Académique Documents
Professionnel Documents
Culture Documents
ATTACHMENT
Date : February 22, 2019 Specification Pipeline Welding
RECORD REVISION
Rev Implemented
Section Page Company’s Comment Explanation
Code (Y/N)
Date : February 22, 2019 Specification Pipeline Welding
TABLE OF CONTENT
1. INTODUCTION .............................................................................................................. 6
1.2 Scope.................................................................................................................... 6
3. REQUIREMENTS .......................................................................................................... 8
4. FABRICATION ............................................................................................................... 8
1. INTODUCTION
1.2 Scope
This specification defines minimum requirements for the welding of carbon steel pipeline
for 4" Gas Pipeline Project “Front End Engineering Design (Feed) Jaringan Distribusi
Gas Bumi Jambi ".
1.3 Definition
The definitions contained in this document are as follows:
Where fabrication and design criteria in this specification are affected by regulatory
authorities and jurisdiction, local or otherwise, this specification shall be modified as
necessary to ensure compliance.
All Work shall be performed in accordance with the following order of precedence of the
following codes and standards:
1. Indonesian Act and Regulations
2. Project Scope of Work and Design Basis Memorandum
3. Internationally Recognized Codes and Standards
4. Good Engineering Practice
It is the CONTRACTOR responsibility to present the issues and / or differences among
the codes and standards above to the CLIENT for resolution. The more stringent
requirement shall prevail unless otherwise approved by the CLIENT.
Any latest amendments / new additions to the standard and regulation shall be
incorporated.
If the CONTRACTOR proposes to employ an alternative standard this shall be approved
by the CLIENT before Work can proceed.
3. REQUIREMENTS
4. FABRICATION
4.1 General
All fabrications shall conform to API 1104 or ASME 31.8 as applicable and the additional
requirements of this specification. Any discrepancies in the referenced codes and
specifications shall be reported to the CLIENT representative for the resolution. The
material of pipes and fittings shall meet the requirements of project specifications.
Date : February 22, 2019 Specification Pipeline Welding
4.3 Marking
Before materials are cut, permanent identification (head pipe numbers) shall be
transferred.
Each weld shall be marked with the identification symbol of the welder or welding
operator next to the weld area or records shall be maintained to identify the work of each
welder, i.e. weld numbers, shift, passes, left of right side of pipe, etc. Failure to use the
symbol or maintain adequate records shall be cause for rejection of the work and
removal of the weld.
For all welds, weld identification numbers shall be painted on the pipe coating using
contrasting colour. A reference between weld numbers and pipe numbers shall be
maintained. The width of each letter or number shall not be less than 19 mm (3/4).
Weld identification must be legible using sequential numbers or combination of
English block letters and numbers.
butt weld shall be done >1.5 OD or greater. For pipe with nominal size less than 3 in,
butt welds should be separated from adjacent weld with minimum 1,5 OD.
Circumferential butt welds closer than the above limits shall not remain without CLIENT
approval.
Branch I nozzle and other pressure attachment welds shall not be loser than 3 in (75
mm) (measured toe to toe) to adjacent pressure welds. Any cases that fail to meet this
criterion shall be approved by the CLIENT representative before commencement of
fabrication.
Attachment welds that are not pressure containing, such as pipe support welds, are
generally not allowed on the surface of the pipeline. If such welds are part of the
approved design, then each shall be a minimum of 2 in (50 mm) from any other pressure
containing welds (measured toe to toe).
Branch fittings such as weldolets and similar attachments shall not be located on or
close to a circumferential weld or the longitudinal seam of the pipe.
4.8 Welding
Welding of the pipeline shall be in accordance with the requirements of API 1104
(Nineteenth Edition, September 1999) and the most recent edition of ASME B31.8, as
amended or modified by this specification. All welds shall be performed using the
approved and certified Welding Procedure(s) and meet the acceptance standards of API
1104, as amended and modified by this specification.
Welding shall be permitted only when conditions are acceptable per API Standard 1104.
Backing rings shall not be used.
Root penetration shall not exceed 3 mm.
Partially completed joint: The minimum number of passes before the joint is allowed to
cool to ambient temperature. The stage at which line up clamps are removed.
Immediately after the weld joint is prepared and the pipe ends properly aligned and
spaced, the root pass shall be run for the full circumference of the pipe. The root pass
shall be ground, it is not sufficient to only brush the weld, to remove all slag and leave a
smooth and uniform contour for the next pass, and in no circumstance should more time
elapse between the root and hot passes than that permitted by the welding procedure.
All slag and rough or uneven areas between passes shall be removed by using brushing
or grinding, as required, prior to commencing the subsequent pass.
All pieces of welding rod shall be collected in a suitable container and properly disposed
of. In no circumstance is any welding rod to be left on the ground or disposed of in the
trench.
When welding valves into the line, gate, globe, and check valves shall be in the closed
position and ball valves shall be in the open position.
The welding supervisors and inspectors shall possess a full knowledge of pertinent
specification requirements or modifications required by this specification. Current copies
of all pertinent documentation, such as specifications and approved Welding
Procedures, shall be available to the welding crew supervisors and inspection personnel
during all work.
Mill certification of all welding rods used in the work shall be furnished to CLIENT. The
storage and use of welding rods shall be as specified by the manufacturer.
The physical properties of the welding consumable shall be similar to the properties of
the base material.
Date : February 22, 2019 Specification Pipeline Welding
4.10 Tie In
Any tie-in spools or pipe strings used for completion of a tie-in after the full hydrostatic
test shall be subjected to a pre-installation hydrostatic test prior to welding into the
pipeline.
Any tie-in welds, which will not be subject to full hydrostatic test, shall be ultrasonically
tested and 100% radiographed.
Wherever possible, tie-ins shall be undertaken in the trench. Where tie-ins are required
outside of the trench, holding and lowering operations shall be undertaken in such a
manner as to minimize the stresses in the pipe. Due consideration shall also be given
to ambient temperature changes throughout the day and the resultant pipe length
changes / stresses.
The qualification test piece shall meet the acceptance standard of API 1104 for visual
and radiographic examination.
5.1 General
All pipelines welding shall be undertaken in accordance with latest edition of API
Standard 1104, Welding of pipelines and related facilities.
Only certified and qualified welders using qualified procedures shall be used for welding
the pipeline. All work shall be completed in a workman-like manner.