Académique Documents
Professionnel Documents
Culture Documents
I. PART – B
HYDRO–MECHANICAL WORKS
SECTION - HM 01
3.0. GENERAL
Expansion Joint will be provided for all Volute pumps in the discharge
piping as shown in the G.A. drawings enclosed with this tender.
3.3.2. The design shall be suitable for the pressures and type of
fluid i.e. raw river water.
3.3.3. The tube (i.e. inner cover) and the cover (outer) shall be
made of natural or synthetic metallic of adequate hardness.
The shore hardness shall be less than 50 deg. A for outer
and 50 deg. A for inner cover.
3.3.4. The carcass between the tube and the cover shall be made
of high quality cotton duck, preferably, square woven to
provide equal strength in both directions of the wave. The
fabric plies shall be impregnated with age resistant metallic
3.3.7 Reinforcement
The expansion joints shall be adequately reinforced, with
solid steel rings, to meet the service conditions under which they
are to operate.
uniform and free from any blisters porosity and other surface
defects.
3.3.11Control Units
Each control unit shall consist of two (2) numbers of
triangular stretcher bolt plates, a stretches bolt washers, nuts and
lock nuts. Each plate shall be drilled with three holes, two for fixing
the plate on to the companion steel flange and the third for fixing
the stretcher bolt.
I.4.2 All bear bellows shall be subjected to deflection test under pressure,
pressure being raised from zero to design pressure in regular steps
and deflection measured at each step.
a) Metalic compound test slab after vulcanizing shall be tested for tensile
strength, elongation and hardness.
b) Fabric strength of synthetic fibre for reinforcement shall be checked and test
for metalic to fabric, metalic to metal adhesion shall be carried out. Test on
metalic shall include hydraulic stability check as per ASTM D- 471.
3.4.4.2 Immediately after the vacuum test, a hydraulic test, as per the
relevant, standards shall be conducted on the expansion joints. The
rate of pressure duration the test shall not be less than 1 bar/ second.
The hydraulic tests shall be conducted on the expansion joint in three
different positions for duration of 30 minutes (minimum) in each
position.
3.4.4.3 Either during the hydraulic test or during the vacuum test, the
expansion contraction or deformation shall not be move 1.5%.
However, a cumulative error is not allowed. The purpose of conducting
hydraulic test or vacuum test is to ensure the stability to withstand
deflection in axial and transverse direction.
Twenty four (24) hours. After the above test, the permanent set (variation in
dimensions with respect to its original dimensions) shall be measured and
recorded. The permanent set shall not be more than 0.5%.
EM 04 MOTOR
operating range. The motor rotor shall be dual cage, copper bar brazed
type for long corrosion free service type.
4.0. SCOPE:
The scope of this section covers design, manufacture, testing at
manufacturer’s works before dispatch, supply, erection at site, testing and
commissioning of Motors. The scope of supply shall also include all parts,
accessories, and spares etc., which are necessary for erection, operation and
maintenance of Motors. The Motor shall match in respect of speed, runaway
speed, moment of Inertia, overload capacities and any other requirement with
that of the Pump.
4.1. TYPE AND RATING:
Each Motor shall be of vertical shaft, alternating current synchronous type,
conforming to the latest edition of IS 4722 or IEC 34 or any other equivalent
international standards unless other wise specified here in and shall be directly
coupled to the shaft of VT Pump.
The rating of each Motor shall be as follows:
1. Type: Vertical mounting, alternating current synchronous Machine
. 2. Rated continuous output : 120% of rating of the pump, 0.95
pf lead.
3. Power factor : 0.95 lead.
4. Speed : Matching with the rotational
Speed of the VT Pump.
5. Frequency : 50 Hz.
6. No. of phases : Three (3)
7. Rated terminal voltage between phases 11 KV
8. Range of voltage variation
over which maximum output
must be obtained. : +/- 10%
9. Range of Frequency variation : 48.5 Hz to 51.5 Hz.
10. Direction of rotation : As per pump
11. Short circuit ratio : Shall be greater than 0.75.
12. Inertia constant. : Shall not be less than 1.25
The Motor shall be suitable for operation in all respects and shall deliver
the rated output over the range of voltage variation and of frequency variation as
specified above.
Each Motor shall be star connected and the main and neutral leads shall
be brought out of the stator frame for insertion of current transformers for
protection and metering and surge protection apparatus.
4.2. GENERAL :
The Motor shall be designed and constructed so as to facilitate easy
repair/replacement of generator stator bars and rotor poles. Starting of the
The Motor shall be guaranteed to be capable of giving its rated output and
maximum output without exceeding the temperature rise.
4.5.4. PENALTY FOR SHORT-FALL IN EFFICIENCY AND
OUTPUT:
While testing Motor, for any short-fall in the tested values of rated output,
maximum output and weighted average efficiency from the guaranteed values,
penalty shall be applied
No tolerance shall be permitted over the test figures of output. Tolerance in
computation of losses for determining efficiency shall be allowed in accordance
with IEC codes.
4.6. GENERATOR TERMINAL CUBICLES (LINE & NEUTRAL):
All the six terminals of Motor (three phase and three neutral) shall be
brought out of the generator with suitable cable sealing ends. Connections
between these terminals and the line terminal cubicles as well as neutral
terminal cubicles shall be made at site. The line and neutral terminal cubicles
shall be complete with all equipments/devices such as Surge arrestors,
capacitors, Current and voltage transformers for Protection and metering, and
shall include all necessary insulating supports, enclosures, supporting frames,
flexible connections, insulating boards, rigid conductors etc., The bus- bar
connections shall be adequately supported on insulators and designed to take
care of terminal thermal expansion, short circuit stresses etc. and also the line
and neutral terminals will be connected to the required Switchgear through XLPE
cables. All joints shall be of bolted type. The entire assembly shall be suitably
guarded by strong metallic screen and the housing shall be provided with
arrangement for proper ventilation and shall be vermin proof.
All current transformers, voltage transformers, isolating switches and lightning
arrestors provided shall comply with the latest issues of relevant Indian or
equivalent International Standards. Neutral point of Motor will be made star
connected through soft starters being envisaged.
plate. The water supply to each of the air coolers shall be controlled by
separate valves so that any one of the coolers can be isolated, if
necessary.
All water piping including ring header, connecting pipe from the
cooling header, control valves near each cooler etc., shall be supplied.
The extent of supply of cooling water pipes shall be in complete as
required.
Resistance temperature detectors shall be provided in air coolers for
indication and recording of inlet and outlet air temperatures.
Dial type thermometers shall be provided in air coolers for indication of
inlet and outlet air temperature, and to provide alarm and trip initiations in
case of high temperature of inlet/outlet air.
water flow indicators, relays shall be provided with flow indicator and
suitable contacts to provide normal flow indicators and alarm in case of
failure of cooling water flow in bearings as well as stator coolers.
4.8. CO2 FIRE EXTINGUISHING SYSTEM:
The fire extinguishing equipment shall be of the carbon dioxide
(CO2) type, protection system with automatic operation shall be installed
for the protection of Motor. Protection being effected by filling the motor
air circuit with CO2 at the concentration sufficient to dilute the air content
to a point where combustion cannot continue.
Necessary high-pressure pipe-work, distribution nozzles and
electrical release trips etc. shall be provided. The battery of CO2
cylinders should be of sufficient capacity to provide the rapid total flooding
of the Motor air circuit at a high concentration.
A pressure-operated switch should be fitted in the pipe work to each
machine to initiate the alarm on the release of CO2 gas. In the event of a
fire occurring inside the Motor discharge of CO2 gas should be manually
initiated on observation of Fire/ smoke detection alarm. The system
should be arranged such that the testing of electrical circuit could be
carried out without the release of CO2 gas. In addition, a beam scale-
weighing unit shall be provided to enable the cylinders to be weighed in-
situ to ascertain whether any gas has been lost.
The smoke detectors shall be so designed that the operation of any
detector shall actuate an alarm- giving device to give indication and alarm
in the control room.
The equipment shall be simple in design, easily operated, inspected
and maintained. The equipment shall comply in all respects with the
appropriate regulations of Insurance Association of India or similar
approved organisation.
4.9. CONSTRUCTION:
Each Motor shall be designed with one main thrust and guide
bearing located above the rotor and one guide bearing below the rotor.
The Motor shall be vertical shaft synchronous type, with the stator, rotor,
and all other accessories to be incorporated. Static brushless excitation
system together with automatic voltage regulator/constant current
regulator shall also be included in the scope of supply of the Motor. .
All parts of Motor shall be designed and constructed to safely
withstand maximum stresses during operation, run away speed, short
circuit conditions out of phase synchronizing, and brake application. The
housing of Motor shall be supported on VT Pump / concrete foundation.
All necessary sole plates, dowels, etc. required for the erection of the
Motor shall also be supplied. The Motor shall be suitable for lifting from
service bay after being completely assembled and wound. Suitable lugs
with stator frame for lifting purposes shall also be provided.
All internal wiring and conduits for control, relaying fire protection
internal illumination and other systems shall be brought out to terminal
boxes outside the body of stator.
4.9.1. BEARINGS:
Each Motor shall preferably be equipped with one thrust and guide
bearings located above the rotor and one guide bearing below the rotor as
per good design practices
The removing/replacing of the thrust-bearing pad shall be done without
disturbing/dismantling the Pump motor unit. Bearings shall be oil
lubricated and without any external circulation. An effective sealing cover
shall be provided to prevent leakage of oil vapor through close running
clearance between the bearing housing and the shaft.
The design of the bearing shall be such that temperature for alarm and
trip out for high bearing temperature shall not be higher than 70 Deg.C
and 75 Deg.C. respectively at rated operating conditions.
The bearing shall be capable of operating without any damage for a
period of a least 15 minutes after the failure of cooling water supply to
bearing oil coolers with generator loaded up to the rated capacity and
rated speed at the end of which it is expected that the unit shall be shut
down.
The guide bearing shell shall be made of steel plate lined with high quality
babbitt metal on its inner surface.
The bearings shall be adequately insulated where considered
necessary, to prevent any harmful circulating currents from passing
through the bearing surface.
4.9.2. OILS
Oil for the first filling plus 10% as spare required for the Motor bearings
lubrication system etc. shall be supplied by the Contractor. The oil to be used
for Motor bearing lubrication etc. shall be identical with that used for the pump
e) The breaker shall have two trip coils each operating on two independent
sources of supply. Trip circuit supervision relays shall be provided for each coil
independently.
Operating mechanism: The spring operated mechanism shall be compete
with motor, opening spring, closing spring and all other necessary mechanism to
complete the operating unit. Each mechanism shall be so designed as to enable
a continuous sequence of circuit breaker opening, closing and opening in the
event of failure of supply to motor. Spring charging by the motor shall be
automatic and charging time shall not exceed 15 seconds.
f) Charging of closing spring after each operation of the breaker shall occur
automatically. It shall also be possible to charge the spring manually by means of
an emergency handle. A local indication shall be provided to show the status of
the spring. Potential free contacts of spring charged ON/OFF indication shall be
wired to terminal blocks for remote indication.
The breaker mechanism shall be such that failure of any spring shall not
prevent any tripping.
g) The closing coils and other auxiliary devices shall operate satisfactorily at
all voltages between 85% -110% of the control voltage. The trip coil shall operate
satisfactorily at all voltage between 70-100% of the rated control voltage
i.e110/220V DC.
h) When the breaker is in closed or open position, same operation of an
initiating control devices shall not result in the further operation of the breaker
closing or opening mechanism or discharging of the closing spring.
i) Mechanically operated targets to show the open and closed positions of
the breaker shall be provided.
j) The draw out mechanism shall have four positions: service, test, isolate
and maintenance position.
a) Service : Both power and auxiliary contacts in Service.
b) Test : Power contacts isolated but the auxiliary
contacts are in service.
c) Isolated : Both power and auxiliary contacts are
isolated.
d) Maintenance : Both power and auxiliary contacts isolated and the
CB is partially withdrawn on to the special rails temporarily inserted inside the
cubicle, suitable for maintenance.
6.3.2 LV Fuses.
a)Type : HRC
b)Continuous full load current rating of fuses : 10 A
c)Symmetrical fault rating of fuses : 50 KA
6.3.4 Capacitors
a) Type : Single pole, Non - Inflammable oil
impregnated
b) Voltage Rating : 15 KV
c) Capacitance : 0.25 Micro Farad
All the materials shall be of the quality as per the Indian or International
Standards.
b) Voltage class : 14 KV
c) Transformation ratio : 2000 /1 A, 800/1A
d) Rated output : 60 V A
e) Class of Accuracy : PS, 5P20, 0.5
f) Minimum Knee point -- >400 Volts for class PS
Communication
7.1 PROVISIONS
7.1.1 GENERAL
The proposed layout of the control room shall be finalized during detailed
design and engineering as per requirement. Panels shall be of simplex type
fabricated front MS sheet of not less than 3 mm thickness for weight bearing
members and 2 mm thick for other portions conforming to IEEE or other
standard as applicable. All equipments on and inside panels shall be mounted
and completely wired to the terminal blocks ready for external connections. All
control wiring shall be carried out with 650 V grade, single core, stranded copper
conductor of size 1.5/2.5 mm2 FRLS cables
The computerized control and monitoring system shall be of high end PLC
/ distributed type built up on the following components:
- Workstation/plant computer for programming and central control and
supervision of the plant.
- Pump level control and common Auxiliaries control.
- Each controller shall have the redundant CPU, I/O cards ,out put and
other relays , Temperature recorders, Indicating instruments etc as required.
- Dual Communication network allowing the data interchange between the
unit controller and the central control system.
- Dual operator stations for man-machine interface
- Provision for Remote control of the station i.e pumps control from other
station / control center through standard communication networks and protocol
contacts wired further to UCB for necessary fault annunciation alarms and
tripping.
ix) Status indication of switchgear equipment i.e. isolators, breakers.
Provision for logging of temperature of Motors, bearing shall be made as
required. Logging of important levels shall also be done.
Necessary control and metering functions for AC auxiliaries shall be
provided.
The EPABX interface and the telephone etc. shall be as per the relevant
CCIIT recommendation of ITU. The exchange shall be compatible for
interconnection to other similar exchanges through fiber optics link as well as
overhead line alignment for trunk working.
The exchange shall incorporate a built in diagnostic unit, which shall
assist in identification and localization of various system faults. Visual and
audible alarm shall be provided in the system for fault conditions.
Suitable interconnection between powerhouse and dam site by means of
fiber optic cable shall be provided. Public address system shall be
interconnected to EPABX through suitable interface paging system.
415 Volts A.C. 3 Phase 4 wire LT Switchgear panels shall consists of the
following equipment.
Station auxiliary boards (SABs) : 5 Nos.
Each LT Board shall consist of the following
a) Potential Transformers
b) Under voltage relays
c) Current Transformers
d) Voltmeters with selector switch
e) Energy meters
f) Current Transformers
g) Air circuit breaker (ACB)
h) Ammeter with selector switch.(Ammeter for 3 phase current)
The feeders shall be provided with electrically operated draw out
type air circuit breaker of 3 phase, 415 volts, 2000 Amps capacity, 40 KA/1sec.
short circuit capacity and shall have shunt trip facility with built in static type
adjustable thermal over load and short circuit protection with suitable high
interrupting capacity etc. These Air circuit breakers can be able to be operated
from local /remote with necessary interlocks in full auto operation through station
auxiliary controller.
Each SAB shall able to feed the each pump house auxiliaries and
Each load shall be fed through MCCBs of suitable capacity All the pumps shall
have the similar type of equipment and system. The SAB shall have two
incoming feeders from Reserve boards
Reserve Boards shall able to feed all the powerhouse loads
(Common auxiliaries) and SAB’s
a) Complete power house lighting
b) EOT Cranes
c) Air compressors
c) Operating mechanism:
Each breaker shall be power operated by stored energy
charged spring mechanism for both closing and opening operations. The
mechanism complete with opening spring, closing spring and other accessories
shall operate breaker through local/remote control switches. Once charged, the
springs shall be capable of B-M-B operation of the breaker. Accidental failure of
any spring shall not trip or close a breaker. Charging shall be automatic by DC
motor complete with accessories and the motor shall keep the spring charged at
all times. The maximum charging time of fully exhausted springs shall not
exceed fifteen (15) seconds. Charging motor and closing coil shall operate
between 85% and 110% of 230V AC and trip coil between 70% and 110% of
230V AC. The making capacity of the breaker shall be certified for manual as
well as electrical closing.
d) Breaker shall close upon closing a contact in its closing circuit
momentarily. A sustained closing impulse shall have no effect on the closing
mechanism.
e) Manually operated lever or push buttons shall be provided to close
and trip the breaker mechanically without opening the door. Means shall be
provided for emergency manual operation of electrically operated breaker
without opening the door. Arrangement shall also be provided to slowly open
and close the breaker for maintenance.
f) Breaker shall be provided with No Volt trip and static type
adjustable thermal overload and short circuit protection.
g) Arrangement for obtaining auto trip annunciation of the breaker
shall be provided.
h) Mechanically operated targets should be provided to show the
open and closed positions of the breaker
i) The drawout mechanism shall have 4 positions - Service, test, isolated
and maintenance positions.
1) Service : Both power and aux. contacts are in service.
2) Test : Power contacts isolated but the aux contacts are
in service.
3) Isolated : Both power and aux contacts are isolated.
4) Maintenance: Both power and aux contacts are isolated and ACB is
partially withdrawn on to the special rails temporarily inserted inside the cubicle.
Suitable for maintenance. In the maintenance position, the breaker shall remain
in the cubicle providing access to all the parts enabling to attend simple
maintenance. When the ACBs are drawn out, provision shall be made to close
the shutters automatically to avoid accidental contact with the live parts.
8.6. INSTRUMENT TRANSFORMERS:
All Potential Transformers and current transformers shall comply with the
following requirements :
a) Nominal System voltage : 415 V
brought to the terminal blocks for purchaser's external use(for remote alarm and
control system).
8.11 BUSBARS:
a) The Board shall be provided with 1000A three Phase and Neutral
bus bars.
b) The bus bars shall be of high conductivity Aluminium confirming to
IS: 5082, liberally sized for the specified current ratings (both short circuit and
continuous current ratings). Maximum temperature rise of the bus-bar and bus
bar connections when carrying rated normal current shall not exceed 40 degrees
C above ambient temperature. The neutral bus shall run along side and full
length of the phase busbar and it shall be rated for half the normal current rating
of the main bus for the same short circuit current.
c) Calculations for arriving at the cross section of the bus bars taking
into consideration the temperature rise and fault level shall be furnished along
with the prequalification bid.
d) Busbar shall be of uniform section/rating throughout the length of
the panel and shall be capable of being easily extended at site on either side.
e) The horizontal and vertical busbars shall be insulated throughout
their length by heat shrunk, colored PVC sleeves to provide protection. The
sleeves shall be able to withstand the temperatures attained by busbars during
normal service and short circuit conditions. Painting of Busbars will not be
considered as Insulation .Main busbar joints shall be provided with removable
thermosetting plastic shrouds/heat shrinkable PVC tape.
f) Appropriate colour bands shall be used in each compartment to
identify the phase sequence of the horizontal and vertical busbars.
g) Busbars shall be adequately supported and braced to withstand
the stresses due to short circuit currents. All the busbar supports shall be made
of glass reinforced thermosetting plastic having anti tracking design.
h) Separate support shall be provided for each phase of the bus bars.
If a common support is provided for all the three phases, anti tracking barrier
shall be incorporated.
i) The busbars shall be housed in totally enclosed bus bar chambers
completely shrouded from the feeder units and cable chambers. The incoming
connections from the bus bars to various feeders shall be so designed as not to
disturb the cabling connection, to ensure safety of operating and maintenance
personnel and facilitate work on the outgoing side of a particular feeder without
the necessity to switch off the adjacent feeders .
j) Horizontal and vertical bus bars shall be enclosed in separate
chambers.
k) The bus bars and supports shall be designed to withstand a short
circuit fault level of (40KA) for 3 seconds. (Necessary type test certificates shall
be enclosed.)
l) All joints of bus bars shall be made by suitable bolts and nuts only
and shall be tightened using Belleville washers only.
m) Disconnect able neutral link shall be provided for each out going
feeder.
n) A separate aluminum/copper earth bus of adequate cross section
as per the relevant IS shall be provided through out the length of the Board.
MIMIC DIAGRAM:
The panels shall be provided with PVC/Painted or Aluminum
overlaid mimic showing the bus connection and tap off feeders.
m) Colour of the panel : The exterior and interior colors of the panels
will be RAL 7032 / white
Space Heater and Panel illumination lamp shall be incorporated as per
statutory requirement.
8.13 TERMINATIONS:
All the incomers and outgoing feeders will be terminated using 1100V
grade PVC insulated Aluminum/ Copper cables. The entry for these cables and
terminations shall be from bottom rear side of the panels only. The termination
shall be located at least a gap of 300mm above ground level.
WIRING:
a) Internal wiring shall be properly dressed and supported over cable
ways. All equipment shall be completely shop wired and be ready for external
connections at site.
b) All wires connecting the equipment on the front door to the internal
position of the cubicle shall have suitable flexible arrangement to facilitate
frequent opening and closing of the door.
c) For control circuits minimum 1.5 sq.mm, copper,pvc insulated
flexible, wire shall be used. For CT, and metering circuits minimum 2.5 sq.mm ,
copper, PVC insulated flexible wire shall be used with colour coding.
d) All the wires shall have PVC insulation for 1100 Volts grade and
shall be suitable for switchboard wiring and comply with requirements of latest
issue of IS 1554(Part I). Each wire shall bear an identifying ferrule at both ends.
All the operating coils and small wires shall withstand as erected, a power
frequency test voltage of 2 KV for 1(one) minute.
e) All outgoing control wiring, including that for connecting between shipping
sections shall terminate on terminal blocks preferably vertically mounted on the
side of each cubicle. Suitable cable glands and supports shall be provided for
the incoming cables. All spare contacts of the relays, contactors, circuit breaker
auxiliary contacts etc shall be supplied wired up to the terminal blocks for
customer use.
EM 09 STATION TRANSFORMER
9.0. Scope: Five No.s 750 KVA, 3 Phase, 11 KV/415 Volts, Delta/Star,
%impedance 5.% at normal tap Outdoor type, oil filled, ONAN type cooling,
type transformer , copper winding capable to feed the loads of pump house
with minimum protection, features such as PRV and Bucholtz protections.
The standards shall be of IS 2026. The details of transformer being supplied
shall be enclosed
9.1. TECHNICAL SPECIFICATIONS OF TRANSFORMER
9.1.1. GENERAL:
The offer for supply of transformer shall include all parts and
accessories which are useful and necessary for the efficient and safe
operation, such parts and accessories shall be deemed to be within the
scope of this specifications whether specifically mentioned or not.
Drawings showing the general arrangements foundation details, fittings
shall be
furnished along with the offer. The schedule of guarantees and technical
particulars shall be furnished along with the offer for each type of
transformer. List of past supplies made to Govt. / Quasi Govt.
Corporation/Undertakings shall be enclosed. The rates quoted for the
transformers shall be for designs, manufacturer, supply and deliver at
respective destinations.
Packing shall be sturdy and adequate to protect all assemblies,
components and
accessories from injury by corrosion, dampness heave rains, breakage,
vibration
encountered during transportation, handling and storage at site.
9.2. TECHNICAL SPECIFICATIONS :
9.2.1 (a) The Transformer shall be copper wound distribution Transformer.
(b) The Transformer is of 3 phase, 50Hz. AC double wound, oil immersed
Naturally
cooled, core type and suitable for outdoor installations. The Rating of the Transformer
shall be 750 KVA.
(c) The make of the Transfer should have been approved by AP DISCOM’s A
certificate to that extent shall have to be enclosed along with the tender.
Transformers with ISI marking shall be specifically mentioned in the tender.
The Distribution Transformer should confirm to IS 2026 of 1962 or the latest
revision thereof.
The transformer shall be Delta-star connected with neutral brought out on LT
Side,
with Vector group Dyn11.
The Transformers shall be supplied with first filling or transformer oil. The drain
valve shall be provided with locking arrangements.
The transformer shall be provided with LV cable box on LT side with a base plate
and glands shall be provided for cable entry.
(d) Temperature rise shall not increase 40 degrees centigrade for oil and 55
degrees
centigrade for winding over a maximum ambient temperature of 45 degrees
centigrade.
Off load tap switch shall be provided to vary HT Volts by +5% to –10% in steps
of 2.5% the tap switch should be gang operated operating simultaneously on all
three phases with multiple indicator and mechanical locking devices.
(e) The LT cable boxes (of adequate size with sufficient space for free movement
of
cables for connecting Aluminum armoured cables) with cable entries, with
suitable cable glands suitable to receive purchasers incoming cable of the
following sizes shall be provided.
(e) The bottom plate of the cable box shall be detachable type where the cable
glands
are provided.
The Transformer shall be painted with one coat of red oxide initially and two
coats
of epoxy gray enamel paint.
3 Machine hall (high bay) High bay fixtures MH & HPSV 260 lux
4 Transformer area MH fixtures 100 lux
5 outside yard and other approach Roads
a) Street light fixtures HPSV / LED fixtures 150 lux
these shall be fed from LDB. The wiring for these sockets shall be run in
separate conduits.
h) Main lighting board (MLB):
i) The metal clad MLB shall be of freestanding, totally enclosed, dust
vermin and drip proof and shall be compartmentalized. The panel (MLB) shall
be made of 2.0mm CR sheet or 2.5mm Hot rolled sheet and having smooth
finish and elegant appearance. All door panels and removable covers shall be
provided with gaskets to render effective protection against dust.
Each vertical panel of all boards shall be equipped with
space heaters and shall be provided with voltmeter and ammeter and shall be
illuminated suitably by lamps.
ii) All in coming and outgoing power cables shall enter bottom.
i) Lighting distribution boards (LDB)/Sub distribution board (SDB):
LDB shall be suitable for mounting on wall or column. The enclosure shall
be constructed of sheet steel of thickness 2.0mm.
j) Conduits & other Accessories:
a) Conduits: Conduits shall be of rigid PVC with dia of 25mm. All conduits
in Air-conditioned areas where false ceiling is provided shall be concealed in the
false ceiling. However in these areas conduits leading to switches and sockets
shall be concealed in walls. Screwing of conduits shall be carried out to give
clean threads standard bends, inspection type fittings shall be used. All conduits
shall be terminated by screwing and securing by a lock nut to the respective
accessory, outlet or luminaire and fully protected from the weather. Opening
through walls and floors for conduits shall be sealed and made weather proof.
b)Junction boxes: FRP junction boxes shall be used. The size of such
J.B. shall be adequate to house the bends and extra length of PVC wires and
double check nuts for conduits termination.
c) Cables/Wires: The LT power cables shall be 1.0 KV grade Aluminum
stranded conductor, PVC sheathed (un -armoured) confirming to standards.
The lighting wires shall be 650V grade copper PVC insulated single core
(sheathed) confirming to standards Color code for respective phase and black
for neutral shall be maintained within enclosure such as for switches, J.B. and
sockets etc, shall be used with green color PVC wire.
specified extra lighting fixtures shall be added so as to achieve the specified lux
level.
EM 14 EOT CRANES
14.18 PAINTING.
All fabricated steel material shall receive one shop coat of anti-
corrosive paint after having been thoroughly cleaned of all loose mill scales, rust
and foreign matter. Machine finished surfaces shall be coated with white lead
and yellow before dispatch. Paint shall be applied at temperature of 4-5o C or
lower. Paint shall be stirred frequently to keep the pigment in suspension. One
additional coat of read lead paint shall be applied for all steel work after erection.
The interior surfaces of box sections and surfaces in accessible after assembly
or erection, shall be thoroughly cleaned and painted with two coats of red lead
paint or any other anti-corrosive paint, before assembly.
Any steel scratches during erection shall be touched up after erection with lead
paint.
All bright parts shall be applied with suitable rust preventive paint which can be
easily removed during erection.
The slings, D - shackles of various capacities for general purpose, spares for five
years of operation & maintenance and special tools, tackle etc., shall also be
supplied.
Pump House Earthing shall be provided with suitable size of Mild steel
(MS) flat as per the standards from the bottom most point of pump house. The
earthing system shall be suitable to meet the earthing of all the electrical
equipment in the powerhouse.
All the electrical equipment shall be grounded at two points.
Earthing shall be provided by means of an earth mat laid right into the tail race to
keep the earth resistance to minimum. The earth mat shall be designed duly
taking into consideration of the local soil particulars.
fans if necessary. The Ventilation and Air conditioning system shall consist of
the following equipment for full functioning and easy maintenance and for
installation.
a. Ventilation Equipment :Fans, air filter units, heat exchanger and their
fittings including painting and foundations.
b. Air - Conditioning Equipment
Air-handling units, refrigerating machines, circulating pumps and
their fittings including painting, thermal insulation and foundations.
c. GI Air duct:Air duct, air dampers, air outlets and inlets and their fittings
including painting and thermal insulation.
d. Electrical Equipment
Power source panel, operating panel, control system conduit tubes
and cables for the ventilation and air conditioning system, and their fittings
including painting.
e. Water piping
Purpose Expansion tank, headers, water pipes and fitting such as
elbows, bees, couplings, valves, supports etc. for air-conditioning system
including painting and thermal insulation.
f. Refrigerant piping
EM 18 HT CABLES
18.1 SCOPE:
mm interval all along the cable length. Cables without such core identifications
shall not be accepted.
19.3 CABLE DRUMS:
Cables shall be supplied in non-returnable wooden/steel drums of heavy
construction. For wooden drums, the wood used for construction for the drum
shall be properly seasoned, sound and free from defects. Wood preservative
shall be applied to the entire drum.
The standard lengths for each size of power cables shall be 500/1000
meters. and control cables shall be 1000 meters. The cable length per drum
shall be subject to tolerance of ± 4% of the standard drum length agreed
between Purchaser and Contractor. However the total quantity of cables after
taking into consideration of all cable drums shall be within the tolerance of ±
2%.
A layer of water-proof paper shall be applied to the surfaces of the drums
and over the outer most cables layer.
A clear space of at least 40 mm shall be left between the cables and
the logging.
Each drum shall carry the manufacture’s name, the Purchaser’s name,
address and contract number, item number and type, size and length of cable,
net and gross weight printed on both sides of drum. A tag containing the same
information shall be attached to the leading end of the cable. An arrow and
suitable accompanying wordings shall be marked on one end of the reel
indicating the direction in which it should be rolled.
Packing shall be sturdy and adequate to protect the cables from any
injury due to mishandling or other conditions encountered during
transportation, handling and storage. Both cable ends shall be sealed with
PVC/Rubber caps so as to eliminate ingress of water during transportation,
storage and erection.
Armouring: No armouring is required for cables laid inside the power
house.
GI round wire Armouring shall be provided for cables laid outside the
power-house. All LT cables shall be of FRLS .
painted supports inside the power house and GI supports out side
the power house.
1.2. Laying
Cables shall be laid in ducts and in Cable trays. Segregation shall be
made in laying the control and power cables. Cables shall have identification
tags.
Termination
The cables shall be terminated to the panels / equipment with suitable
cable glands. The 11 kV XLPE Cables shall be terminated with suitable HV
termination kits. All materials such as cable Glands, Copper Lugs for termination,
Bolts and nuts and 11KV termination kits are included in the scope.
The cores of the cable shall be terminated with suitable copper lugs and
identification ferrules. The ferrules provided for identification shall have the
termination identification to which it is being terminated and also the identification
of the termination at other end for clear understanding. The terminations shall be
carried out based on the customer approved cable schedules and termination
drawings.
1.3. TESTS:
XLPE insulated power cables shall comply with all type tests and subjected
to all routine and acceptance tests as per IS:7098 Part-I (as amended up to
date) or equivalent of any IEC or International standards.
PVC insulated power and control cables shall comply with all type tests and be
subjected to all routine and acceptance tests as per IS:1444 Part-I. (as
amended up to date) or equivalent of any IEC or International standards.
Additional Type Tests:
The cables of all types and sizes shall also meet the following
additional type tests.
i) Oxygen index and temperature rise test as per ASTMD-2863. The
minimum value of oxygen index shall be 29.0
ii) Flame retardence test on single cable.
iii) Flame retardence test on bunch cable.
iv) Rodent and termite proof test.
Additional Acceptance Tests:
The following additional acceptance test on cables of each type and
size shall be carried out and cover at least 10% of the cable drums:-
i) Flame retardance test on single cable.
ii) Oxygen index and temperature index test as per ASTMD- 2863.
iii) Cold bend test for outer sheath.
iv) Cold impact test for outer sheath.
v) Resistance test for armour.
vi) Rodent and termite proof test.
with salt and charcoal. The lighting protection air termination rods and /
or horizontal air termination conductors shall be fixed in such as way that
they remain in their installed position even during severe weather
conditions. The lighting protection system shall comply with IS: 2309.All
joints in the down conductors shall be of welded / brazed type.
2.3.5. All metallicstructures with 2 mm vicinity of down conductors shall be
bonded to the lightingprotection system. Every down conductor shall be
provided with a test joint at about 1000 mm above ground level. The test
joint shall be directly connected to the earthing system electrode.
2.3.6. The lighting protection system shall not be in direct contract with
underground metallic service ducts, cables, cable conduits and metal
enclosures of electrical equipment.
2.3.7. The Contractor shall design the earthing system in such a way that the
over all earth resistance of pump house, without connecting to any other
earth grid shall not exceed 3 Ohms. The design calculations are subject to
the approval of Engineer. Supply and installation of earthing conductors
for interconnection of pumping station earthing grid with adjacent earthing
grid shall be covered under contractors scope.
ANNEXURES
ANNEXURE - AEM 01
4. Details of drive:
a) In case of direct drive through electric motor.
i. Rating : kW
ii. Type squirrel cage/slip ring/ :
drip proof/vertical/hollow-spindle/
solid shaft
iii. Details of power supply :
iv. Revolutions per minute :
b) In case of gear head drive, give:
i. Model :
ii. Speed rating :
ANNEXURE - AEM 02
1) General requirements:
1. Size of the valve: mm
2. Quantity
3. Fluid handled . . . . . . . . . .
4. Maximum working . . . . . . MPapressure
5. Design pressure . . . . . . . . . . . . MPa
6. Maximum differential pressure ( when valve shut ) . . . . . . . . . . . . MPa
7. Maximum flow . . . . . . . . ..m3/h and corresponding pressure..............MPa
8. Normal flow . . . . . . . . . . . . m3/h
9. Temperature of fluid. . . .. . . . . . . K
10. Maximum allow able pressure drop ( meters of water column ). . . . . . . . . .
. . MWC
11. Operating time( for power operated valves ) . . . . . . . . . . . . S
2) Service:
1. Tight shut off
2. Regulation
3. Low leakage rate
4. Suitability for flow in both directions
3) Mode of operation:
1. Manual with lever or handwheel or chainwheel or power actuator
2. Power/voltage/frequency/No. of phases/air supply pressure/type of
operator.
3. Direction of rotation of hand wheel.
4. Orientation of hand wheel/lever with reference to pipeline
4) Type of construction:
1. Flanged or wafer [ lug wafer single/ wafer flange/flangeless wafer/U-
section wafer ]
2. Face to face dimension ( short or long series )
3. Flange specification
4. Whether lifting lugs and mounting feet
6) Any other information not covered under in the section
ANNEXURE - AEM 03
1. Type : motor
*2. Rating
a)KW
b) KVA
c) KVAR
5. Power factor
a) Maximum
b) Minimum
7. Frequency : 50 Hz.
8. No. of phases : 3
9. Speed :
a) Normal
b) Runaway
c) Specific speed at
rated head
*10. Efficiency (%) at 100%, 80%, 60% and 30% of output (The windage
friction loss by the integral parts of motor is included).
Armature windings :
Field windings
a) Stator winding :
b) Rotor winding :
c) Other parts :
19. Stator
a) Number of sections :
i) Normal coil :
i) Normal coil :
ii) Terminal coil :
20. Rotor
a) Rotor diameter :
c) Number of poles :
d) Lowest factor of :
safety of any part of
rotor, calculated on
yield stress when
running at run away speed
a) Type :
b) No. of coolers :
including one spare cooler
i) Quantity :
ii) Water pressure :
iii)Temperature of cooled air :
22. Cooling
a) Type
i) Rotor :
ii) Stator :
Type
a) Rating :
g) Regulator gain :
a) Name of manufacturer :
b) Type :
i) To earth
ii) Between turns
Stator laminations
Rotor windings
i) To earth
ii) Between turns
26. i) Reactance
d) Transient (Unsaturated) :
f) Sub-transient (Quadrature):
(Unsaturated)
ii) Resistances :
27. Symmetrical root mean square short circuit currents with generator
isolated. (Fundamental component)
a) Initial 3 phase
c) Sustained 3 phase
b) Saturation at rated KVA and zero power factor under excited and
over excited.
30. Name and location of part having the least factor of safety under runaway
or short circuit conditions :
a) Amplitudes of harmonics as :
a percentage of fundamental
i) Capacity KVA :
ii) Ratio :
c) Diameter of bearing :
i) Quantity :
ii) Pressure :
e) Location :
a) Location
b) Type
c) Bearing Area
d) Cooling water
i) Quantity
ii) Pressure
36. Weights
c) Weight of stator
Name
Weight
Dimensions Approx.
Name
Dimensions
Name
Weight
Dimensions
Name
Weight
Dimensions
i) Material
Dia.
iii) Length
iv) Dia. of coupling flange
v) Dia. of axial holes
vi) Weight
i) Material
ii) Construction
ANNEXURE - AEM 04
Separate schedule shall be furnished for each type of bus duct if used.
8. Conductor Material
Cantilever strength
a. Upright (KG)
V) LIGHTNING ARRESTORS :
8. Characeterstics :
i) Ratio & Phase angle curves
ii) Magnetisation curve
iii) Ratio correction factor curves
VII) CAPACITOR :
1. Make and Type
2. Voltage rating (rms) (KV)
3. Capacitance, (Micro farads)
.DC hold test (10 Secs.)
4. Test voltage between terminal
and tank (KV)
5. Impulse Voltage (KV)
6. Compliance with standards
7. Discharge time of discharge resistor (Secs)
IX) CAPACITOR :
1. Make and Type
2. Voltage rating (rms) (KV)
3. Capacitance, (Micro farads)
a.DC hold test (10 Secs.)
4. Test voltage between terminal
and tank (KV)
5. Impulse Voltage (KV)
6. Compliance with standards
7. Discharge time of discharge resistor (Secs)
ANNEXURE - AEM 05
4. LAVT Cubicles
6. Synchronising Panel
1. Type.
3. a) Front.
b) Back.
c) Side.
1) Temperature range
a) Operation range :
b) Storage range.
2) Humidity :
3) Seismic test :
4) Insulation test
a) High voltage test
b) Impulse voltage test.
6) transient test :
1) Weight
2) Mounting arrangement :
3) Enclosure protection class :
(shall be IP54 or Better)
1. Type
2. Make
4. Software configuration
7. Type of Hardware
8. Sampling frequency
i) Analog
ii)Digital
9) Processor details
a) Type.
b) Make
a) No. of CT inputs.
b) No. of PT Inputs Á
11) Communications:
a) Internal:
b) Remote :
21) Self diagnostic facilities and frequency of Self diagnosis for trouble
shooting in case of faults.
Processor.
Power supply.
Type.
Make.
Technical Particulars.
Auxiliary supplies.
Any other particulars not mentioned above and in the scope of supply
shall be given.
1. Control Wiring.
(Type.....Make..........)
Voltage Grade.
Insulation.
Conductor material.
Colour code of wires used.
Voltage Grade.
Type of terminals.
Conductor Material.
Colour code of wires used.
Voltage grade
Type of terminals.
ANNEXURE - AEM 06
I. Switchgear Cubicles:
1. Type.
b) Back.
c) Side.
3. Standard applicable.
4. Rated Voltage.
6. Current Rating.
a) As per manufacturer's standard.
b) Derating factor (if any) for site conditions.
7. Rated frequency.
8. Rated voltage.
36. List of type tests carried out (Certificate to be attached with the tender)
List of routine tests proposed to be carried out.
6. Current Rating.
a) As per manufacturer's standard.
b) rating factor (if any) for site conditions.
c) Under site conditions.
7. Rated frequency.
8. Rated voltage.
9. Ultimate breaking capacity (KA Rms), Icu.
10. Service breaking capacity (% of ultimate breaking capacity), Ics (Service
breaking capacity shall not be less than 65 KA).
11. Overload and short circuit protection.
12. Symmetrical interrupting capacity, MVA
13 Symmetrical interruption current, KA
12. Making current, KA (peak).
13. Rated 1 second current, KA (rms) or
14. Main contacts:
i) Material
ii) Whether silver faced.
a. Between phases.
b. Between Live parts and ground.
V BUS BARS
1. Material.
2. Size
3. Type of insulation.
4. Minimum clearance : Between Phases.
Phase to nearest earthed part.
5. Continuous current rating.
1. Make
2. Type.
3. Applicable Standards.
4. Ratio
5. Accuracy Class.
6. Rated burden.
7. Rated accuracy limit factor.
8. 3 second short time thermal rating KA (rms)
9. Rated dynamic current KA (peak)
10. Type of insulation
11. Maximum temp. rise of wining above ambient temp. specified.
1. Make
2. Type.
3. Applicable Standards.
4. Setting range for Over current element.
5. Setting range for instantaneous element.
6. Burden characteristics.
7. Characteristic curves (to be attached with the tender)
1. Make
2. Type.
3. Applicable Standards.
4. Accuracy.
5. Case size.
6. No. digits of display.
7. Burden characteristics.
1. Make
2. Type.
3. Applicable Standards.
4. Ratio
5. Accuracy.
6. Burden.
7. Type of insulation
8. List of type tests carried out (Certificate to be attached with the tender)
9. List of routine tests proposed to be carried out.
X. CURRENT TRANSDUCERS
1. Make
2. Type.
3. Applicable Standards.
4. Input range
5. Output range.
6. Accuracy.
7. Overload capacity.
8. Details of Auxiliary supply.
XI. VOLTAGE TRANSDUCERS:
1. Make
2. Type.
3. Applicable Standards.
4. Input range
5. Output range.
6. Accuracy.
7. Overload capacity.
8. Details of Auxiliary supply.
1. Make
2. Type.
3. Applicable Standards.
4. Range of U/V and O/V settings.
5. Time delay provided.
6. No. of contacts Provided for external use.
7. Type of indication for
a) Under voltage
b) Over voltage
c)Reverse sequence.
8. Auxiliary supply
9. Input Voltage (110/415V)
XIV. WIRING:
1. Control Wiring:
(Type.......Make.......)
Voltage gradeInsulation.
ANNEXURE - AEM 07
2. Manufacturer’s type
3. Country of origin
6. Type of cooling.
7. Rating
a) Rated KVA
b) Rated voltage of HV
c) Rated Voltage of LV
d) Temp. rise by resistance winding
e) Rated frequency
8. No. of Phases
9. Connections
HV
LV
11. Tappings
High voltage Percentage
Low voltage Percentage
frequency at ____
a) Positive sequence at
principal tap.
b) Zero sequence at
principal tap.
c) Positive sequence at
maximum voltage tap.
d) Positive sequence at
minimum voltage tap.
a) 100% load
b) 50% load
Neutral
ANNEXURE - AEM 08
A. GENERAL
2. Applicable standards
1. Type
3. Ampere-hour capacity at
10Hr. rate of discharge.
4. Terminal voltage
i) 1 Minute load
ii) 2 Hour load.
iii) 10 Hour load.
7. Material of containers.
Type :
1. a) Boost charger.
b) Float charger.
7. Overall efficiency
1. Make
2. System voltage.
3. Maximum interrupting current.
4. Current rating.
1. Make
2. Type
1. Make
2. Type
ANNEXURE - AEM 09
i) Hoist
ii) Cross travels
iii) Long travel
iv) Acceleration values
for
a) Cross Travel
b) Long Travel
ii) 100% load lowering at full speed with the brake blocked open.
9) Hoisting Rope :
i) Main hoist
i) Main hoist
14) Bearings :
AC :
DC :
a) Overload tests.
b) Moor insulation tests.
c) All necessary speed tests.
d) Inching tests.
ANNEXURE - AEM 10
1. ELECTRIC FANS:
i) Name of manufacturer.
v) Class of construction
2. INDUCTION MOTORS:
i) Name of Manufacturer.
ii) Rated:
a) Output KW:
b) Speed (RPM):
3. FILTERS:
i) Name of Manufacturer.
ii) Type offered (washable/throwaway)
i) Material construction
ii) Thickness of sheet
iii) Type of construction
5. GRILLES/DIFFUSERS:
i) Name of manufacturer:
ii) Capacity of CFM
iii) Material
iv) Volume control damper provided Yes/No.
6. REFRIGERANT COMPRESSOR:
i) Manufacturer's Name:
ii) Type
iii) No. of Stages.
iv) Refrigerant
v) Type of cooling.
vi) Capacity at operating conditions (vi, vii, viii)
vii) Capacity and BHP
viii) BHP at operating conditions (vi,vii,viii)
ix) Noise level (db)
x) Any other data.
7. COOLING COILS:
i) Type
ii) Make
iii) Capacity
8. REFERIGERANT CONDENSERS:
9. HUMIDIFIER:
i) Make
ii) Type
iii) Material of construction
iv) Water Pressure
v) Any other information supplied.
ANNEXURE - AEM 11
I. DIESEL ENGINE
(i) Type :
(ii) Make : ...............
8. Exhaust system
(ii) Make :
9. Engine protection
II) GENERATOR/ALTERNATOR
B. ELECTRICAL EQUIPMENT
i) Type : ...........
ii) Make : ...........
iii) Rating : ...........
☼ ☼ ☼