GypLyner UNIVERSAL (C)_120408:Layout 1 26/05/2008 15:47 Page 263
GypLyner™ UNIVERSAL
Key facts
● General purpose and versatile ceiling lining
● Suitable for concrete soffits or timber joists
● Seamless lining surface
● Ceiling void accommodates small service
1 routings
● Stand-off can be adjusted up to 175mm
● Commonality of ceiling and wall lining
components
263
May 2008
GypLyner UNIVERSAL (C)_120408:Layout 1 26/05/2008 15:47 Page 264
www.gypsum.ie
CLASSIC
UNIVERSAL
Components
GypWall™
Gyproc and Glasroc board products Gypframe metal products
GypLyner™
264
May 2008
GypLyner UNIVERSAL (C)_120408:Layout 1 26/05/2008 15:47 Page 265
GypLyner™ UNIVERSAL
Gypframe metal products Fixing and finishing products
265
May 2008
GypLyner UNIVERSAL (C)_120408:Layout 1 26/05/2008 15:47 Page 266
www.gypsum.ie
CLASSIC
UNIVERSAL
Components
GypWall™
Fixing and finishing products
GypLyner™
266
May 2008
GypLyner UNIVERSAL (C)_120408:Layout 1 26/05/2008 15:47 Page 267
GypLyner™ UNIVERSAL
Construction tips
● Estimated construction time 3m2 / man hour (single layer ceiling) or 2m2 - 2.5m2 / man hour (double layer ceiling) -
ready for finishing
● For concrete soffits allow for a stand-off of 25mm-75mm plus lining thickness using Gypframe GL2 Brackets,
25mm-125mm plus lining thickness using Gypframe GL9 Brackets, and 25mm-175mm plus lining thickness using
Gypframe GL12 Brackets
● For timber joists using Gypframe GL5 or GL6 Timber Connectors, allow for a maximum cavity depth of 35mm and
120mm respectively (measured from the bottom of the joists to the underside of the lining)
● Gypframe GL11 GypLyner Anchors are recommended for fixing brackets to solid concrete and masonry
● Seal all gaps at the perimeter of the ceiling and any small air paths with Gyproc Sealant to maintain air-tightness
and optimum sound insulation
● Predetermine the position of fixtures and fittings with supplimentary framing, and use Gyproc Profilex Access
Panels at key access points
267
May 2008
GypLyner UNIVERSAL (C)_120408:Layout 1 26/05/2008 15:47 Page 268
www.gypsum.ie
CLASSIC
UNIVERSAL
Installation - concrete soffit
GypWall™
GypLyner™
1 2 3
• Determine the required ceiling level • Fix brackets at 1200mm maximum • Locate Gypframe GL1 Lining Channel
and mark the position of Gypframe GL8 centres. Position each bracket, fold down into the perimeter track.
Track on the walls. one leg and fix through bracket slot to
the soffit using a Gypframe GL11
• Fix Gypframe GL8 Track with the GypLyner Anchor.
longer leg at the bottom, at 600mm
centres using suitable fixings (by others). Mark protruding leg of each bracket to
indicate the fixing level of the Gypframe
• Mark lines on the soffit to determine GL1 Lining Channel.
the GypLyner bracket positions. Position
the lines at 450mm (maximum) Select Gypframe GL2 Bracket for
7 intervals for 12.5mm linings, or 600mm
(maximum) intervals for 15mm linings.
stand-offs between 25mm and 75mm;
Gypframe GL9 Bracket for stand-offs
between 25mm and 125mm; or
Gypframe GL12 Bracket for stand-offs
268 between 25mm and 175mm.
May 2008
GypLyner UNIVERSAL (C)_120408:Layout 1 26/05/2008 15:48 Page 269
GypLyner™ UNIVERSAL
4 5 6
• Position the channel, bend down the • Bend back the protruding leg of each • Extend channel sections, where
other leg of each bracket in turn and bracket to sit back from the channel required, by engaging channel ends over
screw fix each leg to the GL1 Lining face. a Gypframe GL3 Channel Connector.
Channel using Gyproc Wafer Head Fixtures
Drywall Screws.
Ensure that the channel is level
• Install any additional channel or
supplimentary framing as required to
before fixing. support fixtures and fittings.
269
May 2008
GypLyner UNIVERSAL (C)_120408:Layout 1 26/05/2008 15:48 Page 270
www.gypsum.ie
GypWall™
GypLyner™ CLASSIC
UNIVERSAL
270
May 2008
GypLyner UNIVERSAL (C)_120408:Layout 1 26/05/2008 15:48 Page 271
GypLyner™ UNIVERSAL
Installation - timber joists
1 2 3
• Determine the required ceiling level, • Fix timber connectors at 1200mm • Engage one side of the Gypframe GL1
mark and fix Gypframe GL8 Track at maximum centres. Fix each timber Lining Channel into a row of timber
perimeter as for concrete soffits. connector to the side of a joist using connectors and twist into position.
two Gyproc Drywall Timber Screws.
• Mark lines beneath the joists to • Push the channel to locate into the
determine the timber connector fixing Allow two holes between fixings perimeter track.
positions. Position lines at 450mm for Gypframe GL6 Timber Connector.
(maximum) intervals for 12.5mm Align accurately since the connectors
• Extend channel sections, where
required, by engaging channel ends over
linings, or 600mm (maximum) intervals cannot be adjusted once fixed. a Gypframe GL3 Channel Connector.
for 15mm linings.
271
May 2008
GypLyner UNIVERSAL (C)_120408:Layout 1 26/05/2008 15:48 Page 272
www.gypsum.ie
CLASSIC
UNIVERSAL
Installation - existing ceiling
GypWall™
GypLyner™
Board fixing
• If the existing ceiling is to be retained,
• Fix board to supports as for concrete Gypframe GL2, GL9 or GL12 Brackets are
soffits but ensure that board edge joints fixed to joists through the retained
do not coincide with the position of ceiling with suitable fixings. Gypframe
timber connectors. GL1 Lining Channels and boards are
fixed to form the new ceiling.
272
May 2008
GypLyner UNIVERSAL (C)_120408:Layout 1 26/05/2008 15:48 Page 273
GypLyner™ UNIVERSAL
Construction details
5
5
1
2
2 3
Typical layout (12.5mm x 900mm x 1800mm board on Typical layout (15mm x 1200mm x 2400mm board on 600mm