Académique Documents
Professionnel Documents
Culture Documents
gas plant
Selecting equipment for a sulphur block requires balancing technical
performance and costs, as well as local conditions and regulations
Jan-Willem Hennipman and Karen Hanlon Kinsberg Jacobs Comprimo Sulfur Solutions
T
he configuration of acid
gas treating and sulphur
Sulphur block
recovery units (the sul-
phur block) in a new gas plant SRU TGTU
Stack
is mainly determined by the
treated gas specification and Inlet
AGRU Dehydration Hydrocarbon Gas LNG or
receiving polishing sales gas
SO2 emissions specification.
recovery
contains no CO2
• Simultaneous removal of both
CO2 and H2S Main
Treated gas to
dehydration Off-gas to
incinerator
Feed LP steam
gas
Reboiler
Rich solvent to
TGTU regenerator
FC
Air
Feed Air
gas
oxidation, such as EuroClaus and SuperClaus, In the quench column, the gas is cooled and
can achieve SREs in the range 99.0-99.6% the remaining H2S is captured in the amine
depending on the feed gas composition. The absorber. From the regenerator that H2S is
remaining 0.4-1.0% of sulphur species are incin- recycled back to the burner on the combustion
erated and sent to the atmosphere as SO2. For chamber. Treated gas is sent to the incinerator
higher SREs, SO2 can be captured from the flue to convert any remaining sulphur species to SO2
gas with a caustic scrubber downstream of the before release to atmosphere. With a standard
incinerator. The SO2 forms sodium sulphate amine based TGTU using regular MDEA as the
which can be treated via the wastewater treat- solvent, 99.9% recovery should be achievable.
ment unit. For large plants in remote areas, the This SRE corresponds to about 550-700 mg/Nm3
scrubber option may not be feasible due to han- SO2 or 200-250 ppm SO2 in the flue gas to the
dling and transporting the large quantities of stack, on a dry basis with 3% excess oxygen.
caustic required to capture SO2. For example, a To meet 150 mg/Nm3 SO2, as specified in the
900 t/d SRU would require daily about 30 m3 of former WBS (which corresponds to about 99.98%
30 wt% sodium hydroxide (NaOH). A detailed recovery), the H2S concentration from the treated
analysis is recommended to investigate the best gas leaving the absorber must be reduced to a
alternate solutions when no suitable water treat- strict minimum, together with small amounts of
ment facilities are available locally. See Figure 4 COS, CS2 and mercaptans that may pass through
for the SRU-selective oxidation process line-up the hydrogenation reactor unconverted. This
for a gas plant. high recovery standard also requires treatment
of vent gas from the sulphur degassing unit.
Amine based tail gas treating unit Pressurised degassing allows routing the vent
If sulphur recoveries above 99.5% are required, gas back to the combustion chamber in the Claus
amine based tail gas treating units are the unit. Alternatively, the use of blowers or steam
industry standard. See Figure 5 for a typical eductors to recycle vent gas from atmospheric
SRU configuration consisting of two catalytic degassing back to the thermal reactor has met
Claus reactors with amine based tail gas treat- with varying degrees of success.
ing. The remaining sulphur species from the For an SRE of 99.98%, the following additional
Claus reactors will be hydrogenated and hydro- features are required compared to 99.8% or
lysed to H2S over a catalyst in a third reactor. 99.9% sulphur recovery:
Incinerator and
Air
waste heat boiler
HP HP HP Recycle gas
steam steam steam (H2S) to main
HP burner
steam Quench Absorber
Reheater Reheater Reheater TGTU
Recycle gas (H2S) reactor column
from reflux drum
Waste heat Regenerator
boiler Claus Claus
H2S - 2SO2
Reactor Reactor
LP LP LP QC HP
steam steam steam steam LP steam
Combustion
chamber Reboiler
Condenser S S S
Condensate
to SWS
To sulphur
storage
Pressurised degassing
for SRE = 99.8%
FrC
Figure 5 SRU with amine based TGTU with pressurised degassing for 99.98% SRE
• Pressurised degassing to recycle sulphur very effective technology choices when wanting to
vapours from sulphur degassing to the front end minimise total plant SO2 emissions. Other features
of the thermal reactor. of this type of tail gas treating technology are:
• Use of acid-aided MDEA instead of regular • Degassing vapours and other sulphur contain-
MDEA. Particularly in hot climates, the high ing gases such as from the AGE absorber, which
performance amines, Flexsorb SE Plus (EMRE), normally bypass the SRU, can be sent to the
OASE yellow (BASF) or Jefftreat Ultra (Shell/ incinerator without losing SRE. The SO2 formed
Huntsman), have demonstrated better per- will be captured in the Cansolv or SolvR unit and
formance with respect to the amine circula- recycled to the Claus unit combustion chamber
tion rate and reboiler duty. In colder climates, • The temperature of the acid gas burner in the
this advantage over acid aided MDEA is less Claus unit needs to be checked as the addition
pronounced. of the SO2 recycle will lower the flame temper-
It is important to note that depending on the ature. This can hinder the BTEX destruction
feed gas quality, the 99.98% SRE might not be capability of the burner
achievable with only these fea- • The unit produces a dilute
tures, and the off-gas might Feed gas design basis and sulphate waste stream which
require other polishing steps. treated gas specification possibly requires an effluent
treatment plant for further
Flue gas SO2 recovery unit Component Mol% Mol% processing.
H2S 9.7 <4 ppmv
Removal of SO2 from flue gas CO2 8.6 <0.5
is another method of attaining N2 5.0 - Case study
low sulphur emissions. Shell’s See Table 1 for the conditions
CH4 76.5 -
C2H6 0.2 -
Cansolv and MECS SolvR are COS 150 ppmv <40 ppmv of a typical feed gas from a
examples of this type of technol- R-SH
Total sulphur
80 ppmv <10 ppmv
<60 ppmv
European gas plant. Based on
ogy. Such units can easily meet Temperature 25 this feed, a case study has been
150 mg/Nm3 in the stack gas Pressure 75 barg created to demonstrate the
Flow rate 250 000 Nm /h
3
100
99.90
ent configurations in this arti-
90 99.80 cle. If a minimum SRE of 99.5%
80
is required, it is very likely that
70
60
simpler catalytic conversion
50 processes will outperform other
99.50
40 technologies with respect to
30 investment cost, operating cost,
20 NPV, and equivalent CO2 emis-
10 sions. However, if LP steam is
0
0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0
freely available at the site, with
SO2 emissions, kiloton/year no appreciable unit cost, the cat-
alytic TGTU process could result
Figure 9 Annual CO2 emissions for utilities, catalyst and chemicals in operating costs and CO2 emis-
Appendix A:
Equipment specifications for the AGRU, large equipment items only
Equipment data
In Tables A1 to A5, the equip- AGRU Size M.o.C.
Main absorber 3.3 m x 19.2 m CS
ment data used for the case Regenerator 4.7 m x 15.3 m CS
study is specified. The power Flash vessel 3.7 m x 13.7 m CS
provided for the pump sizes Reflux drum 3.3 m x 5.0 m CS
indicates the absorbed power Solvent drain drum 8.0 m x 15.8 m CS
Lean/rich exchanger 400 m2, 26500 kW SS
estimate, which is used to cal- Lean solvent air cooler 1500 m2, 26600 kW SS
culate the electrical power con- Lean solvent trim cooler 300 m2, 7600 kW CS
sumption of the unit. Reboiler 1750 m2, 53000 kW SS
For the amine based tail Overhead condenser 1200 m2, 16600 kW CS
Lean solvent pump 1070 m3/h, 560 kW SS
gas treating unit, air coolers Lean solvent booster pump 1000 m3/h, 3000 kW SS
or plate and frame type heat Reflux pump 50 m3/h, 30 kW SS
exchangers are applied. Plate Lean solvent filter 20 m2 CS
and frame type heat exchangers Activated carbon bed 4.0 m x 4.0 m CS
Solvent storage tank 11.5 m x 17.0 m CS
have proven good performance
in TGTUs at relatively low cost
and small plot area compared Table A1
to shell and tube exchangers.
All equipment items as pro- items that deviate are specified SRE of 99.98%. Only within the
vided in Table A2 for an SRE in Table A4. TGTU part and the degassing
of 99.8% are also applicable for All equipment items as pro- the equipment items that devi-
an SRE of 99.9%. Only within vided in Table A2 for an SRE of ate are specified in Table A5.
the TGTU part the equipment 99.8% are also applicable for an
Table A2
Equipment specifications SRU with 99.8% SRE amine based TGTU Equipment specifications SRU with 99.9% SRE
amine based TGTU
Amine based TGTU Size M.o.C.
Acid gas KO drum 2.5 m x 3.8 m CS TGTU absorber 4.2 m x 10.4 m CS
Main burner and Regenerator 3.1 m x 20.4 m CS
combustion chamber 4.4 m x 3.8 m CS + lining Lean/rich exchanger 560 m2, 22.8 MW SS
Waste heat boiler Exchanger 4.1 m x 7.5 m, 45 MW CS + partly lined Lean solvent air cooler 610 m2, 7.3 MW CS
Steam drum: 2.6 m x 7.5 m Lean solvent trim cooler 140 m2, 3.7 MW CS
1st Claus reactor 4.7 m x 16.0 m CS + lining Reboiler 620 m2, 18.9 MW SS
2nd Claus reactor 4.7 m x 16.0 m CS + lining Overhead condenser 610 m2, 8.5 MW CS
1st Sulphur condenser 2.9 m x 5.0 m, 8.7 MW CS + partly lined Rich solvent pump 350 m3/h, 130 kW SS
2nd Sulphur condenser 2.9 m x 5.0 m, 7.4 MW CS + partly lined Lean solvent pump 380 m3/h, 140 kW SS
3rd Sulphur condenser 2.9 m x 5.0 m, 3.4 MW CS
1st Reheater 970 m2, 2700 kW CS
2nd Reheater 540 m2, 1500 kW CS Table A4
TGTU reheater 610 m2, 2300 kW CS
TGTU reactor 4.6 m x 18.0 m CS
Quench column 4.3 m x 8.1 m SS
TGTU absorber 4.1 m x 9.5 m CS Equipment specifications SRU with 99.98% SRE
Regenerator 2.8 m x 19.5 m CS
amine based TGTU
Reflux drum 3.0 m x 8.5 m CS
Solvent drain drum 6.0 m x 12.0 m CS
Quench water air cooler 1100 m2, 15.2 MW SS TGTU absorber 4.3 m x 12.0 m CS
Quench water trim cooler 200 m2, 5.1 MW CS Regenerator 3.6 m x 20.4 m CS
Lean/rich exchanger 510 m2, 20.6 MW SS Lean/rich exchanger 27.3 MW SS
Lean solvent air cooler 540 m2, 6.5 MW CS Lean solvent air cooler 8.7 MW CS
Lean solvent trim cooler 130 m2, 3.4 MW CS Lean solvent trim cooler 4.5 MW CS
Reboiler 510 m2, 15.6 MW SS Reboiler 28.2 MW SS
Overhead condenser 470 m2, 6.3 MW CS Overhead condenser 15.7 MW CS
Quench water pump 450 m3/h, 100 kW SS Rich solvent pump 420 m3/h, 170 kW SS
Rich solvent pump 320 m3/h, 120 kW SS Lean solvent pump 450 m3/h, 150 kW SS
Lean solvent pump 340 m3/h, 125 kW SS Sulphur degassing vessel 4.1 m x 20.0 m CS
Reflux pump 20 m3/h, 15 kW SS Sulphur collecting vessel 3.5 m x 5.0 m CS
Quench water filter 5 m2 SS Sulphur degassing pump 20 m3/h, 11 kW SS
Lean solvent filter 10 m2 CS Sulphur transfer pump 20 m3/h, 11 kW SS
Solvent storage tank 6.0 m x 12.0 m CS
Incinerator burner and
combustion chamber 4.2 m x 13.6 m CS + lining
Incinerator waste Table A5
heat boiler Exchanger 3.7 m x 7.2 m, 25 MW CS
Steam drum: 2.0 m x 7.4 m
Main air blower 83000 kg/h, 1900 kW CS
Incinerator air blower 78000 kg/h, 600 kW CS
Sulphur pit, incl. degassing 65 m x 22 m x 5 m Concrete
Sulphur transfer pump 20 m3/h, 11 kW SS
Table A3
Appendix B: Utility, The background data used for the Appendix C: Net present
chemical and catalyst cost utility, chemicals and catalyst cost value input data
estimates are provided in the
estimate background data
Tables B1 and B2. The data used for the NPV calcula-
Utility, chemical and catalyst cost unit rates tion has been tabulated in Table C1.
Table B1
Table B2
Appendix D: CO2 footprint CO2 footprint unit rates for utilities, chemicals and catalyst
estimate background data
for utilities, chemicals and Utility/chemical/catalyst
Electric power
Value
0.54
Unit
kg CO2/kWh
Remarks
catalyst Sour water treating 18.38 kg CO2/m3 Treating sour water takes
150 kg LP steam/m3 sour water
The background data used to Cooling water
Fuel gas
0.14 kg CO2/m3
2.66 kg CO2/kg fuel gas
estimate the CO2 footprint for Boiler feed water 0.87 kg CO2/m3
the utility, chemicals and cata- HP steam 0.10 kg CO2/kg stm
LP steam 0.12 kg CO2/kg stm
lyst consumption is provided LP condensate 0 kg CO2/m3 Used as BFW make-up;
in Table D1 based on the infor- consumption and therefore
mation of references 9 and 12.
no net CO2 effect
(High perf.) Amine 2.00 kg CO2/kg amine
With the consumption figures Claus catalyst Al2O3 5.00 kg CO2/ltr Estimated
in Table B2, the footprint per Claus catalyst TiO2
TGTU hydrogenation catalyst 5.00 kg CO2/ltr Estimated
utility, chemical and catalyst Selective oxidation catalyst 5.00 kg CO2/ltr Estimated
can be calculated.
Table D1