Step Specific Hazard Assessment

Area: SWRO-1

Equipment Descript/ KKS: Emergency Lighting System


Task Description: Rectification & Replacement of defective Emergency lighting condiuts, cables, Junctions boxes and Lights JHA Number: 2016-0053

Task Step # Task Step Description Potential Hazard Steps Taken to Avoid Hazard PPE Required

Impact, Chemical, Penetration,


Hand Protection, Safety glass , Safety
Compression, Electrical, Thermal, Light- Racked out, Isolated, Drained, Purged, Area Barricaded, Flushed,
Helmet, Dust Mask, Arc-flash Suit, other
Non-Ionizing Radiation (Welding Flash), Welding Curtains, Tie-Off, etc.
required necessary safety harness etc.,
Falls, Atmospheric, Mechanical

Inspected/Insulated tools & A-TYPE Ladder, If required Necessary


1 No Isolation Permit to be accepted Electrical Hazard Regular PPE, Insulated tools
Safety Harness
Inspected/Insulated tools & A-TYPE Ladder, If required Necessary
2 Check the lighting system functionality Electric Hazard Regular PPE, Insulated tools
Safety Harness

3 Self Isolation and proper caution tagging (If required) Electrical Hazard AC power supply isolation and tagging Inspected & Insulated tools and regular
PPE
Rectification & Replacement of defective Emergency
Inspected/Insulated tools & A-TYPE Ladder, If required Necessary
4 lighting condiuts, cables, Junctions boxes and Lights (If Electric Hazard & Falling Hazard Regular PPE, Insulated tools
Safety Harness
required)
Closing of all lighting panels/Covers, JB'S and sealing all Inspected/Insulated tools & A-TYPE Ladder, If required Necessary
5 Electric Hazard & Falling Hazard Regular PPE, Insulated tools
covers Safety Harness

6 House keeping Falling , Fire or tripping Hazard Do Complete housekeeping in the work place and surrounding Regular PPE

7 Lighting scrap disposal Environmental, Physical Hazard Follow proper disposal procedure Regular PPE

Tools Needed: Insulated Tools and Inspected Instruments


HA Written/ Revised By: A. R. Chowdary JHA Reviewed By: CRE JHA Reviewed By: AE Date of Revision:06/03/2016