Sr No Delayed Milestone Completion date

1 Foundation drawings for Online shot blasting machine 14-Mar-19


2 Foundation drawings for Transformers and Cable trenches 14-Mar-19
Foundry shed
1 Foundry brickwork 1-Apr-19
2 Foundry internal plasterwork 1-May-19
Machine shed
1 Works upto floor level with earth filling & Floor PCC 28-Mar-19
2 Brick Work in Super Structure 15-Apr-19
Foundation readiness for equipments
1 Furnace room Readiness 15-Apr-19
2 Emergency tank &cooling tower foundation readiness 15-May-19
3 Foundation readiness for DE anf FE System 15-Apr-19
4 Utility and compressor room 27-May-19
5 Online Shot blasting machine foundation readiness 11-Apr-19
Linked equipment Impact on
Current status
Delievery date current plan

0% No
50% No

90% No
No

90% No
90% No

90% 22-Apr-19 No
0% No
60% 15-May-19 No
40% 30-May-19 No
0% 25-Jun-19 No
Remark/Action plan

Expecetd by 25th April,


Expecetd by 20th April, work started at site

it will be completed after sand plant erection work

Plating foundation is balance

will be completed by 22th april


Not started still in design phase,options working
Will be ready by 15th May(FE arrival date)
due to manufaturer specs Design change for this area,
foundation/support structure will be ready upto 25th une