ID Task Task Name Start Finish Duration

Mode 20 May '19 03 Jun '19 17 Jun '19 01 Jul '19 15 Jul '19 29 Jul '19
SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S
1 PEKERJAAN FIRE SPRINKLER 26 December 2018 02 August 2019 197 days
2 CONVEYOR BELT 2B 26 December 2018 02 August 2019 197 days
3 Area CV Unit 2B Section 1 19 February 2019 28 June 2019 112,71 days
4 Install Support UNP 100 19 February 2019 26 February 20197 days
5 Install Main Pipe CS Pipe Sch. 40 8", 6", 4", 3", 2,5", 24 February 2019 05 March 2019 9 days
2"

6 Install Branch Pipe CS pipe Sch. 40 1,5", 1" 23 February 2019 27 February 20193,43 days
7 Joint Pipe 26 February 2019 05 March 2019 7 days
8 Install Gate Valve OS&Y - Strainer, Deluge Valve 27 May 2019 29 May 2019 3 days Minus Deluge Menunggu Hydro

9 Install Open Sprinkler (Nozzle) 13 June 2019 15 June 2019 3 days Cover Coneyor Belum terpasang

10 Pressure Test 23 May 2019 25 May 2019 3 days


11 Install Junction Box c/w Control Module and Mini 03 March 2019 09 March 2019 7 days
Module

12 Wiring Cable FR s x 2.5 mm2 08 March 2019 10 March 2019 3 days


13 Wiring Line Heat Detector 26 June 2019 28 June 2019 3 days Cover Coneyor Belum terpasang

14 Area CV Unit 2B Section 2 13 February 2019 26 June 2019 116 days


15 Install Support UNP 100 13 February 2019 18 February 20195 days
16 Install Main Pipe CS Pipe Sch. 40 8", 6", 4", 3", 2,5", 18 February 2019 26 February 8 days
2" 2019

17 Install Branch Pipe CS pipe Sch. 40 1,5", 1" 20 February 2019 22 February 20193 days
18 Joint Pipe 22 February 2019 01 March 2019 7 days
19 Install Gate Valve OS&Y - Strainer, Deluge Valve 23 May 2019 25 May 2019 3 days Cover Coneyor Belum terpasang

20 Install Open Sprinkler (Nozzle) 13 June 2019 14 June 2019 2 days


21 Pressure Test 20 May 2019 22 May 2019 3 days
22 Install Junction Box c/w Control Module and Mini 03 March 2019 09 March 2019 7 days
Module

23 Wiring Cable FR s x 2.5 mm2 11 March 2019 14 March 2019 4 days


24 Wiring Line Heat Detector 24 June 2019 26 June 2019 3 days
25 Area CV Unit 2B Section 3 01 February 2019 22 June 2019 123 days
26 Install Support UNP 100 01 February 2019 04 February 20193 days
27 Install Main Pipe CS Pipe Sch. 40 8", 6", 4", 3", 2,5", 04 February 2019 06 February 3 days
2" 2019

28 Install Branch Pipe CS pipe Sch. 40 1,5", 1" 17 February 2019 19 February 20193 days
29 Joint Pipe 19 February 2019 25 February 20196 days
30 Install Gate Valve OS&Y - Strainer, Deluge Valve 20 May 2019 22 May 2019 3 days Minus Deluge Menunggu Hydro

31 Install Open Sprinkler (Nozzle) 13 June 2019 15 June 2019 3 days Cover Coneyor Belum terpasang

32 Pressure Test 16 May 2019 18 May 2019 3 days


33 Install Junction Box c/w Control Module and Mini 03 March 2019 09 March 2019 7 days
Module

34 Wiring Cable FR s x 2.5 mm2 15 March 2019 17 March 2019 3 days

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Revisi Schedule Fire Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline

Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1
ID Task Task Name Start Finish Duration
Mode 20 May '19 03 Jun '19 17 Jun '19 01 Jul '19 15 Jul '19 29 Jul '19
SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S
35 Wiring Line Heat Detector 21 June 2019 22 June 2019 2 days Cover Coneyor Belum terpasang

36 Area CV Unit 2B Section 4 15 January 2019 21 June 2019 139 days


37 Install Support UNP 100 15 January 2019 19 January 2019 5 days
38 Install Main Pipe CS Pipe Sch. 40 8", 6", 4", 3", 2,5", 18 January 2019 26 January 2019 8 days
2"

39 Install Branch Pipe CS pipe Sch. 40 1,5", 1" 14 February 2019 18 February 20194 days
40 Joint Pipe 16 February 2019 23 February 20197 days
41 Install Gate Valve OS&Y - Strainer, Deluge Valve 16 May 2019 20 May 2019 4 days Minus Deluge Menunggu Hydro

42 Install Open Sprinkler (Nozzle) 13 June 2019 17 June 2019 4 days Cover Coneyor Belum terpasang

43 Pressure Test 13 May 2019 16 May 2019 4 days


44 Install Junction Box c/w Control Module and Mini 03 March 2019 09 March 2019 7 days
Module

45 Wiring Cable FR s x 2.5 mm2 13 March 2019 15 March 2019 3 days


46 Wiring Line Heat Detector 18 June 2019 21 June 2019 4 days Cover Coneyor Belum terpasang

47 Area CV Unit 2B Section 5 02 January 2019 15 June 2019 146 days


48 Install Support UNP 100 02 January 2019 07 January 2019 5 days
49 Install Main Pipe CS Pipe Sch. 40 8", 6", 4", 3", 2,5", 05 January 2019 14 January 2019 8 days
2"

50 Install Branch Pipe CS pipe Sch. 40 1,5", 1" 11 February 2019 14 February 20194 days
51 Joint Pipe 13 February 2019 20 February 20197 days
52 Install Gate Valve OS&Y - Strainer, Deluge Valve 19 February 2019 22 February 20194 days
53 Install Open Sprinkler (Nozzle) 13 June 2019 17 June 2019 4 days Cover Coneyor Belum terpasang

54 Pressure Test 03 May 2019 07 May 2019 4 days


55 Install Junction Box c/w Control Module and Mini 04 March 2019 11 March 2019 7 days
Module

56 Wiring Cable FR s x 2.5 mm2 18 March 2019 21 March 2019 4 days


57 Wiring Line Heat Detector 11 June 2019 14 June 2019 4 days Cover Coneyor Belum terpasang

58 Area CV Unit 2B Section 6 26 December 2018 19 June 2019 155 days


59 Install Support UNP 100 31 December 2018 04 January 2019 5 days
60 Install Main Pipe CS Pipe Sch. 40 8", 6", 4", 3", 2,5", 02 January 2019 10 January 2019 8 days
2"

61 Install Branch Pipe CS pipe Sch. 40 1,5", 1" 26 December 2018 29 December 2018
4 days
62 Joint Pipe 07 January 2019 15 January 2019 8 days
63 Install Gate Valve OS&Y - Strainer, Deluge Valve 25 January 2019 29 January 2019 4 days
64 Install Open Sprinkler (Nozzle) 13 June 2019 17 June 2019 4 days Cover Coneyor Belum terpasang

65 Pressure Test 29 March 2019 06 April 2019 8 days


66 Install Junction Box c/w Control Module and Mini 03 March 2019 09 March 2019 7 days
Module

67 Wiring Cable FR s x 2.5 mm2 20 March 2019 23 March 2019 4 days


68 Wiring Line Heat Detector 14 June 2019 19 June 2019 5 days Cover Coneyor Belum terpasang

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Revisi Schedule Fire Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline

Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 2
ID Task Task Name Start Finish Duration
Mode 20 May '19 03 Jun '19 17 Jun '19 01 Jul '19 15 Jul '19 29 Jul '19
SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S
69 TEST COMISSIONING CONVETOR BELT 2B 24 June 2019 03 July 2019 9 days
70 Inspection and Preparation 28 June 2019 03 July 2019 5 days
71 Function test 03 July 2019 08 July 2019 5 days
72 Repair (if any) 08 July 2019 03 August 2019 26 days
73 CONVEYOR BELT 2C 23 March 2019 03 August 2019 115,71 days
74 Install Support UNP 100 13 May 2019 16 May 2019 4 days
75 Install Main Pipe CS Pipe Sch. 40 6", 3", 2" 16 May 2019 24 May 2019 8 days
76 Install Branch Pipe CS pipe Sch. 40 1,5", 1" 20 May 2019 23 May 2019 4 days
77 Joint Pipe 17 May 2019 24 May 2019 7 days
78 Install Gate Valve OS&Y - Strainer, Deluge Valve 29 May 2019 11 June 2019 3 days
79 Install Open Sprinkler (Nozzle) 29 May 2019 11 June 2019 3 days
80 Pressure Test 27 May 2019 30 May 2019 4 days
81 Install Junction Box c/w Control Module and Mini 23 March 2019 25 March 2019 2 days
Module

82 Wiring Cable FR s x 2.5 mm2 25 May 2019 27 May 2019 2 days


83 Wiring Line Heat Detector 25 May 2019 27 May 2019 2 days
84 TEST COMISSIONING CONVETOR BELT 2C 28 June 2019 02 August 2019 34 days
85 Inspection and Preparation 28 June 2019 02 July 2019 4 days
86 Function test 03 July 2019 08 July 2019 5 days
87 Repair (if any) 08 July 2019 03 August 2019 26 days
88 CONVEYOR BELT 7 17 May 2019 03 August 2019 64 days
89 Install Support UNP 100 20 May 2019 29 May 2019 10 days
90 Install Main Pipe CS Pipe Sch. 40 8", 6", 4", 3", 2,5", 2" 22 May 2019 08 July 2019 35 days

91 Install Branch Pipe CS pipe Sch. 40 1,5", 1" 27 May 2019 15 July 2019 37 days
92 Joint Pipe 17 May 2019 08 July 2019 39 days
93 Install Gate Valve OS&Y - Strainer, Deluge Valve 17 June 2019 19 June 2019 3,29 days
94 Install Open Sprinkler (Nozzle) 13 July 2019 18 July 2019 5,29 days
95 Pressure Test 27 May 2019 29 May 2019 3,43 days
96 Install Junction Box c/w Control Module and Mini 22 May 2019 24 May 2019 3,29 days
Module

97 Wiring Cable FR s x 2.5 mm2 25 May 2019 27 May 2019 2 days


98 Wiring Line Heat Detector 19 July 2019 24 July 2019 5 days
99 TEST COMISSIONING CONVETOR BELT 7 28 June 2019 02 August 2019 34 days
100 Inspection and Preparation 28 June 2019 02 July 2019 4 days
101 Function test 03 July 2019 08 July 2019 5 days
102 Repair (if any) 08 July 2019 03 August 2019 26 days

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Revisi Schedule Fire Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline

Milestone Inactive Task Manual Task Manual Summary External Tasks Progress