STERLING AND WILSON DOC. No.

:
METHOD STATEMENT FOR
RAHEJA-SW-MS-PHE-THREAD-04
GI PIPE INSTALLATION REV. No.: 00

PROJECT: : RAHEJA, 12D MIND SPACE HITEC CITY

INDEX

1. OBJECTIVE

2. RESPONSIBILITY

3. ROLE OF THREADING PROCEDURE.

4. PREPARATION & EXECUTION OF WORKS


4.1. Edge Preparation
4.2. Fit Up
4.3. Operation
STERLING AND WILSON DOC. No.:
METHOD STATEMENT FOR
RAHEJA-SW-MS-PHE-THREAD-04
GI PIPE INSTALLATION REV. No.: 00

PROJECT: : RAHEJA, 12D MIND SPACE HITEC CITY

1. OBJECTIVE
The purpose of generating this method statement is to define the procedure step by step to
implement the correct practices for threading.
2.

3. RESPONSIBILITY
 The Field Engineer (s) is / are responsible for the preparation, execution and control the
entire process.
 The Engineer is responsible for the inspection and documentation of the weld work.
 QC Engineer / Client / Consultant will witness the process from edge preparation to
finishing of welder qualification.

4. ROLE OF THREADING PROCEDURE SPECIFICATION


 A test Threaded piece to be prepared by Sterling & Wilson and to be shown for Client’s /
Consultant’s approval.
 Project Specifications will be followed for all grooved joint and pipe fabrication.

5. PREPARATION & EXECUTION OF WORKS


5.1. Edge Preparation

 Threading both ends by using threading machine (15mm to 50mm dia)


 Coat threaded ends with thread, holdite.
5.2. Fit Up
 Fit up will be given as per Treading standards.
 Will be checked by Sterling & Wilson and Client / Consultant Engineers.
5.3. Operation
 Prepare the die stock
 Mount the cutting dies with pipe thread R 1-inch in the sequence of operations 1 to 4.
 Set the fine adjustment for the entering tap.
 Open the pilot
 Chuck the pipe, apply cutting fluid to the deburred end of the pipe.
 Place the die stock, pilot end first, on the pipe end, and adjust the pilot.
 Make an entering cut and rough cut over 19 mm length by turning evenly in clockwise
direction. Then loosen the clamping screw and break the burr with a short jerk to the right.
 Open the die stock and remove it. (Do not turn it to remove it).
 Set the fine adjustment for re-threading.
 Place the die stock on the pipe and adjust the pilot.
 Re-thread, then loosen the clamping screw and deburr the pipe.
 Open the stock and remove it from the pipe (Do not turn it to remove it).
 Clean the thread and apply some grease to it.
STERLING AND WILSON DOC. No.:
METHOD STATEMENT FOR
RAHEJA-SW-MS-PHE-THREAD-04
GI PIPE INSTALLATION REV. No.: 00

PROJECT: : RAHEJA, 12D MIND SPACE HITEC CITY

 Screw the pipe into the elbow fitting until it stops. Use a pipe wrench
 Pipe Alignment will be checked by Spirit level

************************
For Sterling & Wilson For Consultant For Client

Name and Signature