No: HSE/FRM-01
Rev. : 00
JOB SAFETY ANALYSIS FORM
Date: June 22, 2016
Page: 1 of 3

Brown / Green Field


Project PAPCO-WOPMP-FZP Area Safety Helmet, Safety Shoes,
Area PPEs Required: Cover All, Hand Gloves, Goggles.
Date Supervisor
Job: Assembling of Internal Floating Roof.
Equipment/Tool Responsible Risk
Item Detail of Activity Risk Involved Preventive Measures
Used Parson Rating
 Each employee should be provided
training on the safe and proper use of
Muscle strains, pulls the most important, primary tool.
and repetitive  Proper techniques of stretching,
motion injuries. lifting, bending, moving, rolling,
securing good footing, the importance
of hydration, etc., should be address.
 Communication methods or jargon
should be discussed and agreed upon
prior to moving materials.
Area In-
1 Material Shifting, Handling. charge / Low
Lack of  IFR plan should be discussed before
Supervisor
communication attempting to move materials inside.
 Instructions should come from one
person when working in teams of two
or more.
 Workers need to maintain constant
Foot or leg awareness of their feet in relation to
objects being moved and avoid
injuries.
placing them under materials, workers
to enter the tank.
 It is recommended that workers use
either bars or hand lifting techniques
to minimize the potential for injuries to
hands.
Area In-
Finger or hand
2 Assembling IFR. Hand Tools, Grinder.
injuries.
charge / Medium
 If hands are absolutely necessary in
Supervisor
the presence of bars, extreme caution
and 100% communication with other
workers should follow.

This document is the Intellectual Property of Descon. Any unauthorized use, including the modification and reproduction of the content is strictly prohibited. © Copyrights Ordinance 2002, All Rights Reserved.
Doc. No: HSE/FRM-01
Rev. : 00
JOB SAFETY ANALYSIS FORM
Date: June 22, 2016
Page: 2 of 3

 Crew members should work as a


team, following the direction of the
crew or leader.
 When moving material or applying
leverage, workers need to remain
crushing aware of potential hazards, and
injuries, position themselves in such a way to
pinch’s, minimize their exposure.
unexpected
movements,  Check object for greasy/slippery
etc. surfaces. Remove grease prior to
lifting. Wear gloves to improve grip.
Wear safety toe shoes/boots.
 Do not pinch object between your
thumb and forefinger. Wear gloves to
improve grip.
 Stack material in a manor to avoid
any obstruction during job.
Trips, Falls
 Do not climb over IFR if not secured
properly.
 Ensure proactive monitoring of HSE
representative for emergency retrieval
of personnel from confined space.
Entrapment,
 Installs permanent supports timely to
Collapse
divide load on bearer.
 Excessive walking over IFR must be
avoided.
Left  Barricade the entry point of tank and
Unattended. post warning signs. Area
3 Completion In-charge / Low
Foreign  Ensure there is no tool, equipment, Supervisor
Material Inside rags or other material left inside.
Severity Rating Insignificant Low Medium High Extreme
Minor irritation/no
First Aid MTC RWI/LTI Fatality
F.A

What am I going to do? How am I going to do? What are the risks? How do I control risks? Is risk too high?

This document is the Intellectual Property of Descon. Any unauthorized use, including the modification and reproduction of the content is strictly prohibited. © Copyrights Ordinance 2002, All Rights Reserved.
Doc. No: HSE/FRM-01
Rev. : 00
JOB SAFETY ANALYSIS FORM
Date: June 22, 2016
Page: 3 of 3

Area Engineer / Supervisor HSE Representative

This document is the Intellectual Property of Descon. Any unauthorized use, including the modification and reproduction of the content is strictly prohibited. © Copyrights Ordinance 2002, All Rights Reserved.