Vous êtes sur la page 1sur 6

High Voltage Energy Cables Go Underground – How

to Improve Installation Efficiency


Gerard Plumettaz, Jouni Heinonen
Plumettaz Holding SA, Bex, Switzerland
+41-244630630 · gerard.plumettaz@plumettaz.ch

Abstract relatively short cable sections, at high installation cost. To


A new method to install high voltage cables up to 225 kV using increase installation distances additional pushing and continuous
water under pressure has already been successfully tested and improvements on lubrication have enhanced the installation
applied in France in recent years. The method enables the performances over the last years. However cable pulling with a
installation of continuous sections of power cables in one step rope requires manpower at both ends, i.e. on winch side and on
into a duct up to 3.5 km long. Pressurized water and a pushing drum side of the duct. Further said process is less performing
device are used. Unlike pulling the installation process takes when compared to installation lengths achieved with the new
place from one end of the duct only, therefore reducing process described hereafter at lower cost.
manpower and avoiding coordination hazards. Installation time
is halved when compared to pulling, hence cost saving. When 2. High voltage cable installation
using this new method the pulling forces required for reaching methods
distances beyond those achieved with traditional installation 2.1 Direct burying method
methods, like winching, are far lower than pulling forces Generally, direct burying of power cables has been the preferred
generally met with said traditional methods. This offers technology. The method is nothing else than opening a trench
increased safety for both personnel and cable. between two points manually or mechanically and installing the
This method, named “Watucab” (WAter TUbe CAble), provides cable in the trench. Also, in many countries the cable is placed
the means to remarkable overall project cost savings and in pre-laid channels or culverts, which are subsequently filled
increased cable reliability with sand and covered with a lid, providing additional protection
. to the cable. Direct burying has been used due to its low direct
cost and lack of alternative technologies available. The method
is time consuming, creating a lot of disturbance to the
Keywords: Watucab, high voltage cables; duct; push-pull;
neighbourhood and requires a lot of manpower, which is costly
pulling; jetting; floating;
in many countries. Due to these drawbacks the method is
gradually being replaced by alternative methods described
1. Introduction hereafter.
Mainly for urban areas, or to cope with unfavorable climate
conditions, there is a growing trend to get high voltage energy 2.2 Pulling method
cables underground. The main reason behind this new Installing cables in pre-laid ducts is getting more and more
installation method is of social and economical nature. Indeed popular. Even though material cost might in some cases be
traditional direct burial of power cable, requiring the opening of higher than those for direct burying, cable installation in ducts
long trenches, 500 m to 1 km long, along busy streets imposes offers long term benefits, as the cable can be replaced at the
long lasting disturbance of several weeks or even months to later stage without disturbing the neighbourhood. The duct
urban traffic and to resident businesses and inhabitants, offers also an additional protection to the cable again improving
hereinafter named “the neighborhood” during construction its reliability.
work. Cost is an other reason. Compared with the cable direct The ducts used for cable installation are typically made of either
burial method, the adoption of ducts offers the benefit of a HDPE or PVC. Also PE corrugated dual wall ducts, offering
drastically reduced duration of the disturbance to the good radial rigidity once installed underground and good
neighborhood like difficult or impossible access. This, because flexibility combined with low weight thus facilitating their
the duct burial procedure can be implemented step by step i.e. in installation are mainly adopted for medium voltage distribution
short trenches of approx. 100 m. Once the duct is in place the cables (see figure 1).
trench is closed, the surface rehabilitated for traffic. Such
procedure is not conceivable for direct buried cable as too many
splices would be required. Further, connecting a duct is easy,
splicing a power cable is a delicate, time-consuming and costly
operation. Furthermore, a duct provides for an additional
protection to the power cable. It also enables an upgrading of the
cable connection, as ducted cables can be removed and replaced
by one of larger power capacity without need to reopen a trench.
The main issue is how do we get the heavy high voltage cable
into the duct efficiently? Pulling the cable with a rope is an
established method, but the installation length is limited to
Figure 1. PE dual wall duct

International Wire & Cable Symposium 169 Proceedings of the 58th IWCS/IICIT
For all ducted systems preparation is the same: the ducts sector. Worldwide adopted is the jetting method, especially for
segments are laid in a trench and joined together before the the installation of optical cable, where air is used as propelling
cable installation. The trench is typically opened and closed in fluid. In some countries, like Hungary, Denmark, Sweden and
sections, thus reducing additional or exhaustive disturbances to France, water is used as the propelling fluid, this method is
the neighbourhood and traffic. In the same time the jointing commonly known as cable floating. One could wonder why the
chambers are built. After completion of the duct route between jetting method was never used for energy cable installation?
each jointing chamber, including filling the trench, rehabilitating This is due to the fact that the amount of air needed to install
for traffic the actual cable placement can start. A thin steel wire large cables in large ducts exceeds the capacity (volume flow)
or P-line is blown trough the duct. Typically a stronger rope or of field compressors available on the market. Thanks to the
winch-line is then pulled trough the duct. The winch-line is then much higher viscosity of water compared to that of air the
connected to the cable end and the cable is pulled with winch. volume flow for floating is much less. Furthermore, the
Quite often also lubricant is used to reduce the friction between Archimedes uplift of the water acting on the cable makes the
the cable and the duct. The method requires operators on both lengths reached by floating generally longer compared to jetting
ends of the duct to operate the winch and the cable drum. The by air.
installation lengths achieved by this method are limited by The system to float the cable is shown in figure 4. The cable is
friction and the number of curves and the undulation. The fed into the pre-installed duct with a cable pusher, typically
method is typically used for distances up to 1 km. The method is driven by caterpillars or belts. Immediately after the cable
presented in figure 2. pusher a water inlet chamber attached to the duct. The role of
the water is, next to providing uplift to the cable, to reduce and
stabilise by cooling the friction between cable and duct, thus
enabling to reach greater lengths. Quite often a small amount of
environment friendly additive is introduced in the water to
reduce the friction. Another benefit provided by this system
when compared to the cable pull or the cable push-pull methods
is that the floating method is a one step process, avoiding steps
like P-line and winch-line installation. Also control of the whole
process is done from one side only, i.e. the drum side. This
Figure 2. Pulling method remarkably reduces the required manpower and it also makes it
easier to control the cable feeding process. For installations in
ducts having an outer diameter of up to 60 mm the floating
2.3 Push-pull method
method has been used successfully for the insertion of single
To increase the installation length achieved with pulling, in
phase power cables 240 mm2 of up to 20 kV over 2 km in a
particular in the projects where the cable has to pass several
50/42 mm HDPE duct in one step (see figure 5). This method is
curves, the idea to push the cable simultaneously with pulling
not applicable for floating in ducts of over 60 mm outer
was introduced years ago. At first sight the method is equivalent
diameter due to excessive water consumption, causing water
to the pulling method. Indeed preparation and equipment are the
logistics problems.
same, except for a pusher placed between cable drum and duct
inlet. Typically the pusher is a two or three belt caterpillar
synchronised with the cable winch located at the other end of
the duct. Also in this case lubricant is generally used to reduce
the friction between the cable and the duct. The system is shown
in figure 3.

Figure 4. Floating method

Figure 3. Push-pull method

When compared to cable pulling the push-pull method has the


advantage of achieving longer lengths. For underground high
voltage cable installation, the distance between splices must be
maximised in order to minimise the cost. Therefore any
improvement in cable installation length performance is very
welcome.
2.4 Floating method
Cable installation by using fluids that propel the cable has been
Figure 5. Floating of a single phase cable
widely used for more than 20 years in the telecommunications

International Wire & Cable Symposium 170 Proceedings of the 58th IWCS/IICIT
2.5 Watucab method 3.1 Reference cables
The patented Watucab method [1] is combining the benefits of Two reference cables are considered. Their respective
the push-pull and the floating methods. According to this characteristics are shown on Table 1. These cables are currently
method a cable is fed into the pre-installed duct via a water inlet available and have been successfully installed with the new
chamber attached to said duct. A watertight pig [2] is attached to Watucab method [3]. The associated ducts are commonly used
the end of the cable. Pressurized water is fed into the duct via and fulfill conditions according to (1) and (2)
the water inlet chamber, the pressure difference over the
watertight pig exerting a mechanical thrust, resulting in a pulling
force at the cable foremost end. In addition to this pulling force Cable # Voltage Conductor Screen
a pushing force is exerted on the cable by means of a [kV] [mm2]
mechanical pusher located between cable drum and water inlet 1 225 1200 Al Al
chamber. Similar to floating the cable is subjected to
Archimedes uplift and friction can be reduced by environmental 2 63 630 Al Al
friendly additives in the water. The method is shown in the Cable # Outer dia Dc Lin. weight Stiffness
figure 6. [mm] [N/ m] [N/ m2]
1 109 111 6000
2 66 43 1800
Cable # Max pull Duct ID Diduct Ampl/ Period
allowed [N] [mm] [mm] / [m]
1 48000 192 200 / 28
2 25200 102 125 / 17.5

Table 1. Reference cables


Figure 6. Watucab method
Due to the presence of a watertight pig, the water flow is limited 3.2 Reference duct route
to the amount that travels with the cable, facilitating the water The reference duct route is intended to simulate typical urban
logistics, also for ducts of over 60 mm outer diameter. The route conditions. It follows a horizontal plane and has 90° bends
Watucab method offers several important benefits when with 10 m radius are evenly spread along the RDR i.e. every
compared to other high voltage cable installation methods: 150 m, the undulation defined by Amplitude A and Period T is
1) longer installation lengths in one step hence fewer splices, determined according to (2). (see figure 7)
even along heavily tortuous duct routes
2) one step process, no need for P-line or winch-line
3) control of the whole process from drum side only reducing
need for manpower and hazards inherent to communication or
coordination
4) cable integrity better insured by drastically lower tensile and
radial forces. As a result the Watucab method is much faster,
less costly and safer for cable, duct and environment. The
method has been tested and used several times in France with
good performance and the cable lengths of 3 to 4 km have been
reached in one step.

3. Maximum distances by method


In this chapter the maximum distances achieved, using the
traditional pulling and push-pull method and the new watucab Figure 7. Reference duct route (RDR)
method are compared using two reference cables and ducts over
reference duct route (RDR). The choice of duct which is specific
for each reference cable fulfills the generally applied rule 3.3 Performances analysis
regarding the minimum ratio between cable outer diameter Dc The installation performances achieved over the RDR are
and the duct inner diameter Diduct [1] . Also, as sections of buried obtained from calculations based on the theory of cable
ducts between bends are never perfectly straight it is assumed installation in ducts [4]. The results obtained from said
that they are continuously undulating. The chosen undulation calculations are closely matching with field experience
period (T) and amplitude (A) match with field observation, T worldwide and can therefore be considered as highly reliable.
being a multiple of the duct outer diameter Doduct and A being The performances achieved with each above mentioned
equal to Doduct[2] installation method are calculated with the same RDR
Diduct / Dc ≥ 1.5 (1) parameters as described in para. 3.2. Four different values for
the coefficient of friction m between reference duct inner wall
T = 140 x Doduct [m] A = Doduct [mm] (2) and cable jacket are considered: Mu = 0.1, 0.125; 0.15 & 0.2.
Performances achieved per method are described on Table 2.

International Wire & Cable Symposium 171 Proceedings of the 58th IWCS/IICIT
3.3.1 General observations 3.3.2 Forces exerted on the cable
From table 2 and 3 the performances achieved using the Pulling 3.3.2.1 Pulling force:
, Push-pull and Watucab method, one will note the significant The pulling force F [N] needed for achieving the installation
performance increase of 35 to 60% brought by the push-pull lengths shown on figure 2 are identical for the pull and push-
method, respectively 87 to 95% by the Watucab method when pull methods and correspond to the maximum allowable pulling
compared to conventional pulling . The coefficient of friction forces Fadm applicable for cable 1 & 2. These forces F are equal
Mu has a similar impact on all above mentioned installation to:
methods. This means that lubrication remains a key element
F = Fadm = σadm x Scond [N]
Where: σadm is the max admissible tensile load on the conductor
given by the cable manufacturer and S is the cable conductor
Mu = 0.1
metallic cross section [mm2]. For reference cables 1 and 2
Cable # Pulling Push-pull Watucab
σadm = 40 [N/mm2]
1 0.00% 40.00% 90.00%
2 0.00% 60.00% 100.00% Scond = 1200 resp 630 [mm2]
With Watucab the pulling forces F correspond to the force
Mu = 0.125 exerted by the water tight pig. They are equal to
Cable # Pulling Push-pull Watucab
F = P x Sduct [N]
1 0.00% 37.50% 87.50%
2 0.00% 62.50% 100.00% Where P is the water pressure [N/mm2] and Sduct is the duct
inner cross area [mm2]
Mu = 0.15
Cable # Pulling Push-pull Watucab
3.3.2.2 Pushing forces:
The pushing force Fs [N] applied in our case is 10000 [N]. This
1 0.00% 34.87% 94.81% corresponds to the push exerted by available pushing
2 0.00% 63.85% 93.64% mechanism which is common for both methods, i.e. Push-pull
and Watucab. This value satisfies the cable manufacturer
Mu = 0.2
requirements.
Cable # Pulling Push-pull Watucab
For the above described performance comparison, the pushing
1 0.00% 40.00% 93.87%
forces Fs [N] is identical for the Push-pull and Watucab method.
2 0.00% 60.00% 100.00% our case i.e.10000 [N] for cable 1 and 2. see table 5
From table 4 below one notes the considerably lower pulling
Table 2. Relative length increase per method forces exerted on cable 1 and 2 when compared to the pulling
having a direct impact on the installation length, from Table 2 force applied with the pulling or push-pull method. This
one can note that, for 0.1 < Mu < 0.2, the installation length is contributes to enhance the service reliability of the cable
more or less inversely proportional to the coefficient of friction
Mu.
Push-pull

F / Fadm
Watucab
(Fadm)
(Fadm)
Pulling

Mu = 0.1 (F)
Cable # Pulling Push-pull Watucab
cable#
1 1500 2100 2850
2 1500 2400 3000 1 48000 48000 17370 36.19%
2 25200 25200 6120 24.29%
Mu = 0.125
Cable # Pulling Push-pull Watucab
Table 4. Pulling forces comparison
1 1200 1650 2250
2 1200 1950 2400
Mu = 0.15
Fs Push-pull

Fs Watucab

Fs Push-pull
Fs Pulling

Fs Watucab/

Cable # Pulling Push-pull Watucab


1 1001 1350 1950
[N]

[N]

[N]

2 1007 1650 1950


cable#
Mu = 0.2
Cable # Pulling Push-pull Watucab 1 0 10000 10000 100%
1 750 1050 1454 2 0 10000 10000 100%
2 750 1200 1500
Table 5. Pushing forces comparison
Table 3. Performance per method, installation length

International Wire & Cable Symposium 172 Proceedings of the 58th IWCS/IICIT
4. Cost comparison of methods This buried duct route, made of 160/152 mm PVC includes a
Although it is very difficult to compare the methods in specific total of fourteen 90° bends and 3 siphons evenly spread over
countries in real monetary terms we have made an analysis of 976 m. This represents a cumulated angular deflection of 1620°.
the cost factors based on man-hours and number of splice This is more severe than most urban duct routes.
chambers required for the construction of a typical 21 km long For validation purpose 1 km of 90 kV, 1000 mm² Al, with ext.
underground power line cases. Manpower needed for duct diameter 82 mm, 68 N/m has been successfully placed in the
placement and cable drum logistic is not taken into account here above described test circuit. Furthermore said cable has been
as it remains more or less equivalent with all installation placed and removed several times (for tests and demonstration
methods analyzed here . The results are shown in table 5. purpose) To remove the cable the Watucab process is reversed
i.e. water is injected from the opposite duct end after having
pivoted the pig in order to make it act on the cable extremity as
a pusher instead of a puller. The pusher is also reversed and
becomes a puller. In this way the cable is removed from the duct
and recoiled on the drum at a very low load. This demonstrates
that Watucab is a reversible process allowing for an efficient
upgrading of power-lines as the removed cable can be replaced
by an other with larger capacity.
Installation forces exerted on the cable : 6000 N for pulling
respectively 7000 N for pushing.

5.2 Projects / field experience


5.2.1 Floating method
Numerous customers’ projects have been accomplished and
successfully achieved for low and medium voltage applications
i.e. up to 25 kV networks. For instance:. lighting of highway
interchanges, power distribution in dense urban areas, and
special industrial application such power transmission in tunnels
and water shafts.
Table 5. Cost factor in cable installation methods
In the Neuchâtel region, Switzerland (see Figure 9), floating in
The numbers shown on table 5, based on recent experience, one step over a 2.7 km route, 3 x 12/20 kV, 125 mm2 Cu, linear
clearly indicate the importance of the savings obtained by the weight 14 N/m, ext. diameter 34.5 mm, linear weight 23 N/m.
reduction of the quantity of joint chambers i.e., 60% when Duct used: 3 x HDPE diameter 48/42 mm , wall mounted (water
compared with pulling and 37% when compared with push-pull. shaft).
The cost savings for labor is also significant i.e. 54% of the
amount of man-days needed

5. Examples of tests and achievements


using Floating and Watucab
5.1 Validation
A dedicated test circuit has been built in France as described on
figure 8.

Figure 9 : Neuchâtel

5.2.2 Watucab method


Over the last 4 years seven high voltage projects have been
successfully carried out in France. The aim of the projects was
to replace overhead power line sections heavily exposed to
storms or, in urban areas, to meet new requirements for urban
planning. To this day more than 100 km of single phase cable of
63 to 225 kV have been installed using the Watucab method.
Section lengths range from 1.6 to 3.3 km. Two typical projects
Figure 8 : trial circuit are:
In Normandy, France (see Figure 10), installation over a 6.1 km
long route, 3 x 90 kV, 630 mm2 Al single phase cable, ext.
diameter 72 mm, linear weight 49 N/m. Duct used: 3 x HDPE

International Wire & Cable Symposium 173 Proceedings of the 58th IWCS/IICIT
diameter 160/132 mm. Average section length 2.03 km, longest 5) Faster and less costly installation
section: 2.3 km 6) reversible process allowing network upgrade
The high voltage cables are installed in increasing amounts under
ground for several reasons. The main drivers are better protection
of the cable against weather hazards and public acceptance than
for aerial cables. The main limiting factor for underground cables
has been the higher installation cost than for aerial cable
networks. Watucab offers an efficient solution to install high
voltage cable under ground at lower cost compared to any other
underground cable installation method. The system has proved to
be viable and offering important benefits to the cable companies,
installers and the end customers
7. Acknowledgements
Special thanks to Willem Griffioen for his precious support and
advice during the preparation of this paper.

8. References
[1] EP 1456923. “Method for Installing a High or Medium
Voltage Power Cable in the Ground.” Plumettaz SA
[2] EP 1518307 « Pig for installing a cable in a conduit »
Plumettaz SA
[3] M. Le STUM & Al., “Report on the Use of Extruded Cables
on the French Grid”.Chap. 4 B1-204, CIGRE 2006,
www.cigre.org
[4] W. Griffioen, «Installation of Cables in Ducts”, Plumettaz
Figure 10 : Normandy
SA Bex (CH) (1993) ISBN 9072125 37 1
In Brittany, France (see Figure 11), installation over a 19 km
long route, 3 x 63 kV, 800 mm2 Al single phase cable, ext
diameter 68 mm, linear weight 51 N/m. Duct used: 3 x HDPE
The Authors
Gerard Plumettaz received a MS degree
125/102 mm The average section length is 3.17 km, longest
in mechanical engineering at the Swiss
section: 3.31 km..
Federal Institute of Technology, Zürich,
in 1970 with an emphasis on machine
tool techniques. Joined his family
business, Plumettaz SA, Bex, Switzer-
land, in 1971 and became instrumental in
product design, development and
marketing. Initial task was to design
and develop winching concepts for
military tank retrieval. Here specialized
winching techniques led to the design of underground placement
methods. Until 2009, CEO of Plumettaz SA. Today Chairman of
Plumettaz Holding SA, he is continuing to be active in the pursuit
of advanced methods in underground placement technology.
Jouni Heinonen holds a MS degree in
mechanical engineering from the
Tampere University of Technology, in
Finland. He began his career in 1986 as
Product manager at Falcon Chemicals
Figure 11 : Brittany in Finland and then joined Nokia Cable
Machinery in Finland as Product
6. Conclusions Development Engineer. In 1988
A new method for installation of high voltage energy cables in he joined Nokia-Maillefer Oy as
pre-installed ducts has been developed and successfully applied. Product Development Manager and
The method is applicable for ducts with an outer diameter superior moved to Switzerland to join Nokia-
to 60 mm. The main benefits gained from this innovation are Maillefer SA, initially as Project leader
1) longer installation lengths in one step saving expensive joints to finally become Managing Director in 1996. From 1998 he held
2) one step process the role of Executive VP of Business Group Plastics of Nextrom
3) process control from drum side only enabling easy visual and became CEO of Nextrom Holding SA from 1999. From 2005
communication between active parties thus avoiding hazards to 2008, he held the role of CEO of Gurit Holding AG. Today, he is
4) Increased protection of cable integrity acting as CEO of Plumettaz Holding SA in Switzerland, a leading
manufacturer of cable laying equipment.

International Wire & Cable Symposium 174 Proceedings of the 58th IWCS/IICIT

Vous aimerez peut-être aussi