Académique Documents
Professionnel Documents
Culture Documents
The following is a summary of several smarts that An additional concern was the predicted
contributed to the success of the Permanent Way differential settlement between the two. The plinth
design and the project as a whole track was not expected to settle and the
embedded rail on imported fill had a worst case
predicted to settle of up to 30mm.
Transitions between ballast and slabtrack, have
the advantage that misalignment due to settlement
can be rectified by reinstating the ballasted track to
its original position. With embedded rail it is not
feasible to adjust the alignment thus an innovative
solution was required.
The solution was to install the first few lengths of
plinth track lower than necessary and achieve the
require rail level with removable packers. If the
settlement causes the rail alignment to be out of
tolerance the packers can be removed such that a
compliant alignment is reinstated. Effectively, as
the earth structure settles, we lower the first 15m
of the bridge alignment in varying degrees to suit.
It was necessary to select a baseplate and
fastening system that had the flexibility to adjust
the rail level independently of the baseplate but
more importantly allowed for the shims to be
removed without cutting and removing the rail. The
chosen fastening system was the Vossloh UTS
300.
Each abutment had a different predicted
settlement due to the varying substrata and
volumes of imported fill. The length of each
transition slab and extent of removable shims on
Figure 1 : Aerial view of route showing the structure was calculated to suit ensuring the
station location slab length was minimised to provide a cost
effective solution.
Image Courtesy of the GoldLinQ consortium, delivering
stage one of the Gold Coast light rail project. The rail profile also changed at the transitions.
Plinth track utilised Vignole rail 49E1 and the
embedded rail utilised grooved rail 51R1. The
2.1 Transitions corresponding depths were 150mm and 130mm.
In addition the Vignole rail is symmetrical, and
As with all rail projects special attention was
installed with a 1:40 inclination, whilst the grooved
necessary at the transition between different track
rail is asymmetrical and is installed vertically with a
types and supporting structure.
1:40 inclination machined in the rail head. These
Transitions are normally complex due to the major differences, See figure 2 ruled out the use of
sudden change in track stiffness or track modulus composite welding.
‘k’, particularly for transitions from ballasted to slab
track. GCLR is all slabtrack and each variant was
design to have a similar track stiffness. Any
variation in stiffness would be a result of the
supporting ground/structure below.
On GCLR the trackform transitions were from
embedded rail on earth fill to direct fixation plinth
track on piled structure. The transition between the
slightly different k-values was achieved using a
transition slab that bridged the two trackforms
The Performance Scope and Requirements ‘PSR’
specified a minimum transition length of just 6m, it
was necessary to increase this and use a 13m
continuous slab with the change from embedded
to plinth track occurring half way along. Figure 2 : Mismatch in rail profiles
Guideline Original BOStrab The particular issues identified were applying cant
PGCLR about the centre of the low rail and also applying
requirements the inclination to the surrounding trackslab, kerbs
etc. Till this time 12d was predominantly a civil
Curves Cant Lateral
based design tool and these rail specific functions
deficiency = acceleration:0.67m/s2
weren’t present at the time.
80mm max
In addition the chosen software was required to
0.97m/s2 exceptional analysis and document Sight Stopping Distances
Transitions Rate Max jerk rate to a 200mm object on the track. This is a standard
55mm/s 0.65m/s3 requirement for highway design, but not for rail
projects which typically operate in a segregated
Gant 1in400 1in400 corridor and relies on signalling, not line of sight.
Gradient Therefore the software needed to apply highway
Table 1 : Comparison between the two tools inside the Light Rail corridor.
alignment requirements During the initial stages of the design process it
was necessary to develop and adapt of a number
of macros within the 12d software to efficiently and combinations for the route (see Table 1 for
accurately model the light rail design. summary of route-wide maximum values). In
designing the trackslabs, localised loads were
Following the success of the GCLR design stage, used where possible to give more economical
these tools are now inbuilt into the latest versions designs.
of 12d. This close working with the software Vertical Lateral
developers demonstrated that this is mutually Load Load
beneficial to all parties and should be encouraged. Wheel (kN) 108.71 65
2.4 Track stiffness and Rail Stress analysis Wheel Set (kN) 135.46 56.3
GCLR has a unique combination of the Bogie (kN) 266.76 84.21
Bombardier Flexity 2 LRV, Vossloh 300UTS DFF Table 2 : Results from WRI Study
baseplates, 49E1 and 51R1 and the phoenix 3
piece boot. Without the luxury of another system 2.6 Components for Embedded Rail
with this exact combination to demonstrate the Although this system is new for Queensland, all
compatibility and behaviour for these combinations components used in the construction were
it was necessary to result in first principle design to required to have a minimum of 5 year service
prove the track system as a whole met the record in an equivalent system around the world.
requirements. All suppliers were required to have proof of this
Several techniques were used, such that each criterion when proposing their products.
could validate the other.
2.6.1 Rail
The track loading was determined using
Huddersfield University outputs from the Wheel The 51R1 grooved rail profile was chosen based
Rail Interface analysis, and reviewed by Arup on the WRI study to match the preferred wheel
designers using the Eisenmann and AREMA profile of the Flexity 2 tram used on this project.
dynamic factor calculations. The rail is welded continuous over the project
length and protrudes by a nominal 6mm above
The first technique was to use Arups in house adjacent track slab top surface to allow for future
design software ‘GSA’, to determine, deflection, rail wear.
stresses, thermal expansion, rail/structure
analysis. 2.6.2 Rail Boot
Finally, each of these aspects were calculated The rails were provided with a rubber boot system
independently using first principle design to isolate the rails from the track slab concrete for
calculations. Testing is currently occurring on site the following reasons;
and at the time of writing this paper, we do not • provide the rails with a resilient (flexible)
have final results. support system which resulted in reduced rail
The majority of rail design today is done by wear and cushioning to the concrete;
applying asset owner standards that are well
• control and limit noise and vibration from the
documented, proven and have been refined over
wheel rail interface so as to enable the
many years of empirical data. The designers on
environmental limits for the project to be
GCLR had the opportunity to apply and learn skills
achieved, particularly through the medical-
that are no longer common in the Permanent way
based properties along the route;
engineers tool box.
2.5 Wheel Rail Interface (WRI) Study
Arup engaged the Rail Technology Unit from
Manchester Metropolitan University (now
Huddersfield University) to run simulations of the
Light Rail Vehicle (LRV) on the alignment. These
simulations incorporated vehicle suspension, a
range of vehicle masses (to suit passenger loading)
and aspects like track cant, wheel and rail wear,
rail lubrication and wind loads. The primary
objective was to assess issues like wheel-rail
compatibility, risk of derailment and rail wear.
However, the simulations were also able to
produce detailed track loads generated by the Figure 4 : Typical Section of 51R1 Rail and
vehicle under various load cases, including Rail Boot
dynamic enhancements. The results of this study
were used to determine lateral and vertical loading
4. CONSTRUCTION
Construction of the Light Rail began in early 2011
and is currently set for completion in mid-2014.
GoldLinQ and MacDow are working together to
deliver the 13-kilometer light rail corridor from
Griffith University to Broadbeach, passing through
the various key centres along the way including
Southport and Surfers Paradise.
4.1 Bridge construction – Rail on Plinth
Track
There are four major bridges on the Project
spanning roadway and watercourses. These are;
Smith Street Viaduct – Spans over the Smith
Street Motorway and green fields from Griffith
University to the Depot Viaduct. The structure is
Figure 5 : Anchor Bolts Installed
approximately 370m long. The form comprises of
12 spans of prestressed concrete girders with a Image Courtesy of the GoldLinQ consortium, delivering
reinforced concrete deck. stage one of the Gold Coast light rail project.
Nerang River Bridge – Carries the corridor over
the Nerang River Bridge connecting Southport to Once the anchors are installed, the precast plinths
Main Beach. The structure is approximately 380m are lowered into place.
long. The form comprises of 12 spans of
prestressed concrete girders with a reinforced
deck.
MacIntosh North and South Bridges - Carry the
alignment over the Nerang River at two locations
spanning approximately 32m and 43m respectively
along the Gold Coast Highway. The structures
comprise of precast concrete deck units and a
reinforced concrete deck.
All of these adopt a plinth track construction. The
plinth is a proprietary precast plinth that is
anchored to the deck slab via post installed
anchors The proprietary epoxy used to anchor the
bolts into the concrete deck provides electrical
isolation of the bolts from the reinforcement in the
deck. Figure 6 : Plinth Installation
Image Courtesy of the GoldLinQ consortium, delivering
stage one of the Gold Coast light rail project.