DETAIL OF STRUCTURES

Pile Cap Pedestal Column Wall


Sl. Str. Name Start Date End Date Drg Completed Drg Completed Drg Completed
No. Drg Excv Comp
Lift 1 Lift 2 Lift 1 Lift 2 Lift 1 Lift 2
1 CPP (Ground Floor) 10/3/2018 - 24 20 16 - - - 32 16 8 - - -
2 CPP (1st Floor) - - - - - - - - 28 0 0 - - -
3 CPP (2nd Floor) - - - - - - - - 21 0 0 - - -
4 Reformer Radiant 10/22/2018 3/8/2019 8 8 8 49 49 - - - - - - -
5 Reformer WHR 11/22/2018 - 5 3 3 26 23 - - - - - - -
6 Reformer Steam Drum 1/1/2019 - 14 14 12 37 0 - - - - - - -
7 Reformer FG Stack 1/9/2019 - 1 1 1 1 1 - - - - - - -

8 Reformer Flue Gas Blower 2/11/2019 - 1 1 1 9 0 0 1 1 0 - - -

9 Combustion Air Blower 3/20/2019 - 3 3 0 14 0 0 1 0 0

10 CC 451 12/19/2018 - 1 1 1 1 0 0 - - - - - -
11 RB 401 1/19/2019 - 1 1 1 1 0 0 - - - - - -
12 Tech. Str. 2 10/27/2018 3/11/2019 12 12 12 12 12 - - - - - - -
13 Tech. Str. 1 9/24/2018 - 11 11 11 17 14 0 - - - - - -
14 Main Pipe Rack 1/16/2019 - 21 15 12 - - - 22 8 0 - - -
15 Branch Pipe Rack 2/9/2019 - 12 2 2 - - - 24 0 0 - - -
16 TT 451 8/28/2018 1/18/2019 1 1 1 - - - - - - 1 1 -
17 TT 452A 8/24/2018 12/30/2018 1 1 1 - - - - - - 1 1 -
18 TT 452B 10/9/2018 12/13/2018 1 1 1 - - - - - - 1 1 -
19 TT 602 8/20/2018 4/26/2019 1 1 1 - - - - - - 1 1 2
20 VV 801 9/1/2018 - 2 2 2 2 2 0 - - - - - -
21 VV 802 (CBD) 1/19/2019 - 1 1 1 2 0 - - - - 2 1 0
22 Comp House 9/19/2018 - 24 13 13 30 9 - - - - - - -

23 Comp Fdn (KA0431) 11/24/2018 - 1 1 1 - - - 6 6 0 - - -


(Ground Floor)

24 Comp Fdn (KA0411) 12/19/2018 - 1 1 1 - - - 6 6 0 - - -


(Ground Floor)
25 Tech. Str. 3 3/16/2019 - 1 1 1 4 0 0 6 0 0 - - -
26 Tech. Str. 4 - - 1 0 0 5 0 0 - - - - - -
Total 149 115 103 210 110 0 147 37 8 6 5 2