Vous êtes sur la page 1sur 15

PT.

ENERGASINDO HEKSA KARYA

PT. PUSTEK E&T

FRONT END ENGINEERING DESIGN (FEED)


JARINGAN DISTRIBUSI GAS BUMI JAMBI

SPECIFICATION PIPELINE WELDING


DOC. NO. : EHK-P.ET-FDPJ-PL-SPC-006

0 22-02-2019 Issued for Review DV AF TS RK


PREP’D CHK’D APP’D APP’D
REV DATE DESCRIPTION
PT. PUSTEK E&T PT. EHK
Date : February 22, 2019 Specification Pipeline Welding

Rev : 0 EHK-P.ET-FDPJ-PL-SPC-006 Page : 2 of 15

TABULATION OF REVISION SHEET


REVISION REVISION
SHEET REMARKS SHEET REMARKS
0 1 2 3 4 5 0 1 2 3 4 5

ATTACHMENT
Date : February 22, 2019 Specification Pipeline Welding

Rev : 0 EHK-P.ET-FDPJ-PL-SPC-006 Page : 3 of 15

RECORD REVISION
Rev Implemented
Section Page Company’s Comment Explanation
Code (Y/N)
Date : February 22, 2019 Specification Pipeline Welding

Rev : 0 EHK-P.ET-FDPJ-PL-SPC-006 Page : 4 of 15

TABLE OF CONTENT

TABULATION OF REVISION SHEET ................................................................................... 2

RECORD REVISION ............................................................................................................ 3

TABLE OF CONTENT .......................................................................................................... 4

1. INTODUCTION .............................................................................................................. 6

1.1 Project Overview ................................................................................................... 6

1.2 Scope.................................................................................................................... 6

1.3 Definition ............................................................................................................... 6

2. REFERENCES CODE AND STANDARD....................................................................... 7

2.1 Indonesian Act and Regulations ............................................................................ 7

2.2 Codes and Standards ........................................................................................... 7

2.3 Order of Precedence ............................................................................................. 7

3. REQUIREMENTS .......................................................................................................... 8

3.1 Quality Control ...................................................................................................... 8

4. FABRICATION ............................................................................................................... 8

4.1 General ................................................................................................................. 8

4.2 Equipment and Consumables ............................................................................... 9

4.3 Marking ................................................................................................................. 9

4.4 Non Ferrous Metal ................................................................................................ 9

4.5 Pressure Containing Welds ................................................................................... 9

4.6 Spacing of Welds .................................................................................................. 9

4.7 Allignment of Pipe Ends ...................................................................................... 10

4.8 Welding ............................................................................................................... 11

4.9 Weather Protection ............................................................................................. 12

4.10 Tie In ................................................................................................................... 12

4.11 Post Weld Heat Treatment .................................................................................. 12

4.12 Welding Procedure Qualification ......................................................................... 12


Date : February 22, 2019 Specification Pipeline Welding

Rev : 0 EHK-P.ET-FDPJ-PL-SPC-006 Page : 5 of 15

4.13 Welder Qualification ............................................................................................ 13

5. WELDING AND WELD INSPECTION .......................................................................... 13

5.1 General ............................................................................................................... 13

5.2 Welding Joint Preparation ................................................................................... 13

6. INSPECTION AND TESTING ...................................................................................... 14

6.1 Non Destructive Testing ...................................................................................... 14

6.2 Visual Inspection ................................................................................................. 14

6.3 Radiographic Examination .................................................................................. 14

6.4 Personal Qualification Requirements .................................................................. 14

6.5 Independent Testing Services ............................................................................. 15


Date : February 22, 2019 Specification Pipeline Welding

Rev : 0 EHK-P.ET-FDPJ-PL-SPC-006 Page : 6 of 15

1. INTODUCTION

1.1 Project Overview


PT. Energasindo Heksa Karya (EHK) plans to build gas pipeline from two tie-in location,
tie-in from Payo Selincah (KP 34) and tie-in from Paal 10 (KP 15). Tie-in from Payo
Selincah consist of 4” sized pipeline with 60 km length as gas distribution facilities to 29
customers with 2” pipeline. Tie-in from Paal 10 consist of 4” sized pipeline with 20 km
length as gas distribution facilities to 8 customers with 2” pipeline. Gas pressure at each
tie-in is equal to 650 psig with estimated maximum flowrate of 1.6 MMSCFD in tie-in
Payo Selincah and 2.2 MMSCFD in tie-in Paal 10.

1.2 Scope
This specification defines minimum requirements for the welding of carbon steel pipeline
for 4" Gas Pipeline Project “Front End Engineering Design (Feed) Jaringan Distribusi
Gas Bumi Jambi ".

1.3 Definition
The definitions contained in this document are as follows:

CLIENT PT Energasindo Heksa Karya (EHK) as an Owner of the project


and End User.
CONSULTANT PT. PUSTEK Energi dan Teknologi, as selaku pihak yang
menyediakan layanan konsultasi teknis “Front End Engineering
Design (Feed) Jaringan Distribusi Gas Bumi Jambi ".
CONTRACTOR Company which is choosen by CLIENT, responsible for provide
services to perform a passage of scope contract upon the name
of the CLIENT
VENDOR/ Company that choosen by CLIENT or CONTRACTOR, which is
MANUFACTURER responsible for the specification of procurement agreement.
MIGAS The representatives from the Indonesia Government which is
responsible for issuing licenses and permits Oil and Gas
facilities
Date : February 22, 2019 Specification Pipeline Welding

Rev : 0 EHK-P.ET-FDPJ-PL-SPC-006 Page : 7 of 15

2. REFERENCES CODE AND STANDARD

2.1 Indonesian Act and Regulations

1. 300.K/38/M.PE/1997 Decree of the Minister of Mining and Energy


Regarding The Work Safety of Oil and Natural
Gas Distribution Pipeline.

2. 84.k/38/djm/1998 Inspection Guidelines for Safety On Facilities,


Equipment and Technology Used In Oil and Gas
And Geothermal Activities.

2.2 Codes and Standards

American Society of Mechanical Engineers (ASME)

ASME B31.8 Gas Transmission and Distribution Piping


Systems
ASME B36.10 Welded and Seamless Wrought Steel Pipe

Manufacturers Standardization Society of the Valve and Fittings Industry, Inc.

MSS SP-25 Standard Marking system for Valves, Fittings,


Flanges, and Unions

American Petroleum Institute (API)

API 5L Specification for Line Pipe


API Spec 1104 Welding of Pipelines and Related Facilities

Where fabrication and design criteria in this specification are affected by regulatory
authorities and jurisdiction, local or otherwise, this specification shall be modified as
necessary to ensure compliance.

2.3 Order of Precedence


Wherever conflicts or commissions between codes, specifications, and contract occur,
the most onerous condition shall apply. CONTRACTOR is responsible for reviewing the
list below and informing the CLIENT of any commissions. All conflicts shall be formally
brought to the attention of the CLIENT.
Date : February 22, 2019 Specification Pipeline Welding

Rev : 0 EHK-P.ET-FDPJ-PL-SPC-006 Page : 8 of 15

All Work shall be performed in accordance with the following order of precedence of the
following codes and standards:
1. Indonesian Act and Regulations
2. Project Scope of Work and Design Basis Memorandum
3. Internationally Recognized Codes and Standards
4. Good Engineering Practice
It is the CONTRACTOR responsibility to present the issues and / or differences among
the codes and standards above to the CLIENT for resolution. The more stringent
requirement shall prevail unless otherwise approved by the CLIENT.
Any latest amendments / new additions to the standard and regulation shall be
incorporated.
If the CONTRACTOR proposes to employ an alternative standard this shall be approved
by the CLIENT before Work can proceed.

3. REQUIREMENTS

3.1 Quality Control


A system shall be employed for linking unique inspection records, weld numbers and
welder identification. Detailed procedures for the control of welding quality shall be
established. The procedures shall be submitted for review and accepted by the CLIENT
before starting fabrication and shall include as a minimum:
a. Welding and weld repair
b. Storage, control and identification of welding consumables
c. Welder qualification records
d. Inspection & NDE
e. Monitoring the progress and quality of welding
f. Material and NDE traceability

4. FABRICATION

4.1 General
All fabrications shall conform to API 1104 or ASME 31.8 as applicable and the additional
requirements of this specification. Any discrepancies in the referenced codes and
specifications shall be reported to the CLIENT representative for the resolution. The
material of pipes and fittings shall meet the requirements of project specifications.
Date : February 22, 2019 Specification Pipeline Welding

Rev : 0 EHK-P.ET-FDPJ-PL-SPC-006 Page : 9 of 15

4.2 Equipment and Consumables


Descriptions of all welding equipment, type of machinery, welding materials to be used,
tools, and all other required items shall be submitted to the CLIENT for approval.
This equipment shall consist of, but not limited to, DC welding machines, welding
generators, equipment and machinery for cutting, bevelling, pre-heating, post weld heat
treating (PWHT), internal and external line-up clamps, welding consumables, welder
tools, tents, testing equipment and insulations blankets for weather protection.
All welding consumables shall be controlled during site condition.

4.3 Marking
Before materials are cut, permanent identification (head pipe numbers) shall be
transferred.
Each weld shall be marked with the identification symbol of the welder or welding
operator next to the weld area or records shall be maintained to identify the work of each
welder, i.e. weld numbers, shift, passes, left of right side of pipe, etc. Failure to use the
symbol or maintain adequate records shall be cause for rejection of the work and
removal of the weld.
For all welds, weld identification numbers shall be painted on the pipe coating using
contrasting colour. A reference between weld numbers and pipe numbers shall be
maintained. The width of each letter or number shall not be less than 19 mm (3/4).
Weld identification must be legible using sequential numbers or combination of
English block letters and numbers.

4.4 Non Ferrous Metal


Whenever possible, only stainless steel tools or grinding disks dedicated to stainless
steel shall be used. Material supports, internal purge dams, alignment clamps, and other
tools may be coated with a compatible material approved by the CLIENT.

4.5 Pressure Containing Welds


All pressure containing welds shall be made with a minimum two passes with overlap of
starts and stops.
4.6 Spacing of Welds
The spacing of welds shall meet the requirements of the following based on the type of
weld and attachment.
The maximum possible distance shall separate circumferential butt weld. However,
between piping fitting and tie-ins, etc., short pipe length may be required. In this situation,
Date : February 22, 2019 Specification Pipeline Welding

Rev : 0 EHK-P.ET-FDPJ-PL-SPC-006 Page : 10 of 15

butt weld shall be done >1.5 OD or greater. For pipe with nominal size less than 3 in,
butt welds should be separated from adjacent weld with minimum 1,5 OD.
Circumferential butt welds closer than the above limits shall not remain without CLIENT
approval.
Branch I nozzle and other pressure attachment welds shall not be loser than 3 in (75
mm) (measured toe to toe) to adjacent pressure welds. Any cases that fail to meet this
criterion shall be approved by the CLIENT representative before commencement of
fabrication.
Attachment welds that are not pressure containing, such as pipe support welds, are
generally not allowed on the surface of the pipeline. If such welds are part of the
approved design, then each shall be a minimum of 2 in (50 mm) from any other pressure
containing welds (measured toe to toe).

4.7 Allignment of Pipe Ends


Butt weld alignment shall meet the requirements of API 1104, the qualified weld
procedure dimensional limitations, and the conditions of this section.
All pipe ends shall be lined up for welding by use of an internal or external lined up
clamp.
Lined clamps shall not be removed until the root and hot pass have been completed.
In specific instances where it is not possible or practical to use the internal I external line
up equipment, the CLIENT representative may accept alternate method. This
requirement is to minimize the possibility of high low due to misalignment and to permit
continuous welding of the root pass for the full circumference of the pipe.
Internal grinding or machining may be conducted to improve root alignment if
misalignment is equal to or less than 1/8 in (3.2 mm). However, the taper shall not
exceed 1 in 4 and the minimum wall thickness shall be maintained.
Maximum permissible offset of pipe ends of the same wall thickness shall be 1/32 in.
Longitudinal welds of adjacent pipes shall be staggered b at least 30° or 3 in (75 mm),
whichever is less and by not more than forty-five degrees (45°).
Welded sections of single lengths shall be assembled and lowered into the ditch so that
the longitudinal seams shall remain on the top half of the pipe. An exception to this is on
bend joints where the pipe seams are to be at right angles to the bend, on the neutral
axis of the bend. Longitudinal weld seams shall have a minimum 4 in offset between
abutting joints, measured along the circumference of the pipe.
Date : February 22, 2019 Specification Pipeline Welding

Rev : 0 EHK-P.ET-FDPJ-PL-SPC-006 Page : 11 of 15

Branch fittings such as weldolets and similar attachments shall not be located on or
close to a circumferential weld or the longitudinal seam of the pipe.

4.8 Welding
Welding of the pipeline shall be in accordance with the requirements of API 1104
(Nineteenth Edition, September 1999) and the most recent edition of ASME B31.8, as
amended or modified by this specification. All welds shall be performed using the
approved and certified Welding Procedure(s) and meet the acceptance standards of API
1104, as amended and modified by this specification.
Welding shall be permitted only when conditions are acceptable per API Standard 1104.
Backing rings shall not be used.
Root penetration shall not exceed 3 mm.
Partially completed joint: The minimum number of passes before the joint is allowed to
cool to ambient temperature. The stage at which line up clamps are removed.
Immediately after the weld joint is prepared and the pipe ends properly aligned and
spaced, the root pass shall be run for the full circumference of the pipe. The root pass
shall be ground, it is not sufficient to only brush the weld, to remove all slag and leave a
smooth and uniform contour for the next pass, and in no circumstance should more time
elapse between the root and hot passes than that permitted by the welding procedure.
All slag and rough or uneven areas between passes shall be removed by using brushing
or grinding, as required, prior to commencing the subsequent pass.
All pieces of welding rod shall be collected in a suitable container and properly disposed
of. In no circumstance is any welding rod to be left on the ground or disposed of in the
trench.
When welding valves into the line, gate, globe, and check valves shall be in the closed
position and ball valves shall be in the open position.
The welding supervisors and inspectors shall possess a full knowledge of pertinent
specification requirements or modifications required by this specification. Current copies
of all pertinent documentation, such as specifications and approved Welding
Procedures, shall be available to the welding crew supervisors and inspection personnel
during all work.
Mill certification of all welding rods used in the work shall be furnished to CLIENT. The
storage and use of welding rods shall be as specified by the manufacturer.
The physical properties of the welding consumable shall be similar to the properties of
the base material.
Date : February 22, 2019 Specification Pipeline Welding

Rev : 0 EHK-P.ET-FDPJ-PL-SPC-006 Page : 12 of 15

4.9 Weather Protection


It is a requirement that all necessary protective shelters and sunshades shall be
provided during the execution of the work. Should this equipment not be utilized during
the execution of the work, then CLIENT representative will suspend welding operations
should adverse weather conditions prevail. Should thereafter the equipment be
provided, and has been approved by the CLIENT representative, CLIENT may authorize
the resumption of such operations. All such stoppages shall not be to CLIENT cost.

4.10 Tie In
Any tie-in spools or pipe strings used for completion of a tie-in after the full hydrostatic
test shall be subjected to a pre-installation hydrostatic test prior to welding into the
pipeline.
Any tie-in welds, which will not be subject to full hydrostatic test, shall be ultrasonically
tested and 100% radiographed.
Wherever possible, tie-ins shall be undertaken in the trench. Where tie-ins are required
outside of the trench, holding and lowering operations shall be undertaken in such a
manner as to minimize the stresses in the pipe. Due consideration shall also be given
to ambient temperature changes throughout the day and the resultant pipe length
changes / stresses.

4.11 Post Weld Heat Treatment


Post weld heat treatment and / or stress relief procedures, if required, shall be according
to the requirements of ASME B31.8 as applicable and shall be carried out in accordance
with an approved procedure.

4.12 Welding Procedure Qualification


A welding Procedure Qualification shall be developed and submitted to Company for
approval prior to start of welding. The Welding Procedure shall be qualified in
accordance with API 1104 and shall have MIGAS certification.
Welding repair procedures shall be developed and approved by CLIENT for any repair
of defective welds prior to performing any weld repair. Welding repair procedures shall
take into account the amendments and modifications to API 1104 detailed in this Scope
of Work and Pipeline Specification. The repair procedures shall not permit a repair to a
repair without the approval, in advance, of the CLIENT representative or inspector.
An independent testing laboratory, approved by CLIENT, shall perform all destructive
tests for Procedure Qualifications.
Date : February 22, 2019 Specification Pipeline Welding

Rev : 0 EHK-P.ET-FDPJ-PL-SPC-006 Page : 13 of 15

The qualification test piece shall meet the acceptance standard of API 1104 for visual
and radiographic examination.

4.13 Welder Qualification


Welders shall be qualified per API Standard 1104, to the MIGAS certified and CLIENT
approved Welding Procedure.
Unless otherwise approved in advance by the CLIENT, both CLIENT and MIGAS
representatives shall witness each welder's qualification test. The acceptance standards
for non-destructive testing applied for the welder's qualification test shall be as amended
and modified by this specification. The welder qualification documents are to be
submitted and signed by CLIENT and MIGAS. The completed welder Qualification
Certificates shall be submitted to CLIENT inspector, before the welder may begin work
on the pipeline.
Each qualified welder shall be assigned an identification number and mark his welds
with the identification number using a suitable indelible marking pen. A listing of each
qualified welder, identifying qualification date and stamp number shall be supplied to the
CLIENT inspector. The identification numbers shall be unique and exclusive and shall
not be reassigned to another welder in the case of welder replacement or substitution.

5. WELDING AND WELD INSPECTION

5.1 General
All pipelines welding shall be undertaken in accordance with latest edition of API
Standard 1104, Welding of pipelines and related facilities.
Only certified and qualified welders using qualified procedures shall be used for welding
the pipeline. All work shall be completed in a workman-like manner.

5.2 Welding Joint Preparation


Bevelled edges shall be smooth and free of gouges; the bevel angle and land shall meet
the requirements of the welding procedure. Bevelled edges shall be ground or buffed to
clean metal immediately prior to fit up and free from paint, oil, dirt, scale, oxides and
other foreign material.
If conflict or need clarification of weld joint preparation arises shall be brought to the
attention of the CLIENT representative for resolution.
Date : February 22, 2019 Specification Pipeline Welding

Rev : 0 EHK-P.ET-FDPJ-PL-SPC-006 Page : 14 of 15

6. INSPECTION AND TESTING

6.1 Non Destructive Testing


Non-destructive examinations shall comply with API 1104 and the additional
requirements of this specification. The required examination procedures shall be
submitted and demonstrated for CLIENT acceptance before welding.
CLIENT shall accept the selection of the NDE Subcontractor prior to its mobilization.
CLIENT representative shall be present during examinations / inspections. Sufficient
notice shall be given before any examination is scheduled to take place so that CLIENT
can arrange to have a representative present before any welding occurs.

6.2 Visual Inspection


The root pass and the final weld shall be visually inspected and ensured that there
should not be any defect like cracks, porosity, blowholes, slag etc.

6.3 Radiographic Examination


All girth weld shall be 100% radiographically examination.
All welds incorporated into the work shall be examined by Radiographic methods by the
NDE Subcontractor according to API 1104, unless the CLIENT accept alternate method
of NDE permitted by API 1104 or other applicable codes and standards. All costs
associated with this NDE shall be part of the work.
The extent of inspection for other applications shall be as defined in contract documents,
or ASME B31.8 as appropriate. Welds shall be selected to ensure that the work product
of each welder or welding operator doing the production welding is included.

6.4 Personal Qualification Requirements


The qualification of inspection personnel shall meet the requirements of API Standard
1104 and ASME B31.8 as appropriate. All documentation of these records shall be
retained and the records made available to the CLIENT.
The Non-destructive Testing Personnel shall be certified to the requirements of API
Standards 1104, ASME B31.8 and all applicable MIGAS regulations. It is a requirement
that all records of assigned certified non-destructive testing personnel shall be retained
and the records made available to the CLIENT. NDT personnel used to interpret
radiographs of the welds shall be minimum Level II qualified in all disciplines.
A certificate for each examiner on the site shall be available at all times while fabrication
is in progress. Qualification records shall be available for review on short notice.
Date : February 22, 2019 Specification Pipeline Welding

Rev : 0 EHK-P.ET-FDPJ-PL-SPC-006 Page : 15 of 15

6.5 Independent Testing Services


CLIENT shall have the right, in accordance with API 1104, to require welds to be
removed and destructively tested by an Independent Testing Laboratory. In this case
the actual cost of the Independent Testing services to have the testing performed is a
requirement of the work for those welds that fail the test, and for the account of the
CLIENT for those welds, which are found acceptable. Other costs involved in removing
the weld(s) to be tested from the work and re-welding as required shall not be to CLIENT
cost, unless CLIENT approves otherwise.

Vous aimerez peut-être aussi