Académique Documents
Professionnel Documents
Culture Documents
INSTITUTE OF TECHNOLOGY
DEPARTMENT OF ELECTRICAL AND COMPUTER
ENGINEERING
Title: Establish a Construction site
Project Management and Resource Allocation
(INDUSTRIAL CONTROL STREAM)
Group members: ID NO
1. Adissu Adefris……………………………..GUR/0060/07
2. Dires Melaku……………………………….GUR/0321/07
3. Enanwo Wondem…………………………..GUR/0369/07
4. Fentahun Mulat…………………………….GUR/
5. Hiwot Dessie……………………………......GUR/0611/07
6. Tadesse Yikan………………………………GUR/1055/07
7. Takele Shitahun………………………….....GUR/1059/07
Submission date:
ESTABLISH A CONSTRUCTION SITE
OBJECTIVE
To provide comfortable environment for construction.
To provide security for building occupants and assets from man made and natural
hazards.
To optimize building space and material use.
To identify potential risks in a given construction.
To calculated each department/section budgets quickly.
Establish site
Erect
fence
Surfaces Utility Asbestos Strip
Survey site
Fit
Stone Gates
Electrical
up site service Specialist
Install
clearance
camera
Water
services
Demolish
Stone
sheds
up
Drain
access
connection
Clear rubbish
road
Scheduling Systems
Critical Path Method (CPM)
Program Evaluation and Review Technique (PERT)
Gantt Chart
1) Critical Path Method (CPM)
The critical path method has four key elements
Critical path analysis
Float determination
Early start and finish calculation
Latest start and finish calculation
a) Determine the activities of the project
Assume each tasks are assigned in the following ways:
A=Stone up site and access rod
B= Drain concentration, electrical and water service
C=Specialized clearance, demolish sheds and clear rubbish
D=erect fence, fit gats and install camera
E=Surface
F=Utilities
G=Asbestos survey
H=Strip site
I=Fit out
J=Clear site
K=Security
L=Establish site
b) Identify the predecessors and successor activities and allocate time for each activity
E I
A F L
End
B
Start C H J
G K
D
E
I
F
A L
End
B J
Start
C H K
G
D
Where
T=critical path duration
D=proposed (specified) time
=project standard deviation
The probability that the project will be completed in less than 15 days can be
D−T
𝑍=
15−12.49
(d) 𝑍 = =2.58
0.88
3) Gantt Chart
GANTT chart from the information obtained by PERT/CPM are:
A
B
C
D
E
F
G
H
I
J
K
L
0 6 15 25 39
Step 2: Place time windows for non-critical tasks
A
B
C
D
E
F
G
H
I
J
K
L
0 5 6 8 12 14 15 22 25 29 32 33 34 39
Step 3. Schedule non-critical task
Step 4. Indicate precedence relationships:
A
B
C
D
E
F
G
H
I
J
K
L
0 5 6 8 12 14 15 17 21 22 25 29 32 33 34 39