Académique Documents
Professionnel Documents
Culture Documents
DESIGN GUIDE
FOR
SLABS ON GRADE
FLOPPY NO :
FILE NAME : SLAB.DOC
VALID UPTO
REV.NO R0 ISSUE
PPD.BY DVSBNR
CKD.BY SBK R0
APP.BY RBG
DATE
TATA CONSULTING ENGINEERS SECTION:REV.STAT.
TCE.M6-CV-064 SHEET ii OF iii
SLABS ON GRADE
ISSUE
R0
CONTENTS
1.0 INTRODUCTION 1
2.0 SCOPE 1
APPENDIX-1 - TABLES 11
APPENDIX-2 - FIGURES 14
ISSUE
R0
1.0 INTRODUCTION
2.0 SCOPE
This design guide covers different design methods being practised to arrive at
the optimum grade slab thickness for the required design loads. It also
covers guidelines for sub base thickness and joint practices.
In general this guide can be used to arrive at the thickness of the grade slab
in the buildings used for industrial purposes.
4.1 DEFINITIONS
ISSUE
R0
Slab : This is the main structural concrete element forming the floor. This
may be either reinforced or unreinforced, depending upon site conditions and
design details.
Wearing Surface : This may be the upper surface of the slab suitably
finished, or an applied topping or covering material.
4.2 NOTATIONS
in : inches
For weak subgrades of soil types, such as clay, silt and sandy silty clay with
water table within 600 mm of formation level, a sub-base of 150 mm
thickness is recommended. In case of normal sub-grades of soil types
comprising of well graded and drained sand or sandy gravel, 80 mm thick
sub-base is recommended.
ISSUE
R0
Where the ground is very unstable or where considerable depths of fill have
been used and high settlements are expected, the floor may be designed as a
suspended slab on pile foundations.
Normally, for good abrasive resistance under the action of moving wheels,
dragging of heavy castings and such other metal equipments, fork lifts with
iron-typed wheels, etc. Concrete with a cube-crushing strength of 40
N/mm2 at 28 days, (grade M40) is recommended. Under normal loading
conditions grade M15 is generally adequate.
Thus the topping may be about 50 mm for integral construction and about
75 mm for bonded construction.
From practical considerations, preferably the bay width should not exceed
about 4.5 m. If the slab is unreinforced, joints should be formed at
intervals not exceeding 6 m. Floors are usually constructed as follows.
Chequer Board Construction : In fill bays are usually laid after 7 days or
more in an attempt to eliminate shrinkage contraction movement.
ISSUE
R0
Portland Cement Association has studied the pavement theory and developed
thickness design charts for floors on grade. The design methods are also
published by Portland Cement Association. The method is also
applicable to slabs on ground for outdoor storage and material handling
areas. The factors involved in determining the required floor slab thickness
are:
Following factors are required to arrive at the thickness of the grade slab.
If the tyre data is not available, the contact area can be estimated for pneumatic
tyres by dividing wheel load by inflation pressure. Safety factors in the range
ISSUE
R0
of 1.5 to 2.0 are suggested for industrial floors. For light traffic, lower safety
factors can be used.
Procedure
640
Concrete working stress = = 320 psi
2
320
Slab stress per 1000 lb of axle load = = 12.8 psi
25
Refer Fig.2.0, locate the point left hand side vertical axis corresponds to
stress 12.8 psi, move right to contact area of 114 sq.inches, down to wheel
spacing of 37 inches taken right to read a slab thickness of 7.9 inches on the
line for subgrade modulus k of 100 psi.
When loads on rack legs exceed the wheel loads of vehicles operating in
the wear house, leg loads will control the thickness of slab. When a correct
size of the base plate is used, concrete bearing and punching shear stresses
will remain within acceptable limits. The design factors are same as used
for vehicle loads except that a higher safety factor is selected. Safety factors
in the range of 3.9 to 4.8 will satisfy building code requirements when
the rack leg is regarded as a supporting column and the slab is
regarded as an unreinforced spread footing.
ISSUE
R0
Data
Procedure
Refer Fig.3.0, locate the point on left hand side corresponds to effective
contact area of 50 sq. inches and a stress of 20 psi, move right to Y-spacing
of 60 inches, upto X-spacing of 50 inches taken right to read a slab thickness
of 11.4 inches.
Uniform loads are defined as loads distributed over a large area. For most
wear houses and industrial floors, concentrated loads are the controlling
design factor since distributed loads do not usually produce stresses of the
same magnitude.
ISSUE
R0
Reinforcing steel will enhance the performance of the slab on grade. Steel
reinforcement will help in preventing the formation of cracks.
There are two aspects to give attention in the use of reinforcement for
industrial floors. One is the quantity of the reinforcement. The second
is the placement of the steel within slab.
The amount of longitudinal and transverse steel required per metre width
or length of slab is computed by the following formula:
Lfw 2
Area of steel, A = cm /m width or length
2S
Where L = Dist. in 'm' between free transverse or free longitudinal joints
ISSUE
R0
Where,
As = Cross sectional area of reinforcement
L = Panel length in metre between expansion joints where
provision is made for movement of panel
ISSUE
R0
These joints are meant to accommodate expansion and are provided with a
clear gap for the full depth between adjacent slabs. They are spaced at 25 m
to 30 m along the slab length and are filled with an expansion joint filler
which is compressible enough to accommodate the expansion of the adjacent
slabs. For this purpose, it is required to use a filler confirming to IS:1838.
Dowel bars may be omitted for slabs less than 150 mm thick. Expansion
joints may be provided with load transfer devices which are generally dowel
bars cantilevering out 450 mm on either side of the joint or tongue-and-
groove joints.
Load transfer devices transfer the load from one panel to the other at the
expansion joint.
It is not possible to have a load transfer device at the entrance; the base slab
thickness may therefore be locally increased by 50 percent.
7.3 CONTRACTION JOINTS (OR) CONTROL JOINTS: Control joints act to relieve
stress and with proper spacing they eliminate the cause of uncontrolled
random cracking. They allow horizontal movement of the slab. Control
joints in industrial and commercial floors are usually cut with a saw. They
should be cut to a depth of generally 1/4 the slab thickness.
The objective is to form a plane of weakness in the slab so that the crack
will occur along that line to avoid random cracking and curling. In case of
thick slabs a crack inducer is anchored to the subgrade immediately
below the joint. Load transfer across a control joint is provided by the
interlocking of the jagged face formed at the crack. For long joint
spacings or heavily loaded slabs, dowel bars are used as load transfer
devices. The above discussed varieties of control joints are shown in
Fig.7.0.
ISSUE
R0
7.3.1 Longitudinal Control Joints : These are the main construction joints to
be provided at not more than 4.5 m apart. Tie bars, 12 mm dia, 900 mm long
at 600 mm centre to centre at every fourth longitudinal joint should be
debonded to permit contraction movement.
7.3.2 Transverse Control Joint : These joints limit the concrete tensile stresses
to control cracking. Control joints are spaced at 5 m to 6 m intervals and
are formed by providing a continuous, crack inducing dummy groove or saw
cut in the upper portion of the base slab. In case sawed joints are
adopted,the depth of the saw cut should not be less than the diameter of the
largest-size coarse aggregate. The width of the dummy groove should be 5 to
10mm and its depth one fifth of the slab thickness with a minimum of 25
mm and a maximum of 50 mm. In slabs thicker than 200 mm, the lower
crack inducer reduces the depth of the surface groove. The closer joint
spacing in unreinforced slabs can limit the crack width and eliminate the
tying. A free contraction joint is normally used only for slabs thicker than
225 mm, subject to heavy wheel loads over 5t. The grooves should be filled
with hot applied sealing compounds confirming to IS:1834.
7.4 CONSTRUCTION JOINTS : Construction joints usually form the edges at the
end of each day's work. They are located to confirm to the floor jointing
pattern. Where there is no control or isolation joint, a butt-type construction
joint is satisfactory for thin floors. For thick and more heavily loaded
floors, a tongue and groove joint is used or dowels are added to the butt
joint. A bonded construction joint in a plain slab is a butt type construction
joint with tie bars when concrete placement is interrupted for 30 minutes.
Different varieties of construction joints are shown in Fig.8.0.
ISSUE
R0
TABLE - I
ISSUE
R0
TABLE-II
ISSUE
R0
TABLE-III
À
Occupancy Min. slab Reinforcement
Thickness
(mm)
Sub-slab under other slabs 2" (50) None
Domestic or light commercial 4" (100) One layer 6x6 10/10 welded wire
(loaded less than 100 psf) (488.2 fabric, minimum for ideal conditions:
kg/m2) 6x6 8/8 for average conditions
À
For single layer, the reinforcement shall be provided at 50 mm from top
surface. For two layers, top mat shall be provided at 50 mm from top and
bottom mat shall be provided at 50 mm from bottom of slab.
Á
6x6 6/6 means 6" x 6" spacing in both directions
6/6 wire gauge number in both directions
ISSUE
R0