Académique Documents
Professionnel Documents
Culture Documents
May 1, 2001
In each district there should be a designer or Combinations of the above four methods may be
advisor, usually the District Hydraulics Engineer, used. Even protective works destroyed in floods
have proven to be effective and cost efficient in
knowledgeable in the application of bank protection
principles and the performance of existing works. minimizing damage to highways.
Information is also available from headquarters Design of protective features should be governed by
specialists in the Division of Design and the the importance of the facility and appropriate design
Division of Structures. The most effective designs principles. Some of the factors which should be
result from involvement with Design, Structures, considered are:
Construction, and Maintenance (for further
• Roughness. Revetments generally are less
discussion on functional responsibilities see Topic
resistant to flow than the natural channel bank.
802).
Channel roughness can be significantly reduced
if a rocky vegetated bank is denuded of trees
870-2 HIGHWAY DESIGN MANUAL
May 1, 2001
and rock outcrops. When a rough natural bank • Limits. Horizontal and vertical limits of
is replaced by a smooth revetment, the current protection should be carefully designed. The
is accelerated, increasing its power to erode, bottom limit should be secure against scour.
especially along the toe and downstream end of The top limit should not arbitrarily be at high-
the revetment. Except in narrowed channels, water mark, but above it if overtopping would
protective elements should approximate natural cause excessive damage and below it if floods
roughness. Retards, baffles and jetties can move slowly along the upper bank. The end
simulate the effect of trees and boulders along limits should reach and conform to durable
natural banks and in overflow channels. natural features or be secure with respect to
design parameters.
• Undercutting. Particular attention must be paid
to protecting the toe of revetments against
undercutting caused by the accelerated current
871.3 Selected References
along smoothed banks. Hydraulic and drainage related publications are
listed by source under Topic 807. References
• Standardization. Standardization should be a
specifically related to slope protection measures are
guide but not a restriction in designing the
repeated here for convenience.
elements and connections of protective
structures. (a) FHWA Hydraulic Engineering Circulars
(HEC) -- The following five circulars were
• Expendability. The primary objective of the
developed to assist the designer in using
design is the security of the highway, not
various types of slope protection and
security of the protective structure. Cheap
channel linings:
replaceable protection may be more economical
than expensive permanent structures. • HEC 11, Design of Riprap Revetment
(1989)
• Dependability. An expensive structure is
warranted primarily where highways carry high • HEC 14, Hydraulic Design of Energy
traffic volumes, where no detour is available, or Dissipators for Culverts and Channels
where roadway replacement is very expensive. (1983)
• Longevity. Short-lived structures or materials • HEC 15, Design of Roadside Channels
may be economical for temporary situations. with Flexible Linings (1988).
Expensive revetments should not be placed on
• HEC 18, Evaluating Scour at Bridges
banks likely to be buried in widened
(1990)
embankments, nor on banks attacked by
transient meander of mature streams. • HEC 20, Stream Stability at Highway
Structures (1990)
• Materials. Optimum use should be made of
local materials, considering the cost of special (b) FHWA Highways in the River Environment
handling. Specific gravity of stone is a major (1990) -- A comprehensive treatise of
factor in shore protection and the specified natural and man-made impacts and
minimum should not be lowered without responses on the river environment,
increasing the mass of stones. For example, sediment transport, bed and bank
10% decrease in specific gravity requires a 55% stabilization, and countermeasures.
increase in mass (say from a 9 tonne stone to a (c) FHWA Hydraulic Design Series (HDS) --
14 tonne stone) for equivalent protection. HDS 4, Design of Roadside Channels,
• Selection. Selection of class and type of contains information on erosion control
protection should be guided by the intended measures and channel lining practices.
function of the installation.
HIGHWAY DESIGN MANUAL 870-3
May 1, 2001
(d) AASHTO Highway Drainage Guidelines -- • The present alignment of the stream or river and
General guidelines for good erosion control potential meander changes.
practices are covered in Volume III -
• The ratio of cost of highway replacement versus
Erosion and Sediment Control in Highway
cost of protection.
Construction, and Volume XI - Guidelines
for Highways Along Coastal Zones and • Whether the protection need be permanent or
Lakeshores. temporary.
• Analysis of foundation and materials
Topic 872 - Planning and Location explorations.
Studies The second step is the selection and layout of
protective elements in relation to the highway
872.1 Planning facility.
The development of cost effective protective works
requires careful planning. Planning begins with site 872.2 Class and Type of Protection
investigation. The selection of the class of Protective devices are classified according to their
protection can be determined during or following function. They are further categorized as to the
site investigation. For some sites the choice is type of material from which they are constructed or
obvious; at other sites several alternatives or shape of the device. For additional information on
combinations may be applicable. See the FHWA specific material types and shapes see Topic 873,
publication, "Highways in the River Environment", Design Concepts.
for a complete and thorough discussion of hydraulic
and environmental design considerations associated There are two basic classes of protection, armor
with hydraulic structures in moveable boundary treatment and training works. Table 872.1 relates
waterways. different location environments to these classes of
protection.
Some specific site conditions that may dictate
selection of a class and type of protection different 872.3 Site Consideration
from those shown in Table 872.1 are:
The determination of the lengths, heights,
• Available right of way. alignment, and positioning of the protection are
affected to a large extent by the facility location
• Available materials.
environment.
• Possible damage to other properties through
An evaluation is required for any proposed highway
streamflow diversion or increased velocity.
construction or improvement that encroaches on a
• Environmental concerns. floodplain. See Topic 804, Floodplain
Encroachments for detailed procedures and
• Channel capacity or conveyance.
guidelines.
• Conformance to new or existing structures. (1) Young Valley. Typically young valleys are
• Provisions for side drainage, either surface narrow V-shaped valleys with streams on steep
waters or intersecting streams or rivers. gradients. At flood stage, the stream flow
covers all or most of the valley floor. The usual
The first step is to determine the limits of the
situation for such locations is a structure
protection with respect to length, depth and the
crossing a well-defined channel in which the
degree of security required.
design discharge will flow at a moderate to high
Considerations at this stage are: velocity.
• The severity of attack.
870-4 HIGHWAY DESIGN MANUAL
May 1, 2001
Table 872.1
Drop Structure
Stacked Conc.
Grouted Rock
Grouted Rock
Conc. Blocks
Fabric Filled
Conc. Lined
Rock Earth
Bulk heads
Vegetation
Gabions
Fencing
Fencing
Riprap
Piling
Piling
Other
Other
Cribs
Earth
Rock
Cross Channel
Young Valley X Ø X X X
Mature Valley X Ø Ø Ø X X X X X X X X X X X X
Parallel Encroachment
Young Valley X Ø X X X
Mature Valley X X Ø Ø Ø X Ø X X X X X X X X X X X X X
Lakes and Tidals Basins X X Ø Ø Ø X Ø X
Ocean Front X Ø Ø X X X X X
Desert-wash
Top debris cone X Ø Ø Ø X X
Center debris cone X Ø Ø Ø X X X X
Bottom debris cone X Ø Ø Ø X X X X
Overflow and floodplain X X Ø X Ø X X X X
Artificial channel X X Ø Ø Ø X Ø X
Culvert
Inlet X X Ø X
Outlet X X Ø X
Bridge
Abutment X Ø Ø X Ø X
Upstream X X X X X X
Downstream X X X X X X X
Roadside ditch X X X Ø X
Ø Where large rock for riprap is not available
HIGHWAY DESIGN MANUAL 870-5
May 1, 2001
(a) Cross-Channel Location. A cross channel constriction of the waterway. The most
location is a highway crossing a stream on common constriction is in width, to shorten
normal or skewed alignment. The erosive the structure. Next in frequency is
forces of parallel flow associated with a obstruction by piers and bents of bridges or
normal crossing are generally less of a partitions of multiple culverts.
threat than the impinging and eddy flows
The risk of constricting the width of the
associated with a skewed crossing. The
waterway is closely related to the relative
effect of constriction by projection of the
conveyance of the natural waterway
roadway embankment into the channel
obstructed, the channel scour, and to the
should be assessed.
channel migration. Constricting the width
Characteristics to be considered include: of flow at structures has the following
effects:
• Stream velocity.
• Increase in the upstream water surface
• Scouring action of stream.
elevation (backwater profile).
• Bank stability.
• Increase in flow velocity through the
• Channel constrictions (artificial or structure opening (waterway).
natural).
• Causes eddy currents around the
• Nature of flow (tangential or upstream and downstream ends of the
curvilinear). structure.
• Areas of impingement at various stages. Unless protection is provided the eddy
currents can erode the approach roadway
• Security of terminals. embankment and the accelerated flow can
Common protection failures occur from: cause scour at bridge abutments. The
effects of erosion can be reduced by
• Undermining of the toe (inadequate providing transitions from natural to
foundation). constricted and back to natural sections,
• Local erosion due to eddy currents. either by relatively short wingwalls or by
relatively long training embankments or
• Inadequate upstream and downstream structures.
terminals or transitions to erosion-
resistant banks or outcrops. Channel changes, if properly designed, can
improve conditions of a crossing by
• Structural inadequacy at points of reducing skew and curvature and enlarging
impingement overtopping. the main channel. Unfortunately there are
Any of the more substantial armor "side effects" which actually increase
treatments can function properly in such erosion potential. Velocity is almost
exposures providing precautions are taken always increased by the channel change,
to alleviate the probable causes of failure. both by a reduction of channel roughness
If the foundation is questionable for grouted and increase of slope.
rock or other rigid types it would not be At crossing locations, lateral erosion can be
necessary to reject them from consideration controlled by positive protection, such as
but only to provide a more acceptable armor on the banks, jetties to deflect
treatment of the foundation, such as heavy currents away from the banks, retards to
rock or sheet piling. reduce riparian velocity, or vertical walls or
Whether the highway crosses a stream bulkheads. The life cycle cost of such
channel on a bridge or over a culvert, devices should be considered in the
economic considerations often lead to
870-6 HIGHWAY DESIGN MANUAL
May 1, 2001
attacking it. If sand supply is less plentiful or embankment face, or (3) off shore devices like
subject to seasonal variations, the new beach groins to aggrade the beach at embankment toe.
can be induced or retained by groins.
See Index 873.3(2) for further discussion on
If sand is in scant supply, backwash from a determining the size of rocks necessary in shore
revetment tends to degrade the beach or bed protection for various wave heights.
even more than the seasonal variation, and an
(5) Desert Wash Locations. Special consideration
allowance should be made for this scour when
should be given to highway locations across the
designing the revetment, both as to weight of
natural geographical features of desert washes,
stones and depth of foundation. Groins may be
sand dunes, and other similar regions
ineffective for such locations; if they succeeded
susceptible to intrinsic erosion.
in trapping some littoral drift, downcoast
beaches would recede from undernourishment. Desert washes are a prominent feature of the
physiography of California. Many long
Seasonal shifts of the shore line result from
stretches of highway are located across a
combinations of:
succession of outwash cones. Infrequent
• Ranges of tide. discharge is typically wide and shallow,
transporting large volumes of solids, both
• Reversal of littoral currents.
mineral and organic. Rather than bridge the
• Changed direction of prevailing onshore natural channels, the generally accepted
winds. technique is to concentrate the flow by a series
of guide dikes leading like a funnel to a
• Attack by swell. relatively short crossing.
Generally the shift is a recession, increasing the The important consideration at these locations
exposure of beach locations to the hazard of is instability of the channel (see Figure 872.2).
damage by wave action. On strands or along For a location at the top of a cone (Line A),
extensive embayments, recession at one end discharge is maximum, but the single channel
may result in deposition at the other. emerging from the uplands is usually stable.
Observations made during location assessment For a location at the bottom of the cone (Line
should include investigation of this C), instability is maximum with poor definition
phenomenon. For strands, the hazard may be of the channel, but discharge is reduced by
avoided by locating the highway on the infiltration and stream dispersion. The energy
backshore facing the lagoon. of the stream is usually dissipated so that any
Foundation conditions vary widely for beach protection required is minimal. The least
locations. On a receding shore, good bearing desirable location is midway between top and
may be found on soft but substantial rock bottom (Line B), where large discharge may
underlying a thin mantle of sand. Bed stones approach the highway in any of several old
and even gravity walls have been founded channels or break out on a new line. Control
successfully on such foundations. Spits and may require dikes continuously from the top of
strands, however, are radically different, often the cone to such a mid-cone site with slope
with softer clays or organic materials protection added near the highway where the
underlying the sand. Sand is usually plentiful at converging flow is accelerated.
such locations, subsidence is a greater hazard
than scour, and location should anticipate a
"floating" foundation for flexible, self-adjusting
types of protection.
In planning ocean-front locations, the primary
decision is a choice of (1) alignment far enough
inshore to avoid wave attack, (2) armor on the
870-10 HIGHWAY DESIGN MANUAL
May 1, 2001
• The scour depths that can be anticipated. A set of plans and specifications must be prepared
to define and describe the protection that the design
• The lack of good foundation. engineer has in mind. These plans should show
Effective protective methods include armor controlling factors and an end product in such detail
along the highway and at structures and the that there will be no dispute between the
probable need for baffles to control the construction engineer and contractor. To serve the
direction and velocity of flow. Installations of dual objectives of adequacy and economy, plans
rock, fence, palisades, slope paving, and dikes and specifications should be precise in defining
have been successful. materials to be incorporated in the work, and
flexible in describing methods of construction or
872.4 Data Needs conformance of the end product to working lines
and grades.
The types and amount of data needed for planning
and analysis of bank and shore protection varies Recommendations on channel lining, slope
from project to project depending upon the class protection, and erosion control materials can be
and extent of the proposed protection, site location requested from the District Hydraulics Engineer, the
District Materials Branch and the Erosion Control
HIGHWAY DESIGN MANUAL 870-11
May 1, 2001
and Geosynthetics Branch of the Engineering determining the design frequency, velocity,
Service Center. The Office of Landscape backwater, and other limiting factors should include
Architecture can be of assistance in selecting the an evaluation of the consequences of failure on the
best practices for temporary and permanent erosion highway facility and adjacent property. Stream
and sediment control measures. The Caltrans Joint stability and sediment transport of a watercourse are
Bank Protection Committee is available on request critical factors in the evaluation process that should
to provide expert advise on extraordinary situations be carefully weighted and documented. Designs
or problems. See Index 802.3 for further should not be based on an arbitrary storm or flood
information on the organization and functions of the frequency. Such designs imply that limiting factors
Committee and related risks have been adequately evaluated
which is seldom, if ever, the case.
Combinations of armor-type protection can be used,
the slope revetment being of one type and the A suggested starting point of reference for the
foundation treatment of another. The use of rigid, determination of the design high water level is that
non-flexible slope revetment may require a flexible, the protection withstand high water levels caused by
self-adjusting foundation for example: grouted rock meteorological conditions having a recurrence
on the slope with heavy rock foundation below, or interval of one-half the service life of the protected
PCC slope paving with a steel sheet-pile cutoff wall facility. For example, a modern highway
for foundation. embankment can reasonably be expected to have a
service life of 100 years or more. It would therefore
Bank protection may be damaged while serving its
be appropriate to base the preliminary evaluation on
primary purpose. Cheap replaceable facilities may
a high water elevation resulting from a storm or
be more economical than expensive permanent
flood with a 2 percent probability of exceedance (50
structures. However, an expensive structure may be
year frequency of recurrence). The first evaluation
economically warranted for highways carrying large
may have to be adjusted, either up or down, to
volumes of traffic or for which no detour is
conform with a subsequent analysis which considers
available.
the importance of the encroachment and level of
Cost of stone is extremely sensitive to location. related risks.
Variables are length of haul, efficiency of the
There is always some risk associated with the
quarry in producing acceptable sizes, royalty to
design of protection features. Special attention
quarry and, necessity for stockpiling and
must be given to life threatening risks such as those
rehandling. On some projects the stone is available
associated with floodplain encroachments.
in roadway excavation.
Significant floodplain risks are classified as those
Cost of stone is not very sensitive to size. having probability of:
Quarrying produces a wide range of sizes. If only a
light riprap is specified, the large stones have to be • Catastrophic failure with loss of life.
broken by spot blasting. If heavy riprap is required, • Disruption of fire and ambulance services or
the run of the quarry may be usable without closing of the only evacuation route available to
reblasting. With Method A placement, one 8 tonne a community.
stone can be set quicker than two 4 tonne stones.
Refer to Topic 804, Floodplain Encroachments, for
further discussion on evaluation of risks and
873.2 Design High Water and Hydraulics
impacts.
The most important, and often the most perplexing
(1) Streambank Locations. The velocity along the
obligation, in the design of bank and shore
banks of watercourses with smooth or
protection features is the determination of the
uniformly rough tangent reaches may only be a
appropriate design high water elevation to be used.
small percentage of the average stream velocity.
The design flood stage elevation should be chosen
However, local irregularities of the bank and
that best satisfies site conditions and level of risk
streambed may cause turbulence that can result
associated with the encroachment. The basis for
870-12 HIGHWAY DESIGN MANUAL
May 1, 2001
in the bank velocity being greater than that of should be based on the owners schedule of
the central thread of the stream. The location of operation.
these irregularities is not always permanent as
Except for inland tidal basins affected by
they may be caused by local scour, deposition
wind tides, floods and seiches, the static or
of rock and sand, or stranding of drift during
still-water level used for design of shore
high water changes. It is rarely economical to
protection is the highest tide. In tide tables,
protect against all possibilities and therefore
this is the stage of the highest tide above
some damage should always be anticipated
"tide-table datum" at MLLW. To convert
during high water stages.
this to MSL datum there must be subtracted
Essential to the design of streambank protection a datum equation (0.8 to 1.2 m) factor. If
is sufficient information on the characteristics datum differs from MSL datum, a further
of the watercourse under consideration. For correction is necessary. These steps should
proper analysis, information on the following be undertaken with care and independently
types of watercourse characteristics must be checked. Common errors are:
developed or obtained:
• Ignoring the datum equation.
• Design Discharge
• Adding the factor instead of subtracting
• Design High Water Level it.
• Flow Types • Using half the diurnal range as the stage
of high water.
• Channel Geometry
To clarify the determination of design high-
• Flow Resistance
water, Fig. 873.2A shows the Highest Tide
• Sediment Transport in its relation to an extreme-tide cycle and
to a hypothetical average-tide cycle,
Refer to Chapter 810, Hydrology, for a general
together with nomenclature pertinent to
discussion on hydrologic analysis and
three definitions of tidal range. Note that
specifically to Topic 817, Flood Magnitudes;
the cycles have two highs and two lows.
Topic 818, Flood Probability and Frequency;
The average of all the higher highs for a
and Topic 819, Estimating Design Discharge.
long period (preferably in multiples of the
For a detailed discussion on the fundamentals
19-yr. metonic cycle) is MHHW, and of all
of alluvial channel flow, refer to Chapter III,
the lower lows, MLLW. The vertical
"Highways in the River Environment", and to
difference between them is the diurnal
HEC-20, Stream Stability at Highway
range.
Structures, for further information on sediment
transport. Particularly on the Pacific coast where
MLLW is datum for tide tables, the stage of
(2) Ocean & Lake Shore Locations. Information
MHHW is numerically equal to diurnal
needed to design shore protection is:
range.
• Design High Water Level The average of all highs (indicated
• Design Wave Height graphically as the mean of higher high and
lower high) is the MHW, and of all the
(a) Design High Water Level. The flood stage lows, MLW. Vertical difference between
elevation on a lake or reservoir is usually these two stages is the mean range.
the result of inflow from upland runoff. If
the water stored in a reservoir is used for See Index 814.5, Tides and Waves, for
power generation, flood control, or information on where tide and wave data
irrigation, the design high water elevation may be obtained.
HIGHWAY DESIGN MANUAL 870-13
May 1, 2001
Figure 873.2B
(3) The upstream terminal can be (1) General Features. This kind of
determined best by observation of protection, commonly called riprap,
consists of rock courses placed upon
870-20 HIGHWAY DESIGN MANUAL
May 1, 2001
the embankment or the natural slope • Depth at which the stones are
along a stream. Rock, as a slope founded (bottom of toe trench).
protection material, has a number of
desireable features which have led to • Elevation at the top of protection.
its widespread application. • Thickness of protection.
It is usually the most economical type • Need for geotextile and backing
of revetment where stones of sufficient material.
size and quality are available, it also
has the following advantages: • Face slope.
becomes part of the fill. With this is generally the case with Method
type of construction fill material B placement. With Method B
can filter down through the voids placement, most of the finer
of the large stones and that portion material will naturally settle to the
of the fill above the rocks could be bottom and coarser stones will
lost. If it is necessary to carry work to the outside. Consult the
embankment material out over the District Hydraulics Engineer
rock slope protection a geotextile and/or the District Materials
is required to prevent the loses of Branch on the need for fabric or
fill material. rock backing.
The embankment fill slope is When fabric is used with rock
usually determined from other slope protection classes 1/2 T or
considerations such as the angle of larger, a layer of rock backing is
repose for embankment material, needed to anchor the fabric.
or the normal 1:2 specified for Backing material must be sized so
high-standard roads. If the that it will not work out through
necessary size of rock for the given the voids of the large stones
exposure is not locally available, overlaying it. For very large
consideration should be given to classes of protection with severe
flattening of the embankment slope exposure it may be appropriate to
to allow a smaller size stone, or use a smaller class of rock slope
substitution of other types of protection to perform the backing
protection. On high embankments, and bedding function.
alternate sections on several slopes Determining the need for fabric,
should be compared, practically rock backing, or multiple layers of
and economically; flatter slopes rock slope protection requires
require smaller stones in thinner sound engineering judgment in
sections, but at the expense of evaluating the character of the
longer slopes, a lower toe embankment or native material
elevation, increased embankment, being protected, the slope rate of
and perhaps additional right of the embankment, the relative
way. importance and risk of loss of the
protected facility as well as the
(d) Rock Slope Protection Fabric and
cost of the protective works
Rock Backing -- Rock Slope
relative to the protected facility.
protection fabric and/or rock
backing can be used directly on the Rock slope protection and rock
slope to prevent the erosion of the backing material stone sizes,
underlying embankment material gradings and quality requirements
or native material through the are contained in Section 72-2.02 of
voids of the rock slope protection. the Standard Specifications.
They may be warranted where
(2) Streambank Protection Design. In the
embankment material is not
lower reaches of larger rivers wave
cohesive, or where the slope
action resulting from navigation or
protection is subject to wave
wind blowing over long reaches may
action. They may not be necessary
be much more serious than velocity. A
if the slope protection is graded
0.6 m wave, for example, is more
from fine to coarse from
damaging than direct impingement of a
embankment to water exposure as
current flowing at 3 m/s.
870-22 HIGHWAY DESIGN MANUAL
May 1, 2001
Figure 873.3A
Nomograph of Stream-Bank Rock Slope Protection
870-24 HIGHWAY DESIGN MANUAL
May 1, 2001
Table 873.3B
Rock Slope Protection Design Guide
Mean PARALLEL FLOW ALONG TANGENT BANK IMPINGEMENT FLOW AGAINST CURVED BANK
Stream Bank Minimum Protection Placement Section Bank Minimum Protection Placement Section
Velocity Velocity Stone Class Method Thickness Velocity Stone Class Method Thickness
VM VA W WC T VB W WC T
fps fps lb A or B ft fps lb or T A or B ft
4.5 3 None 6 3 lb None
6 4 None 8 15 Facing B 1.8
7.5 5 1 None 10 57 1/4 ton B 3.3
9 6 3 None 12 170 1/4 ton B 3.3
10.5 7 7 Facing B 1.8 14 430 1/2 ton A 3.3
B 4.2
12 8 15 Facing B 1.8 16 950 1 ton A 4.2
B 5.3
13.5 9 30 Light B 2.5 18 1.0 T 2 ton A 5.3
15 10 57 1/4 ton B 3.3 20 1.8 4 ton A 6.7
18 12 170 1/4 ton B 3.3 24 5.5 8 ton A 8.3
21 14 430 1/2 ton A 3.3 28 13.7 Special
B 4.2
24 16 950 1 ton A 4.2 32 30.4 Special
B 5.3
NOTES:
1. All Values in Figure 873.3A and Table 873.3B are in U.S. Customary Units. Conversions to the S.I. System are; 1 ft. =
0.305 m
1 lb. = 0.454 kg
1 ton = 0.907 tonne
2. See Section 72 of the Standard Specifications for Gradations of the Protection Classes (WC) indicated.
HIGHWAY DESIGN MANUAL 870-25
May 1, 2001
Figure 873.3C
Rock Slope Protection
Notes:
(1) If necessary. See text. (4) Bed stone is 50% to 100% heavier than face stone.
(2) Thickness "T" from Table 873.3B. (5) This is not a standard design. Dimensions
(3) Face stone is determined from Figure 873.3D. and details should be modified as required.
870-26 HIGHWAY DESIGN MANUAL
May 1, 2001
Figure 873.3D
Nomographs For Design of Rock Slope Shore Protection
HIGHWAY DESIGN MANUAL 870-29
May 1, 2001
(b) Sacked-Concrete Slope Protection. This below the flow line of the stream is
method of protection consists of facing the common practice.
embankment with sacks filled with
If the ends are not tied into rock or other
concrete. It is an expensive but much used
nonerosive material, cutoff returns are to
type of revetment. Much hand labor is
be provided and if the protection is long,
required but it is simple to construct and
cutoff stubs are built at 10 m intervals, in
adaptable to almost any embankment
order to prevent or retard a progressive
contour. Economic justification for this
failure.
type of revetment often depends upon the
use of local pit-run material for aggregate, Protection should be high enough to
which need not conform to that ordinarily preclude overtopping. If the roadway
associated with structural concrete. grade is subject to flooding and the
Details of sacked concrete slope protection shoulder material does not contain
are shown on Standard Plan D101. sufficient rock to prevent erosion from the
top, then pavement should be carried over
Tensile strength is low and as there is no
the top of the slope protection in order to
flexibility, the installation must depend
prevent water entering from this direction
almost entirely upon the stability of the
embankment for support and therefore For good appearance, it is essential that the
should not be placed on face slopes much sacks be placed in horizontal courses. If
steeper than the angle of repose of the the foundation is irregular, corrective work
embankment material. Slopes steeper than such as placement of entrenched concrete
1:1 are rare; 1:1.5 is common. The flatter or sacked concrete is necessary to level up
the slope, the less is the area of bond the foundation. Refer to "Highways in the
between sacks. From a construction River Environment", Section 5.3.4, for
standpoint it is not practical to increase the further discussion on the use of sacked
area of bond between sacks; therefore for concrete slope protection.
slopes as flat as 1:2 all sacks should be laid (c) Concrete Slope Paving.
as headers rather than stretchers.
(1) General Features. This method of
Integrity of the revetment can be increased protection consists of paving the
by embedding dowels in adjoining sacks to embankment with portland cement
reinforce intersack bond. A No. 10 concrete. Details of concrete slope
deformed bar driven through a top sack protection are shown on Standard Plan
into the underlying sack while the concrete D101. Slope paving is used only
is still fresh is effective. At cold joints, the where flow is controlled and will not
first course of sacks should be impaled on over-top the protection.
projecting bars that were driven into the
last previously placed course. The extra It is particularly adaptable to locations
strength may only be needed at the where high-velocity flow is not detri-
perimeter of the revetment. mental but desirable and the hydraulic
efficiency of smooth surfaces is
Almost all failures of sacked concrete are a important. It has been used very little
result of stream water eroding the in shore protection. On a cubic meter
embankment material from the bottom, the basis the cost is high but as the
ends, or the top. thickness is generally only 75 to 150
The bottom should be founded on bedrock mm, the cost on a basis of area covered
or below the depth of possible scour. In will usually be less than for sacked-
the case where streambed sands have concrete slope protection. This is
normal specific gravity a depth of 1.5 m especially so when sufficiently large
quantities are involved and alignment
870-32 HIGHWAY DESIGN MANUAL
May 1, 2001
is such as to warrant the use of mass fine aggregate concrete into the inplace
production equipment such as slip- fabric mat. Fabric mattresses are made in
form pavers. 50 to 300 mm thickness and in a variety of
block sizes and configurations.
Due to the rigidity of PCC slope
paving, its foundation must be good Hydrostatic uplift pressure is relieved
and the embankment stable. Although through filter points or plastic weep tubes
reinforcement will enable it to bridge inserted in the mats. A filter fabric is used
small settlements of the embankment under the mat when relief of hydrostatic
face, even moderate movements could pressure is necessary.
be disastrous. The toe must be on
bedrock or extend below possible Table 873.3F
scour. When this is not feasible
without costly underwater construc- Channel Linings
tion, rock or PCC grouted RSP have
been used as a foundation. A better Mean Thickness of Lining (mm) Minimum
Velocity Reinforcement
but much more expensive solution is to (m/s)
place the toe on a PCC wall or piles. Sides Bottom
Every precaution must be taken to
Portland Cement Concrete
exclude stream water from pervious
or Air Blown Mortar
zones behind the slope paving. The
light slabs will be lifted by <3 75 -90 90 - 100 152x152-
comparatively small hydrostatic MW19.4 x
pressures, opening joints or cracks at MW19.4
other points in a series of progressive welded wire
Fabric
failures leading to extensive or
complete failure. 3 - 4.5 100 -125 125 -150 #15 Bars at
300 mm and
Considering the severity of failure 450 mm
from bank erosion or hydrostatic centers
pressure after overtopping, 0.3 to 0.6 m
4.5 or 150 - 200 175 - 200 #10 Bars at
of freeboard above design high water
more 300 mm
is recommended for this type of centers
revetment. Refer to HEC-11, Design both ways
of Riprap Revetment, Section 6.4, for
further discussion on the use of
concrete slope paving. A major advantage of this type revetment
is the ease of placement. It may be placed
(d) Fabric Formed Protection. This method of in the dry or underwater. The fabric weave
protection uses sectionalized fabric is such that it will restrain cement loss
mattresses filled with a fine aggregate while permitting the release of excess
concrete as facing for embankment, river mixing water which improves the quality
bank, and lake shore. Fabric formed slope of the concrete.
paving is a relatively new and cost
effective alternative to conventional slope A secondary advantage is that sufficient
paving methods. silt and soil is often deposited in the
mattress indentations to support
A double-layered envelope of nylon, vegetation. As a result, the root systems
polypropylene or other suitable synthetic that develop help anchor the mattress.
fabric is laid on the area to be protected
then filled. Filling consists of pumping a
HIGHWAY DESIGN MANUAL 870-33
May 1, 2001
Three most common types of fabric formed width, w, layer thickness and embankment
mattress configurations are shown in slope is shown in Figure 873.3H.
Figure 873.3G.
Soil cement slope protection is to be
(e) Soil Cement Slope Protection. This kind founded on nonerodible material or below
of slope protection consists of constructing the depth of possible scour to ensure
the outer limit of highway embankments against undermining of the toe.
with compacted cement treated material. Consideration should be made to providing
Standard highway construction equipment cutoff stubs at the ends of the installation
may be used to place and compact soil to prevent undercutting by waves or
cement slope protection on 1:1.5 to 1:4 current.
slopes. Where rock riprap material is not
In addition to economy, the following are
readily available, soil cement slope
some of the other advantages to using soil
protection may be the most economical
cement revetments:
alternative type revetment. Soil cement is
also well suited for use in median ditches • Slight settlement or other minor
or other wide drainage areas that cannot be movement of the highway embankment
vegetated. does not impair its stability.
A wide variety of selected on site soils or • It presents a pleasing appearance,
local borrow can be used to make durable usually acceptable in recreational and
soil cement slope protection. Any good environmentally sensitive areas.
sandy soil is generally acceptable and
• No unusual design considerations are
depending on the quality of the soil, the
required.
percent cement will vary from 7% to 14%.
The actual percentage must be determined • No unusual construction practices or
by laboratory tests. If requested, the special equipment are required.
District Materials Engineer can provide
information on the quality of soil available • Properly designed and constructed it is
and recommended cement content. virtually maintenance free.
Figure 873.3G
1.2 m/s. If velocities are in excess of 1.2 m/s, a velocity, or depth of flowing water. As shore
lining maybe needed (See Table 873.3I). protection, they control shoaling and scour by
deflecting the strength of currents and waves.
Temporary channel liners are used to establish
vegetative growth in a drainage way or as slope The degree of permeability is among the most
protection prior to the placement of a important properties of control structures. An
permanent armoring. Some typical temporary impermeable structure may deflect a current
channel liners are: entirely, whereas a permeable structure may
• Straw serve mainly to reduce the strength of water
velocity, currents or waves.
• Excelsior
Training systems of the retard and permeable
• Jute
jetty types are similar in that they are usually
• Woven paper extensive or multi-unit open structures like;
Vegetative and temporary channel liners are piling, fencing, and unit frames. They are
suitable for conditions of uniform flow and dissimilar in function and alignment, retards
moderate shear stresses. being parallel and groins oblique to the banks.
The retard is a milder remedy than jetty
Permanent soil reinforcing mats and rock construction.
riprap may serve the dual purpose of temporary
and permanent channel liner. Some typical (a) Retard Types. A retard is a bank
permanent channel liners are: protection structure designed to check
riparian velocity and induce silting and
• Gravel or cobble size riprap accretion. They are usually placed parallel
• Fiberglass roving to the highway embankment or erodible
banks of channels on stable gradients.
• Geosynthetic mats Retards typically take the following forms
• Polyethelene cells or grids of construction:
• Gabion Mattresses • Fencing - single or double lines
Composite designs are often used where there • Palisades - piles and netting
are sustained low flows of high to moderate
• Timber piling or pile bents
velocities and intermediate high water flows of
low to moderate velocities. Brush layering is a • Steel or timber jacks
permanent type of erosion control technique Retards are applicable primarily on streams
that may also have application for channel which meander to some extent within a
protection, particularly as a composite design. mature valley. Typical uses include the
Further information on brush layering and following:
fiberglass roving methods and techniques are
available from METS. • Protection at the toe of highway
embankments that encroach on a
Design procedures for determining suitable stream channel.
maximum conditions for vegetation, temporary
and permanent channel liners are given in • Training and control to inhibit
Chapter IV, HEC-15, Design of Roadside erosion upstream and downstream
Channels and Flexible Linings. from stream crossings.
• Control of erosion redeposition of
873.4 Training Systems material where progressive
(1) General. Training systems are structures, embayments are creating a
usually within a channel, that act as problem.
countermeasures to control the direction,
870-38 HIGHWAY DESIGN MANUAL
May 1, 2001
Table 873.3I
Permissible Velocities for Flexible Channel Linings
1 Permissible Velocity
Type of Lining
(m/s)
Intermittent Sustained
Flow Flow
Vegetation:
Bermuda Grass, uncut 1.2 0.8
Bermuda Grass, mowed or Crab Grass, uncut 1.2 0.8
Riprap:
Gravel, 25 mm 0.9 0.6
Gravel, 50 mm 1.1 0.8
Cobble, 75 mm 1.5 1.2
Cobble, 150 mm 2.3 2.0
Temporary:
Woven Paper Net 1.4 1.1
Jute Net 1.5 1.2
Fiberglass Roving 1.7 1.4
Straw with Net 2.0 1.4
Curled Wood Mat 2.0 1.4
Synthetic Mat 3.2 2.3
NOTE:
1. Ref. HEC-15 & HDS #4
HIGHWAY DESIGN MANUAL 870-39
May 1, 2001
(1) Fence Type. Fence-type structures are Typical design considerations include:
used as retards, permeable or
• If the stream carries heavy
impermeable jetties, and as baffles.
debris, the elevation of the top of
These structures can be constructed of
the pile should be well below the
various materials.
high-water level in order that
Fence type retards may be effective on heavy objects such as logs will
smaller streams and areas subject to pass over the top during normal
infrequent attack, such as overflow floods.
areas. Single and double rows of • Piles must have sufficient
various types of fencing have been penetration to prevent loss from
used. The principal difference scour or impact by floating
between fence retards and ordinary debris or both. This is especially
wire fences is that the posts of retards important for the piles at the
must be driven sufficiently deep to outer end of jetties. If scour is a
avoid loss by scour. problem, the pile may be
Permeability can be varied in the protected by a layer of rock
design to fit the requirements of the placed on the streambed. Piles
location for single fences, the factor should be long enough to
most readily varied is the pattern of the penetrate below probable scour,
wire mesh. For multiple fences, the with penetration of a least 4.5 m
mesh pattern can be varied or the space in streams with sandy beds and
between fences can be filled to any velocities of 3.0 to 4.5 m/s.
desired height. Making optimum use • Ends of the system should be
of local materials, this fill may be joined to the bank in order to
brush ballasted by rock, or rock alone. prevent parallel high-velocity
flow between the retard and the
(2) Piles and Palisades. Retards and bank. If the installation is long,
jetties may be of single, double, or additional bank connections may
triple rows of piles with the outside or be placed at intervals.
upstream row faced with wire mesh • Facing material should be
fencing material, boards or polymeric fastened to the upstream or
straps interwoven into a high-strength channel side of the piling in
net. The facing adds to the retarding order that the force of the water
effect and may trap light brush or and impact of debris will not be
debris to supplement its purpose. This entirely on the fasteners.
type retard is particularly adapted to
larger streams where the piles will (3) Jacks and Tetrahedrons. Jacks and
remain in the water. The number of tetrahedrons are skeletal frames that
pile rows and amount of facing may be can be used as retards or permeable
varied to control the deposition of jetties. Cables can be used to tie a
material. In leveed rivers it is often number of similar units together in
desirable to discourage accretion so as longitudinal alignment and for
to not constrict the channel but provide anchorage of key units to deadmen.
sufficient retarding effect to prevent Struts and wires are added to the basic
loss of a light bank protection such as frames to increase impedance to flow
vegetation or light rock facing. of water directly by their own
resistance and indirectly by the debris
they collect.
870-40 HIGHWAY DESIGN MANUAL
May 1, 2001
Both devices serve best in meandering intended to alter the channel alignment
streams which carry considerable bed the effect on adjacent property must be
load during flood stages. Impedance assessed. Where deposition of
of the stream along the string of units material is the primary function, the
will cause deposit of alluvium, service life of the installation is
especially at the crest and during the dependent on the deposition rate and
falling stage. Beds of such streams the ultimate establishment of a natural
often scour on the rising stage, retard.
undercutting the units and causing
The length of a retard system should
their subsidence, often accompanied
extend from a secure anchorage on the
by rotation when one leg or side is
upstream end to anchorage on the
undercut more than the other.
downstream end beyond the area under
Deposition of the falling stage usually
direct attack. Since erosion often
restores the former bed, partially or
progresses downstream, this possibility
completely burying the units. In that
should be considered in determining
lowered and rotated poition, they may
the planned length.
still be completely effective in future
floods. The top of a retard need not extend to
the elevation of design high water. In
Retards may be used alone or in
major rivers and streams where drift is
combination with other types of slope
large and heavy it is essential that the
protection. In combination with a
retard be low enough to pass debris
lighter type of armor they may be more
over the top during stages of high flow.
economical than a heavier type of
protection. They can be used as toe For further information on retards refer
protection for other types of slope to Section 5.4.3, "Highways in the
protection where a good foundation is River Environment".
impractical because of high water or (b) Jetty Types. A jetty is an elongated
extreme depth of poor material. artificial obstruction projecting into a
Where new embankment is placed stream or the sea from bank or shore to
behind the retard consideration should control shoaling and scour by deflection or
be given to protecting the slope to redirection of currents and waves.
inhibit erosion until the retard has had This classification may be subdivided with
an opportunity to function. The slope respect to permeability. Impermeable
protection used should promote the jetties being used to deflect the stream and
establishment of a natural cover, such permeable jetties being used not only to
as discussed under Index 873.3(5), deflect the stream but to permit some flow
Vegetation. through the structure to minimize the
Retards on tangent reaches of narrow formation of eddies immediately
channels may, by slowing the velocity downstream. Most jetty installations are
on one side, cause an increase in permeable structures.
velocity, on the other. On wider Permeable jetties typically take the
reaches of a meandering stream they following forms of construction:
may, by slowing a rebounding high
velocity thread, have a beneficial effect • Palisades -- piles and netting.
on the opposite bank. Where the prime • Single and double rows of timber-
purpose of the retard system is to braced piling.
reduce stream bank velocity to
• Steel or timber jacks.
encourage deposition of material
HIGHWAY DESIGN MANUAL 870-41
May 1, 2001
• Precast concrete, interlocking shapes The relation between length and spacing of
or hollow blocks. jetties should approximate unity as a
general rule to assure complete entrapment
Impermeable jetties typically take the
and retention of material. The spacing can
following forms of construction:
be increased if the resulting scalloped
• Guide and spur dikes, earth or rock. effect is not detrimental to the desired
• PCC grouted riprap dikes. result.
• Single and double lines of sheeting or (c) Guide Dikes/Banks. Guide banks are
sheet piling (steel, timber or concrete, appendages to the highway embankment at
framed and braced or on piling). bridge abutments (Figure 873.4A). They
are smooth extensions of the fill slope on
• Double fence, filled.
the upstream side. Approach
• Log or timber cribs, filled. embankments are frequently planned to
Impermeable jetties in the form of filled project into wide floodplains, to attain an
fences and cribs have been used with only economic length of bridge. At these
limited success. Characteristic locations high water flows can cause
performance of these is the development of damaging eddy currents that scour away
an eddy current immediately downstream abutment foundations and erode approach
which attacks the bank and often requires embankments. The purose of guide dikes
secondary protective measures. is twofold. The first is to align flow from a
wide floodplain toward the bridge opening.
Basic principles for permeable jetties are The second is to move the damaging eddy
much the same as for retards, the important currents from the approach roadway
difference being that they deflect the flow embankment to the upstream end of the
in addition to encouraging deposition. The dike.
preceding comment on retards should be
considered as related and applicable to Guide banks are usually earthen
jetties when qualified by this basic embankment faced with rock slope
difference. protection. Optimum shape and length of
guide dikes will be different for each site.
Permeable jetties are placed at an angle Field experience has shown that an
with the embankment and are more elliptical shape with a major to minor axis
applicable in meandering streams for the ratio of 2.5:1 is effective in reducing
purpose of directing or forcing the current turbulence. The length is dependant on the
away from the embankment. When the ratio of flow diverted from the flood plain
purpose is to deposit material and promote to flow in the first 30 m of waterway under
growth, the jetties are considered to have the bridge. If the use of another shape
fulfilled their function and are expendable dike, such as a straight dike, is required for
when this occurs. practical reasons more scour should be
They also encourage deposition of bed expected at the upstream end of the dike.
material and growth of vegetation. Retards The bridge end will generally not be
build a narrow strip in front of the immediately threatened should a failure
embankment, where as permeable jetties occur at the upstream end of a guide dike.
cover a wider area roughly limited by the
envelope of the outer ends.
870-42 HIGHWAY DESIGN MANUAL
May 1, 2001
Figure 873.4D
Typical Stone Dike Groin Details
Width of groin at top should be at least Drop structures or check dams are an
1.5 times the diameter of cap stones, or effective means of gradient control. They
wider if necessary for operation of may be constructed of rock, gabions,
equipment. Side slopes should be concrete, timber, sacked concrete, filled
1:1.5 for optimum economy and fences, sheet piling or combinations of any
ordinary stability. If this slope of the above. They are most suited to
demands heavier stone than is locations where bed materials are
available, side slope can be flattened or relatively impervious otherwise underflow
the cap and face stones bound together must be prevented by cutoffs. Refer to
with grout as shown in Figure 873.3E. "Highways in the River Environment",
Section 5.4.8, for further discussion on the
(e) Baffle. A baffle is a pier, vane, sill, fence,
use of drop structures.
wall or mound built on the bed of a stream
to control, deflect, check or disturb the Floating booms are effective protection
flow or to float on the surface to dampen against the smaller wave actions common
wave action. to lakes and tidal basins. Anchorage is the
prime structural consideration.
Baffles typically take the following forms
of construction:
873.5 Design Check List
• Single or multiple lines of fence.
The designer should anticipate the more significant
• Drop Structures (gabions, rock, problems that are likely to occur during the
concrete, etc.). construction and maintenance of channel and shore
protection facilities. So far as possible, the design
• Dikes of earth or rock.
should be adjusted to eliminate or minimize those
• Floating boom. potential problems.
These devices may vary in magnitude from The logistics of the construction activity such as
a check dam on a small stream to a system access to the site, on-site storage of construction
of training dikes or permeable jetties for materials, time of year restrictions, environmental
deflecting or directing flow. When using concerns, and sequence of construction should be
fences, palisades, or dikes as deflectors carefully considered during the project design.
along the more mature valleys or The stream and shoreline morphology and their
meandering streams, the potential erosion response to construction activities are an integral
to previously unexposed areas, threat to part of the planning process. Communication
adjacent property, eddy currents and between the designer and those responsible for
possibility of scour should all be assessed. construction administration as well as maintenance
When used as a collecting system to are important.
control and direct the flow to new or Channel and shore protection facilities require
existing drainage facilities or to bridge periodic maintenance inspection and repair. Where
openings, the alignment of the installation practicable, provisions should be made in the
should be developed as a series of facility design to provide access for inspection and
curves and intervening tangents guiding maintenance.
the stream through transitions to maintain
smooth and steady flow. The surface and The following check list has been prepared for
curvature of the training device should be both the designer and reviewer. It will help assure
governed by the natural or modified that all necessary information is included in the
velocity. plans and specifications. It is a comprehensive list
for all types of protection. Items pertinent to any
particular type can be selected readily and the rest
ignored.
HIGHWAY DESIGN MANUAL 870-47
May 1, 2001
1. Location of the planned work with respect to: driving requirements, cut-off elevations, and
framing details.
• The highway.
18. On fence-type construction the number of lines
• The stream or shore. or rows of fence, spacing of lines, dimensions
• Right of way. of posts, details of bracing and anchorage ties,
details of ties at end.
2. Datum control of the work, and relation of that
datum to gage datum on streams, and both 19. The details of gabions and the filling material.
MSL and MLLW on the shore. 20. The size of articulated blocks, the placement of
3. A typical cross section indicating dimensions, steel, and construction details relating to
slopes, arrangement and connections. fabrication.
4. Quantity of materials (per meter, per protection 21. The corrosion considerations that may dictate
unit, or per job). specialty concretes, coated reinforcing, or
other special requirements.
5. Relation of the foundation treatment with
respect to the existing ground.
Topic 874 - Definitions
6. Relation of the top of the proposed protection
to design high water (historic, with date; or The following glossary of terms are significant
predicted, with frequency). because of the divergent use of many words and
7. The limits of excavation and backfill as they expressions pertinent to the field of highway
may affect measurement and payment. drainage, erosion control, and channel and shore
protection. The definitions given are not
8. Construction details such as weep holes, rock necessarily those established by case law but have
slope protection fabrics, geocomposite drains been adopted because of their rational or prevalent
and associated materials. usage and for consistency within the Department.
9. Location and details of construction joints, cut- Derived forms are not separately defined when the
off stubs and end returns. meaning should be clear from the basic form, such
10. Restrictions to the placement of reinforcement. as alluvial and alluviation should be implicit after
alluvium is defined.
11. Connections and bracing for framing of timber
or steel. Accretion. Outward growth of bank or shore
sedimentation. Increase or extension of
12. Splicing details for timber, pipe, rails and boundaries of land by action of natural forces.
structural shapes.
Aggradation. General and progressive raising of a
13. Anchorage details, particularly size, type, stream bed by deposition of sediment.
location, and method of connection. Modification of the earth's surface in the
14. Size, shape, and special requirements of units direction of uniformity of grade, or slope, by
such as precast concrete shapes and other deposition as in a river bed.
manufactured items. Alluvium. Stream-borne materials deposited in and
15. Number and arrangement of cables and details along a channel.
of fastening devices. Apron. A lining of the bed of the channel upstream
16. Size, mass per unit area, mesh spacing and or downstream from a lined or restricted
fastening details for wire-fabric or geosynthetic waterway. A floor or lining of concrete, rock,
materials. etc., to protect a surface from erosion such as
the pavement below chutes, spillways, at the
17. On timber pile construction the number of piles toes of dams, or along the toe of bank
per bent, number of bents, length of piling, protection.
870-48 HIGHWAY DESIGN MANUAL
May 1, 2001
Armor. Artificial surfacing of bed, banks, shore or Basin. (1) The surface of the area tributary to a
embankment to resist erosion or scour. stream or lake. (2) Space above or below
ground capable of retaining or detaining water
Arroyo. Waterway of an ephemeral stream deeply
or debris.
carved in rock or ancient alluvium.
Bay. An indentation of bank or shore, including
Articulated. Made flexible by hinging particularly
erosional cuts and slipouts, not necessarily
of small rigid slabs adapted to revetment.
large.
Avulsion. (1) A forcible separation; also, a part
Beach. The zone of sedimentary material that
torn off. (2) The sudden removal of land from
extends landward from the low water line to
the estate of one person to that of another, as
the place where there is marked change in
by a sudden change in a river, the property thus
material or form, or to the line of permanent
separated continuing in the original owner. A
vegetation (usually the effective limit of storm
sudden shift in location of channel.
waves). The seaward limit of a beach, unless
Backing Layer. A layer of graded rock between otherwise specified, is the mean low water line.
rock riprap and underlying engineering fabric A beach includes foreshore and backshore.
or filter layer to prevent extrusion of the soil or
Bed. The earth below any body of water, limited
filter layer material through the riprap.
laterally by bank or shore.
Backshore. The zone of the shore or beach lying
Bed Load. Sediment that moves by rolling, sliding,
between the foreshore and the coastline and
or skipping along the bed and is essentially in
acted upon by waves only during severe
contact with the stream bed.
storms, especially when combined with
exceptionally high water. Berm. (1) A bench or terrace between two slopes.
(2) A nearly horizontal part of the beach or
Backwater. An unnaturally high stage in stream
backshore formed at the high water line by
caused by obstruction or confinement of flow,
waves depositing material. Some beaches have
as by a dam, a bridge, or a levee. Its measure
no berms, other have one or several.
is the excess of unnatural over natural stage,
not the difference in stage upstream and Block. Precast prismatic unit for riprap structure.
downstream from its cause.
Bluff. A high, steep bank composed of erodible
Baffle. A pier, vane, sill, fence, wall or mound materials.
built on the bed of a stream to parry, deflect,
Boil. Turbulent break in a water surface by
check or disturb the flow or to float on the
upwelling.
surface to deflect or dampen cross currents or
waves. Boom. Floating log or similar element designed to
dampen surface waves or control the
Bank. The lateral boundary of a stream confining
movement of drift.
water flow. The bank on the left side of a
channel looking downstream is called the left Bore. A transient solitary wave in a narrow or
bank, etc. converging channel advancing with a steep
turbulent front; product of flash floods or
Bank Protection. Revetment, or other armor
incoming tides.
protecting a bank of a stream from erosion,
includes devices used to deflect the forces of Boulder. Largest rock transported by a stream or
erosion away from the bank. rolled in the surf; arbitrarily heavier than 12
kg and larger than 200 mm.
Bar. An elongated deposit of alluvium within a
channel or across its mouth. Breaker. A wave meeting a shore, reef, sandbar, or
rock and collapsing.
Barrier. A low dam or rack built to control flow of
debris.
HIGHWAY DESIGN MANUAL 870-49
May 1, 2001
Breakwater. A fixed or floating structure that Cobble. Rock smaller than a boulder and larger
protects a shore area, harbor, anchorage, or than gravel; arbitrarily 0.5 to 12 kg, or 75 to
basin by intercepting waves. 200 mm in diameter.
Bulkhead. A steep or vertical structure placed on a Cone. Physiographic form of sediment deposit
bank, bluff, or embankment to retain or prevent washed from a gorge channel onto an open
sliding of the land and protect the inland area plain; a debris cone, also called an alluvial fan.
against damage.
Confluence. A junction of streams.
Bulking. The increase in volume of flow due to air
Constriction. An obstruction narrowing a
entrainment, debris, bedload, or sediment in
waterway.
suspension.
Control. (1) A section or reach of an open conduit
Buoyancy. Uplift force on a submerged body equal
or stream channel which maintains a stable
to the mass of water displaced times the
relationship between stage and discharge. (2)
acceleration of gravity.
For flood, erosion, debris, etc., remedial means
Canal. An artificial open channel. or procedure restricting damage to a tolerable
level.
Canyon. A large deep valley; also the submarine
counterpart. Conveyance. A measure of the water carrying
capacity of a stream or channel.
Cap. Top layer of stone protective works.
Core. Central zone of dike, levee, rock groin, jetty,
Capillarity. The attraction between water and soil
etc.
particles which cause water to move in any
direction through the soil mass regardless of Corrasion. Erosion or scour by abrasion in
gravitational forces. flowing water.
Causeway. A raised embankment or trestle over Corrosion. Erosion by chemical action.
swamp or overflow areas.
Creek. A small stream, usually active.
Cavitation. Erosion by suction, especially in the
Crest. (1) Peak of a wave or a flood. (2) Top of a
partial vacuum of a diverging jet.
levee, dam, weir, spillway or other water
Celerity. Velocity of a moving wave, as barrier or control.
distinguished from velocity of particles
Crib. An open-frame structure loaded with earth
oscillating in the wave.
or stone ballast to act as a baffle in bank
Channel. The space above the bed and between protection.
banks occupied by a stream.
Critical Depth. (Depth at which specific energy is
Check. A sill or weir in a channel to control stage a minimum.) Depth of water in a conduit at
or velocity. which, under certain other conditions, the
maximum flow will occur. These other
Cliff. A high, steep face of rock; a precipice.
conditions are; the conduit is on the critical
Cloudburst. Rain storm of great intensity usually slope with the water flowing in an open
over a small area for a short duration. channel or a conduit partially filled, for which
Coast. (1) The strip of land, of indefinite width the velocity head equals one-half the hydraulic
(up to several kilometers), that extends from mean depth.
the shoreline inland to the first major change in Critical Flow. That flow in open channels at
terrain features. (2) As a combining form, which the energy content of the fluid is at a
upcoast is northerly and downcoast is minimum. Also, that flow which has a Froude
southerly. number of one.
870-50 HIGHWAY DESIGN MANUAL
May 1, 2001
Critical Slope. That slope at which the maximum Detritus Loose material such as; rock, sand, silt,
flow will occur at the minimum velocity. The and organic particles.
slope or grade that is exactly equal to the loss
Dike. (1) Usually an earthen bank alongside and
of head per meter resulting from flow at a
parallel with a river or open channel to restrict
depth that will give uniform flow at critical
overflow (See Levee). (2) An AC dike along
depth; the slope of a conduit which will
the edge of a shoulder.
produce critical flow.
Ditch. Small artificial channel, usually unlined.
Critical Velocity. Mean velocity of flow when
flow is at critical depth. Discharge. A volume of water flowing out of a
drainage structure or facility. Measured in
Current. Flow of water, both as a phenomenon and
cubic meters per second.
as a vector. Usually qualified by adjectives
like downward, littoral, tidal, etc. to show Dissipate. Expend or scatter harmlessly, as of
relation to a pattern of movement. energy of moving water.
Debris. Any material including floating woody Diversion. (1) The change in character, location,
materials and other trash, suspended sediment, direction, or quantity of flow of a natural
or bed load moved by a flowing stream. drainage course (a deflection of flood water is
not a diversion). (2) Draft of water from one
Degradation. General and progressive lowering of
channel to another. (3) Interception of runoff
the longitudinal profile of a channel by
by works which discharge it thru unnatural
erosion.
channels.
Delta. System of channels thru an alluvial plain at
Downdrift. The direction of predominant
the mouth of a stream.
movement of littoral materials.
Deposit. An earth mass of particles settled or
Drain. Conduit intercepting and discharging
stranded from moving water or wind.
surplus ground or surface water.
Depth. Vertical distance, (1) from surface to bed
Drainage. (1) The process of removing surplus
of a body of water. (2) From crest or crown to
ground or surface water by artificial means.
invert of a conduit.
(2) The system by which the waters of an area
Design Discharge. The quantity of flow that is are removed. (3) The area from which waters
expected at a certain point as a result of a are drained; a drainage basin.
design storm. Usually expressed as a rate of
Drawdown. The difference in elevation between
flow in cubic meters per second.
the water surface elevation at a constriction in
Design Flood. The peak discharge (when a stream or conduit and the elevation that
appropriate, the volume, stage, or wave crest would exist if the constriction were absent.
elevation) of the flood associated with the Drawdown also occurs at changes from mild to
probability of exceedance selected for the steep channel slopes and weirs or vertical
design of a highway encroachment in a FEMA spillways.
flood plain. By federal definition, the highway
Drift. (1) Floating or non-mineral burden of a
will not be inundated by the "design flood".
stream. (2) Deviation from a normal course in
See 23 CFR, Part 650, Subpart A, for
a cross current, as in littoral drift.
definitions of "overtopping flood" and "base
flood." Drop. Controlled fall in a stream to dissipate
energy.
Design High Water. The flood stage or tide crest
elevation adopted for design of drainage and Dune. A sand wave of approximately triangular
bank protection structures. (See Design Flood cross section (in a vertical plane in the
and High Water). direction of flow) formed by moving water or
wind, with gentle upstream slope and steep
HIGHWAY DESIGN MANUAL 870-51
May 1, 2001
downstream slope and deposition on the Filter Layer. A layer of even-graded rock between
downstream slope. rock riprap and underlying soil to prevent
extrusion of the soil thru the riprap.
Ebb. Falling stage or outward flow, especially of
tides. Flood Stage. The elevation at which overflow of
the natural banks of a stream begins to run
Eddy. Rotational flow around a vertical axis.
uncontrolled in the reach in which the
Embankment. Earth structure above natural elevation is measured.
ground.
Flood Waters. Former stream waters which have
Embayment. Indentation of bank or shore, escaped from a watercourse (and its overflow
particularly by progressive erosion. channel) and flow or stand over adjoining
Energy. Potential or kinetic, the latter being lands. They remain as such until they
expressed in the same unit (meters) as the disappear from the surface by infiltration,
former. evaporation, or return to a natural watercourse.
They do not become surface waters by
Entrance. The upstream approach transition to a mingling with such waters, nor stream waters
constricted waterway. by eroding a temporary channel.
Ephemeral. Of brief duration, as the flow of a Flow. A term used to define the movement of
stream in an arid region. water, silt, sand, etc.; discharge; total quantity
Erosion. The wearing away of natural (earth) and carried by a stream.
unnatural (embankment, slope protection, Flow, steady. Flow at constant discharge.
structure, etc.) surfaces by the action of natural
forces, particularly moving water and materials Flow, unsteady. Flow on rising or falling stages.
carried by it. Flow, varied. Flow in a channel with variable
Estuary. That portion of a river channel occupied section.
at times or in part by both sea and river flow in Foreshore. The part of the shore lying between the
appreciable quantities. The water usually has ordinary high water mark or upper limit of
brackish characteristics. wave wash traversed by the runup and return of
Face. The outer layer of slope revetment. waves and the water's edge at the low water.
Fan. A cone, but sometimes used to emphasize Freeboard. (1) The vertical distance between the
definition of radial channels. Also reference to level of the water surface usually
spreading out of water or soils associated with corresponding to the design flow and a point of
waters leaving a confined channel. interest such as a bridge beam, levee top or
specific location on the roadway grade. (2)
Fetch. The unobstructed distance over water in The distance between the normal operating
which waves are generated by wind of level and the top of the sides of an open
relatively constant direction and speed. conduit; the crest of a dam, etc., designed to
Filter. A porous article or mass (as of fabric or allow for wave action, floating debris, or any
even-graded mineral aggregate) through which other condition or emergency, without
water will freely pass but which will block the overtopping the structure.
passage of soil particles. Friction. Energy-dissipating conflict among
Filter Fabric (RSP fabric). An engineering fabric turbulent water particles disturbed by
(geotextile) placed between the backfill and irregularities of channel surface.
supporting or underlying soil through which Gabion. A wire basket or cage filled with stone
water will pass and soil particles are retained. and placed as, or as part of, a bank-protection
structure.
870-52 HIGHWAY DESIGN MANUAL
May 1, 2001
Gorge. A narrow deep valley with steep or vertical Hydrostatic. Pertaining to pressure by and within
banks. water due to gravitation acting thru depth.
Grade. Elevation of bed or invert of a channel. Impinge. To strike and attack directly, as in
curvilinear flow where the current does not
Gradient. The rate of ascent or descent expressed
follow the curve but continues on tangent into
as a percent or as a decimal as determined by
the bank on the outside of bend in the channel.
the ratio of the change in elevation to the
length. Isohyet. Line on a map connecting points of equal
precipitation.
Gravel. Rock larger than sand and smaller than
cobble, arbitrarily ranging in diameter from 5 Isovel. Line on a diagram of a channel or channel
to 50 mm. section connecting points of equal velocity.
Groin. A fingerlike barrier structure usually built Jack (or Jack Straw). Bank protection element
perpendicular to the shoreline or oblique to consisting of wire or cable strung on three
primary motion of water, to trap littoral drift, mutually perpendicular struts connected at
retard erosion of the shore, or to control their centers.
movement of bed material.
Jam. Wedged collection of drift in a constriction
Grouted. Bonded together with an inlay or overlay of a channel, such as a gorge or a bridge
of cement mortar. opening.
Guide Bank. An appendage to the highway Jet. An effluent stream from a restricted channel,
embankment at or near a bridge abutment to including a fast current thru a slower stream.
guide the stream through the bridge opening.
Jetty. An elongated, artificial obstruction
Gulch. A relatively young, well-defined and projecting into a stream or the sea from bank or
sharply cut erosional channel. shore to control shoaling and scour by
deflection of strength of currents and waves.
Gully. Diminutive of gulch.
Jump. Sudden transition from supercritical flow to
Head. Represents an available force equivalent to
the complementary subcritical flow,
a certain depth of water. This is the motivating
conserving momentum and dissipating energy;
force in effecting the movement of water. The
the hydraulic jump.
height of water above any point or plane of
reference. Used also in various compound Kolk. Rotational flow about a horizontal axis,
expressions, such as energy head, entrance induced by a reef and breaking the surface in a
head, friction head, static head, pressure head, boil.
lost head, etc.
Lake. A water filled basin with restricted or no
High Water. Maximum flood stage of stream or outlet. Includes reservoirs, tidal ponds and
lake; periodic crest stage of tide. Historic HW playas.
is stage recorded or otherwise known.
Levee. An embankment on or along the bank of a
Hydraulic. Pertaining to water in motion and the stream or lake to protect outer lowlands from
mechanics of the motion. inundation. (See Dike)
Hydrographic. Pertaining to the measurement or Lining. Protective cover of the perimeter of a
study of bodies of water and associated terrain. channel.
Hydrologic. Pertaining to the cyclic phenomena of Littoral. Pertaining to or along the shore,
waters of the earth; successively as particularly to describe currents, deposits, and
precipitation, runoff, storage and evaporation, drift.
and quantitatively as to distribution and
concentration.
HIGHWAY DESIGN MANUAL 870-53
May 1, 2001
Littoral Drift. The sedimentary material (sand) Peak Flow. Maximum momentary stage or
moved along the shoreline under the influence discharge of a stream in flood.
of waves and currents.
Pebble. Stone 10 to 75 mm in diameter, including
Littoral Transport. The movement of littoral drift coarse gravel and small cobble.
along the shoreline by waves and currents.
Permeable. Open to the passage of fluids, as for
Includes movement parallel (longshore
(1) pervious soils and (2) bank-protection
transport) and perpendicular (on-offshore
structures.
transport) to the shore.
Pier. Vertical support of a structure standing in a
Longshore. Parallel to and near the shoreline.
stream or other body of water. Used in a
Marginal. Within a borderland area; more general general sense to include bents and abutments.
and extensive than riparian.
Pile. A long, heavy timber or section of concrete
Marsh. An area of soft, wet, or periodically or metal that is driven or jetted into the earth or
submerged land, generally treeless and usually bottom of a water body to serve as a structural
characterized by grasses and other low support or protection.
vegetation.
Plunge. Flow with a strong downward component,
Mature. Classification for streams which have as in outfall drops, overbank falls, and surf
established flat gradients not subject to further attack on a beach.
scour.
Precipitation. Discharge of atmospheric moisture
Mean Depth. For a stream at any stage, the wetted as rain, snow or hail, measured in depth of fall
normal section divided by the surface width. or in terms of intensity of fall in unit time.
Hydraulic mean depth.
Probability. The chance of occurrence or
Meander. In connection with streams, a winding recurrence of a specified event within a unit of
channel usually in an erodible, alluvial valley. time, commonly expressed in 3 ways. Thus a
A reverse or S-shaped curve or series of curves 10-year flood has a chance of 0.1 per year and
formed by erosion of the concave bank, is also called a 10%-chance flood.
especially at the downstream end, shoals and
Rack. An open upright structure, such as a debris
bank erosions. Meandering is a stage in the
rack.
migratory movement of the channel, as a whole
down the valley. Rainwash. The creep of soil lubricated by rain.
Mesh. Woven wire or other filaments used alone Range. Difference between extremes, as for
as revetment, or as retainer or container of stream or tide stage.
masses of gravel or cobble. Rapids. Swift turbulent flow in a rough steep
Nourishment. The process of replenishing a beach. reach.
It may be brought about naturally, by accretion Ravine. A valley larger than a gulch, smaller than
due to the longshore transport, or artificially, a canyon, and less bold in relief than a gulch or
by the deposition of dredged materials. arroyo.
Outfall. Discharge or point of discharge of a Reach. The length of a channel uniform with
culvert or other closed conduit. respect to discharge, depth, area, and slope.
Outwash. Debris transported from a restricted More generally, any length of a river or
channel to an unrestricted area where it is drainage course.
deposited to form an alluvial or debris cone or Recession. Retreat of shore or bank by progressive
fan. erosion.
Overflow. Discharge of a stream outside its banks;
the parallel channels carrying such discharge.
870-54 HIGHWAY DESIGN MANUAL
May 1, 2001
Reef. Generally, any solid projection from the bed Sand. Granular soil coarser than silt and finer than
of a stream or other body of water. gravel, ranging in diameter from 0.05 to 5
mm.
Regime. The system or order characteristic of a
stream; its behavior with respect to velocity Scour. The result of erosive action of running
and volume, form of and changes in channel, water, primarily in streams, excavating and
capacity to transport sediment, amount of carrying away material from the bed and
material supplied for transportation, etc. banks. Wearing away by abrasive action.
Repose. The stable slope of a bank or Sea. Ocean or other body of water larger than a
embankment, expressed as an angle or the ratio lake; state of agitation of any large body of
of horizontal to vertical projection. water.
Restriction. Artificial or natural control against Seawall. A structure separating land and water
widening of a channel, with or without areas, primarily designed to prevent erosion
construction. and other damage due to wave action. (See
bulkhead).
Retard. Bank-protection structure designed to
check the riparian velocity and induce silting Sedimentation. Gravitational deposit of
or accretion. transported material in flowing or standing
water.
Retrogression. Reversal of stream grading, i.e.,
aggradation after degradation or vice versa. Seepage. Percolation of underground water thru
the banks and into a stream or other body of
Revetment. Bank protection to prevent erosion.
water.
Riparian. Pertaining to the banks of a stream.
Seiche. A standing wave oscillation of an enclosed
Riprap. A layer, facing, or protective mound of waterbody that continues, pendulum fashion,
rubble or stones randomly placed to prevent after the cessation of the originating force,
erosion, scour, or sloughing of a structure or which may have been either seismic or
embankment; also, the stone used for this atmospheric.
purpose.
Sheet Pile. A pile with a generally slender, flat
River. A large stream, usually active when any cross-section that is driven into ground or
streams are flowing in the region. bottom of a water body and meshed or
Rock. (1) Cobble, boulder or quarry stone as a interlocked with like members to form a wall
construction material. (2) Hard natural or bulkhead.
mineral, in formation as in piles of talus. Shoal. A shallow region in flowing or standing
RSP Fabric. (See Filter Fabric). water, especially if made shallow by
deposition.
Rubble. Rough, irregular fragments of rock or
concrete. Shore. The narrow strip of land in immediate
contact with the water, including the zone
Runoff. The surface waters that exceed the soil's between high and low water lines. See
infiltration rate and depression storage. backshore, foreshore, onshore, offshore,
Runup. The rush of water up a beach or structure, longshore, and nearshore.
associated with the breaking of a wave. The Silt. (1) Water-Borne Sediment. Detritus carried
amount of runup is measured according to the in suspension or deposited by flowing water,
vertical height above still water level that the ranging in diameter from 0.005 to 0.05 mm.
rush of water reaches. The term is generally confined to fine earth,
sand, or mud, but is sometimes both suspended
and bedload. (2) Deposits of Water-Borne
HIGHWAY DESIGN MANUAL 870-55
May 1, 2001
Tetrahedron. Bank protection element, basically Uplift. Upward hydrostatic pressure on base of an
composed of 6 steel or concrete struts joined impervious structure.
like the edges of a triangular pyramid, together
Velocity. The rate of motion of objects or
with subdividing struts and tie wires or cables.
particles, or of a stream of particles.
Tetrapod. Bank protection element, precast of
Vernal Pools. Vernal pools are seasonally flooded
concrete, consisting of 4 legs joined at a
landscape depressions that support distinctive
central block, each leg making an angle of
(and many times rare) plant and animal species
109.5 degrees with the other three, like rays
adapted to periodic or continuous inundation
from the center of a tetrahedron to the center of
during the wet season, and the absence of
each face.
either ponded water or wet soil during the dry
Texture. Arrangement and interconnection of season.
surface and near-surface particles of terrain or
Wash. Flood plain or active channel of an
channel perimeter.
ephemeral stream, usually in recent alluvium.
Thalweg. The line following the lowest part of a
Watercourse. A definite channel with bed and
valley, whether under water or not. Usually
banks within which water flows, either
the line following the deepest part of the bed or
continuously or in season. A watercourse is
channel of a river.
continuous in the direction of flow and may
Thread. The central element of a current, extend laterally beyond the definite banks to
continuous along a stream. include overflow channels contiguous to the
ordinary channel. The term does not include
Tide. The periodic rising and falling of the ocean
artifical channels such as canals and drains,
and connecting bodies of water that results
except natural channels trained or restrained by
from gravitational attraction of the moon and
the works of man. Neither does it include
sun acting on the rotating earth.
depressions or swales through which surface or
Topping. The top layer on horizontal revetments errant waters pass.
or rock structures; also capping or cap stones.
Watershed. The area that contributes surface water
Training. Control of direction of currents. runoff into a tributary system or water course.
Transition. A relatively short reach or conduit Waterway. (1) That portion of a watercourse
leading from one waterway section to another which is actually occupied by water. (2) A
of different width, shape, or slope. navigable in land body of water.
Transport. To carry solid material in a stream in Wave. (1) An oscillatory movement of water on or
solution, suspension, saltation, or entrainment. near the surface of standing water in which a
Trough. Space between wave crests and the water succession of crests and troughs advance while
surface below it. particles of water follow cyclic paths without
advancing. (2) Motion of water in a flowing
Turbulence. A state of flow wherein the water is stream so as to develop the surficial
agitated by cross-currents and eddies; opposed appearance of a wave.
to a condition of flow that is quiet and laminar.
Wave Height. The vertical distance between a
Undercut. Erosion of the low part of a steep bank wave crest and the preceding trough.
so as to compromise stability of the upper part.
Wave Length. The horizontal distance between
Undertow. Current outward from a wave-swept similar points on two successive waves (for
shore carrying solid particles swept or scoured example, crest to crest or trough to trough),
from the beach or foreshore. measured in the direction of wave travel.
Updrift. The direction opposite that of the
predominant movement of littoral materials.
HIGHWAY DESIGN MANUAL 870-57
May 1, 2001