2/15/2019
Gross Maximum Quantity
Manpower Productivity Material Used Inner End Inner Unit
FABRICATION
Fabrication of Water line 1/2" PPR pipe 5 5 pcs
Initial Testing (Leak/Hydro) 1MP 5 sets/day 1/2" PPR Elbow 3 3 pcs
1/2" PPR Tee 4 4 pcs
1/2" PPR Coupling 1 1 pcs
CLEARING,STAKING/LAY-OUT
Clearing 1MP 8 Units/day
Lay-out 3MP 22 Units/Week
SLAB MILESTONE
Slab Phase 1
Installation of Septic tank, Cover, Tapping to sewer line Septic Tank 1 1 set
Installation of Sanitary line CHB 10 10 pcs
Construction of Catch Basin 4MP 4 units/week Cement( CB & ST Cover) 2 2 bags
Backfilling and Compaction Solvent 1/2 1/2 can
Flow Test
Lot Leveling
Slab Phase 2 PE Sheet 28 28 l.m
Installation of PE Sheet, Rebars, Water line, Electrical conduit with 10mm dia. RSB 43 43 pcs
House Keeping Tie Wire 1 1 kg
1/2" Elec. Conduit Pipe 10 10 pcs
3/4" Elec. Conduit Pipe 2 2 pcs
7MP 12 units/week
1/2" Elec. Conduit Long Elbow 13 13 pcs
3/4" Elec. Conduit Long Elbow 2 2 pcs
Solvent 1/2 1/2 can
Nylon(Pull Wire) 20 20 l.m
Tape 1/4 1/4 roll
Slab Phase 3
Installation and Dismantling of Form
5MP 20 units/week RMC 4 4 cum.
Concrete Pouring
House Keeping
Slab Fabrication 4" PVC Pipe 6 6 pcs
Sanitary Line 3" PVC Pipe 1 1 pcs
2" PVC Pipe 4 4 pcs
2" 90deg. Bend 5 4 pcs
2" 45deg. Bend 3 3 pcs
3" 90deg. Bend 1 1 pcs
3" 45deg. Bend 1 1 pcs
2MP 9 units/day 4" 45deg. Bend 3 3 pcs
4" x 2" Tee 1 1 pcs
2" P-Trap 1 1 pcs
2MP 9 units/day