Académique Documents
Professionnel Documents
Culture Documents
Minerals Engineering
journal homepage: www.elsevier.com/locate/mineng
a r t i c l e i n f o a b s t r a c t
Article history: Scanalyse in collaboration with JKMRC and Newcrest Mining Limited conducted an extensive study of the
Available online xxxx effect of liner wear on mill performance of a 32 foot SAG mill at Newcrest’s Cadia Valley Operations in
Australia. The methodology of determining the optimum liner shape was previously presented at Met-
Keywords: plant 2011, and expanded on at the SAG11. The results presented indicated that liners with a reduced
Comminution mass and shorter life outperform their longer life counter parts in all key production parameters of
Grinding throughput, energy consumption and product size.
Mill
This paper quantifies the benefit of having shorter liner life cycles for improved performance by calcu-
Mill liner
Optimisation
lating the increase in throughput and reduction in power based on historical data for an operational 32
Condition monitoring foot mill. It also presents the total overall gain by accounting for the increase in required reline effort. This
provides a holistic view of the net achievements when designing liners for performance and not life.
Ó 2012 Elsevier Ltd. All rights reserved.
1. Introduction ner liners would compensate and overcome the extra downtime
incurred.
Liners play a critical role in SAG milling due to their strong Scanalyse in collaboration with JKMRC and Newcrest Mining
influence of load trajectory and ultimately breakage efficiency conducted an extensive 12 month study on the effect of liner wear
(Makokha et al., 2006). Generally breakage efficiency depends on on mill performance of the 32 foot SAG mill at Cadia Valley Oper-
the behaviour of the load inside the mill which governs the nature ations from July 2010 to June 2011. The methodology of determin-
of the ore presentation to breakage. However, there is also a trade- ing the optimum liner shape was previously presented at Metplant
off between liner life and grinding performance which to date has 2011 (Toor et al., 2011a,b), and expanded on at the SAG11 (Toor
not been studied closely. Typically, the start of the shell liner life et al., 2011a,b). The results presented indicated that liners with a
cycle also coincides with the lowest throughput of the cycle. There worn shape and reduced mass, but shorter life outperform their
are several possible causes for this; longer life counter parts in all key production parameters of
throughput, energy consumption and product size. This paper
1. Installation of new liners reduce the internal mill volume. quantifies the benefit of having shorter liner life cycles for im-
2. Possible packing of material in between lifters. proved performance by calculating the increase in throughput
3. Decrease in grate open area if discharge grates are relined. and reduction in power based on historical data for an operational
4. Suitable but overdesign of new liners causing a decrease in 32 foot mill. It also presents the total overall gain by accounting for
breakage. the increase in required reline effort. This provides a holistic view
5. Unsuitable design of new liners for the mill in question. of the net achievements when designing liners for performance
6. Inefficient adjustment of operational parameters during early and not life.
liner life cycle stage.
0892-6875/$ - see front matter Ó 2012 Elsevier Ltd. All rights reserved.
http://dx.doi.org/10.1016/j.mineng.2012.07.004
Please cite this article in press as: Toor, P., et al. Designing liners for performance not life. Miner. Eng. (2012), http://dx.doi.org/10.1016/
j.mineng.2012.07.004
2 P. Toor et al. / Minerals Engineering xxx (2012) xxx–xxx
Table 1
Mill performance summary over liner life; ore availability constrained throughput periods highlighted in italics.
paring a fully worn liner with a new liner, and it also coincides There are also some noticeable outliers where there is a sudden
with a decrease in specific energy of 12%. drop in throughput which were caused by lack of ore availability.
A noticeable reduction in throughput occurs at half-life when These outliers have been highlighted in red in Table 1.
the discharge grates (1/2 set) and the feed outer liners are relined. Finally grinding surveys conducted during the course of the pro-
This causes the regressed throughput curve to taper but still in- ject indicate that SAG product is finer as the liner wears. This is
crease as the shell liners wear further. It should be noted that highlighted in Table 3, which alongside product sizes shows the
the throughput post grate reline is still approximately 3% higher fresh tonnes per hour, recycled tonnes per hour (pebble crusher),
on average than the throughput prior to the grate reline, indicating total tonnes per hour and power (kW). Thus from all data available,
the increase in throughput is not only due to an increased open it appears that as the liners wear in the mill, the three primary per-
area of the grates but also due to the wear in the shell liners (see formance indicators of throughput, power and product size all im-
Table 2). prove considerably.
Another observation is that throughput at the end of liner life is
slightly reduced for this mill, which could be explained by exces-
sive loss of lift caused by severe liner wear at the end of the life cy- 3. JKSimMet modelling
cle (see most worn profile in Fig. 5). However the decrease in
throughput is minor and could therefore potentially be explained JKSimMet Modelling of new and fully worn liners was carried
by other operational parameters and plant noise. out to compare mill performance with the progression of liner
Please cite this article in press as: Toor, P., et al. Designing liners for performance not life. Miner. Eng. (2012), http://dx.doi.org/10.1016/
j.mineng.2012.07.004
P. Toor et al. / Minerals Engineering xxx (2012) xxx–xxx 3
Table 2
Effect of key relines on mill performance.
Period Throughput (tph) Throughput change (%) Specific energy (kWh/tph) Specific energy (%)
Shell reline 6/12/2010–17/12/2010 652 0 9.6 0
Pre grate reline 4/03/2011–9/03/2011 720 10 9.1 5
Grate reline
Post grate reline 9/03/2011–14/03/2011 672 3 9.5 1
Pre shell reline 21/05/2011–01/06/2011 732 12 8.4 12
Table 3
Summary of production parameters at survey times.
Liner life Fresh feed tph Recycle crusher tph Total tph Power (kW) Product size p80 (microns)
New 635 156 791 6015 1630
Half (post grate reline) 725 117 842 6338 1440
80% 581 136 717 6085 1373
Fully worn 754 151 905 5861 1395
Fig. 2. SAG breakage rates over liner life new and fully worn. for the 32’ mill studied.
wear. The comparison of breakage rates across the liner life was of Fig. 2 shows the breakage rates for the two liner conditions fully
particular interest. worn and new. The plot illustrates that there is an increased break-
Please cite this article in press as: Toor, P., et al. Designing liners for performance not life. Miner. Eng. (2012), http://dx.doi.org/10.1016/
j.mineng.2012.07.004
4 P. Toor et al. / Minerals Engineering xxx (2012) xxx–xxx
Fig. 4. Sample 3D thickness models of new liners (left) and completely worn liners (right) as produced by MillMapperTM - note asymmetric wear along shell lifters.
age rate for the size classes below 16 mm for the worn liner. Con- to the increase in the mill cavity and the increase in open area.
versely, the new liners exhibit an increased breakage rate for par- Fig. 3 shows the breakage rates with the interpolated intermedi-
ticles greater than 16 mm. This result can be explained by new ates (half-life and 80% worn) to illustrate how the breakage rates
liners imparting more lift to the charge thereby causing compara- may evolve with liner wear.
tively high impact breakage of the coarse particles whereas the
worn liner causes a greater cascading motion of the charge. Thus
a larger amount of breakage would occur through attrition and 4. Millmapper
abrasion of the finer material for the worn liner case.
SAG feed, which is comprised of fresh feed, recycle crusher MillMapperÒ provides high resolution three-dimensional mill
product and cyclone underflow has F80 characteristics in the order liner thickness information inside a mill by mapping in the order
of 15–20 mm. Thus as the liners wear, approximately 80% of the of 10 million individual survey points. Aside from tracking liner
material entering the mill is experiencing an increased breakage shape and wear, other variables such as liner weight, net mill vol-
rate, which explains the associated increase in throughput. The ume, charge volume, ball size distribution, and discharge grate
important conclusion from this modelling is that the change in open area are also quantified, (Franke et al., 2009). Critically this
liner shape is contributing to the observed increased in through- can be done not just for new liner shapes, but for worn shapes as
put. Traditionally the increase in throughput is solely attributed well, which is the only way to model grinding behaviour at times
Please cite this article in press as: Toor, P., et al. Designing liners for performance not life. Miner. Eng. (2012), http://dx.doi.org/10.1016/
j.mineng.2012.07.004
P. Toor et al. / Minerals Engineering xxx (2012) xxx–xxx 5
Table 4 downtime caused by them. As is evident from the graph, the cur-
Summary of improved performance with shorter liners life cycles. rent setup of a reline every six months is not optimal, regardless
No. of relines/6 Throughput (tph) Power (kW) Specific of how long a reline takes within the range of typical durations.
month cycle energy (kWh/t) At present the shell reline of the 32 ft mill takes approximately
1 707 6684 9.47 30–40 h (average 34 h). Interestingly, the throughput curves for
2 719 6638 9.25 the 30 h and 40 h relines indicate that thinner optimised liners
3 733 6548 8.93 which require reline three times per six month cycle would deliver
4 738 6505 8.81
6 736 6463 8.78
the highest tonnage. This equates to a shell reline every 2 months.
8 736 6463 8.78 However if relines are taking approximately 60 h then there is
little advantage in relining thinner liners more frequently. This
other than the very initial period of a liner life cycle. An example of
a liner 3D thickness model output is presented in Fig. 4. MillMap- Feed Outer
Discharge
per™ allows the optimum liner profile to be as identified by corre- Month Shell And misc
Components Grates
lating the profile with an analysis of mill performance based on
production data and JKSimMet Modelling results. 1 half worn
2
5. Designing liners for performance 3
27
From the plant data, survey results and JKSimMet modelling it 4
can be seen that key mill performance indicators of throughput, 5
specific energy/power and product size all improve as liners wear,
6 34
for the mill investigated. This suggests that liners with a reduced
thickness and mass outperform their larger and heavier counter- Total Reline Duration 6 Months = 61
parts. This section highlights the potential benefits of having short- 7
er life liners which deliver more tonnes at a lower power and 8
produce a finer grind. Importantly it is envisaged the increase in
9 27
downtime due to the additional relines is overcome and exceeded
due to the increase in mill performance. 10
It is possible to predict the throughput of liners with reduced 11
mass by analysing existing plant data. For example, to estimate
12 34
the total life cycle throughput for a new liner design with a half-life
shape, one would simply average the throughput from the second Total Reline Duration 12 Months = 122
half of the original liner life. Referring to Table 1, this would simply 13
require the averaging of throughputs from the 09/03/2011 to the 14
01/06/2011. Using this approach, it is possible to predict the result-
15 27
ing increase in mill performance based on having thinner liners, by
utilising existing plant data. Table 4 summarises the increase in 16
mill performance with shorter liner lives and additional relines. 17
It should be noted that the outliers mentioned in Table 1 were ex-
18 34 half worn
cluded when determining the values provided.
Using simplified examples of each additional reline taking a Total Reline Duration 18 Months = 183
possible l 20, 30, 40, 50 or 60 h, Fig. 6 quantifies the combined ef-
fect of shorter but more productive life cycles and additional Fig. 7. Case study current reline schedule.
Please cite this article in press as: Toor, P., et al. Designing liners for performance not life. Miner. Eng. (2012), http://dx.doi.org/10.1016/
j.mineng.2012.07.004
6 P. Toor et al. / Minerals Engineering xxx (2012) xxx–xxx
Table 6
Discharge
Month Shell Feed Outer Operations summary with predicted revenue increase.
Grates
1 Gold Copper
half worn
Current throughput (tph) 707 707
2
Mill availability% 96 96
3 41 Feed grade 1.31 g/t 0.51%
Recovery% 85 90
4
Annual production 6620411.347 g 2729025t
5 Annual Au production (oz) 212854 N/A
6 Price $1,600.00/oz $6/kg
34
Annual revenue $340,567,089 $163,741,470
Total Reline Duration 6 Months = 75
Additional annual revenue (1.25% increase) $4,257,089 $2,046,770
7 Total $6,30 M
8
9 41
10
11 Table 7
Reline cost estimates.
12 34
Relining costs
Total Reline Duration 12 Months =150
Volume current shell liners (m^3) 22.9
13
Mass current shell liners (kg) 178,620
14 Cost of material @ 3$/kg $535,860
Cost of labour @ 10% $53,586
15 41 Total cost of reline $589,446
16 Total annual cost of reline (2 per year) $1,178,892
Volume proposed shell liners (m^3) 18.3
17
Mass proposed shell liners (kg) 142,740
18 34 half worn Cost of material @ 3$/kg $428,220
Cost of labour @ 10% $42,822
Total Reline Duration 18 Months =225 Total cost of reline $471,042
Total annual cost of reline (4 per year) $1,884,168
Fig. 8. Case study proposed reline schedule.
Annual increase of reline cost $705,276
Table 5
Comparison of throughput and power for current and proposed shell liner design - improvements are highlighted in bold.
Please cite this article in press as: Toor, P., et al. Designing liners for performance not life. Miner. Eng. (2012), http://dx.doi.org/10.1016/
j.mineng.2012.07.004
P. Toor et al. / Minerals Engineering xxx (2012) xxx–xxx 7
Table 8 8. Conclusions
Net annual revenue estimates.
Summary of potential benefit The aim of the paper is to quantify the benefit of using shorter
Annual increase in revenue $6.30 M life liners. Previous work (Toor et al., 2011a,b), utilised plant data,
Annual increase of reline cost $0.71 M plant surveys, JKSimMet and MillMapper to quantify the improve-
Net annual revenue increase $5,60 M ment in throughput, power consumption and product size experi-
enced by the mill as the liners wore. Using this data a new design
was proposed with reduced mass and shorter life. Upon using plant
data to predict the new throughput and estimating the additional
As stated earlier, the fact that the extra reline can be incorpo- downtime required it was found that the additional throughput
rated into a non-shell reline shut to minimise the amount of down- gained by the proposed design outperforms the current design
time makes a redesign far more appealing. Fig. 6 illustrates that with an increase in throughput of 1.25% annually. This equates to
reducing the additional downtime increases the throughput bene- an increase in revenue of over AUD 5 million accounting for an
fit. Assuming that using half shape liners as derived from MillMap- additional cost of only AUD 0.7 million in relining.
per will only require an extra 14 h of reline per 6 month cycle, a It is acknowledged that a change to relining schedule has to be
comparison can be made between the two designs based on overall considered in conjunction with general plant maintenance work,
tonnes processed at the power required. The comparison of the so plant maintenance and operational input is required before
two designs is summarised in Table 5 which shows that by using pursing such a course of action.
the proposed design an increase of 35 k-tonnes is predicted, or A simple half-life liner profile has been used, there is clearly fur-
1.25%, with a power reduction 292 MWh, or 1.10%, over a 6-month ther opportunity to optimise the liner profile if a shorter liner life is
period. targeted. Optimisation would aim at minimising the wasted shell
plate thickness that is evident at the end of the liner life, plus
7. Cost benefit analysis case study changing lifter width to reduce metal wastage there. The excessive
width is a function of the structure required for the very high new
A broad estimate can be made of the economic benefit possible lifter bar, so is not required for a lower lifter design. Improvements
in utilising liners designed for performance and not life. Tables 6–8 along these lines would further decrease the liner cost, and lighter
present a summary of the expected benefits for the mill that was liners are faster to replace, with the added potential to decrease the
studied. Note that all dollar figures are given in Australian Dollars. number of liner elements in line with the liner handlers capacity.
For the above table, the following data was used: These additional opportunities will be pursued in ongoing liner
studies.
Assumed mill availability of 96%.
Feed grades represent the average gold and copper grades in the References
block cave material from 1 July 2011 to 1 March 2012.
Franke, J., Redman, N., Johnson, G. & Michalek, S. (2009). Mill Management Using
Recoveries were sourced from the Newcrest Cadia Quarterly
MillMapper™ – An Answer to the Skills Shortage – A Tool for Cost Cutting. In:
Report End June 2008. 10th Mill Operators’ Conference 2009, Milling Through the Boom, Adelaide,
Australia, 12–14 October 4. The Australasian Institute of Mining and Metallurgy,
Publication Series No 11/2009, ISBN 978 1 921522 12 3. pp. 71–80.
To estimate the cost of relining the figure of $3/kg of steel was
Makokha, A.B., Moys, M.H., Bwalya, M.M., Kimera, K., 2006. A new approach to
used for material cost plus 10% for labour costs. The volume of the optimising the life and performance of worn liners in ball mills: Experimental
shell liners were obtained from MillMapper for new shell liners study and DEM simulation. Minerals Engineering, 1439–1445.
and half-life shell liners (proposed design). Tables 7 and 8 summa- Newcrest Mining Limited (2008). Newcrest Cadia Quarterly Report End June 2008.
<http://www.newcrest.com.au/>.
rise the estimated cost of relining. Russell, J., Advanced grinding mill relining for process metallurgists and
From Table 8 it can be seen that the estimated increased in An- management (2006). SAG’06, 2006. In: Proceedings International autogenous
nual Revenue is in the order of 5 million dollars. It should also be and Semiautogenous Grinding Technology 2006. Published CIM, Vancouver, BC.
Toor, P., Perkins, T., Powell, M Franke, J., (2011), The Influence of Liner Wear on
noted that the new design is expected to reduce energy consump- Milling Efficiency. In: Proceedings Metplant 2011 Plant Design and Operating
tion and/or specific energy thus further increasing the net revenue Strategies – World’s Best Practice, Perth Australia, August 8–9. Pp. 193–212 The
achieved. Based on the survey data presented in Table 3, it could Australasian Institute of Mining and Metallurgy.
Toor, P., Franke, J., Powell, M.S., Perkins, T., (2011), Quantifying the Influence of Liner
also be reasoned that the new design would also reduce the P80 Shape on Mill Performance. In: Flintoff, et al., (Eds.), Proceedings International
of the product, thereby increasing the flotation recovery. These autogenous and semiautogenous grinding technology 2011, September 25–28,
two additional benefits of reduced specific energy and possible in- Published CIM.
crease in recovery add further commercial weight to the proposed
design with reduced mass.
Please cite this article in press as: Toor, P., et al. Designing liners for performance not life. Miner. Eng. (2012), http://dx.doi.org/10.1016/
j.mineng.2012.07.004