U. of Technology - Dept. Of Pet . Tech.

4th. Year Natural Gas Engineering Mon. 25/11/2013

A gas well is centered in a radial cylindrical reservoir with fixed pressure at the
outer reservoir boundary. The production rate is 100 Mscf/d and remains constant.
Calculate the cumulative gas production just 10 days before the effect of outer
boundary is felt. Additional data: re=2500 ft., rw= 0.25 ft., k=11 mD., ϕ=0.18,
μg=0.015 cP, Ct= 6x10-4 psi-1.