Académique Documents
Professionnel Documents
Culture Documents
Abstract: The Three Gorges Project is one of the essential key projects for flood controlling and water resources regulation in
the Yangtze River. The project includes a river-crossing dam, underground powerhouses, and navigation structures. Because of
the huge size and complicated construction technologies, the project faced a series of challenging engineering issues. In terms of
rock mechanics, there are many key technical issues, including the sliding resistance and stability of the dam section along the
foundations of powerhouses No.1–5, the slope stability of the double-line five-stage shiplock, excavation of large-scale
underground powerhouses, and curtain grouting under the dam. With decades of scientific research and 16 years of practical
construction experiences and reservoir operations, these key technical issues in construction of the Three Gorges Project are
successfully resolved, which will attribute to the development of hydropower technology. On the basis of the monitoring data during
construction and normal operation periods of the Three Gorges Project, this paper presents a systematic analysis of these key rock
mechanical issues in terms of behaviors, solutions, dynamic controlling, monitoring arrangement and integrated assessment.
Key words: Three Gorges Project; rock mechanics; dam sliding resistance and stability; high shiplock slope; underground
powerhouses; curtain grouting
1 Introduction
generating units in the powerhouses on the left and experts were engaged to the scientific research,
right banks of the river behind the dam were put into computational analyses and optimization design of the
operation. Thus, the hydropower complex was project. Moreover, the required productive
completed (excluding the construction-postponed ship experiments were conducted, and related feedback
lift), and the reservoir was ready to impound to the information was achieved. With these efforts,
normal level of 175 m. The Three Gorges Reservoir systematic and scientific technical requirements for
started a trial water storage at the end of rainy season engineering design and construction of the project
in 2008, and in December 2010, the Three Gorges dam were formulated [1–6].
had experienced three years of trial water
impoundment. The water level in the reservoir reached
172 and 175 m after the end of rainy season of 2009 2 Sliding resistance and stability of
and 2010, respectively. All monitoring data and left-bank powerhouses No.1–5
analytical results show that the operation of the Three
Gorges Project is normal. Since its water 2.1 Solutions
impoundment from 2003, the Three Gorges Project The dam sections of powerhouses No.1–5, on the
has shown comprehensive benefits in flood control,
left bank of the Three Gorges dam site, are located in
power generation, navigation, water supply, and
the riverfront slopes of mountainous region. The host
environmental protection, greatly contributing to the
rock masses in the dam foundation are primarily
sustainable development and steady growth of the
composed of fresh flash-cloud plagioclase granite,
Chinese economy.
containing crevices with long and large low-angle dips
1.2 Key rock mechanical issues
with an occurrence of NE-NNE, inclined SE (inclined
Key rock mechanical issues of the Three Gorges
towards the left bank of the lower reach of the river),
Project include the sliding resistance and stability of
the deep layers of the dam sections of powerhouses as well as a small number of crevices with
No.1–5, the slope stability in the double-line five- intermediate inclination towards the lower reach of the
stage continuous shiplock, the excavation of large- river. The powerhouses are arranged behind the dam.
scale underground powerhouses, and the curtain The dam section of the powerhouses has a foundation
grouting under the dam. To cope with these technical elevation of 90 m. The powerhouses have an elevation
issues, numerous field geotechnical investigations and of 22.2 m, resulting in a steep slope behind the dam,
scientific experiments were conducted in the 1950s, which has a gradient of 54°, a temporary height of
allowing the engineers to identify the characteristics 67.8 m and a permanent height of 39.0 m, as shown in
and fundamental parameters of the rock masses in the Fig.2. These factors make it possible for the deep
dam area. In addition, a number of research institutes, layers at the dam section of the left-bank powerhouses
universities, design institutes and several foreign No.1–5 to slide.
Fig.2 Typical foundation profile at the dam section of left-bank powerhouses No.1–5 and dam foundation reinforcement (unit: m).
Qixiang Fan et al. / J Rock Mech Geotech Eng. 2011, 3 (4): 329–342 331
To meet the required stability of deep layers in the the dam foundation ranged from –0.7 to 0.6 mm. After
dam, the following engineering measures were reservoir impoundment, the variation slightly
introduced: (1) slightly reducing the foundation increased, ranging from –0.8 to 3 mm. After the
elevation, and setting a cutoff trench at the dam heel; experimental water impoundment in the Three Gorges
(2) increasing the width of the dam bottom towards Reservoir, the water level reached 175 m in 2010, and
the upstream, and moving the curtain water drainage the variation in horizontal displacements of the dam
forward; (3) setting up a contact grouting system foundation ranged from 1.89 to 2.69 mm, with an
between the powerhouses and the rock slope of the annual change of 0.44–0.88 mm. The horizontal
dam to ensure the integrity of concrete and the rock displacements of deep foundation rock masses for the
slope; (4) setting keyways at the cross joints on the left-bank powerhouses No.1–5, which have an
dam section of the left-bank powerhouses No.1–5, and elevation below 95 m, ranged from –1.27 to 3.3 mm,
filling these joints with grouting to strengthen the and the increment in the horizontal displacements at
overall functions of the dam sections; (5) carrying out the foundation drainage tunnels before and after the
solid grouting in certain locations of the tail water experimental impoundments, in 2008 and 2010,
channels of the hydropower plant to ensure the ranged from –0.09 to 0.17 mm. The annual increments
functions of the downstream resistance body; (6) in displacement are basically consistent. The minimum
adding prestressed anchorage cables on the crevices increment occurred in 2010. Foundation deformation
with long and large low-angle dips from the on the dam section of the left-bank powerhouses
downstream slope surface; (7) considering a down- No.1–5 is converged.
stream drainage gallery with an elevation of 26 m 2.2.2 Monitoring of settlements at dam foundation
below the foundation of the dam section of the Figure 4 shows the measured settlements of the
left-bank powerhouse No.3; (8) adding 3 000 kN-grade upstream and downstream grouting galleries of the
prestressed anchorage cables on the structural plane of left-bank powerhouses No.1, 3 and 5.
crevices with long and large low-angle dips at the LD01ZC013 (No.1)
left-bank powerhouses No.1–3; and (9) carrying out 0
Displacement (mm)
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
4.0, which can meet the design requirements and
Date
provide a considerable safety margin. (a) Upstream.
2.2 Monitoring results of the dam sections of the LD02ZC013 (No.1)
0
Displacement (mm)
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2002
2003
2004
2005
2006
2007
2008
2009
2010
typically about 0.5 mm, indicating that there was no been basically stabilized since 2001.
uneven settlement in the dam foundation. Statistical analyses of the downstream horizontal
2.2.3 Monitoring of deformations inside rock displacements of the left-bank powerhouses No.1 and 5
foundation indicate that the downstream horizontal displacements
It can be observed from Fig.5 that horizontal in the foundation can be divided into two parts, one is
displacements inside the deep rock masses (with a approximately 1.4 mm induced by water pressure and
depth of 45–55 m) measured by a clinograph were another one is less than 2.5 mm induced by temporal
small. Measuring holes in direction A (upstream and effect. The temporal effect component varied mildly,
downstream) had a maximum cumulative downstream but not completely constrained. It is consistent with
displacement of 15.6 mm, and the rest had a the pattern of changes in the temporal effect
displacement of –5.8–9.3 mm. The measured values component at the foundation galleries of right-bank
fluctuated around the median value, while powerhouses No.24–26 and left-bank powerhouse
measurement had a measuring error of ±6 mm. No.14. The incomplete displacement constraint of the
Instrument IN1CF5 did not detect any dislocation of temporal effect is largely attributed to the relatively
the rock strata in a hole at depth of 50 m, indicating short duration of impoundment in the reservoir.
that the rock masses remained stable. Therefore, further monitoring is needed. Generally, the
rock masses at the foundation of the left-bank
20 powerhouses No.1–5 are stable.
Displacement (mm)
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
0.9
0.6 of the left-bank powerhouse using a dynamometer.
0.3 SF1CF05 No.5 (88.0 m) Tonnage: 3 030.5 kN
#1 (5.0 m) #2 (10.0 m)
0.0 31 Loss rate 2 950
#3 (25.0 m) #4 (35.0 m)
25 2 790
Loss rate (%)
Force (kN)
0.3
2 630
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
19
13 Anchoring force 2 470
Date
7 2 310
Fig.6 Time-dependent curves of cumulative displacement at 1 2 150
each measuring point measured by multi-point borehole
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
extensometer.
Date
Fig.7 Time-history curves of force changes in anchorage cable
It can be observed from Fig.6 that horizontal measured by a dynamometer.
displacement of rock masses was small at the depth of
35.0 m, and had a springback of less than 1.1 mm in It can be observed from Fig.7 that over 1.5 years
the downstream direction. The other eight boreholes after installation, the prestressed anchorage cables
also had a small magnitude of deformation, ranging experienced a considerable loss of prestress.
from 0.6 to 2.3 mm with an annual change of –0.03– Afterwards, the loss rate decreased, and the prestress
0.06 mm. The displacement curves indicate that the change had a close relation with temperature, i.e.
deformation of the rock masses behind the dam has rising when temperature went up and falling when
Qixiang Fan et al. / J Rock Mech Geotech Eng. 2011, 3 (4): 329–342 333
temperature went down. After 2006, the prestress geological conditions. A water pressure distribution
remained stable, indicating that the bedrocks behind chart was prepared on the basis of actual
the dam were stable. measurements after impoundment at 175 m, as shown
2.2.6 Monitoring of drainage and seepage pressures at in Fig.8. It can be observed from Fig.8 that the
foundation measured groundwater level is lower than the slip
In a global sense, the dam sections of the left-bank plane; therefore, no impact will be induced on the
powerhouses No.1–5 experienced insignificant changes stability of the dam body. It also shows that the
in seepage pressure before and after experimental measured uplift pressure is smaller than the designed
impoundment in each year. The seepage increased value. From 2008 to 2010 after experimental
slightly after experimental impoundment and impoundment at 175 m, the measured uplift pressures
exhibited an upward tendency. The uphole of drainage at the foundation of the left-bank powerhouse No.3
tunnel No.1 had a flow of less than 2.0 L/min. It was were 48.81%, 49.38% and 49.6% of the designed
generally free water, indicating that the dam uplift pressures, respectively. The measured uplift
foundation behind the main drainage curtain at an pressure was smaller than the designed uplift pressure.
elevation of 74 m (and upward) was dry. The drainage Analysis of data obtained from piezometer tubes on
tunnel had a total seepage rate of less than 135 L/min. the left-bank powerhouses No.1–5 shows that the
The total seepage declined slightly after 2003, and the uplift pressure coefficients behind the upstream and
drainage tunnel had a measured seepage rate of downstream curtains at the dam foundation are smaller
approximately 85.1 L/min on November 30, 2008, than corresponding designed values of 0.25 and 0.30.
77.5 L/min in January 2010, and 66.85 L/min on The water level between the upstream and
October 30, 2010. Preliminary analysis suggests that downstream drainage tunnels is far below the
the steady decline in total seepage at the dam deep-layer slip plane. The water levels between
foundation is basically attributed to the following upstream and downstream drainage tunnels are
factors: (1) silting was increased in front of the dam; basically the same and do not change with the rise and
and (2) seepage crevices inside the bedrocks became fall of the upstream water level. The measured uplift
compacted due to the water pressure from the pressures on the two typical deep-layer slip planes are
reservoir basin filled up by silt. The steady decline of 40%–56% of the designed value.
total seepage at the foundation of the Three Gorges
▽185
dam was basically consistent with the variation ▽175 Sliding path
▽171.26 Designed pressure
patterns of seepage in other projects after Measured water level
Measured pressure
▽153.06
impoundment. Water levels in the piezometer tube at
20+000.000
▽136.89
20+35.000
1 Unit: m
experimental impoundment in each year did not show
▽108
any significant change. The seepage pressure at the ▽106.6
2
20+118.000
3
dam foundation behind the main drainage curtain on ▽90 ▽91.10
A ▽81.7
the upstream left-bank powerhouses No.1–5 was ▽85
▽ 74 B ▽75
4
▽65 ▽65.4
below the elevation of 52 m. Actually measured
▽ 51.89 ▽ 53.44 C
▽ 50
seepage pressure in the deep holes of the piezometer F
▽42
5
175 m ▽36.47
tube in the middle of the foundation of the left-bank I
20+015.600
20+007.200
▽ 26.34 ▽ 25
▽23.5 ▽23.6
powerhouse No.3 was 49–52 m (41–38 m below the
169.750
I
110.000
20+
▽0
Fig.9 Instrument layout of cross-section 17-17 (stake 15+675) of the shiplock (unit: m).
TP29GP02 (245 m) TP09GP01 (170 m) during excavation and increased with increasing depth
295
Displacement (mm)
199601
199712
199912
200312
200512
200712
200912
200112
Excavation outline
50 260 TP/BM39GP02, stake number: 15+850,
40
Excavation elevation (m)
225 80 200
30 elevation: 215 m, (No.3, south)
70 185
displacement (mm)
20 190
170
The maximum
10 155 60
50 155
0 120
10 40 140
85 TP/BM15GP01, stake number: 125
30
199401
199601
199712
199912
200312
200512
200712
200912
15+851
200112
20 110
Excavation elevation 95
10
0 80
Date
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
Stress (MPa)
100 140
80 Stress 130
September 1999, the deformation rate slowed down 60 120
and was gradually stabilized. In December 2010, the 40 110
20 Excavation elevation 100
northern and southern slopes of the shiplock had 0 90
20 80
maximum displacements of 53.9 and 71.57 mm,
199701
199901
200101
200301
200501
200701
200901
201301
201101
respectively. After the experimental impoundment to
elevation of 175 m in 2010, slope displacement varied Date
Fig.13 Time-history curve of stress changes in the anchorage
within an observational error of ±1.5 mm, indicating rods for cross-section 17-17 (stake 15+675) of the southern
that impoundment had no drastic effect on slope slope above the shiplock head.
deformation.
3.3.2 Monitoring of stresses of anchorage cables for excavation. The stresses of the anchorage rods,
shiplock slopes ranging from –116.38 to 136.65 MPa, had a negative
Figure 12 shows the time-history curve of stress relation with temperatures, and 52% of the total
changes in the anchorage cables at the cross-section anchorage rods had a stress less than 50 MPa. The
17-17 (stake 15+675) of the northern slope above the stresses of most anchorage rods fluctuated with
shiplock head. temperature, with an annual change of 5.07–57.81
MPa and accumulative stress change of 15 MPa. This
No: SF12GP01, stake number: 15+675, elevation: 180 m indicates that the anchorage rods and cables are
Anchoring force (kN)
3 000
2 840 effective in reinforcing the high slopes of the shiplock.
2 680
The displacement has been controlled since the
2 520
1 2 3 anchorage rods were installed, and the slopes were
2 360
2 200 stable overall [7, 8].
199701
199901
200101
200301
200501
200701
200901
201301
201101
drainage trenches, are effective for the project. The main underground powerhouse of the Three
Before the impoundment in September 2010, total Gorges Project is equipped with six 700 MW
seepages in the drainage tunnels on the 1st to 7th hydro-turbine generating units. The cross-section of
layers in the southern and northern slopes were 981.07 the chamber of the main powerhouse was roughly
and 920.99 L/min, respectively. After the rectangular with an arch-curved roof. The crest of the
impoundment in October 2010, the seepage flow chamber is set at the elevation of 105.3 m.
dropped to 60.08 L/min, indicating that impoundment Powerhouses below the rock anchorage beams have a
at elevation of 175 m had no impact on seepage in the span of 31.00 m, and 32.60 m for those above the rock
high slopes. Seepage in the drainage tunnels was anchorage beams. The dimensions of powerhouse are
primarily affected by rainfall, and the duration of 87.3 m high and 311.30 m long. The cross-section of
rainfall reduced agreed well with the period of underground powerhouse No.4 and distribution of
impoundment. Generally, the seepage of shiplock deformation of surrounding rock masses are shown in
drainage system exhibited a downward tendency Fig.14.
before and after impoundment. The main underground powerhouse is located at the
As the shiplock head and the chambers were right bank of the Three Gorges. The surrounding rock
supported by concrete lining, a crisscross drainage masses of the powerhouses are primarily fresh
system was arranged at the high slopes and vertical plagiogranite and diorite rocks of the Presinian system.
walls behind the lined walls. Monitoring data Fractures were developed in the rock masses, and the
major faults include F20 and F22 with a NNW
indicated that the shiplock and the back of the
orientation, and F84 (a fault zone) and F10 with a
chamber walls had a small seepage pressure, typically
NE-NEE orientation. The surrounding rock masses of
with water head less than 1.0 m. The shiplock head
the powerhouses are slightly permeable strata due to
and the chambers basically remained dry. Only in a
faults and strong weathering. Groundwater mainly
few locations, the measured water head reached 2.4 m,
comes from the upstream reservoir, right hill,
but still much lower than the designed value of 8.0 m.
atmospheric precipitation, and construction-induced
The water head on the bottom was typically below 4.0 m, water.
with the maximum of 6.9 m (the northern line of To ensure that the excavation quality of the main
Chamber 1), indicating that the drainage system was powerhouse could meet the design requirements, a
effective. At present, seepage flows in the foundation series of indoor and field experiments were carried out.
drainage galleries on the southern and northern lines Significant results were achieved: (1) The excavation
were 2 537.12 and 2 215.64 L/min, respectively, precision of the main powerhouse was ensured by
highest in winter and lowest in summer. The change of adopting a series of advanced construction technologies.
seepage flow is related to temperatures, water-proof A significant improvement on excavation precision
and impoundment. The back of the shiplock walls was observed. The average over-excavation at the top
typically has a water head less than 1.0 m, and the arch was controlled at 8.5 cm. More than half of
highest one, as measured in certain location, is 0.023 over-excavation was controlled within 20 cm. (2) To
MPa. The highest seepage pressure on the bottom of further improve the effect of tensile anchorage rods,
the chambers is 0.068 7 MPa. experiments on grout injection equipment and
Actual monitoring data show that the deformation techniques for anchorage rods, as well as water-
of the rock masses in the slopes primarily occurred cement ratio, were conducted and optimized. As a
during excavation and increased with further result, the compactness of cement around the
excavation. The deformation rate dropped gradually anchorage rods is more than 90%. (3) Some
after excavation was completed. The slopes can be significant breakthroughs were made in environmental
seen as stable as all monitoring data are within the protection and occupational health by introducing new
designed ranges. concepts and measures. (4) Adding access road,
smooth blasting and presplitting blasting was adopted
4 Key excavation technologies for to ensure normal construction of the main powerhouse.
underground powerhouses These efforts ensured the top arch deformation to be
controlled within 2 mm. Thus, the stability of the
4.1 Excavation technologies for the Three Gorges surrounding rock masses of the large chambers during
underground powerhouses construction is ensured [10, 11].
338 Qixiang Fan et al. / J Rock Mech Geotech Eng. 2011, 3 (4): 329–342
Fig.14 Cross-section of underground powerhouse No.4 and distribution of deformation of surrounding rock masses (unit: mm).
4.2 Monitoring of underground powerhouse blocks, six multi-point borehole extensometers were
4.2.1 Monitoring of deformation of surrounding rock set on top of the arch of the powerhouses. The
masses measured displacement was relatively small, ranging
Figure 15 shows the time-history curves of from 1.24 to 1.86 mm.
displacement and excavation changes in M13DC04. 4.2.2 Monitoring of anchorage rod stresses
#1 (34.1 m) Figure 16 shows the time-history curves of stress
Excavation elevation (m)
Excavation elevation 80
Displacement (mm)
30
25 70 changes in the anchorage rods on the upstream and
20 60 downstream sidewalls and arch crown of generating
15 #2 (22.9 m) #3 (13.3 m) 50
10 #4 (3.9 m) 40 unit No.4.
5 30
0 20
R23DC04 #4 upstream arch abutment
5 10
200601
200701
200801
200901
201001
Date
15 7
Fig.15 Time-history curves of displacement and excavation 10 R13DC04 #4 downstream sidewall 5
changes in M13DC04. 5 2
0 0
It can be observed from Fig.15 that the deformation
200501
200601
200701
200801
200901
201001
201201
201101
4.2.3 Monitoring of anchorage cable stresses sidewalls, the opening width of generating unit No.4
Monitoring was carried out from 2006 to 2011 on was 5.59 mm, while 0.0–0.58 mm at other locations
the section of generating unit No.1 (the 4th layer) of (0.58 mm at arch crown of access tunnel). Currently,
the upstream sidewalls, key block No.7 of the main the rock anchorage beams on K0+30.0 to K0+471.0,
powerhouse, the section of generating unit No.4 (the upstream segment of installation section II of the main
2nd layer) of the downstream sidewalls. The measured powerhouse, have an internal temperature of 6.0 °C–
data of downstream keyway of generating unit No.4 11.5 °C, while those on K0+51.0 to K0+61.0 have an
were used to analyze the process of changes in internal temperature of 8.3 °C–13.0 °C. Measured data
anchoring force of the anchorage cables, as shown in on the rock anchorage beams showed that the stress
Fig.17. ranged from 9.7 to 33.99 MPa, within the allowable
SF22DCXYQ (No.4, keyway)
limits.
3 250 4.2.5 Monitoring of seepage
Anchoring force (kN)
200701
200801
200901
201001
201201
201101
Drainage gallery
120.00 (250 cm 300 cm)
Drainage gallery
108.00
98.00 (300 cm 350 cm)
85.00 90.00
Dam axis 75.00 82.00
Drainage gallery Grouting hole
(300 cm 350 cm) 45.00 (hole distance 200 cm, 50.00
Drainage gallery
Drainage gallery row distance 80 cm) (250 cm 300 cm)
(250 cm 300 cm) 20.00 23.00 25.00
15.00 Drainage gallery
Drainage hole
Grouting hole 0.00 2.00 Grouting hole
(hole distance 300 cm)
(hole distance 250 cm) Drainage hole 14.00
Drainage hole 27.00 (hole distance 200 cm)
(hole distance 200 cm) 66.00
80.00
Left powerhouse section profile No.3
Fig.18 Layout of the impervious curtain and drainage arrangements on the foundation of a typical dam section (unit: m).
construction, and high-pressure grouting tests were average cement injection of 28.32, 9.96 and 6.23 kg/m,
conducted during construction. During dam curtain respectively.
grouting, a variety of measures were adopted, After grouting was completed, water was filled up
including pressure-increasing grouting, intense for checking. Results showed that the main curtain had
grouting, postponed treatment and re-grouting, a seepage rate of 0.01–0.11 Lu (L/min), and 99.56% of
acrylate grouting, and high-performance chemical the sections had a seepage rate no more than 1 Lu. For
(elastic polyurethane) grouting, etc. During grouting, the enclosed curtain, 99.06% of the sections had a
the complex geological conditions were carefully seepage rate no more than 1 Lu, which was below the
considered, such as water inrush in the drilling holes, allowable limit of 1 Lu. It indicated that the
grouting intensity due to water loss, poor adhesion of micro-crevices had been effectively filled up by
grouting, strongly weathered strata, pervious deep grouting. Single-hole and cross-hole sound wave tests
channels, and weak fault belts. In general, curtain were conducted. A pre-grouting average velocity of 5
grouting was conducted in three phases, with a total 100–5 400 m/s and a post-grouting average velocity of
grouting length of approximately 2.0×105 m. The 5 300–5 600 m/s were observed, increased by
main curtain of the dam had a total grouting length of 2.45%–8.40%. Measured results of large-diameter
1.307×105 m, and the holes in phases I, II and III had drilling holes showed that the rocks after cement
an average cement injection of 18.42, 6.90 and 4.49 grouting were compacted, integrated and well-bonded
kg/m, respectively. The enclosed curtain of the dam [12, 13].
had a total drilling routing length of 6.81×104 m. In Table 1 presents the results of an analysis after the
addition, the holes in phases I, II and III had an dam curtain grouting.
Table 1 Results of analysis of hole permeability of the dam curtain with filled water after grouting.
Seepage rate ≤1 Lu Seepage rate >1 Lu Permeability (Lu)
Curtain Location Dam section Hole No. Total section Frequency Frequency
Sections Sections Maximum Average
(%) (%)
Left non-overflow
35 421 416 98.81 5 1.19 3.70 0.09
section
Left
Powerhouse section 53 773 769 99.48 4 0.52 4.40 0.11
bank
Flood discharge
56 866 862 99.54 4 0.46 1.95 0.31
Main section
curtain Right powerhouse
56 831 831 100 0 0 0.74 0.02
Right section
bank Right non-overflow
3 39 39 100 0 0 0.11 0.01
section
Total 203 2 930 2 917 99.56 13 0.44 4.40 —
Left powerhouse
21 268 267 99.63 1 0.37 1.47 0.32
section
Left
Flood discharge
bank 45 550 529 96.18 21 3.82 4.30 0.63
section
Enclosed Left powerhouse 26 239 239 100 0 0 0.20 0.02
curtain Right Powerhouse
Right 59 867 867 100 57 0.94 0.00 —
section
bank
Right powerhouse 18 160 160 100 0 0 0.40 0.01
Total 464 6 071 6 014 99.06 44 0.72 0.40 —
Qixiang Fan et al. / J Rock Mech Geotech Eng. 2011, 3 (4): 329–342 341
Coefficient 1
0.15 172.8 m (post storage, 20081109)
foundation (including that of the powerhouse) were 0.10
261.75 and 275.46 L/min, respectively, with an 0.05
increase of 13.71 L/min. The seepage rates on the
0.00
right-bank dam foundation (including that of the
0.05
powerhouse) were 310.58 and 351.33 L/min,
L-N6
L-N8
L-N10
L-N15
L-P2
EIII
L-P10
L-D1
D5
D10
D15
D20
R-V2
R-P18
R-P22
R-N1
respectively, with an increase of 40.75 L/min. Figure 19
Measuring point
shows the time-history curves of seepage rates on the
Fig.20 Distribution of the uplift pressure coefficients at the
left- and right-bank dam foundations. drainage curtain of the upstream grouting gallery of the Three
Gorges dam.
1 400 210
Seepage rate (L/min)
200301
200401
200501
200601
200701
200801
200901
201001
201201
201101
500 200
175 m (post storage, 20101026)
Water level (m)
200701
200801
200901
201001
201201
201101
Measuring point
Date Fig.21 Time-history curves of distribution of uplift pressure
(b) Right-bank dam. coefficients at the downstream drainage curtain on the left
Fig.19 Time-history curves of seepage rate on the left- and diversion-right horizontal dam section.
right-bank dam foundations.
In Fig.21, all uplift pressure coefficients at the
5.3.2 Seepage pressure upstream drainage curtain of the downstream enclosed
Water levels in the piezometer tubes in front of the gallery were smaller than 0.50. The maximum uplift
curtain rose with increasing reservoir water level. After pressure coefficients on the left-bank powerhouse dam
water level reached 175 m, the curtain on the left-bank section, the flood discharge dam section, the left-bank
dam experienced the maximum water rising of 16.13 m powerhouse, and the right-bank powerhouse dam
to hit 171.58 m, 3.42 m lower than the reservoir water section were within the ranges of 0.00–0.37, 0.04–0.34,
level. The water level behind the curtain fluctuated 0.06–0.30, 0.00–0.37, and 0.08–050, respectively.
within a narrow range of 0.27–5.0 m. Water level in Figure 22 shows the distribution of uplift pressure
front of the curtain on the right-bank dam experienced on discharge dam section No.2.
a maximum increase of 13.26 m to hit 160.87 m. Water
Downstream surface
0
level behind the curtain fluctuated within the range of 30
60
Depth (m)
0.0–1.48 m. 90
20081109
20091120
Figure 20 shows the distribution of the uplift 120 Uplift pressure (20101026)
150 20101026
pressure coefficients at the drainage curtain of the
180
upstream grouting gallery of the Three Gorges dam. 0 20 40 60 80 100 120 140
Distance to upstream (m)
Monitoring results of the impervious curtain of the Fig.22 Distribution of uplift pressure on discharge dam section
dam show that all uplift pressure coefficients at the No.2.
upstream drainage curtain were below the designed
limit of 0.25. The maximum uplift pressure coefficients On October 26, 2010, when water level reached 175 m,
342 Qixiang Fan et al. / J Rock Mech Geotech Eng. 2011, 3 (4): 329–342
the actual uplift pressure on discharge dam section (3) Various grouting methods were considered to
No.2 was 35 555.2 kN/m, 63.31% of the designed ensure the quality of dam curtains.
value. The actual uplift pressure was smaller than the The monitoring data from 16 years of construction
designed level, helpful for the anti-sliding stability of experiences and related tests show that the optimized
the dam site. Figure 23 shows the time-history curves schemes are very successful. It will also contribute to
of seepage in left- and right-bank dam foundations the advancement and development of hydropower
during the impoundment periods from 2002 to 2010. technology in the future.
200301
200401
200412
200512
200612
200712
200812
200912
201012
Engineering Science, 2004, 6 (1): 48–52 (in Chinese).
[3] Ge Xiurun, Ren Jianxi, Li Chunguang, Zheng Hong. 3D-FEM
Date
analysis of deep sliding stability of #3 dam foundation of left
Fig.23 Time-history curves of seepage rate at dam foundation.
powerhouse of the Three Gorges Project. Chinese Journal of
It can be observed from Fig.23 that the seepage Geotechnical Engineering, 2003 25 (4): 389–394 (in Chinese).
[4] Feng X T, Zhang Z Q, Sheng Q. Estimating mechanical rock mass
exhibited a downward tendency after water level
parameters relating to the Three Gorges Project permanent shiplock
reached 135 m, possibly due to the effects of silting on
using an intelligent displacement back analysis method. International
the reservoir bottom near the dam. The forefront Journal of Rock Mechanics and Mining Sciences, 2000, 37 (7): 1 039–
blocking line of the dam currently had a seepage rate 1 054.
of 614.53 L/min, and those in the left- and right-bank [5] Changjiang Institute of Survey, Planning, Design and Research.
dam foundations were 276.22 and 338.31 L/min, Report on design quality management in 2010 on the Three Gorges
respectively. In total, all uplift pressure coefficients at Project. Wuhan: Changjiang Institute of Survey, Planning, Design and
the drainage curtain in the upstream and downstream Research, 2011 (in Chinese).
[6] China Three Gorges Corporation. Report on the quality and operations
enclosed galleries were within the permitted ranges in
of the Three Gorges hydropower complex in 2010. Yichang: China
the design. Actual uplift pressures were smaller than
Three Gorges Corporation, 2011 (in Chinese).
the values allowed, and seepage declined gradually, [7] Zhang Chaoran. Practice and experimental verification of TGP’s
indicating that the impervious curtain at the foundation permanent shiplock slope. Engineering Science, 2001, 3 (5): 22–27 (in
of the Three Gorges dam was effective [13, 14]. Chinese).
[8] Fan Qixiang, Gu Wenhong. Field testing study and quality control of
6 Conclusions high strength structure bolt for the Three Gorges permanent shiplocks.
Chinese Journal of Rock Mechanics and Engineering, 2001, 20 (5):
There are many rock mechanical issues in the Three 657–660 (in Chinese).
Gorges Project, but the sliding resistance and stability [9] Zhou Yu, Qian Xingxi, Fan Qixiang. Development and application of
full-variable diameter slipforms of inclined shafts. Engineering
of the dam section of the foundation for powerhouses
Science, 2002, 4 (9): 75–80 (in Chinese).
No.1–5, the slope stability of the double-line five-stage
[10] Li Yongquan, Wu Liang. Study on the law of blasting vibration
shiplock, excavation for large-scale underground
attenuation regarding the excavation of Three Gorges underground
powerhouses, and curtain grouting for the dam are
power plant. Engineering Blasting, 2009, 15 (2): 7–10 (in Chinese).
more complicated. [11] Wu Aiqiang, Xu Ping, Xu Chunmin, Yu Yong. Researches on stability
(1) Some special measures were adopted at for surrounding rock masses of underground power house in the Three
powerhouses No.1–5. New technologies such as Gorges Project. Chinese Journal of Rock Mechanics and Engineering,
dynamic design approach and methodology, the 1 000 2001, 20 (5): 690–695 (in Chinese).
kN-grade double-protection unbonded anchorage [12] Dai Huichao, Su Huaizhi. Stability against sliding in intake dam
cables (with corrugated tubes) and 3 000 kN-grade section of Yangtze River Three Gorges Project. Rock and Soil
double-protection unbonded anchorage cables, were Mechanics, 2006, 27 (4): 643–648 (in Chinese).
used to ensure the stability of the vertical sections of [13] Zhou Hougui, Li Yan. New construction techniques for dam
the slopes of the shiplock. foundation grouting and anti-seepage cofferdam of Three Gorges
(2) With new slip-casting method, significant Project. Water Resources and Power, 2009, 27 (1): 140–144 (in Chinese).
breakthroughs in environmental concepts were applied [14] Yang Xiying, Yang Zhenfeng. Curtain grouting under special
geological condition. China Three Gorges Construction, 2004, 11 (1):
to underground powerhouses to ensure stability of the
25–27 (in Chinese).
surrounding rock masses.