and the choice of window and external
windows and doors, must be so constructed that door areas. The use of the Energy Frame,
transmission loss is not considerably increased as a however, requires several calculations.
consequence of moisture, wind or the inadvertent When either the Heat Loss Frame or the Energy
passage of air. Frame is used to verify that the requirements for
Requirements concerning cold bridges have been thermal insulation of a single family house are
tightened up in Appendix 1 (By og met, also the minimum requirements for thermal
Boligministeriet 2001) to the Building Regulations insulation of the individual construction element
for Small Dwellings and in Appendix 4 to DS 418. shall be observed.
Cold bridges are those parts of the building
envelope which are markedly worse insulated than U-value requirements
the rest of the envelope. They occur in ribs around The requirements in Building Regulations for
the windows an along internal foundations. These Small Dwellings can be met by choosing
cold bridges are being considered by making a construction elements with U-values lower
calculation of an average U-value for the than or equal to those listed in table 10 and at
construction element in question. It is not new to the same time ensuring that the total area of
take these cold bridges into consideration. The new windows and external doors does not exceed
thing is that it is now required to take into 22 per cent of the total heated floor area of the
consideration that at corners, or where there is a house. Examples of constructions fulfilling
change in the thickness of insulation, we find two or
three dimensional effects resulting in additional
these U-value requirements, are shown in the
heat loss. These additional thermal losses are previous chapters.
referred to as linear loss and spot loss.
The symbol for linear loss is ψ. The thermal loss
through these thermal bridges is proportional to the
SBI Direction 189
KLJ 70
Table 10 Building Regulations for Small Table 11. Building Regulations for Small
Dwellings: U-value requirements for Dwellings: Requirements to minimum thermal
construction elements surrounding heated insulation of all heated rooms. ψ-value
rooms. ψ-value requirements acc. to DS 418 requirements according to DS 418
Construction element U Construction element U
W/m2K W/m2K
External walls External walls
with mass below 100 kg/m2 0.20 with mass below 100 kg/m2 0.30
External walls with mass above100 External walls with mass above100
kg/m2 and basement external walls kg/m2 and basement external walls
under ground 0.30 under ground 0.40
Partition walls and storey partitions Partition walls and storey partitions
adjacent to unheated rooms 0.40 adjacent to unheated rooms 0.60
Ground supported floors, basement Ground supported floors, basement
floors, storey partitions towards the floors, storey partitions towards the
outside and ventilated crawl spaces. 0.20 outside and ventilated crawl spaces
Ground supported floors, basement irrespective of floor heating 0.30
floors, storey partitions towards the Attic and roof constructions
outside and ventilated crawl spaces 0.15 Including walls between attic and
with floor heating. wasted attic space 0.25
Attic and roof constructions Flat roofs and sloping walls
Including walls between attic and directly against roof 0.25
wasted attic space 0.15 Windows and external doors,
Flat roofs and sloping walls skylights, glass walls and hatches. 2.90
directly against roof 0.20 ψ
Windows and external doors, sky W/m K
lights, glass walls and hatches. 1.80 Foundations, irrespective of floor
ψ heating 0.60
W/m K Joint between external wall and
Foundations 0.25 windows/ext.doors, glass walls, gates
Foundations surrounding floors with or hatches 0.10
floorheating 0.20 Joint between roof construction and
Joint between external wall and windows in roof or skylights 0.30
windows/ext.doors, glass walls, gates 0.03
or hatches
Joint between roof construction and
windows in roof or skylights 0.10
(There are no specific U-value requirements to
ventilation openings, smaller than 500 cm2).
Figure 85. Guideline for the connection between U-values in external walls and U-values and areas of
windows and external doors towards the outside in light external walls, sloping walls and in flat
roofs.
Figure 86. Guideline for the connection between U-values in external walls and U-values and areas of
windows and external doors towards the outside in heavy external walls.
have a U-value of 1.6 W/m2K. calculated to 105.5 m2. The external perimeter of
When calculating the Heat Loss Frame adjoining the house is 2 x 14.4 m+ 8.4 m) = 45.6 m
houses are considered as one building. Use of The The storey height is 2.6 - measured from topside
Heat Loss Frame must always be accompanied by ground supported floor to topside ceiling
matching calculations, see subsequent example. insulation The transmission area of the vertical
external planes (i.e. external walls, windows and
Example of Heat Loss Frame used on a single- external doors) is 45.6 m x 2.6 m = 118.6 m2.
family house The window and external door area is 26.6 m2,
The example is based on a 1-storey house with a corresponding to 22 percent of the heated floor
floor area of 121 m2, see figure 87. Bathroom and area. The length of the joints around windows and
toilet with floor heating – remaining part of the external doors is 59.8 m. The house is naturally
house with radiators. The external dimensions of the ventilated.
house are 14.4 m x 8.4 m and external walls are The Heat Loss Frame of the house is 3.64 kW, see
heavy, 350 mm thick. Internal dimensions are 13.7 table 12. The area of windows and external
m x 7.7 m (disregarding the internal walls) doors may be increased to 26.9 per cent of the
Based on this, the transmission area for the roof and heated floor area by choosing energy glass and
for the ground-supported floor can be thus changing the U-values to 1.6 W/m2 K, see
table 13.
Table 12. The Heat Loss Frame for single family house shown in figure 87
Toilet
Figure 87. The single family house
used in the example. The area of
Living Kitchen Bedroom windows and external doors
room area
corresponds to 22 per cent of the
heated floor area
Plan
Energy Frame
The thermal insulation may also be determined The possibilities and advantages of using the
on the basis of the so-called Energy Frame Energy Frame are described in more detail in
combined with a calculation of the total heat the SBI Directive 190: “Building design and
requirements for room heating heat requirements”.
and ventilation. The Energy Frame expresses The net heat requirement is the heat, which
the accepted total annual net heat requirement must delivered directly to rooms or to the
for heating and ventilation per m2 heated floor ventilation air and does not include losses
area from the production of the heat in for example
a boiler.
Table 13. The heat loss from the single family house shown in figure 87 with increased
window area and using better insulating energy glass.
Building component Area, length U-, Ψ -value Temperature Heat loss
m2 , m W/ m2 K, W/m difference, K W
External walls 84.7 0.30 32 813
Roof 121.0 0.15 32 581
Ground supported floor in bathroom and 11.7 0.15 20 35
toilet
Ground supported floors in other rooms 93.8 0.20 10 188
Windows and external doors 33.9 1.60 32 1736
External wall foundation in bathroom and 4.1 0.15 42 26
toilet
External wall foundation, other rooms 41.5 0.25 32 201
Joints: Windows and doors 61.6 0.03 32 59
Heat loss 3639
E-W
Figure 88. Guiding values for possible window and external door area in typical detached 1-
storey house - using the Energy Frame. The graphs also apply to semidetached houses
(adding up the total floor area)
Window and external door area in percent of heated floor area
2 storeys 2 storeys
Minimum
width 250 mm
100
100
Wet zone
Dimensions in mm Wet zone
Figure 90: Wet zone and moist zone in wet Figure 91: Fixed shower enclosures:
rooms with shower stall. The wet zone When enclosures have a minimum width
includes floor and wall areas within the of 250 mm only the part of the wall inside
stall area plus an additional 500 mm zone. the stall is considered a wet zone. Pipes
The wet zone on the walls reaches the may penetrate the floor immediately
ceiling. In rooms with an extraordinary outside the stall area provided the floor
room height, the area above normal room inside the stall is recessed or provided
height may be considered a moist zone. The with a curb.
hatched area shows the part of the floor
where a slope is required. No pipes must
organic materials such as concrete, light
penetrate the floor in this area. The area
weight concrete and brick work has until
stretches 500 mm outside the limit of the
recently been considered adequate wet rooms
stall.
solutions.
However, some of the non-organic materials
usually be adequate. A recess is preferable to a such as light weight concrete and brick work
curb as water on the floor outside the shower are rather water absorbent and others may
area e.g. from washing the floor will be able to have leaky joints between elements.
run into the drain. At the same time the room is Consequently, such materials should have a
better suited for wheelchair access. The water-proof surface treatment when used in
recessed area should be sufficiently big to allow areas exposed to water. It should be noted that
water from a shower curtain to drip off inside a normal tile cladding is not considered water
the recess. proof and therefore must be supplemented
with water tight treatment before fixing tiles.
Waterproofing Stud walls as well as walls and floors
The application of a waterproof cladding or a containing organic materials must be supplied
waterproof surface treatment may be with a waterproof surface treatment. In the
necessary in order to secure water tightness of wet zone the treatment shall be carried out by
floors and walls The use of a water repellent
surface treatment or cladding on top of non-
Moist zone
Wet zone
100
100
Wet zone
Wet zone
Dimensions in mm
∗
MK refers to the Danish Building Material Control
Board
SBI Direction 189, 81
Translation: KLJ
testing and approval conditions concerning wall additional concrete slab is cast on top of the first
claddings in wet rooms (1996). MK approval does slab – as shown in figures 94 and 95. The two
not apply to sealant systems and paints used in the slaps are separated either by a sliding layer
moist zone but it is possible to obtain an approval. consisting of a double 0.15 mm PE-foil or
The various possibilities of fulfilling the separated by an insulating layer. The concrete
requirements for water proofing in wet zones and must be stiff plastic, type pea gravel or pebble, 20
moist zones in floors and walls are thoroughly Mpa, and it must be at least 60 mm thick. A
treated in the following. reinforcement of 6 mm round steel is laid in a grid
Water running down the walls must be led to the with 150 mm grid distance. Alternatively a similar
floor surface. Consequently, the joint between the reinforcement mesh may be used. Additives
wall and the floor must be established using a
watertight seal, or the watertight layer on the wall
must overlap the floor curb.
When using doorframes with a threshold, the
distance between floor surface and the lower level
of the threshold must be min. 20 mm. In this way
the floor will be able to contain a certain amount of
water, for example originating from a leaking water
installation. Alternative solutions must be sought
when the bathroom is arranged with regard for
physically handicapped.
Floors
Heavy floor constructions with the purpose of increasing impermeability
Heavy floor constructions consist of in situ cast should be used and the concrete must be vibrated.
concrete slab or a slab made from prefab light Slopes can be established directly in the concrete
weight clinker concrete elements. In most cases an slab or in a 10-40 mm cement mortar screed
(C100/400). As concrete creeps and shrinks during
curing the tiles must be laid as late as possible in
∗
VA is a Danish certification system for Water and Sewer installations
SBI Direction 189, 82
Translation: KLJ
the building process. The concrete must cure at least Tightness between floor and wall can be secured
for 2-3 weeks at 20 oC . In order to compensate for by covering the joint with a flashing for example
additional contraction in the concrete it is advisable using a fibre reinforced membrane as shown in
to use a tile glue with plastic properties. The best figure 26, page 32 and in figure 30, page 34. When
curing method is to cover the concrete with a the wall is waterproofed using a membrane the
polyethylene foil or similar during the first few days flashing is created by leading the wall membrane
after casting. all the way down and taking it 100 mm into the
Normally, the execution of concrete work as floor area. When membranes are placed in both
floor and wall the two membranes must be long
term compatible and the joint between them must
be sealed.
Joints
Elastic joints are used to absorb movements
between building components. In order to
secure a long life span, elastic joints must be
designed with geometry – sufficient width and
Kitchen Kitchen
100 cm2 opening from Natural ventilation:
access room Ventilation duct with cross
Also recommended 1. sectional area of 200 cm2
Hinged window or
or Mechanical ventilation:
Hatch Volume flow rate 20 l/s
or and
External door Hood with mechanical
extraction to the outside
or
Fresh air vent with a
cross sectional area of
30 cm2
Bathrooms Bathrooms
100 cm2 opening from Natural ventilation:
access room Ventilation duct with cross
Also recommended 1. sectional area of 200 cm2
Hinged window or
or Mechanical ventilation:
Volume flow rate 15 l/s Figure 102. Example of a fresh air vent,
Hatch a so-called dish valve.
or
Fresh air vent with a
cross sectional area of
100 cm2 Natural
ventilation
WC and scullery WC and scullery
100 cm2 opening from Natural ventilation:
access room Ventilation duct with cross
Total cross sectional area, cm2
Floor area, m2
Figure 101. Requirements on the supply of
fresh air and the removal of indoor air.. Figure 103. Cross sectional area of fresh
Basements must also be ventilated. air vents in habitable rooms in relation to
SBI Direction 189
floor area.
KLJ 91
Kitchen, bathroom and toilet
Kitchens, bathrooms and toilets are the rooms the door or in the wall. The purpose of
in the dwelling contaminated by moisture establishing this opening is to secure that the
saturated and polluted air. Indoor air must be removal of air from the rooms functions
removed from the house trough these rooms according to the intention, and to secure that
either by mechanical exhaust or by natural the extraction of air from the rooms
ventilation. contributes to the supply of fresh air to the
When applying mechanical exhaust the habitable rooms.
requirements to the volume flow rate are 20 l/s The requirement concerning a ventilation
from kitchen, 15 l/s from bathroom and 10 l/s opening from access rooms only applies to
from toilet. Applying natural ventilation the above mentioned rooms as it is mainly the
requires a ventilation duct with a cross sectional doors to these rooms which are kept closed,
area of at least 200 cm2 in each of the above but in general it is considered a good idea also
mentioned rooms. Usually, 200 cm2 to install air vents in the doors or in the walls
corresponds to the net cross sectional area of a between other rooms. This is because closed
15 x 15 cm duct. doors in some parts of the house may have an
Extractor fans intended for periodic use are not adverse effect on the functionality of the
considered as real exhaust systems. ventilation system. Air vents between
Normal procedure when applying mechanical habitable rooms should be sound proofed.
ventilation is to install adjustable valves in the In cases where one of the walls surrounding a
air vents. The setting of the valves must room is an external wall it is a must to supply
correspond to the air flow required by the outdoor air to that room For this particular
system. Normally, these settings are not to be reason at least one of the walls in a bathroom
changed at a later stage. should be an exterior wall. The fresh air vent
Irrespective of the ventilation in the kitchen in these rooms should only be opened when
being natural or mechanical the kitchen shall be there is a need for extra ventilation as an open
supplied with a hood with extraction to the air vent reduces the airflow in the habitable
outside. rooms.
Natural ventilation requires both a ventilation
duct and a duct for the hood. The hood must not Other rooms, crawl spaces and basements
be connected to the ventilation duct. A hood The rules applying to a toilet concerning the
duct is usually automatically blocked during the supply of removal of air also applies to a
periods when the hood is not in use. scullery.
If a hood is considered an integral part of a Basements shall be ventilated to the outside
mechanical exhaust system the volume flow through air vents with the same cross sectional
rate through the hood must be continuous and at areas as those in a habitable room. As
least 20 l/s. In this case the noise level of the basements are not habitable rooms the
hood must not exceed 30 dB in kitchen and requirement for draught-free air supply is not
habitable rooms. applicable. Ventilation (mechanical or natural)
Where the kitchen is a part of a living room the must be established in at least one basement
requirements, stated in figure 101 concerning room.
the supply of fresh air and the removal of
indoor air, are applicable. Fresh air vents and ventilation ducts
In kitchens, bathrooms and toilets an opening of Fresh air vents
100 cm2 from access rooms is required. The The primary function of the fresh air vents is
demand can be fulfilled by establishing a crack to secure a controlled supply of outdoor air to
beneath the door or by installing an air vent in the dwelling. Also, the fresh air valves give
the occupants a possibility of regulating the
distribution of the supplied outdoor air. Fresh
Chimneys
Chimneys shall be sufficiently high to ensure
adequate flue. Also, chimneys shall be
Stoking effect, kw
sufficiently high (in relation to roofs and
surroundings) to ensure that the smoke is quickly
dispersed and diluted into the atmosphere.
Figure 107: Cross sectional area limits for
Cross-sectional area small chimneys used for oil and solid fuel
The cross-sectional area of the chimney must be stoking. Sizes are determined as a result of the
adjusted to the amount of smoke. The cross total stoked effect at maximum load. The bold
sectional area must be sufficiently large to horizontal lines represent minimum
requirements in Building regulations for Small
Dwellings. The values apply to closed heating
appliances
Class 2 covering
1000 mm
Max. 1
coverings or the packing material of the same
200mm
Max
shall carry an indication of approval according
Max. 200 mm
200 mm
Max.
SBI
SBIDirection
Direction189189 111-126
KLJ 68
Enclosure E. Heat
requirements
1
4
1