NATIONALTRANSMISSION AND DISPATCH CO.

LTD
Senior Engineer 22OKV Grid Station NTDCL

No. ____________ Dated: 09 / 02 /2017

The Superintending Engineer,


220 KV (GSO) NTDCL, Circle

Subject: APPROVAL OF SHUTDOWNS AT 220 KV GRIDSTATION GSO NTDC

The following shut downs are required for general cleaning, maintenance and testing of electrical
equipments at 220 KV Grid Station Muzaffar Garh.
The detail is as under please.

Sr.NO. Controlling CBs


and isolators Time(Hrs) Remarks
Name of Equipment Date
From To
160MVA,220/132KV Auto-Transformer D1Q1,D1Q11,D1Q1 Both T/Fs are
2,E1Q1,E1Q11,E1Q1 running in
T-1 along with 220 KV Bus Bar –Ι and
1 2,D5Q1,D5Q11,D5Q 13.03.2017 08:30 17:00 parallel.
132 KV Bus Bar-I ( 4 hrs each bus 12,E10Q1,E10Q11&
E10Q12 Note:
bars )
Approx.40MW
160MVA,220/132KV Auto-Transformer D1Q1,D1Q11,D1Q1
load
2,E1Q1,E1Q11,E1Q1
T-1 along with 220 KV Bus Bar –ΙI and shedding/load
2,D5Q1,D5Q11,D5Q
management will
2 132 KV Bus Bar-II ( 4 hrs each bus bars 12,E10Q1,E10Q11& 14.03.2017 08:30 17:00 be required.
E10Q12
)

160MVA,220/132KV Auto-Transformer D2Q1,D2Q11,D2Q1


2,E2Q1,E2Q11,E2Q1
T-2 along with 220 KV Bus Bar –Ι and
3 2,D5Q1,D5Q11,D5Q 15.03.2017 08:30 17:00
132 KV Bus Bar-I ( 4 hrs each bus bars) 12,E10Q1,E10Q11&
E10Q12
160MVA,220/132KV Auto-Transformer D2Q1,D2Q11,D2Q1
2,E2Q1,E2Q11,E2Q1
T-2 along with 220 KV Bus Bar –ΙI and
4 2,D5Q1,D5Q11,D5Q 16.03.2017 08:30 17:00
132 KV Bus Bar-II ( 4 hrs each bus 12,E10Q1,E10Q11&
E10Q12
bars)
220 KV TPS Phase II Line along with
Both T/Fs are
5 Bus bar-I&II ( 4 hrs each bus) D3Q1,D3Q11,D3Q1 17.03.2017 08:30 17:00 running in
2,D3Q10 parallel.
6 220 KV Multan Line along with Bus D4Q1,D4Q11,D4Q1 20.03.2017 08:30 17:00
Note:
bar-I&II ( 4 hrs each bus) 2,D4Q10
132KV M.Garh City Circuit-I along E6Q1,E6Q11, E6Q12 Approx.40MW
load
7 with Bus bar-I&II ( 4 hrs each bus bar) &106,ES6 21.03.2017 08:30 17:00
shedding/load
management will
132KV M.Garh Circuit-II along with E7Q1,E7Q11, E7Q12 be required.
8 Bus bar-I&II ( 4 hrs each bus bar) &107,ES07 22.03.2017 08:30 17:00

132KV D.G Khan Circuit-I along with E4Q1,E4Q11, E4Q12


Bus bar-I&II ( 4 hrs each bus bar) &104,ES4
9 24.03.2017 08:30 17:00

132KV Mehra Khas Circuit along with E5Q1,E5Q11, E5Q12


10 Bus bar-I&II ( 4 hrs each bus bar) &105,ES5 27.03.2017 08:30 17:00

132 KV line Industrial estate –I along E8Q1,E8Q11,E8Q12, Both lines are


running in
11 with Bus bar-I&II ( 4 hrs each bus bar) 108&ES-8, E10Q1, 28.03.2017 08:30 17:00
parallel.
E10Q11&E10Q12
132 KV line Industrial estate –I along E9Q1,E9Q11,E9Q12, Note:
Approx.60 MW
with Bus bar-I&II ( 4 hrs each bus bar) 109&ES-9,E10Q1
load
12 E10Q11&E10Q12 29.03.2017 08:30 17:00 shedding/load
management will
be required.

132 KV line FEL –I along with Bus bar- E11Q1,E11Q11,E11 Both lines are
running in
I&II ( 4 hrs each bus bar) Q12,109&ES-
13 30.03.2017 08:30 17:00 parallel.
11,E10Q1
Note:
E10Q11&E10Q12
Approx.40MW
132 KV line FEL –I Ialong with Bus E12Q1,E12Q11,E12
load
bar-I&II ( 4 hrs each bus bar) Q12,109&ES- shedding/load
management will
12,E10Q1
14 31.03.2017 08:30 17:00 be required.
E10Q11&E10Q12

10/13 MVA ,132/11 KV Power E3Q1 , E3Q11


The Power
Transformer T-3 along with Bus bar- &E3Q12,E10Q1,E10
Transformer T-3
I&II ( 4 hrs each bus bars) Q11&E10Q12 for only grid
station auxiliary
15 03.04.2017 08:30 17:00 supply ,during
shutdown , the
500 KV Grid
Station M/Garh
auxiliary supply
will be use.

It is therefore requested to please approach the quarter concerned for approval of the above shutdowns, so that
the work can be carried out accordingly and well in time.
Senior Engineer
220KV GRID STATION NTDCL