DOC. NO.

: 344/Quot/CVB-RK/0319-05 FORM NO : 2B
BIDDER : CV. BANGKIT DATE : 4/12/2019
INQUIRY NO. : PROJECT : JAMBARAN
TIUNG BIRU
WORK TITLE : GPF PRECAST DRAINAGE INSTALLATION & GPF CONCRETE ROAD JOB. N0 : 4650000076
PACKAGE - 1
COST BREAKDOWN
(WORK ITEM WISE)
:
Unit Price
Total Unit Price Total Cost
Quantity Unit < Indirect Cost
No. Description Specification Direct Material Direct Equip't Direct Workers (Rp) (Rp) Remark
(*)
(A) - (B) (C) (D) (E) ( F=B+C+D+E ) ( G=AxF )
0

2.4 EARTH WORK (FOR ROAD)


Mass 200 gr/m2 (Type Geosinido/GRX40, UMMS/U-TEXPP200,
2.4.1 Geotextile Woven 10,110.70 m2 - -
Geoforce/GTW
95% of max.dry200, or equivalent)
density modified proctor CBR 20% (include filling >
2.4.2 Capping Limestone 3,825.82 m3 - -
for shoulder)
2.4.3 Crushtone Filling (Base Course) 95% of max.dry density modified proctor CBR 50% 1,221.46 m3 - -

2.5 CONCRETE WORK (FOR ROAD)


2.5.1 Concrete Material
Compressive Strength fc' 24 Mpa, Cement Type I Include wooden triangle for contraction joint 1,755.11 m3 - -
2.5.2 Rebar & Wiremesh
Rebar Plain SNI 07-2052, BJTP-24; For Dowel Bar 4.11 TON - -

2.74 - -
Rebar Deform SNI 07-2052, BJTS-40, For Tie Bar TON
Wiremesh M6-150x150 Install only 16,286.12 m2 - -
2.5.3. Formwork
Oily wood panel 15mm thk (oil w/ Sika Separol 10 or equivalent) 431.00 m2 - -
Plastic sheet Poly Ethylene 0.2mm thk ASTM D2103 8,143.06 m2 - -
2.5.4 PVC Pipe
dia 1 1/2" AW Class 579.28 m' - -

2.5.5 Concrete Joint

Joint Filler ASTM D1751 or equivalent 503.28 m' - -


Joint Sealant ASTM D2628 or equivalent 2,950.10 m' - -
2.5.6 Curing Compound 0,4 ltr/m2 (ex. Sika Antisol or equvalent) 7,630.91 m2 - -

SUBTOTAL PERMANENT WORK -

GRAND TOTAL

Vous aimerez peut-être aussi