MATARA-KATARAGAMA RAILWAY EXTENSION PROJECT (MATARA-BELIATTA SECTOR-PHASE-01)

Employer: Ministry of Transport.


Engineer: Central Engineering Consultancy Bureau.(CECB)
Contractor: China National Machinery Imp.& Exp.Corporation.

RISK ASSESMENT-TERMITE TREATMENT


Name of station
DATE : Location
yard:

Item to inspect Evaluation Remarks

The pest control operator is licensed operator under state legislation  Yes /  N/A

The required personnel protective equipments are wear the workers and
 Yes /  N/A
staff

Approved method statement is used as reference  Yes /  N/A

Surface preparations are completed including all the testing works  Yes /  N/A

The service line identified and protected ( if required)  Yes /  N/A

Ordinary peoples/workers are not entered to the area during the


 Yes /  N/A
treatment.

The drilling holes or treatment area is not below to the ground water table  Yes /  N/A

The chemicals are not mix to natural water body during / after the
 Yes /  N/A
treatment

The chemicals are not sprayed to the unnecessary areas  Yes /  N/A

After finished the works, the waste material disposed properly  Yes /  N/A

No Peron is entered to the treated area until the spray has dried  Yes /  N/A

The treated area is covered as specified in material data sheets/


 Yes /  N/A
approved method statement

Other general HSE measures are taken during / after completed the
 Yes /  N/A
works

Checked by Position Name Signature Date

Contractor :

Consultant Engineer

Accepted by contractor Reviewed by Engineer

Name, Signature & Date Name, Signature & Date