Vous êtes sur la page 1sur 4

Optimal Load Shedding: An Economic Approach

Deepak Kumar Singh Rajiv Shekhar Prem K Kalra


Dept. of Electrical Engineering Dept. of MME Dept. of Electrical Engineering
IIT Kanpur, India IIT Kanpur, India IIT Kanpur, India
deepaks@iitk.ac.in vidtan@iitk.ac.in kalra@iitk.ac.in

Abstract—In this paper an economic criterion based optimal load communication systems has inspired centralized load shedding
shedding algorithm has been developed. The objective is to schemes [22] that used frequency and voltage values from
minimize the sum of curtailed load and also the total system different parts of the system as inputs. Some load shedding
interruption cost within the frame-work of system operational schemes are also based on optimization procedures [23–26]
and security constraints. The load shedding problem is
which reduce the cost incurred due to load shedding, some
formulated as a non-linear optimization model that is optimized
using Genetic Algorithm (GA). A test system designated as the others researchers have used neural networks and fuzzy logic
RBTS [30, 31] is used to test the technique. The system includes [27–29] as an aid for determining the amount and location of
two generator busbars with eleven generating units, nine load shedding. It can be observed though that most of these
transmission lines and five load busbars where six distribution schemes primarily focus on technical issues and electrical
systems are connected. parameters such as frequency or voltage. Economic criterion
has been rarely used in the load shedding schemes .This paper
Keywords-component; Power System; Load shedding, Genetic presents a unique load shedding scheme that combines
Algorithm technical criteria of load shedding with economic parameters
so that the total economic loss of the system can be
I. INTRODUCTION minimized.
The rapid growth in demand of electricity, both in developing This paper is organized as follows: Section 2 defines the
and developed countries has thrown a big challenge to the customer interruption cost index used as a base for
power system planners and operators. Past experiences formulating the objective function. Section 3 will describe the
indicates that the growth in load demand is always ahead of optimal load shedding technique followed by the test system
the growth in generation. Electric supply failures can have used in section 4. Section 5 consists of results and analysis of
serious monetary and reliability impacts on the system the results.
customers. During power deficit situation, system operators
are required to make load shedding decisions based on system
II. CUSTOMER INTERRUPTION COST INDEX
security concerns, such as voltage, current, power and
frequency constraints, to alleviate the constraints and maintain To evaluate unreliability cost indices of distribution systems, a
system stability. customer interruption cost models for different customers is
The distribution systems are the final link of the needed. A standard industrial classification (SIC) can be used
interconnection between power systems and the consumers. If to divide customers into different segment viz. large user,
there is the necessity to cut the load for the safety restrictions, industrial, commercial, agriculture, residential, government
usually the shedding occurs in the distribution system. Various and institutions and office and buildings categories. The sector
types of load shedding schemes have been studied by the customer damage functions (SCDF) data used here is taken
researchers in the past. Most of these are traditional schemes from the survey conducted by conducted by the University of
that relied heavily on local measurements for inputs and shed Saskatchewan and Canadian electric power utilities to estimate
a preset amount of load when frequency or voltages reached a customer interruption costs. The survey data have been
critical level. Some advance schemes used semi-adaptive and analyzed to give sector customer damage functions (SCDFs)
adaptive under frequency load shedding schemes [1–8] that that are then used as customer interruption cost models. The
tried to overcome the problem of under shedding or over SCDFs for the seven different customer sectors are shown in
shedding of load by utilizing the rate of change of frequency Fig. 1.
along with the frequency value to make decisions about The development of composite customer damage model can
shedding load. Under voltage load shedding schemes [9–21] be done by weighting each sectoral customer damage function
are also gained popularity in last few years as they proved to (SCDF) of the interested area by the ratio energy consumption
be an economical and effective technique to maintain voltage to obtain composite customer damage function (CCDF). The
stability as against expensive and time consuming methods equation is as below:
like shunt compensation, new additions to the main circuit,
etc. The increase in use of advanced metering and

978-1-4244-6890-4/10$26.00 ©2010 IEEE 636 TENCON 2010


n has been developed. The objective is to minimize the total
CCDF (t ) = ∑ ci × SCDFi (t ) (1) local distribution system interruption cost subject to technical
i =1 constraints. The procedure is discussed in the following
Where: section.
i is customer type, When a distribution system suffers load deficiency caused by
n is a number of each customer type, decrease in generation or sudden increase in demand, system
ci is energy consumption of customer type i, and operators usually open one or more feeders to maintain the
SCDFi is scdf of customer type i. frequency limits and hence integrity of other parts of the
system. A group of feeders need to be shred is called a feeder
The CCDF in equation 1 is in the unit of $/kWpeak. However, set. Feeders have different load capacities and different type of
we can transform it into the unit of $/kWavg to be used in customers. Customers have different per unit customer
outage cost evaluation by using equation 2 damage costs for specific failure durations which we have
discussed in previous paragraph. These damage functions are
n
ci × SCDFi (t ) known as SCDF. By using the survey data the mathematical
CCDF (t ) = ∑ (2) functions of different sectors can be derived. These factors
i =1 LFi affect the total customer interruption cost of the feeder. Using
In this paper a new measure of customer cost has been used. these SCDFs we can formulate the total interruption cost
This measure is inspired by CCDF and explained in next (TIC) of a specific feeder which can be summed up to get the
section. total interruption cost of the bus. This TIC has been used as
the objective function in this paper so that minimizing it will
minimize the economic losses of the system. The final
objective function can be represented as follows:
n
TIC = ∑ Pi * f i (t i ) (3)
i =1
Where:
Pi is the power cut required on ith node
∑ Pi = total required power cut (i.e. power deficit)
fi () is the sectoral cost damage function of ith node
ti is the duration of power cut on ith node.

Figure 1. Customer damage function for different sectors

III. OPTIMUM LOAD SHEDDING TECHNIQUE


When the demand exceeds the power supply and there is not
enough capacity available to serve all the customers connected
to the distribution system, a load-shedding decision must
therefore be made to drop load on the distribution system
feeders. Different techniques of load-shedding can result in
different load point interruption costs. Optimum load shedding
is therefore an important issue.
An optimum load-shedding technique based on the Figure 2. Flowchart for proposed load shedding algorithm
interruption costs of customers and load deficiency matching

637
IV. TEST SYSTEM V. TEST RESULTS AND ANALYSIS
The test system we have used here is known as Roy To test the algorithm on RBTS it is assumed that there is a
Billington Test System (RBTS) [31], The RBTS is a 6 bus test sudden increase of 20MW in load for 150 minutes. The
system with five load buses (bus2-bus6). The RBTS has proposed algorithm is applied as give in flow chart. The best
eleven generators and nine transmission lines. The installed results achieved by running GA for several iteration are
capacity is 240 MW and the average load of the system is 185 tabulated as follows:
MW. The one line diagram of RBTS is shown in figure 1.
Usage of different types of customers on all the buses is also TABLE 2. Results
given.
Outage Duration Load to be shed
BUS 1 0 0
BUS 2 0 0.1425
BUS 3 30 0.3759
BUS 4 15 0.0814
BUS 5 60 0.2485
BUS 6 45 19.151

As majority of customers on BUS6 are farm and residential so


the power cut on that bus is maximum, this way the
economical loss can be minimized.
The final TIC in case of above load shedding scenario is
6.8893 $/KW
VI. CONCLUSION
This paper investigates the effect of load-shedding procedures
on distribution system reliability cost indices. An optimum
load-shedding technique is developed to minimize the total
customer interruption costs in a local distribution system.
Customer concerns regarding interruption costs are
incorporated in the load-shedding decision process when a
bulk system deficiency occurs. This algorithm is been tested
on RBTS. This technique has a limitation, as it does not take
care of social issues for load shedding. This bottleneck can be
Figure 3. One line diagram for test system removed by applying different weights to different customer;
these weights will be dependent upon the social importance of
The distribution of different type of customers on all the buses that specific sector.
of RBTS is as shown in the Table 1.
REFERENCES
TABLE 1. Detail of customer type on different buses [1] P.M. Anderson, M. Mirheydar, “An adaptive method for setting
underfrequency load shedding relays,” IEEE Transactions on Power
BUS 2 BUS3 BUS4 BUS5 BUS6 Systems 7 (May (2)) (1992) 647–655.
(in MW) (in MW) (in MW) (in MW) (in MW) [2] B. Fox, J.G. Thompson, C.E. Tindall, “Adaptive control of load
shedding relays under generation loss conditions,” in: Fourth
Large User 0 55.50 1.85 0 0 International Conf. on Developmentsin Power Protection, April, 1989,
pp. 259–263.
Small
3.82 3.05 22.45 0 3.05 [3] D. Prasetijo, W.R. Lachs, D. Sutanto, “A new load shedding scheme for
Industries
limiting underfrequency,” IEEE Transactions on Power Systems 9
Commercial 6.55 4.70 0 3.70 1.70 (August (3)) (1994) 1371–1378.
[4] J.R. Jones, W.D. Kirkland, “Computer algorithm for selection of
Farm 0 0 0 0 7.40 frequency relays for load shedding,” IEEE Computer Applications in
Power 1 (January (1)) (1988) 21–25.
Residential 5.00 19.90 15.7 8.90 7.85 [5] H. You, V. Vittal, Z. Yang, “Self-healing in power systems: an approach
Govt. and using islanding and rate of frequency decline-based load shedding,”
4.625 0 0 5.55 0 IEEE Transactions on Power Systems 18 (February (1)) (2003) 174–
Institution
181.
Office [6] Z. Zhang, K.K. Li, X.G. Yin, Y.H. Zhang, D.S. Chen, “An adaptive
0 1.85 0 1.85 0
Building microcomputer based load shedding relay,” in: Industry Applications
Total 20 85 40 20 20 Conference 3, October, 1999, pp. 2065–2071.
[7] V.N. Chuvychin, N.S. Gurov, S.S. Venkata, R.E. Brown, “An adaptive
approach to load shedding and spinning reserve control during

638
underfrequency conditions,” IEEE Transactions on Power Systems 11 Conf. on Computers, Communications, Control and Power Engineering,
(November (4)) (1996) 1805–1810. October 3, 2002, pp. 1778–1781.
[8] M. Larsson, C. Rehtanz, “Predictive frequency stability control based on [29] S.K. Tso, T.X. Zhu, Q.Y. Zeng, K.L. Lo, “Evaluation of load shedding
widearea phasor measurements,” IEEE Power Engineering Society to prevent dynamic voltage instability based on extended fuzzy
Summer Meeting 1 (July) (2002) 233–238. reasoning,” IEE Proceedings Generation, Transmission and Distribution
[9] C.W. Taylor, “Concepts of undervoltage load shedding for voltage 144 (March (2)) (1997) 81–86.
stability,” IEEE Transactions on Power Delivery 7 (April (2)) (1992) 48 [30] R. Billinton, S. Kumar, L. Goel, Y. N. Chowdhuri, K. Chu, K. Debnath,
488. E. Khan, P. Kos, G. Nourbaklhsh, J. Oteng Adjei, “A reliability test
[10] S.S. Ladhani, W. Rosehart, “Under voltage load shedding for voltage system for educational purposes - basic data,” IEEE Trans. Power Syst.,
stability overview of concepts and principles,” IEEE Power Engineering 1989, 4, (3), pp. . -- 1238-1244
Society General Meeting 2 (June) (2004) 1597–1602. [31] R. Billinton, J. Satish, “A test system for teaching overall power system
[11] T. Van Cutsem, C.Moors, D. Lefebvre, “Design of load shedding reliability assessment,” IEEE Trans. Power Syst., 1996, 11, (4), pp.
schemes against voltage instability using combinatorial optimization,” 167g1675
IEEE Power Engineering Society Winter Meeting 2 (January) (2002)
848–853.
[12] C. Moors, D. Lefebvre, T. Van Cutsem, Design of an undervoltage load
shedding for the Hydro-Quebec system, IEEE Power Engineering
Society General Meeting 4 (July) (2003) 2036.
[13] T.Q. Tuan, J. Fandino, N. Hadjsaid, J.C. Sabonnadiere, H. Vu,
“Emergency load shedding to avoid risks of voltage instability using
indicators,” IEEE Transactions on Power Systems 9 (February (1))
(1994) 341–351.
[14] S. Kolluri, T. He, “Design and operating experience with fast acting load
shedding scheme in the Entergy System to prevent voltage collapse,”
IEEE Power Engineering Society General Meeting 2 (June) (2004)
1625–1630.
[15] J. Mechenbier, A. Ellis, R. Curtner, S. Ranade, “Design of an under
voltage load shedding scheme,” in: IEEE Power Engineering Society
General Meeting, June, 2004, pp. 1612–1619.
[16] M. Klaric, I. Kuzle, S. Tesnjak, “Undervoltage load shedding using
global voltage collapse index,” in: IEEE PES Power Systems Conf. and
Exposition 1, October, 2004, pp. 453–459.
[17] C.M. Affonso, L.C.P. da Silva, F.G.M. Lima, S. Soares, “MW and
MVar management on supply and demand side for meeting voltage
stability margin criteria,” IEEE Transactions on Power Systems 19
(August (3)) (2004) 1538–1545.
[18] Z. Feng, V. Ajjarapu, D.J. Maratukulam, “A practical minimum load
shedding strategy to mitigate voltage collapse,” IEEE Transactions on
Power Systems 13 (November (4)) (1998) 1285–1290.
[19] S. Arnborg, G. Andersson, D.J. Hill, I.A. Hiskens, “On influence of load
modeling for undervoltage load shedding studies,” IEEE Transactions
on Power Systems 13 (May (2)) (1998) 395–400.
[20] R. Balanathan, N.C. Pahalawaththa, U.D. Annakkage, P.W. Sharp,
“Undervoltage load shedding to avoid voltage instability,” IEE
Proceedings Generation, Transmission and Distribution 145 (March (2))
(1998) 175–181.
[21] S. Imai, “Undervoltage load shedding improving security as reasonable
measure for extreme contingencies,” in: IEEE PES General Meeting,
June, 2005.
[22] S.A. Nirenberg, D.A. McInnis, K.D. Sparks, “Fast acting load shedding,
IEEE Transactions on Power Systems,” 7 (May (2)) (1992) 873–877.
[23] Y. Halevi, D. Kottick, “Optimization of load shedding system, IEEE
Transactions on Energy Conversion,” 8 (June (2)) (1993) 207–213.
[24] D. Xu, A.A. Girgis, “Optimal load shedding with dynamic market
modeling,” IEEE Power Engineering Society Winter Meeting 2
(January) (2002) 906–911.
[25] P. Wang, R. Billinton, “Optimum load-shedding technique to reduce the
total customer interruption cost in a distribution system,” IEE
Proceeding Generation, Transmission and Distribution 147 (January (1))
(2000) 51–56.
[26] S. Shah, S.M. Shahidehpour, “A heuristic approach to load shedding
scheme,” IEEE Transactions on Power Systems 4 (November (4))
(1989) 1421–1429.
[27] D. Novosel, R.L. King, “Using artificial neural networks for load
shedding to alleviate overloaded lines,” IEEE Transactions on Power
Delivery 9 (January (1)) (1994) 425–433.
[28] M.H. Purnomo, C.A. Patria, E. Purwanto, “Adaptive load shedding of
the power system based on neural network,” in: TENCON ‘02 Proc. of

639

Vous aimerez peut-être aussi