Vous êtes sur la page 1sur 41

SYLLABUS

EN BANC
1. REMEDIAL LAW; CIVIL PROCEDURE; PARTIES; INTEREST OF PERSON
ASSAILING THE CONSTITUTIONALITY OF A STATUTE MUST BE DIRECT AND PERSONAL. —
The question on legal standing is whether such parties have "alleged such a personal stake
[G.R. No. 155001. May 5, 2003.]
in the outcome of the controversy as to assure that concrete adverseness which sharpens
the presentation of issues upon which the court so largely depends for illumination of
difficult constitutional questions." Accordingly, it has been held that the interest of a person
SYNOPSIS assailing the constitutionality of a statute must be direct and personal. He must be able, to
show, not only that the law or any government act is invalid, but also that he sustained or
is in imminent danger of sustaining some direct injury as a result of its enforcement, and
On October 5, 1994, Asia's Emerging Dragon Corp. (AEDC) submitted an not merely that he suffers thereby in some indefinite way. It must appear that the person
unsolicited proposal to the Government for the development of Ninoy Aquino International complaining has been or is about to be denied some right or privilege to which he is lawfully
Airport International Passenger Terminal III (NAIA IPT III) under a build-operate-and- entitled or that he is about to be subjected to some burdens or penalties by reason of the
transfer arrangement pursuant to RA 6957, as amended. It was endorsed to the National statute or act complained of.
Economic Development Authority (NEDA), which, in turn, reviewed and approved it for
bidding. The Paircargo Consortium was the only company that submitted a competitive 2. ID.; ID.; ID.; ID.; FINANCIAL PREJUDICE IS A LEGITIMATE INTEREST
proposal. AEDC questioned, among others, the financial capability of Paircargo Consortium. SUFFICIENT TO CONFER THE REQUISITE STANDING. — [P]etitioners have a direct and
However, the Pre-Qualification Bids and Awards Committee (PBAC) had prequalified the substantial interest to protect by reason of the implementation of the PIATCO Contracts.
Paircargo Consortium to undertake the project. Later, Paircargo Consortium incorporated They stand to lose their source of livelihood, a property right which is zealously protected
into Philippine International Airport Terminals Co., (PIATCO). And for failure of AEDC to by the Constitution. Moreover, subsisting concession agreements between MIAA and
match the price proposal submitted by PIATCO, the project was awarded to PIATCO. On petitioners-intervenors and service contracts between international airlines and petitioners-
July 12, 1997, the Government signed the 1997 Concession Agreement. Thereafter, the intervenors stand to be nullified or terminated by the operation of the NAIA IPT III under
Amended and Restated Concession Agreement (ARCA) and three Supplements thereto were the PIATCO Contracts. The financial prejudice brought about by the PIATCO Contracts on
signed by the Government and PIATCO. Consequently, the workers of the international petitioners and petitioners-intervenors in these cases are legitimate interests sufficient to
airline service providers, claiming that they stand to lose their employment upon the confer on them the requisite standing to file the instant petitions.
implementation of the said agreements, filed before this Court a petition for prohibition
docketed as G.R. No. 155001. Later, the service providers joined their cause. Congressmen 3. ID.;ID.;ID.;ID.;COURT MUST BE MORE LIBERAL IN DETERMINING WHETHER
Salacnib Baterina, Clavel Martinez and Constantino Jaraula, alleging that the said contracts THE PETITIONERS HAVE LOCUS STANDI TO FILE A PETITION. — Standing is a peculiar
compelled government expenditure without appropriation, filed a similar petition docketed concept in constitutional law because in some cases, suits are not brought by parties who
as G.R. No. 155547. And several employees of the MIAA likewise filed a petition docketed have been personally injured by the operation of a law or any other government act but by
as G.R. No. 155661 assailing the legality of these agreements. concerned citizens, taxpayers or voters who actually sue in the public interest. Although we
are not unmindful of the cases of Imus Electric Co. v. Municipality of Imus and Gonzales v.
The Court ruled that in accordance with the provisions of R.A. No. 337, as Raquiza wherein this Court held that appropriation must be made only on amounts
amended, the maximum amount that Security Bank, as one of the members of the immediately demandable, public interest demands that we take a more liberal view in
Paircargo Consortium could validly invest, is only 15% of its entire net worth. The total net determining whether the petitioners suing as legislators, taxpayers and citizens have locus
worth, therefore of the Paircargo Consortium, after considering the maximum amounts that standi to file the instant petition.In Kilosbayan, Inc. v. Guingona,this Court held "[i]n line
may be validly invested by each of its members, is only 6.08% of the project cost, which with the liberal policy of this Court on locus standi,ordinary taxpayers, members of
substantially less than the prescribed minimum equity investment which is 30% of the Congress, and even association of planters, and non-profit civic organizations were allowed
project cost. Thus, the award of the contract by the PBAC to the Paircargo Consortium, a to initiate and prosecute actions before this Court to question the constitutionality or validity
disqualified bidder, is null and void. of laws, acts, decisions, rulings, or orders of various government agencies or
instrumentalities," Further, "insofar as taxpayers' suits are concerned ...(this Court) is not
As to the validity of the agreements, the ARCA obligates the Government to pay devoid of discretion as to whether or not it should be entertained." As such "...even if,
for all loans, advances and obligations arising out of financial facilities extended to PIATCO strictly speaking, they [the petitioners] are not covered by the definition, it is still within
for the implementation of the NAIA IPT III project should PIATCO default in its loan the wide discretion of the Court to waive the requirement and so remove the impediment
obligations to its Senior Lenders and the latter fails to appoint a qualified nominee or to its addressing and resolving the serious constitutional questions raised." In view of the
transferee. This in effect would make the Government liable for PIATCO's loans should the serious legal questions involved and their impact on public interest, we resolve to grant
conditions set forth in the ARCA arise. This is a form of direct government guarantee and standing to the petitioners.
to declare the PIATCO contracts valid despite the clear statutory prohibitions against a
direct government guarantee would only make a mockery of that the BOT Law seeks to 4. ID.;ID.;JURISDICTION; HIERARCHY OF COURTS MAY BE RELAXED WHEN THE
prevent. The Court also ruled that the operation of an international passenger airport REDRESS DESIRED CANNOT BE OBTAINED IN THE APPROPRIATE COURTS. — The rule on
terminal is no doubt an undertaking imbued with public interest. Thus, the privilege given hierarchy of courts will not also prevent this Court from assuming jurisdiction over the cases
to PIATCO is subject to reasonable regulation and supervision by the Government through at bar. The said rule may be relaxed when the redress desired cannot be obtained in the
the MIAA. Another thing, PIATCO, by the mere expedient of claiming an exclusive right to appropriate courts or where exceptional and compelling circumstances justify availment of
operate, cannot require the Government to break its contractual obligations to the service a remedy within and calling for the exercise of this Court's primary jurisdiction. ATaDHC
providers. Accordingly, the 1997 Concession Agreement, the Amended and Restated
Concession Agreement and the Supplements thereto were set aside for being null and 5. ID.;ID.;ID.;PROCEDURAL BARS MAY BE LOWERED TO GIVE WAY FOR THE
void. TCEaDI SPEEDY DISPOSITION OF CASES OF TRANSCENDENTAL IMPORTANCE. — It is easy to
discern that exceptional circumstances exist in the cases at bar that call for the relaxation prospective bidder, for the construction, operation and maintenance of the NAIA IPT III
of the rule. Both petitioners and respondents agree that these cases are oftranscendental project should prove that it has the ability to provide equity in the minimum amount of
importance as they involve the construction and operation of the country's premier 30% of the project cost, in accordance with the 70:30 debt-to-equity ratio prescribed in
international airport. Moreover, the crucial issues submitted for resolution are of first the Bid Documents. Thus, in the case of Paircargo Consortium, the PBAC should determine
impression and they entail the proper legal interpretation of key provisions of the maximum amounts that each member of the consortium may commit for the
the Constitution, the BOT Law and its Implementing Rules and Regulations. Thus, construction, operation and maintenance of the NAIA IPT III project at the time of pre-
considering the nature of the controversy before the Court, procedural bars may be lowered qualification. With respect to Security Bank, the maximum amount which may be invested
to give way for the speedy disposition of the instant cases. by it would only be 15% of its net worth in view of the restrictions imposed by the General
Banking Act. Disregarding the investment ceilings provided by applicable law would not
6. CIVIL LAW; OBLIGATIONS AND CONTRACTS; ARBITRATION CLAUSE; NOT result in a proper evaluation of whether or not a bidder is pre-qualified to undertake the
BINDING TO PERSONS NOT PARTIES TO THE CONTRACT. — It is established thatpetitioners project as for all intents and purposes, such ceiling or legal restriction determines the true
in the present cases who have presented legitimate interests in the resolution of the maximum amount which a bidder may invest in the project.
controversy are not parties to the PIATCO Contracts.Accordingly, they cannot be bound by
the arbitration clause provided for in the ARCA and hence, cannot be compelled to submit 11. ID.;ID.;ID.;ID.;ID.;EVALUATION OF THE FINANCIAL CAPACITY OF THE
to arbitration proceedings. A speedy and decisive resolution of all the critical issues in the BIDDER MUST BE AT THE TIME THE BID IS SUBMITTED. — [T]he determination of whether
present controversy, including those raised by petitioners, cannot be made before an or not a bidder is pre-qualified to undertake the project requires an evaluation of the
arbitral tribunal.The object of arbitration is precisely to allow an expeditious determination financial capacity of the said bidder at the time the bid is submitted based on the required
of a dispute. This objective would not be met if this Court were to allow the parties to settle documents presented by the bidder. The PBAC should not be allowed to speculate on
the cases by arbitration as there are certain issues involving non-parties to the PIATCO the future financial ability of the bidder to undertake the project on the basis of documents
Contracts which the arbitral tribunal will not be equipped to resolve. submitted. This would open doors to abuse and defeat the very purpose of a public bidding.
This is especially true in the case at bar which involves the investment of billions of pesos
7. POLITICAL LAW; ADMINISTRATIVE LAW; REPUBLIC ACT NO. 6957 (BUILD- by the project proponent. The relevant government authority is duty-bound to ensure that
OPERATE-AND-TRANSFER or BOT LAW); CONTRACT SHALL BE AWARDED TO THE BIDDER the awardee of the contract possesses the minimum required financial capability to
WHO SATISFIED THE. MINIMUM FINANCIAL, TECHNICAL, ORGANIZATIONAL AND LEGAL complete the project. To allow the PBAC to estimate the bidder's future financial
STANDARDS REQUIRED BY LAW. — Under the BOT Law, in case of a build-operate-and- capability would not secure the viability and integrity of the project.
transfer arrangement, the contract shall be awarded to the bidder "who, having satisfied
the minimum financial, technical, organizational and leg standards" required by the law, 12. ID.;ID.;ID.;ID.;ID.;IF THE BIDDER FALLS SHORT OF THE MINIMUM
has submitted the lowest bid and most favorable terms of the project. ...Accordingly, ...the AMOUNTS REQUIRED, THE SAID BIDDER SHOULD BE DISQUALIFIED. — Thus, if
Paircargo Consortium or any challenger to the unsolicited proposal of AEDC has to show themaximum amount of equity that a bidder may invest in the project at the time the bids
that it possesses the requisite financial capability to undertake the project in the minimum are submitted falls short of the minimum amounts required to be put up by the bidder, said
amount of 30% of the project costthrough (i) proof of the ability to provide a minimum bidder should be properly disqualified. Considering that at the pre-qualification stage, the
amount of equity to the project, and (ii) a letter testimonial from reputable banks attesting maximum amounts which the Paircargo Consortium may invest in the project fell short of
that the project proponent or members of the consortium are banking with them, that they the minimum amounts prescribed by the PBAC, we hold that Paircargo Consortium was not
are in good financial standing, and that they have adequate resources. a qualified bidder. Thus the award of the contract by the PBAC to the Paircargo Consortium,
a disqualified bidder, is null and void.
8. ID.;ID.;ID.;ID.;TOTAL NET WORTH OF THE PAIRCARGO CONSORTIUM IS LESS
THAT THE PRESCRIBED MINIMUM EQUITY INVESTMENT REQUIRED FOR THE PROJECT. — 13. ID.;ID.;ID.;RESTRICTIVE AND CONSERVATIVE APPLICATION OF THE RULES
We agree with public respondents that with respect to Security Bank, the entire amount of AND PROCEDURE IS NECESSARY. — A restrictive and conservative application of the rules
its net worth could not be invested in a single undertaking or enterprise, whether allied or and procedures of public bidding is necessary not only to protect the impartiality and
non-allied in accordance with the provisions of R.A. No. 337, as amended or the General regularity of the proceedings but also to ensure the financial and technical reliability of the
Banking Act[.] . . . Thus, the maximum amount that Security Bank could validly invest in project. It has been held that: "The basic rule in public bidding is that bids should be
the Paircargo Consortium is only P528,525,656.55, representing 15% of its entire net evaluated based on the required documents submitted before and not after the opening of
worth. The total net worth therefore of the Paircargo Consortium, after considering bids. Otherwise, the foundation of a fair and competitive public bidding would be
the maximum amounts that may be validly invested by each of its members defeated. Strict observance of the rules, regulations, and guidelines of the bidding process
is P558,384,871.55 or only 6.08% of the project cost,an amount substantially less than the is the only safeguard to a fair, honest and competitive public bidding." ACIDSc
prescribed minimum equity investment required for the project in the amount of
P2,755,095,000.00 or 30% of the project cost. cHaADC 14. ID.;ID.;ID.;PURPOSE. — By its very nature, public bidding aims to protect the
public interest by giving the public the best possible advantages through open competition.
9. ID.;ID.;PUBLIC BIDDING; PRE-QUALIFICATION STAGE; GOVERNMENT Thus: "Competition must be legitimate, fair and honest. In the field of government contract
AGENCY MUST DETERMINE THE BIDDER'S FINANCIAL CAPACITY. — The purpose of pre- law, competition requires, not only bidding upon a common standard, a common basis,
qualification in any public bidding is to determine, at the earliest opportunity, the ability of upon the same thing, the same subject matter, the same undertaking,' but also that it be
the bidder to undertake the project. Thus, with respect to the bidder's financial capacity at legitimate, fair and honest; and not designed to injure or defraud the government."
the pre-qualification stage, the law requires the government agency to examine and
determine the ability of the bidder to fund the entire cost of the project by considering the 15. ID.;ID.;ID.;ALL BIDDERS MUST BE ON EQUAL FOOTING ON THE CONTRACT
maximum amounts that each bidder may invest in the project at the time of pre- RIDDED UPON. — An essential element of a publicly bidded contract is that all bidders must
qualification. be on equal footing. Not simply in terms of application of the procedural rules and
regulations imposed by the relevant government agency, but more importantly, on the
10. ID.;ID.;ID.;ID.;ID.;SHOULD DETERMINE THE MAXIMUM AMOUNT THAT EACH contract bidded upon. Each bidder must be able to bid on the same thing.The rationale is
MEMBER OF THE CONSORTIUM MAY COMMIT WITHOUT DISREGARDING THE INVESTMENT obvious. If the winning bidder is allowed to later include or modify certain provisions in the
CEILINGS PROVIDED BY APPLICABLE LAW. — The PBAC has determined that any contract awarded such that the contract is altered in any material respect, then the essence
of fair competition in the public bidding is destroyed. A public bidding would indeed be a because it grants PIATCO a financial advantage or benefit which was not previously made
farce if after the contract is awarded, the winning bidder may modify the contract and available during the bidding process.This financial advantage is a significant modification
include provisions which are favorable to it that were not previously made available to the that translates to better terms and conditions for PIATCO.
other bidders.
19. ID.;ID.;ID.;ID.;SHOULD ALWAYS CONFORM TO THE GENERAL PUBLIC
16. ID.;ID.;ID.;AMENDMENTS TO CONTRACT BIDDED; WINNING BIDDER IS NOT POLICY. — [T]his Court maintains that amendments to the contract bidded upon should
PRECLUDED FROM MODIFYING OR AMENDING CERTAIN PROVISIONS OF THE CONTRACT always conform to the general policy on public bidding if such procedure is to be faithful to
THAT DOES NOT CONSTITUTE SUBSTANTIAL OR MATERIAL AMENDMENTS. — While we its real nature and purpose. By its very nature and characteristic, competitive public bidding
concede that a winning bidder is not precluded from modifying or amending certain aims to protect the public interest by giving the public the best possible advantages through
provisions of the contract bidded upon, such changes must not constitute substantial or open competition. It has been held that the three principles in public bidding are (1) the
material amendments that would alter the basic parameters of the contract and would offer to the public; (2) opportunity for competition; and (3) a basis for the exact comparison
constitute a denial to the other bidders of the opportunity to bid on the same terms.Hence, of bids. A regulation of the matter which excludes any of these factors destroys the
the determination of whether or not a modification or amendment of a contract bidded out distinctive character of the system and thwarts the purpose of its adoption. These are the
constitutes a substantial amendment rests on whether the contract, when taken as a whole, basic parameters which every awardee of a contract bidded out must conform to,
would contain substantially different terms and conditions that would have the effect of requirements of financing and borrowing notwithstanding. Thus, upon a concrete showing
altering the technical and/or financial proposals previously submitted by other bidders. The that, as in this case, the contract signed by the government and the contract awardee is
alterations and modifications in the contract executed between the government and the an entirely different contract from the contract bidded, courts should not hesitate to strike
winning bidder must be such as to render such executed contract to be an entirely different down said contract in its entirety for violation of public policy on public bidding. A strict
contract from the one that was bidded upon. adherence on the principles, rules and regulations on public bidding must be sustained if
only to preserve the integrity and the faith of the general public on the procedure.
17. ID.;ID.;ID.;ID.;SIGNIFICANT AMENDMENTS IN THE PIATCO'S DRAFT
CONCESSION AGREEMENT; TYPES OF FEES THAT MAY BE IMPOSED AND COLLECTED BY 20. ID.;ID.;ID.;ID.;ANY GOVERNMENT ACTION WHICH PERMITS ANY
PIATCO. — When taken as a whole, the changes under the 1997 Concession Agreement SUBSTANTIAL VARIANCE THEREOF IS A GRAVE ABUSE OF DISCRETION. — Public bidding
with respect to reduction in the types of fees that are subject to MIAA regulation and the is a standard practice for procuring government contracts for public service and for
relaxation of such regulation with respect to other fees are significant amendments that furnishing supplies and other materials. It aims to secure for the government the lowest
substantially distinguish the draft Concession Agreement from the 1997 Concession possible price under the most favorable terms and conditions, to curtail favoritism in the
Agreement. The 1997 Concession Agreement, in this respect, clearly gives PIATCO more award of government contracts and avoid suspicion of anomalies and it places all bidders
favorable terms than what was available to other bidders at the time the contract was in equal footing. Any government action which permits any substantial variance between
bidded out.It is not very difficult to see that the changes in the 1997 Concession Agreement the conditions under which the bids are invited and the contract executed after the award
translate to direct and concrete financial advantages for PIATCO which were not available thereof is a grave abuse of discretion amounting to lack or excess of jurisdiction which
at the time the contract was offered for bidding. It cannot be denied that under the 1997 warrants proper judicial action. CaHcET
Concession Agreement only "Public Utility Revenues" are subject to MIAA regulation.
Adjustments of all other fees imposed and collected by PIATCO are entirely within its 21. ID.;ID.;ID.;ID.;DIRECTLY TRANSLATES CONCRETE FINANCIAL ADVANTAGES
control.Moreover, with respect to terminal fees, under the 1997 Concession Agreement, TO PIATCO THAT WERE PREVIOUSLY NOT AVAILABLE DURING THE BIDDING PROCESS. —
the same is further subject to "Interim Adjustments" not previously stipulated in the draft The fact that the ...substantial amendments were made on the 1997 Concession
Concession Agreement. Finally, the change in the currency stipulated for "Public Utility Agreement renders the same null and void for being contrary to public policy.These
Revenues" under the 1997 Concession Agreement, except terminal fees, gives PIATCO an amendments convert the 1997 Concession Agreement to an entirely different
added benefit which was not available at the time of bidding. acHCSD agreement from the contract bidded out or the draft Concession Agreement. It is not
difficult to see that the amendments on (1) the types of fees or charges that are subject to
18. ID.;ID.;ID.;ID.;ID.;ASSUMPTION BY THE GOVERNMENT OF THE LIABILITIES MIAA regulation or control and the extent thereof and (2) the assumption by the
OF PIATCO IN THE EVENT OF THE LATTER'S DEFAULT TRANSLATES BETTER TERMS AND Government, under certain conditions, of the liabilities of PIATCO directly translates
CONDITION FOR PIATCO. — Under the draft Concession Agreement,default by PIATCO of concrete financial advantages to PIATCO that were previously not available during the
any of its obligations to creditors who have provided, loaned or advanced funds for the bidding process.These amendments cannot be taken as merely supplements to or
NAIA IPT III project does not result in the assumption by the Government of these liabilities. implementing provisions of those already existing in the draft Concession Agreement. The
In fact, nowhere in the said contract does default of PIATCO's loans figure in the agreement. amendments discussed above present new terms and conditions which provide financial
Such default does not directly result in any concomitant right or obligation in favor of the benefit to PIATCO which may have altered the technical and financial parameters of other
Government. However, the 1997 Concession Agreement ...[u]nder ...Section 4.04 in bidders had they known that such terms were available.
relation to the definition of "Attendant Liabilities," default by PIATCO of its loans used to
finance the NAIA IPT III project triggers the occurrence of certain events that leads to the 22. ID.; ID.; BOT LAW; PURPOSE. — One of the main impetus for the enactment
assumption by the Government of the liability for the loans.Only in one instance may the of the BOT Law is the lack of government funds to construct the infrastructure and
Government escape the assumption of PIATCO's liabilities, i.e.,when the Government so development projects necessary for economic growth and development. This is why private
elects and allows a qualified operator to take over as Concessionaire. However, this sector resources are being tapped in order to finance these projects. The BOT law allows
circumstance is dependent on the existence and availability of a qualified operator who is the private sector to participate, and is in fact encouraged to do so by way of incentives,
willing to take over the rights and obligations of PIATCO under the contract, a circumstance such as minimizing, the unstable flow of returns, provided that the government would not
that is not entirely within the control of the Government.Without going into the validity of have to unnecessarily expend scarcely available funds for the project itself. As such, direct
this provision at this juncture, suffice it to state that Section 4.04 of the 1997 Concession guarantee, subsidy and equity by the government in these projects are strictly
Agreement may be considered a form of security for the loans PIATCO has obtained to prohibited. This is but logical for if the government would in the end still be at a risk of
finance the project, an option that was not made available in the draft Concession paying the debts incurred by the private entity in the BOT projects, then the purpose of the
Agreement. Section 4.04 is an important amendment to the 1997 Concession Agreement law is subverted.
23. ID.; ID.; ID.; CONDITIONS FOR THE ACCEPTANCE OF THE UNSOLICITED for the use of the said business and its properties as the temporary takeover by the
PROPOSAL FOR A BOT PROJECT. — The BOT Law and its implementing rules provide that government is in exercise of its police power and not of its power of eminent domain.
in order for an unsolicited proposal for a BOT project may be accepted, the following
conditions must first be met: (1) the project involves a new concept in technology and/or 27. ID.;ID.;ID.;ID.;ID.;CANNOT BE CONTRAVENED BY MERE CONTRACTUAL
is not part of the list of priority projects, (2) no direct government guarantee, subsidy or STIPULATION. — PIATCO cannot, by mere contractual stipulation, contravene the
equity is required,and (3) the government agency or local government unit has invited by Constitutional provision on temporary government takeover and obligate the government
publication other interested parties to a public bidding and conducted the same. The failure to pay "reasonable cost for the use of the Terminal and/or Terminal Complex." Article XII,
to meet any of the above conditions will result in the denial of the proposal. Section 17 of the 1987 Constitution envisions a situation wherein the exigencies of the
times necessitate the government to "temporarily take over or direct the operation of any
24. ID.; ID.; ID.; STRICTLY PROHIBITS DIRECT GOVERNMENT GUARANTEE, privately owned public utility or business affected with public interest." It is the welfare and
SUBSIDY AND EQUITY IN UNSOLICITED PROPOSAL. — It is further provided that the interest of the public which is the paramount consideration in determining whether or not
presence of direct government guarantee, subsidy or equity will "necessarily, disqualify a to temporarily take over a particular business. Clearly, the State in effecting the temporary
proposal from being treated and accepted as an unsolicited proposal." TheBOT Law clearly takeover is exercising its police power. Police power is the "most essential, insistent, and
and strictly prohibits direct government guarantee, subsidy and equity in unsolicited illimitable of powers." Its exercise therefore must not be unreasonably hampered nor its
proposals that the mere inclusion of a provision to that effect is fatal and is sufficient to exercise be a source of obligation by the government in the absence of damage due to
deny the proposal. It stands to reason therefore that if a proposal can be denied by reason arbitrariness of its exercise. Thus, requiring the government to pay reasonable
of the existence of direct government guarantee, then its inclusion in the contract executed compensation for the reasonable use of the property pursuant to the operation of the
after the said proposal has been accepted is likewise sufficient to invalidate the contract business contravenes the Constitution.
itself. A prohibited provision, the inclusion of which would result in the denial of a proposal
cannot, and should not, be allowed to later on be inserted in the contract resulting from 28. ID.; ID.; NATIONAL ECONOMY AND PATRIMONY; CONSTITUTION STRICTLY
the said proposal. The basic rules of justice and fair play alone militate against such an REGULATES MONOPOLIES. — A monopoly is "a privilege or peculiar advantage vested in
occurrence and must not, therefore, be countenanced particularly in this instance where one or more persons or companies, consisting in the exclusive right (or power) to carry on
the government is exposed to the risk of shouldering hundreds of million of dollars in a particular business or trade, manufacture a particular article, or control the sale of a
debt. CSDcTA particular commodity." The 1987 Constitution strictly regulates monopolies,whether private
or public, and even provides for their prohibition if public interest so requires. ...Clearly,
25. ID.;ID.;ID.;ID.;VIOLATED IN CASE AT BAR. — The proscription against monopolies are not per se prohibited by the Constitution but may be permitted to exist to
government guarantee in any form is one of the policy considerations behind the BOT aid the government in carrying on an enterprise or to aid in the performance of various
Law.Clearly, in the present case, the ARCA obligates the Government to pay for all loans, services and functions in the interest of the public.Nonetheless, a determination must first
advances and obligations arising out of financial facilities extended to PIATCO for the be made as to whether public interest requires a monopoly. As monopolies are subject to
implementation of the NAIA IPT III project should PIATCO default in its loan obligations to abuses that can inflict severe prejudice to the public, they are subject to a higher level of
its Senior Lenders and the latter fails to appoint a qualified nominee or transferee. This in State regulation than an ordinary business undertaking. ETHIDa
effect would make the Government liable for PIATCO's loans should the conditions as set
forth in the ARCA arise. This is a form of direct government guarantee. ...This Court has 29. ID.;ID.;ID.;ID.;PRIVILEGE GIVEN TO PIATCO SHOULD BE SUBJECT TO
long and consistently adhered to the legal maxim that those that cannot be done directly REASONABLE REGULATION AND SUPERVISION BY THE GOVERNMENT. — The operation of
cannot be done indirectly. To declare the PIATCO contracts valid despite the clear statutory an international passenger airport terminal is no doubt an undertaking imbued with public
prohibition against a direct government guarantee would not only make a mockery of what interest. In entering into a Build-Operate-and-Transfer contract for the construction,
the BOT Law seeks to prevent — which is to expose the government to the risk of incurring operation and maintenance of NAIA IPT III, the government has determined that public
a monetary obligation resulting from a contract of loan between the project proponent and interest would be served better if private sector resources were used in its construction and
its lenders and to which the Government is not a party to — but would also render the BOT an exclusive right to operate be granted to the private entity undertaking the said project,
Law useless for what it seeks to achieve — to make use of the resources of the private in this case PIATCO. Nonetheless, the privilege given to PIATCO is subject to reasonable
sector in the "financing, operation and maintenance of infrastructure and development regulation and supervision by the Government through the MIAA, which is the government
projects" which are necessary for national growth and development but which the agency authorized to operate the NAIA complex, as well as DOTC, the department to which
government, unfortunately, could ill-afford to finance at this point in time. MIAA is attached. This is in accord with the Constitutional mandate that a monopoly which
is not prohibited must be regulated.
26. ID.; CONSTITUTIONAL LAW; POLICE POWER; TEMPORARY TAKEOVER OF
BUSINESS AFFECTED WITH PUBLIC INTEREST; GOVERNMENT IS NOT REQUIRED TO 30. ID.; ID.; ID.; ID.; OPERATION OF PUBLIC UTILITY CANNOT BE DONE IN AN
COMPENSATE THE PRIVATE ENTITY-OWNER. — Article XII, Section 17 of the 1987 ARBITRARY MANNER TO THE DETRIMENT OF THE PUBLIC. — While it is the declared policy
Constitution . . . pertains to the right of the State in times of national emergency, and in of the BOT Law to encourage private sector participation by "providing a climate of
the exercise of its police power, to temporarily take over the operation of any business minimum government regulations," the same does not mean that Government must
affected with public interest. In the 1986 Constitutional Commission, the term "national completely surrender its sovereign power to protect public interest in the operation of a
emergency" was defined to include threat from external aggression, calamities or national public utility as a monopoly. The operation of said public utility can not be done in an
disasters, but not strikes "unless it is of such proportion that would paralyze government arbitrary manner to the detriment of the public which it seeks to serve. The right granted
service." The duration of the emergency itself is the determining factor as to how long the to the public utility may be exclusive but the exercise of the right cannot run riot. Thus,
temporary takeover by the government would last. The temporary takeover by the while PIATCO may be authorized to exclusively operate NAIA IPT III as an international
government extends only to the operation of the business and not to the ownership thereof. passenger terminal, the Government, through the MIAA, has the right and the duty to
As such the government is not required to compensate the private entity-owner of the said ensure that it is done in accord with public interest. PIATCO's right to operate NAIA IPT III
business as there is no transfer of ownership,whether permanent or temporary. The private cannot also violate the rights of third parties.
entity-owner affected by the temporary takeover cannot, likewise, claim just compensation
31. ID.;ID.;BILL OF RIGHTS NON-IMPAIRMENT OF OBLIGATIONS OF CONTRACT;
PIATCO, BY CLAIMING AN EXCLUSIVE RIGHT TO OPERATE, CANNOT REQUIRE THE
GOVERNMENT TO BREAK ITS CONTRACTUAL OBLIGATIONS TO THE SERVICE PROVIDERS. 4. ID.;ID.;LOCUS STANDI; CITIZEN, TAXPAYER AND MEMBERS OF THE HOUSE
— We hold that while the service providers presently operating at NAIA Terminal 1 do not OF REPRESENTATIVES ARE SUFFICIENTLY CLOTHED WITH STANDING TO BRING SUIT
have an absolute right for the renewal or the extension of their respective contracts, those QUESTIONING THE VALIDITY OF CONTRACT AFFECTING PUBLIC INTEREST. — Given this
contracts whose duration extends beyond NAIA IPT III's In-Service-Date should not be Court's previous decisions in cases of similar import, no one will seriously doubt that, being
unduly prejudiced. These contracts must be respected not just by the parties thereto but taxpayers and members of the House of Representatives, Petitioners Baterina et
also by third parties. PIATCO cannot, by law and certainly not by contract, render a valid al.have locus standi to bring the Petition in GR No. 155547. In Albano v. Reyes,this Court
and binding contract nugatory. PIATCO, by the mere expedient of claiming an exclusive held that the petitioner therein, suing as a citizen, taxpayer and member of the House of
right to operate, cannot require the Government to break its contractual obligations to the Representatives, was sufficiently clothed with standing to bring the suit questioning the
service providers. In contrast to the arrastre and stevedoring service providers in the case validity of the assailed contract. The Court cited the fact that public interest was involved,
of Anglo-Fil Trading Corporation v. Lazaro whose contracts consist of temporary hold-over in view of the important role of the Manila International Container Terminal (MICT) in the
permits, the affected service providers in the cases at bar, have a valid and binding contract country's economic development and the magnitude of the financial consideration. This,
with the Government, through MIAA, whose period of effectivity, as well as the other terms notwithstanding the fact that expenditure of public funds was not required under the
and conditions thereof cannot be violated. assailed contract. CcEHaI

32. ID.;ID.;ID.;ID.;MIAA SHOULD ENSURE THAT WHOEVER BY CONTRACT IS 5. ID.;ID.;ID.;MEMBERS OF HOUSE OF REPRESENTATIVES ARE DEPRIVED OF
GIVEN THE RIGHT TO OPERATE NAIA IPT III WILL DO SO WITHIN THE BOUNDS OF THE DISCRETION; CASE AT BAR. — In the cases presently under consideration, petitioners'
LAW. — In fine, the efficient functioning of NAIA IPT III is imbued with public interest. The personal and substantial interest in the controversy is shown by the fact that certain
provisions of the 1997 Concession Agreement and the ARCA did not strip government, thru provisions in the Piatco contracts create obligations on the part of government (through the
the MIAA, of its right to supervise the operation of the whole NAIA complex, including NAIA DOTC and the MIAA) to disburse public funds without prior congressional appropriations.
IPT III. As the primary government agency tasked with the job, it is MIAA's responsibility Petitioners thus correctly assert that the injury to them has a twofold aspect: (1) they are
to ensure that whoever by contract is given the right to operate NAIA IPT III will do so adversely affected as taxpayers on account of the illegal disbursement of public funds; and
within the bounds of the law and with due regard to the rights of third parties and above (2) they are prejudiced qualegislators, since the contractual provisions requiring the
all, the interest of the public. TSHIDa government to incur expenditures without appropriations also operate as limitations upon
the exclusive power and prerogative of Congress over the public purse. As members of the
PANGANIBAN,J.,separate opinion: House of Representatives, they are actually deprived of discretion insofar as the inclusion
of those items of expenditure in the budget is concerned. To prevent such encroachment
1. REMEDIAL LAW; SPECIAL CIVIL ACTION; PROHIBITION; DIRECT RESORT TO upon the legislative privilege and obviate injury to the institution of which they are
THE SUPREME COURT BY THE EMPLOYEES WHO FEARED LOSS OF THEIR JOBS IS members, petitioners-legislators have locus standi to bring suit.
JUSTIFIED. — The Court has, in the past, held that questions relating to gargantuan
government contracts ought to be settled without delay. This holding applies with greater 6. ID.;ID.;ID.;EMPLOYEES ARE CONFRONTED WITH THE PROSPECT OF BEING
force to the instant cases. Respondent Piatco is partly correct in averring that petitioners LAID OFF FROM THEIR JOBS. — Messrs. Agan et al.and Lopez et al.,are likewise taxpayers
can obtain relief from the regional trial courts via an action to annul the contracts. and thus possessed of standing to challenge the illegal disbursement of public funds.
Nevertheless, the unavoidable consequence of having to await the rendition and the finality Messrs. Agan et al.,in particular, are employees (or representatives of employees) of
of any such judgment would be a prolonged state of uncertainty that would be prejudicial various service providers that have (1) existing concession agreements with the MIAA to
to the nation, the parties and the general public. And, in light of the feared loss of jobs of provide airport services necessary to the operation of the NAIA and (2) service agreements
the petitioning workers, consequent to the inevitable pretermination of contracts of the to furnish essential support services to the international airlines operating at the NAIA.
petitioning service providers that will follow upon the heels of the impending opening of Messrs. Lopez et al.are employees of the MIAA. These petitioners (Messrs. Agan et al.and
NAIA Terminal III, the need for relief is patently urgent, and therefore, direct resort to this Messrs. Lopez et al.) are confronted with the prospect of being laid off from their jobs and
Court through the special civil action of prohibition is thus justified. losing their means of livelihood when their employer-companies are forced to shut down or
otherwise retrench and cut back on manpower. Such development would result from the
2. ID.; ID.; ID.; DISPOSITION THEREOF ULTIMATELY RUNS ON QUESTIONS OF imminent implementation of certain provisions in the contracts that tend toward the
LAW; CASE AT BAR. — Contrary to Piatco's argument that the resolution of the issues raised creation of a monopoly in favor of Piatco, its subsidiaries and related companies.
in the Petitions will require delving into factual questions, I submit that their disposition
ultimately turns on questions of law. Further, many of the significant and relevant factual 7. ID.;ID.;ID.;SERVICE PROVIDERS CLAIM TO BE DEPRIVED OF THEIR PROPERTY
questions can be easily addressed by an examination of the documents submitted by the AND OF THE LIBERTY TO CONTRACT WITHOUT DUE PROCESS OF LAW. — Petitioners-in-
parties. In any event, the Petitions raise some novel questions involving the application of intervention are service providers in the business of furnishing airport-related services to
the amended BOT Law, which this Court has seen fit to tackle. international airlines and passengers in the NAIA and are therefore competitors of Piatco
as far as that line of business is concerned. On account of provisions in the Piatco contracts,
3. ID.;CIVIL PROCEDURE; ARBITRATION PROCEEDINGS; CANNOT ADDRESS, petitioners-in-intervention have to enter into a written contract with Piatco so as not to be
DETERMINE AND DEFINITIVELY RESOLVE THE CONSTITUTIONAL AND LEGAL QUESTIONS. shut out of NAIA Terminal III and barred from doing business there. Since there is no
— As will be discussed at length later, the Piatco contracts are indeed void in their entirety; provision to ensure or safeguard free and fair competition, they are literally at its mercy.
thus, a resort to the aforesaid provision on arbitration is unavailing. Besides, petitioners They claim injury on account of their deprivation of property (business) and of the liberty
and petitioners-in-intervention have pointed out that, even granting arguendo that the to contract, without due process of law.
arbitration clause remained a valid provision, it still cannot bind them inasmuch as they are
not parties to the Piatco contracts. And in the final analysis, it is unarguable that the 8. ID.;ID.;ID.;IN CASES OF TRANSCENDENTAL IMPORTANCE, THE SUPREME
arbitration process provided for under Section 10.02 of the Amended and Restated COURT MAY RELAX THE STANDING REQUIREMENTS AND ALLOW A SUIT TO PROSPER. —
Concession Agreement (ARCA),to be undertaken by a panel of three (3) arbitrators And even if petitioners and petitioners-in-intervention were not sufficiently clothed with
appointed in accordance with the Rules of Arbitration of the International Chamber of legal standing, I have at the outset already established that, given its impact on the public
Commerce, will not be able to address, determine and definitively resolve the constitutional and on national interest, this controversy is laden with transcendental importance and
and legal questions that have been raised in the Petitions before us.
constitutional significance. Hence, I do not hesitate to adopt the same position as was and a basis for the precise comparison of bids. Thus, each bidder must bid under the same
enunciated in Kilosbayan v. Guingona Jr. that "in cases of transcendental importance, the conditions; and be subject to the same guidelines, requirements and limitations. The
Court may relax the standing requirements and allow a suit to prosper even when there is desired result is to be able to determine the best offer or lowest bid, all things being equal.
no direct injury to the party claiming the right of judicial review."
15. ID.;ID.;ID.;ID.;SINCE THE ENTIRE BIDDING PROCESS WAS FLAWED. AND
9. POLITICAL LAW; ADMINISTRATIVE LAW; REPUBLIC ACT NO. 6957 (BUILD- TAINTED FROM THE VERY OUTSET, THE AWARD OF CONCESSION WAS VOID. — Inasmuch
OPERATE-AND TRANSFER or BOT LAW); PUBLIC BIDDING; BIDDER MUST SATISFY THE as the Paircargo consortium did not possess the minimum equity equivalent to 30 percent
MINIMUM REQUIREMENTS AND MEET THE TECHNICAL, FINANCIAL, ORGANIZATIONAL AND of the minimum project cost, it should not have been prequalified or allowed to participate
LEGAL STANDARDS. — I must emphasize that the law requires the award of a BOT project further in the bidding. The Prequalification and Bidding Committee (PBAC) should therefore
to the bidder that has satisfied the minimum requirements; and met the technical, financial, not have opened the two envelopes of the consortium containing its technical and financial
organizational and legal standards provided in the BOT Law. DAHaTc proposals; required AEDC to match the consortium's bid; or awarded the Concession
Agreement to the consortium's successor-in-interest, Piatco. As there was effectively no
10. ID.;ID.;ID.;ID.;MUST BE CONDUCTED UNDER A TWO-STAGE SYSTEM. — public bidding to speak of, the entire bidding process having been flawed and tainted from
Section 5 of this statute requires that the price challenge via public bidding "must be the very outset, therefore, the award of the concession to Paircargo's successor Piatco was
conducted under a two-envelope/two-stage system: the first envelope to contain the void, and the Concession Agreement executed with the latter was likewise void ab initio.For
technical proposal and the second envelope to contain the financial proposal." Moreover, this reason, Piatco cannot and should not be allowed to benefit from that
the 1994 Implementing Rules and Regulations (IRR) provide that only those bidders that Agreement. ICDcEA
have passed the prequalification stage are permitted to have their two envelopes reviewed.
In other words, prospective bidders must prequalify by submitting their prequalification 16. ID.;ID.;ID.;ID.;PROTECTION OF THE PROPRIETARY INFORMATION IS
documents for evaluation; and only the pre-qualified bidders would be entitled to have their APPLICABLE TO THE ORIGINATOR OF THE UNSOLICITED PROPOSAL ONLY. — The
bids opened, evaluated and appreciated. On the other hand, disqualified bidders are to be "proprietary information" referred to in Section 11.6 of the IRR pertains only to the
informed of the reason for their disqualification. This procedure was confirmed and proprietary information of the originator of an unsolicited proposal, and not to those
reiterated in the Bid Documents, which I quote thus: "Prequalified proponents will be belonging to a challenger. The reason for the protection accorded proprietary information
considered eligible to move to second stage technical proposal evaluation. The second and at all is the fact that, according to Section 4-A of the BOT Law as amended, a proposal
third envelopes of pre-disqualified proponents will be returned." qualifies as an "unsolicited proposal" when it pertains to a project that involves "a new
concept or technology," and/or a project that is not on the government's list of priority
11. ID.;ID.;ID.;ID.;PROPONENT MUST PROVE THAT IT IS ABLE TO RAISE THE projects.
MINIMUM AMOUNT REQUIRED FOR THE PROJECT. — Aside from complying with the legal
and technical requirements (track record or experience of the firm and its key personnel),a 17. ID.; ID.; ID.; ID.; ID.; RATIONALE. — To be considered as utilizing a new
project proponent desiring to prequalify must also demonstrate its financial capacity to concept or technology, a project must involve the possession of exclusive rights (worldwide
undertake the projects. To establish such capability, a proponent must prove that it is able or regional) over a process; or possession of intellectual property rights over a design,
to raise the minimum amount of equity required for the project and to procure the loans or methodology or engineering concept. Patently, the intent of the BOT Law is to encourage
financing needed for it. Since the minimum amount of equity for the project was set at 30 individuals and groups to come up with creative innovations, fresh ideas and new
percent of the minimum project cost of US$350 million, the minimum amount of equity technology. Hence, the significance and necessity of protecting proprietary information in
required of any proponent stood at US$105 million. Converted to pesos at the exchange connection with unsolicited proposals. And to make the encouragement real, the law also
rate then of P26.239 to US$1.00 (as quoted by the Bangko Sentral ng Pilipinas),the peso extends to such individuals and groups what amounts to a "right of first refusal" to
equivalent of the minimum equity was P2,755,095,000. undertake the project they conceptualized, involving the use of new technology or concepts,
through the mechanism of matching a price challenge.
12. ID.;ID.;ID.;ID.;ID.;NOT COMPLIED WITH IN CASE AT BAR. — However, the
combined equity or net worth of the Paircargo consortium stood at only P558,384,871.55. 18. ID.;ID.;ID.;ID.;BIDDER MUST BE GIVEN ACCESS TO THE ASSUMPTION AND
This amount was only slightly over 6 percent of the minimum project cost and very much THE CALCULATIONS THAT WENT INTO CRAFTING THE COMPETING BID. — A competing
short of the required minimum equity, which was equivalent to 30 percent of the project bid is never just any figure conjured from out of the blue; it is arrived at after studying
cost. Such deficiency should have immediately caused the disqualification of the Paircargo economic, financial, technical and other factors; it is likewise based on certain assumptions
consortium. as to the nature of the business, the market potentials, the probable demand for the product
or service, the future behavior of cost items, political and other risks, and so on. It is thus
13. ID.; ID.; ID.; ID.; RULES, REGULATIONS AND GUIDELINES MUST BE self-evident that in order to be able to intelligently match a bid or price challenge, a bidder
STRICTLY APPLIED; VIOLATED IN CASE AT BAR. — By virtue of the prequalified status must be given access to the assumptions and the calculations that went into crafting the
conferred upon the Paircargo, Undersecretary Cal's findings in effect relieved the competing bid. In this instance, the financial and technical proposals of Piatco would have
consortium of the need to comply with the financial capability requirement imposed by provided AEDC with the necessary information to enable it to make a reasonably informed
the BOT Law and IRR. This position is unmistakably and squarely at odds with the Supreme matching bid. To put it more simply, a bidder unable to access the competitor's assumptions
Court's consistent doctrine emphasizing the strict application of pertinent rules, regulations will never figure out how the competing bid came about; requiring him to "counter-propose"
and guidelines for the public bidding process, in order to place each bidder — actual or is like having him shoot at a target in the dark while blindfolded.
potential — on the same footing. Thus, it is unarguably irregular and contrary to the very
concept of public bidding to permit a variance between the conditions under which bids are 19. ID.;ID.;ID.;DEFINITE AND FIRM TIMETABLE FOR THE SUBMISSION OF THE
invited and those under which proposals are submitted and approved. REQUIREMENTS TO EXPOSE AND WEED OUT UNQUALIFIED PROPONENTS. — The purpose
of having a definite and firm timetable for the submission of the requirements is not only
14. ID.;ID.;ID.;ID.;ESSENCE. — Republic v. Capulong teaches that if one bidder to prevent delays in the project implementation, but also to expose and weed out
is relieved from having to conform to the conditions that impose some duty upon it, that unqualified proponents, who might have unceremoniously slipped through the earlier
bidder is not contracting in fair competition with those bidders that propose to be bound by prequalification process, by compelling them to put their money where their mouths are,
all conditions. The essence of public bidding is, after all, an opportunity for fair competition so to speak.
20. ID.;ID.;ID.;ID.;EASILY CIRCUMVENTED BY MERELY POSTPONING THE is violative of public policy on public biddings, as well as the spirit and intent of the BOT
ACTUAL ISSUANCE OF THE NOTICE OF AWARD. — Nevertheless, this provision can be easily Law. The whole point of going through the public bidding exercise was completely lost. Its
circumvented by merely postponing the actual issuance of the Notice of Award, in order to very rationale was totally subverted by permitting Piatco to amend the contract for which
give the favored proponent sufficient time to comply with the requirements. Hence, to aver public bidding had already been concluded. Competitive bidding aims to obtain the best
or minimize the manipulation of the post-bidding process, the IRR not only set out the deal possible by fostering transparency and preventing favoritism, collusion and fraud in
precise sequence of events occurring between the completion of the evaluation of the the awarding of contracts.That is the reason why procedural rules pertaining to public
technical bids and the issuance of the Notice of Award, but also specified the timetables for bidding demand strict observance.
each such event. Definite allowable extensions of time were provided for, as were the
consequences of a failure to meet a particular deadline. 25. ID.;ID.;ID.;SUBSTANTIVE AMENDMENTS TO A CONTRACT FOR WHICH A
PUBLIC BIDDING HAS ALREADY BEEN FINISHED SHOULD ONLY BE AWARDED AFTER
21. ID.;ID.;ID.;ID.;TO DISCOURAGE COLLUSION AND REDUCE THE ANOTHER PUBLIC BIDDING. — In a relatively early case, Caltex v. Delgado Brothers,this
OPPORTUNITY FOR AGENTS OF GOVERNMENT TO ABUSE THEIR DISCRETION. — The highly Court made it clear that substantive amendments to a contract for which a public bidding
regulated time-frames within which the agents of government were to act evinced the intent has already been finished should only be awarded after another public bidding: "The due
to impose upon them the duty to act expeditiously throughout the process, to the end that execution of a contract after public bidding is a limitation upon the right of the contracting
the project be prosecuted and implemented without delay. This regulated scenario was parties to alter or amend it without another public bidding, for otherwise what would a
likewise intended to discourage collusion and substantially reduce the opportunity for public bidding be good for if after the execution of a contract after public bidding, the
agents of government to abuse their discretion in the course of the award process. DcTSHa contracting parties may alter or amend the contract, or even cancel it, at their will? Public
biddings are held for the protection of the public, and to give the public the best possible
22. ID.;ID.;ID.;PROCEDURE FOR THE AWARD OF THE PROJECTS. — In particular, advantages by means of open competition between the bidders. He who bids or offers the
Section 9.1 of the 1994 IRR prescribed that within 30 calendar days from the time the best terms is awarded the contract subject of the bid, and it is obvious that such protection
second-stage evaluation shall have been completed, the Committee must come to a and best possible advantages to the public will disappear if the parties to a contract
decision whether or not to award the contract and, within 7 days therefrom, the Notice of executed after public bidding may alter or amend it without another previous public
Award must be approved by the head of agency or local government unit (LGU) concerned, bidding." EaIcAS
and its issuance must follow within another 7 days thereafter. Section 9.2 of the IRR set
the procedure applicable to projects involving substantial government undertakings as 26. ID.; ID.; ID.; TERMS, CONDITIONS AND STIPULATIONS OF THE CONTRACTS
follows: Within 7 days after the decision to award is made, the draft contract shall be MUST REMAIN INTACT AND NOT BE SUBJECT TO FURTHER NEGOTIATION. — TheBOT
submitted to the ICC for clearance on a no-objection basis. If the draft contract includes Law cannot be said to allow the negotiation of contractual stipulations resulting in a
government undertakings already previously approved, then the submission shall be for substantially new contract after the bidding process and price challenge had been
information only. However, should there be additional or new provisions different from the concluded. In fact, the BOT Law, in recognition of the time, money and effort invested in
original government undertakings, the draft shall have to be reviewed and approved. The an unsolicited proposal, accords its originator the privilege of matching the challenger's bid.
ICC has 15 working days to act thereon, and unless otherwise specified, its failure to act Section 4-A of the BOT Law specifically refers to a "lower price proposal" by a competing
on the contract within the specified time frame signifies that the agency or LGU may bidder; and to the right of the original proponent "to match the price" of the challenger.
proceed with the award. The head of agency or LGU shall approve the Notice of Award Thus, only the price proposals are in play. The terms, conditions and stipulations in the
within seven days of the clearance by the ICC on a no-objection basis, and the Notice itself contract for which public bidding has been concluded are understood to remain intact and
has to be issued within seven days thereafter. not be subject to further negotiation.Otherwise, the very essence of public bidding will be
destroyed — there will no basis for an exact comparison between bids. Moreover, Piatco
23. ID.;ID.;ID.;VIOLATED IN CASE AT BAR. — Despite the clear timetables set misinterpreted the meaning behind PBAC Bid Bulletin No. 3. The phrase amendments
out in the IRR, several lengthy and still-unexplained delays occurred in the award process, ...from time to timerefers only to those amendments to the draft concession agreement
as can be observed from the presentation made by the counsel for public respondents. issued by the PBAC prior to the submission of the price challenge; it certainly does not
[T]he chronology of events bespeaks an unmistakable disregard, if not disdain, by the include or permit amendments negotiated for and introduced after the bidding process, has
persons in charge of the award process for the time limitations prescribed by the IRR. Their been terminated.
attitude flies in the face of this Court's solemn pronouncement in Republic v. Capulong that
"strict observance of the rules, regulations and guidelines of the bidding process is the only 27. ID.;ID.;ID.;REVISIONS AND AMENDMENTS IN THE CONTRACTS THAT GIVE
safeguard to a fair, honest and competitive public bidding." From the foregoing, the only UNDUE ADVANTAGE TO THE GOVERNMENT IS ILLEGAL. — In sum, the revisions and
conclusion that can possibly be drawn is that the BOT law and its IRR were repeatedly amendments as embodied in the ARCA constitute very material alterations of the terms and
violated with unmitigated impunity — and by agents of government, no less! On account of conditions of the CA, and give further manifestly undue advantage to Piatco at the expense
such violation, the award of the contract to Piatco, which undoubtedly gained time and of government.Piatco claims that the changes to the CA were necessitated by the demands
benefited from the delays, must be deemed null and void from the beginning. of its foreign lenders. However, no proof whatsoever has been adduced to buttress this
claim.In any event, it is quite patent that the sum total of the aforementioned changes
24. ID.;ID.;ID.;CHANGES TO THE CONTRACT BIDDED OUT RESULTED IN A resulted in drastically weakening the position of government to a degree that seems quite
SUBSTANTIALLY DIFFERENT CONTRACT. — After the PBAC made its decision on December excessive, even from the standpoint of a businessperson who regularly transacts with banks
11, 1996 to award the contract to Piatco, the latter negotiated changes to the Contract and foreign lenders, is familiar with their mind-set, and understands what motivates them.
bidded out and ended up with what amounts to a substantially new contract without any On the other hand, whatever it was that impelled government officials concerned to accede
public bidding.This Contract was subsequently further amended four more times through to those grossly disadvantageous changes, I can only hazard a guess. There is no question
negotiation and without any bidding. Thus, the contract actually executed between Piatco in my mind that the ARCA was unauthorized and illegal for lack of public bidding and for
and DOTC/MIAA on July 12, 1997 (the Concession Agreement or "CA") differed from the being patently disadvantageous to government.
contract bidded out[.] It goes without saying that the amendment of the Contract bidded
out (the DCA or draft concession agreement) — in such substantial manner, without any 28. ID.;ID.;ID.;FIRST SUPPLEMENT TO VOID AND INEXISTENT ORIGINAL
public bidding, and after the bidding process had been concluded on December 11, 1996 — CONCESSION AGREEMENT IS ALSO VOID AND INOPERATIVE; CASE AT BAR. — I must
emphasize that the First Supplement [FS] is void in two respects. First,it is merely an cajol or coerce the government into extending a guarantee of payment of the loan
amendment to the ARCA, upon which it is wholly dependent; therefore, since the ARCA is obligations, the risks assumed by the lenders are passed right back to government. I cannot
void, inexistent and not capable of being ratified or amended, it follows that the FS too is understand why, in the instant case, government cheerfully assented to re-assuming the
void, inexistent and inoperative. Second,even assuming arguendo that the ARCA is risks of the project when it gave the prohibited guarantee and thus simply negated the very
somehow remotely valid, nonetheless the FS, in imposing significant new obligations upon purpose of the BOT Law and the protection it gives the government.
government, altered the fundamental terms and stipulations of the ARCA, thus
necessitating a public bidding all over again. That the FS was entered into sans public 33. ID.;ID.;ID.;ID.;THE AMOUNT TO BE PAID BY GOVERNMENT IS GREATER OF
bidding renders it utterly void and inoperative. EITHER THE APPRAISED VALUE OF THE PROJECT OR THE AGGREGATE AMOUNT OF THE
MONEYS OWED BY PIATCO; CASE AT BAR. — Government's agreement to pay becomes
29. ID.;ID.;ID.;SECOND SUPPLEMENT IS ALSO VOID AND INOPERATIVE AS IT effective in the event of a default by Piatco on any of its loan obligations to the Senior
DID NOT UNDERGO ANY PUBLIC BIDDING. — The Second Supplement ("SS") was executed Lenders, and the amount to be paid by government is the greater of either the Appraised
between the government and Piatco on September 4, 2000. It calls for Piatco, acting not Value of Terminal III or the aggregate amount of the moneys owed by Piatco — whether to
as concessionaire of NAIA Terminal III but as a public works contractor, to undertake — in the Senior Lenders or to other entities, including its suppliers, contractors and
the government's stead — the clearing, removal, demolition and disposal of improvements, subcontractors. In effect, therefore, this agreement already constitutes the prohibited
subterranean obstructions and waste materials at the project site. The scope of the works, assumption by government of responsibility for repayment of Piatco's debts in case of a
the procedures involved, and the obligations of the contractor are provided for in Parts II loan default. In fine, a direct government guarantee. It matters not that there is a
and III of the SS. Section 4.1 sets out the compensation to be paid, listing specific rates roundabout procedure prescribed by Section 4.04(c)(iv),(v) and (vi) that would
per cubic meter of materials for each phase of the work — excavation, leveling, removal require, first,an attempt (albeit unsuccessful) by the Senior Lenders to transfer Piatco's
and disposal, backfilling and dewatering. The amounts collectible by Piatco are to be offset rights to a transferee of their choice; and, second,an effort (equally unsuccessful) to "enter
against the Annual Guaranteed Payments it must pay government. Though denominated into any other arrangement" with the government regarding the Terminal III facility, before
as Second Supplement, it was nothing less than an entirely new public works contract. Yet government is required to make good on its guarantee. What is abundantly clear is the fact
it, too, did not undergo any public bidding, for which reason it is also void and inoperative. that, in the devious labyrinthine process detailed in the aforesaid section, it is entirely within
Not surprisingly, Piatco had to subcontract the works to a certain Wintrack Builders, a firm the Senior Lenders' power, prerogative and control — exercisable via a mere refusal or
reputedly owned by a former high-ranking DOTC official. But that is another story inability to agree upon "a transferee" or "any other arrangement" regarding the terminal
altogether. AaSHED facility — to push the process forward to the ultimate contractual cul-de-sac,wherein
government will be compelled to abjectly surrender and make good on its guarantee of
30. ID.;ID.;ID.;THIRD SUPPLEMENT IS VOID AB INITIO AS IT CREATED A NEW payment.
MONETARY OBLIGATION ON THE PART OF THE GOVERNMENT WITHOUT PRIOR
APPROPRIATIONS. — The Third Supplement (TS) depends upon and is intended to 34. ID.;ID.;ID.;ID.;PIATCO CONTRACTS ARE GROSSLY LOPSIDED IN FAVOR OF
supplement the ARCA as well as the First Supplement, both of which are void and inexistent PIATCO AND/OR ITS SENIOR LENDERS. — Piatco also argues that there is
and not capable of being ratified or amended. It follows that the TS is likewise void, no provisorequiring government to pay the Senior Lenders in the event of Piatco's default.
inexistent and inoperative. And even if, hypothetically speaking, both ARCA and FS are This is literally true, in the sense that Section 4.04(c)(vi) of ARCA speaks of government
valid, still, the Third Supplement — imposing as it does significant new obligations upon making the termination payment to Piatco,not to the lenders. However, it is almost a
government — would in effect alter the terms and stipulations of the ARCA in material certainty that the Senior tenders will already have made Piatco sign over to them, ahead
respects, thus necessitating another public bidding. Since the TS was not subjected to public of time, its right to receive such payments from government; and/or they may already have
bidding, it is consequently utterly void as well. At any rate, the TS created new monetary had themselves appointed its attorneys-in-fact for the purpose of collecting and receiving
obligations on the part of government, for which there were no prior appropriations. Hence, such payments. Nevertheless, as petitioners-in-intervention pointed out in their
it follows that the same is, void ab initio. Memorandum, the termination payment is to be made to Piatco, not to the lenders; and
there is no provision anywhere in the contract documents to prevent it from diverting the
31. ID.; ID.; ID.; DIRECT GOVERNMENT GUARANTEE IS PROHIBITED IN proceeds to its own benefit and/or to ensure that it will necessarily use the same to pay off
UNSOLICITED PROPOSALS. — Section 4-A of the BOT Law as amended states the Senior Lenders and other creditors, in order to avert the foreclosure of the mortgage
thatunsolicited proposals,such as the NAIA Terminal III Project, may be accepted by and other liens on the terminal facility. Such deficiency puts the interests of government at
government provided inter alia that no direct government guarantee, subsidy or equity is great risk. Indeed, if the unthinkable were to happen, government would be paying several
required.In short, such guarantee is prohibited in unsolicited proposals. Section 2(n) of the hundreds of millions of dollars, but the mortgage liens on the facility may still be foreclosed
same legislation defines direct government guarantee as "an agreement whereby the by the Senior Lenders just the same.Consequently, the Piatco contracts are also
government or any of its agencies or local government units (will) assume responsibility objectionable for grievously failing to adequately protect government's interests. More
for the repayment of debt directly incurred by the project proponent in implementing the accurately, the contracts would consistently weaken and do away with protection of
project in case of a loan default." government interests. As such, they are therefore grossly lopsided in favor of Piatco and/or
its Senior Lenders. IAEcaH
32. ID.; ID.; ID.; ID.; REASON. — In the final analysis, Section 4.04(c)(iv) to (vi)
of the ARCA is diametrically at odds with the spirit and the intent of the BOT Law. The law 35. ID.;ID.;ID.;ID.;AMENDED AND RESTATED CONCESSION AGREEMENT (ARCA)
meant to mobilize private resources (the private sector) to take on the burden and the risks INTENDS TO HAVE ALL PIATCO'S DEBTS COVERED BY THE GUARANTEE. — While on this
of financing the construction, operation and maintenance of relevant infrastructure and subject, it is well to recall the earlier discussion regarding a particularly noticeable alteration
development projects for the simple reason that government is not in a position to do so. of the concept of "Attendant Liabilities." In Section 1.06 of the CA defining the term, the
By the same token, government guarantee was prohibited, since it would merely defeat the Piatco debts to be assumed/paid by government were qualified by the phrases recorded
purpose and raison d'être of a build-operate-and-transfer project to be undertaken by the and from time to time outstanding in the books of the Concessionaire and actually used for
private sector. To the extent that the project proponent is able to obtain loans to fund the the project.These phrases were eliminated from the ARCA's definition of Attendant
project, those risks are shared between the project proponent on the one hand, and its Liabilities. Since no explanation has been forthcoming from Piatco as to the possible
banks and other lenders on the other. But where the proponent or its lenders manage to justification for such a drastic change, the only conclusion possible is that it intends to
have all of its debts covered by the guarantee, regardless of whether or not they are over Piatco and to allocate its cash resources to the payment of all amounts owed to the
disclosed in its books. This has particular reference to those borrowings which were Senior Lenders before allowing any payment to be made to government. In brief, this
obtained in violation of the loan covenants requiring Piatco to maintain a minimum 70:30 particular provision of the ARCA has placed in the hands of foreign lenders the power and
debt-to-equity ratio, and even if the loan proceeds were not actually used for the project the authority to determine how much (if at all) and when the Philippine government (as
itself. This point brings us back to the guarantee itself. In Section 4.04(c)(vi) of ARCA, the grantor of the franchise) may be allowed to receive from Piatco. In that situation,
amount which government has guaranteed to pay as termination payment is the greater of government will be at the mercy of the foreign lenders. This is a situation completely
either (i) the Appraised Value of the terminal facility or (ii) the aggregate of the Attendant contrary to the rationale of the BOT Law and to public policy. The aforesaid provision rouses
Liabilities. Given that the Attendant Liabilities may include practically any Piatco debt under mixed emotions — shame and disgust at the parties' (especially the government officials')
the sun, it is highly conceivable that their sum may greatly exceed the appraised value of docile submission and abject servitude and surrender to the imperious and excessive
the facility, and government may end up paying very much more than the real worth of demands of the foreign lenders, on the one hand; and vehement outrage at the affront to
Terminal III. (So why did government have to bother with public bidding anyway?) the sovereignty of the Republic and to the national honor, on the other. It is indeed time
to put an end to such an unbearable, dishonorable situation.
36. ID.; ID.; ID.; INSTANCES WHEN TERMINATION COMPENSATION MAY BE
ALLOWED. — Section 7 of the BOT Law as amended in effect provides for the following 41. ID.; CONSTITUTIONAL LAW; NATIONAL ECONOMY AND
limited instances when termination compensation may be allowed: 1. Termination by the PATRIMONY; CONSTITUTION EXPRESSLY PROSCRIBES MAKING A FRANCHISE
government through no fault of the project proponent 2. Termination upon the parties' EXCLUSIVE; VIOLATED IN CASE AT BAR. — What was granted to Piatco was not merely a
mutual agreement and 3. Termination by the proponent due to government's default on franchise, but an "exclusive right" to operate an international passenger terminal within the
certain major contractual obligations. To emphasize, the law does not permit compensation "Island of Luzon." What this grant effectively means is that the government is now estopped
for the project proponent when contract termination is due to the proponent's own fault or from exercising its inherent power to award any other person another franchise or a right
breach of contract. to operate such a public utility, in the event public interest in Luzon requires it. This
restriction is highly detrimental to government and to the public interest. While it cannot
37. ID.;ID.;ID.;ID.;VIOLATED IN CASE AT BAR. — This principle was clearly be gainsaid that an enterprise that is a public utility may happen to constitute a monopoly
violated in the Piatco Contracts. The ARCA stipulates that government is to pay termination on account of the very nature of its business and the absence of competition, such a
compensation to Piatco even when termination is initiated by government. Clearly, this situation does not however constitute justification to violate the constitutional prohibition
condition is not in line with Section 7 of the BOT Law. That provision permits a project and grant an exclusive franchise or exclusive. right to operate a public utility. Piatco's
proponent to recover the actual expenses it incurred in the prosecution of the project plus contention that the Constitution does not actually prohibit monopolies is beside the point.
a reasonable rate of return not in excess of that provided in the contract; or to be As correctly argued, the existence of a monopoly by a public utility is a situation created by
compensated for the equivalent or proportionate contract cost as defined in the contract, circumstances that do not encourage competition. This situation is different from the grant
in case the government is in default on certain major contractual obligations. of a franchise to operate a public utility, a privilege granted by government. Of course, the
grant of a franchise may result in a monopoly. But making such franchise exclusive is what
38. ID.;ID.;ID.;ID.;IN TERMINATION COMPENSATION, IT IS INDISPENSABLE is expressly proscribed by the Constitution.
THAT THE INTEREST OF GOVERNMENT BE DULY INSURED; NOT PRESENT IN CASE AT BAR.
— [I]n those instances where such termination compensation is authorized by the BOT Law, 42. ID.; ID.; ID.; EASY PAYMENT PLAN OF PIATCO CONTRACTS VIOLATES THE
it is indispensable that the interest of government be duly insured.Section 5.08 the ARCA TIME LIMITATION ON FRANCHISES. — Section 11 of Article XII of the Constitutionalso
mandates insurance coverage for the terminal facility; but all insurance policies are to be provides that "no franchise, certificate or any other form of authorization for the operation
assigned, and all proceeds are payable, to the Senior Lenders. In brief, the interest being of a public utility shall be . . . for a longer period than fifty years." After all, a franchise held
secured by such coverage is that of the Senior Lenders, not that of government. This can for an unreasonably long time would likely give rise to the same evils as a monopoly. The
hardly be considered compliance with law. Piatco Contracts have come up with an innovative way to circumvent the prohibition and
obtain an extension. This fact can be gleaned from Section 8.03(b) of the ARCA [.] The
39. ID.; ID.; ID.; PROHIBITS A DIRECT GOVERNMENT SUBSIDY FOR easy payment scheme therein is less beneficial than it first appears. Although it enables
UNSOLICITED PROPOSALS. — It will be recalled that Section 4-A of the BOT Law as government to avoid having to make outright payment of an obligation that will likely run
amended prohibits not only direct government guarantees, but likewise a direct into billions of pesos, this easy payment plan will nevertheless cost government
government subsidy for unsolicited proposals. Section 13.2. b iii. of the 1999 IRR defines considerable loss of income, which it would earn if it were to operate Terminal III by itself.
a direct government subsidy as encompassing "an agreement whereby the Government Inasmuch as payments to the concessionaire (Piatco) will be on "installment basis," interest
...will ... postpone any payments due from the proponent." By any manner of interpretation charges on the remaining unpaid balance would undoubtedly cause the total outstanding
or application, however, Section 8.01(d) of the ARCA clearly mandates balance to swell. Piatco would thus be entitled to remain in the driver's seat and keep
the indefinite postponement of payment of all of Piatco's obligations to the government, in operating the terminal for an indefinite length of time.
order to ensure that Piatco's obligations to the Senior Lenders are paid in full first. That is
nothing more or less than the direct government subsidy prohibited by the BOT Law and 43. ID.;ID.;ID.;MONOPOLY; ELUCIDATED: — Gokongwei Jr. v. Securities and
the IRR. The fact that Piatco will pay interest on the unpaid amounts owed to government Exchange Commission elucidates the criteria to be employed: "A 'monopoly' embraces any
does not change the situation or render the prohibited subsidy any less combination the tendency of which is to prevent competition in the broad and general
unacceptable. DTAIaH sense, or to control prices to the detriment of the public. In short, it is the concentration of
business in the hands of a few. The material consideration in determining its existence is
40. ID.; ID.; ID.; GOVERNMENT WILL BE AT THE MERCY OF THE FOREIGN not that prices are raised and competition actually excluded, but that power exists to raise
LENDERS; CASE AT BAR. — Earlier; I mentioned that Section 8.01(d) of the ARCA prices or exclude competition when desired."
completely eliminated the proviso in Section 8.04(d) of the CA which gave government the
right to appoint a financial controller to manage the cash position of Piatco during situations 44. ID.; ID.; ID.; ID.; PIATCO CONTRACTS GIVE THE CONCESSIONAIRE
of financial distress. Not only has government been deprived of any means of monitoring LIMITLESS POWER OVER THE CHARGING OF FEES, RENTALS AND SO FORTH. — Aside from
and managing the situation; worse, as can be seen from Section 8.01(d) above-quoted, creating a monopoly, the Piatco contracts also give the concessionaire virtually limitless
the Senior Lenders have effectively locked in on the right to exercise financial controllership
power over the charging of fees, rentals and so forth. What little "oversight function" the 49. ID.;ID.;ID.;EXISTENCE OF APPROPRIATIONS AND THE AVAILABILITY OF
government might be able and minded to exercise is less than sufficient to protect the FUNDS ARE INDISPENSABLE TO THE EXECUTION OF GOVERNMENT CONTRACTS. — [T]his
public interest[.] It will be noted that Sec. 6.06 (Adjustment of Non-Public Utility Fees and Court has held that "(I)t is quite evident from the tenor of the language of the law that the
Charges) has no teeth, so the concessionaire can defy the government without fear of any existence of appropriations and the availability of funds are indispensable pre-requisites to
sanction. Moreover, Section 6.06 — taken together with Section 6.03(c) of the ARCA — or conditions sine qua non for the execution of government contracts. The obvious intent
falls short of the standard set by the BOT Law as amended, which expressly requires in is to impose such conditions as a priorirequisites to the validity of the proposed contract."
Section 2(b) that the project proponent is "allowed to charge facility users appropriate tolls,
fees, rentals and charges, not exceeding those proposed in its bid or as negotiated and 50. ID.;ID.;LEGISLATIVE POWER OVER THE PUBLIC PURSE; VIOLATED IN CASE
incorporated in the contract ..." AT BAR. — But the particularly sad thing about this transaction between MIAA and DPWH
is the fact that both agencies were maneuvered into (or allowed themselves to be
45. ID.;ID.;BILL OF RIGHTS; PROHIBITION AGAINST IMPAIRMENT OF maneuvered into) an agreement that would ensure delivery of upgraded roads for Piatco's
CONTRACTS; VIOLATED IN CASE AT BAR. — By the In-Service Date, Terminal III shall be benefit, using funds not allocated for that purpose. The agreement would then be presented
the only facility to be operated as an international passenger terminal at the NAIA; thus, to Congress as a done deal. Congress would thus be obliged to uphold the agreement and
Terminal I and II shall no longer operate as such, and no one shall be allowed to compete support it with the necessary allocations and appropriations for three years, in order to
with Piatco in the operation of an international passenger terminal in the NAIA. The bottom enable DPWH to deliver on its committed repayments to MIAA. The net result is an
line is that, as of the In-Service Date, Terminal III will be the only terminal where the infringement on the legislative power over the public purse and a diminution of Congress'
business of providing airport-related services to international airlines and passengers may control over expenditures of public funds — a development that would not have come about,
be conducted at all. Consequently, government through the DOTC/MIAA will be compelled were it not for the Supplements. Very clever but very illegal!
to cease honoring existing contracts with service providers after the In-Service Date, as
they cannot be allowed to operate in Terminal III. In short, the CA and the ARCA obligate 51. CIVIL LAW; OBLIGATIONS AND CONTRACTS; CRITERIA FOR DETERMINING
and constrain government to break its existing contracts with these service providers. WHETHER THE BEST-EFFORTS BASIS WILL APPLY. — To determine whether the additional
obligations under the Supplements may really be undertaken on a best-efforts basis only,
46. ID.;ID.;ID.;PROHIBITION AGAINST DEPRIVATION OF PROPERTY WITHOUT the nature of each of these obligations must be examined in the context of its relevance
DUE PROCESS; VIOLATED IN CASE AT BAR. — Notably, government is not in a position to and significance to the Terminal III Project, as well as of any adverse impact that may
require Piatco to accommodate the displaced service providers, and it would be unrealistic result if such obligation is not performed or undertaken on time. In short, the criteria for
to think that these service providers can perform their service contracts in some other determining whether the best-efforts basis will apply is whether the obligations are critical
international airport outside Luzon. Obviously, then, these displaced service providers are to the success of the Project and, accordingly, whether failure to perform them (or to
— to borrow a quaint expression — up the river without a paddle.In plainer terms, they will perform them on time) could result in a material breach of the contract.
have lost their businesses entirely, in the blink of an eye. Moreover, since the displaced
service providers, being unable to operate, will be forced to close shop, their respective 52. ID.;ID.;ID.;OBLIGATIONS IN THE SUPPLEMENTS ARE MANDATORY IN
employees — among them Messrs. Agan and Lopez et al. — have very grave cause for CHARACTER AND NOT FOR BEST-EFFORTS COMPLIANCE ONLY. — Viewed in this light, the
concern, as they will find themselves out of employment and bereft of their means of "Additional Special Obligations" set out in Section 4 of the FS take on a different aspect. In
livelihood. This situation comprises still another violation of the constitution prohibition particular, each of the following may all be deemed to play a major role in the successful
against deprivation of property without due process. True, doing business at the NAIA may and timely prosecution of the Terminal III Project: the obtention of land required by PIATCO
be viewed more as a privilege than as a right. Nonetheless, where that privilege has been for the taxilane and taxiway; the implementation of government's existing storm drainage
availed of by the petitioners-in-intervention service providers for years on end, a situation master plan; and coordination with DPWH for the completion of the three left-turning
arises, similar to that in American Inter-fashion v. GTEB.We held therein that a privilege overpasses before the In-Service Date, as well as acquisition and delivery of additional land
enjoyed for seven years "evolved into some form of property right which should not be for the construction of the T2-T3 access road. Conversely, failure to deliver on any of these
removed ...arbitrarily and without due process." Said pronouncement is particularly obligations may conceivably result in substantial prejudice to the concessionaire, to such
relevant and applicable to the situation at bar because the livelihood of the employees of an extent as to constitute a material breach of the Piatco Contracts. Whereupon, the
petitioners-intervenors are at stake. DaIACS concessionaire may outrightly terminate the Contracts pursuant to Section 8.01 (b)(i) and
(ii) of the ARCA and seek payment of Liquidated Damages in accordance with Section
47. ID.;ID.;ID.;PROHIBITION AGAINST DEPRIVATION OF LIBERTY WITHOUT DUE 8.02(a) of the ARCA; or the concessionaire may instead require government to pay the
PROCESS; VIOLATED IN CASE AT BAR. — The Piatco Contracts by locking out existing Incremental and Consequential Losses under Section 1.23 of the ARCA. The logical
service providers from entry into Terminal III and restricting entry of future service conclusion then is that the obligations in the Supplements are not to be performed on a
providers, thereby infringed upon the freedom — guaranteed to and heretofore enjoyed by best-efforts basis only, but are unarguably mandatory in character.
international airlines — to contract with local service providers of their choice, and vice
versa.Both the service providers and their client airlines will be deprived of the right to 53. ID.;ID.;PIATCO CONTRACTS ARE VOID AB INITIO AND INOPERATIVE. — I
liberty,which includes the right to enter into all contracts, and/or the right to make a find that all the Piatco contracts, without exception, are void ab initio,and therefore
contract in relation to one's business. inoperative. Even the very process by which the contracts came into being — the bidding
and the award — has been riddled with irregularities galore and blatant violations of law
48. ID.; LEGISLATIVE DEPARTMENT; PROHIBITION AGAINST DISBURSEMENT OF and public policy, far too many to ignore. There is thus no conceivable way, as proposed
PUBLIC FUNDS WITHOUT VALID APPROPRIATION; EFFECT. — Clearly prohibited by by some, of saving one (the original Concession Agreement) while junking all the rest.
the Constitution is the disbursement of public funds out of the treasury, except in pursuance Neither is it possible to argue for the retention of the Draft Concession Agreement (referred
of an appropriation made by law. The immediate effect of this constitutional ban is that all to in the various pleadings as the Contract Bidded Out) as the contract that should be kept
the various agencies of government are constrained to limit their expenditures to the in force and effect to govern the situation, inasmuch as it was never executed by the parties.
amounts appropriated by law for each fiscal year; and to carefully count their cash before What Piatco and the government executed was the Concession Agreement which is entirely
taking on contractual commitments. different from the Draft Concession Agreement.
54. ID.;ID.;ID.;KEEPING PIATCO ON AS CONCESSIONAIRE IS 2. ID.;ID.;ID.;SUPREME COURT IS NOT A TRIER OF FACTS. — The rule is explicit.
UNCONSCIONABLE. — Ultimately, though, it would be tantamount to an outrageous, A petition for prohibition may be filed against a tribunal, corporation, board, officer or
grievous and unforgivable mutilation of public policy and an insult to ourselves if we opt to person, exercising judicial, quasi-judicial or ministerial functions.What the petitions seek
keep in place a contract — any contract — for to do so would assume that we agree to from respondents do not involve judicial, quasi-judicial or ministerial functions. In
having Piatco continue as the concessionaire for Terminal III. Despite all the insidious prohibition, only legal issues affecting the jurisdiction of the tribunal, board or officer
contraventions of the Constitution, law and public policy Piatco perpetrated, keeping Piatco involved may be resolved on the basis of undisputed facts.The parties allege, respectively,
on as concessionaire and even rewarding it by allowing it to operate and profit from contentious evidentiary facts. It would be difficult, if not anomalous, to decide the
Terminal III — instead of imposing upon it the stiffest sanctions permissible under the laws jurisdictional issue on the basis of the contradictory factual submissions made by the
— is unconscionable. It is no exaggeration to say that Piatco may not really mind which parties. As the Court has so often exhorted, it is not a trier of facts.
contract we decide to keep in place. For all it may care, we can do just as well without
one, if we only let it continue and operate the facility.After all, the real money will come 3. ID.;ID.;ID.;PETITIONS FOR DECLARATORY RELIEF ARE COGNIZABLE BY THE
not from building the Terminal, but fromactually operating it for fifty or more years and REGIONAL TRIAL COURT. — The petitions, in effect, are in the nature of actions for
charging whatever it feels like, without any competition at all.This scenario must not be declaratory relief under Rule 63 of the Rules of Court. The Rules provide that any person
allowed to happen. EAHDac interested under a contract may, before breach or violation thereof, bring an action in
the appropriate Regional Trial Court to determine any question of construction or validity
55. ID.;ID.;ID.;AEDC SHOULD NOT BE ALLOWED TO OPERATE THE TERMINAL arising, and for a declaration of his rights or duties thereunder. The Supreme Court assumes
III. — If the Piatco contracts are junked altogether as I think they should be, should not no jurisdiction over petitions for declaratory relief which are cognizable by regional trial
AEDC automatically be considered the winning bidder and therefore allowed to operate the courts.
facility? My answer is a stone-cold 'No.' AEDC never won the bidding, never signed any
contract, and never built any facility. Why should it be allowed to automatically step in and 4. POLITICAL LAW; SEPARATION OF POWERS; COURT MAY NOT INTRUDE INTO
benefit from the greed of another? EVERY AFFAIR OF GOVERNMENT. — As I have so expressed in Tolentino vs. Secretary of
Finance,reiterated in Santiago vs. Guingona, Jr., the Supreme Court should not be thought
56. ID.;ID.;ID.;GOVERNMENT SHOULD PAY ALL REASONABLE EXPENSES of as having been tasked with the awesome responsibility of overseeing the entire
INCURRED IN THE CONSTRUCTION OF TERMINAL III. — Should government pay at all for bureaucracy. Pervasive and limitless, such as it may seem to be under the 1987
reasonable expenses incurred in the construction of the Terminal? Indeed it should, Constitution, judicial power still succumbs to the paramount doctrine of separation of
otherwise it will be unjustly enriching itself at the expense of Piatco and, in particular, its powers. The Court may not at good liberty intrude, in the guise of sovereign imprimatur,
funders, contractors and investors — both local and foreign. After all, there is no question into every affair of government. What significance can still then remain of the time-honored
that the State needs and will make use of Terminal III, it being part and parcel of the critical and widely acclaimed principle of separation of powers if, at every turn, the Court allows
infrastructure and transportation-related programs of government. In Melchor v. itself to pass upon at will the disposition of a co-equal, independent and coordinate branch
Commission on Audit,this Court held that even if the contract therein was void, the principle in our system of government. I dread to think of the so varied uncertainties that such an
of payment by quantum meruit was found applicable, and the contractor was allowed to undue interference can lead to.
recover the reasonable value of the thing or services rendered (regardless of any
agreement as to the supposed value),in order to avoid unjust enrichment on the part of
government. The principle ofquantum meruit was likewise applied in Eslao v. Commission
on Audit,because to deny payment for a building almost completed and already occupied
DECISION
would be to permit government to unjustly enrich itself at the expense of the contractor.
The same principle was applied in Republic v. Court of Appeals.

57. ID.;ID.;ID.;POSSIBLE PRACTICAL SOLUTION IS TO BID OUT THE OPERATION


OF TERMINAL III. — One possible practical solution would be for government — in view of PUNO, J p:
the nullity of the Piatco contracts and of the fact that Terminal III has already been built
and is almost finished — to bid out the operation of the facility under the same or analogous
Petitioners and petitioners-in-intervention filed the instant petitions for prohibition
principles as build-operate-and-transfer projects. To be imposed, however, is the condition
under Rule 65 of the Revised Rules of Court seeking to prohibit the Manila International
that the winning bidder must pay the builder of the facility a price fixed by government
Airport Authority (MIAA) and the Department of Transportation and Communications
based on quantum meruit;on the real, reasonable — not inflated — value of the built facility.
(DOTC) and its Secretary from implementing the following agreements executed by the
How the payment or series of payments to the builder, funders, investors and contractors
Philippine Government through the DOTC and the MIAA and the Philippine International Air
will be staggered and scheduled, will have to be built into the bids, along with the annual
Terminals Co.,Inc. (PIATCO):(1) the Concession Agreement signed on July 12, 1997, (2)
guaranteed payments to government. In this manner, this whole sordid mess could result
the Amended and Restated Concession Agreement dated November 26, 1999, (3) the First
in something truly beneficial for all, especially for the Filipino people.
Supplement to the Amended and Restated Concession Agreement dated August 27, 1999,
VITUG, J.,separate dissenting opinion: (4) the Second Supplement to the Amended and Restated Concession Agreement dated
September 4, 2000, and (5) the Third Supplement to the Amended and Restated
1. REMEDIAL LAW; CIVIL PROCEDURE; JURISDICTION; SUPREME COURT IS Concession Agreement dated June 22, 2001 (collectively, the PIATCO Contracts).
BEREFT OF JURISDICTION OVER CASES INVOLVING NULLIFICATION OF CONTRACTS. —
This Court is bereft of jurisdiction to hear the petitions at bar. The Constitution provides The facts are as follows:
that the Supreme Court shall exercise original jurisdiction over, among other actual
In August 1989, the DOTC engaged the services of Aeroport de Paris (ADP) to
controversies, petitions for certiorari, prohibition, mandamus, quo warranto,and habeas
conduct a comprehensive study of the Ninoy Aquino International Airport (NAIA) and
corpus.The cases in question, although denominated to be petitions for prohibition, actually
determine whether the present airport can cope with the traffic development up to the year
pray for the nullification of the PIATCO contracts and to restrain respondents from
2010. The study consisted of two parts: first, traffic forecasts, capacity of existing facilities,
implementing said agreements for being illegal and unconstitutional.
NAIA future requirements, proposed master plans and development plans; and second, ii. Next 10 years 7.5%
presentation of the preliminary design of the passenger terminal building. The ADP
submitted a Draft Final Report to the DOTC in December 1989. iii. Next 10 years 10.0%

Some time in 1993, six business leaders consisting of John Gokongwei, Andrew b. The amount of the fixed Annual Guaranteed Payment shall be
Gotianun, Henry Sy, Sr.,Lucio Tan, George Ty and Alfonso Yuchengco met with then subject of the price challenge. Proponent may offer an
President Fidel V. Ramos to explore the possibility of investing in the construction and Annual Guaranteed Payment which need not be of equal
operation of a new international airport terminal. To signify their commitment to pursue amount, but payment of which shall start upon site
the project, they formed the Asia's Emerging Dragon Corp. (AEDC) which was registered possession.
with the Securities and Exchange Commission (SEC) on September 15, 1993. CSaITD
c. The project proponent must have adequate capability to sustain the
On October 5, 1994, AEDC submitted an unsolicited proposal to the Government financing requirement for the detailed engineering, design,
through the DOTC/MIAA for the development of NAIA International Passenger Terminal III construction, and/or operation and maintenance phases of
(NAIA IPT III) under a build-operate-and-transfer arrangement pursuant to RA 6957 as the project as the case may be. For purposes of pre-
amended by RA 7718 (BOT Law). 1 qualification, this capability shall be measured in terms of:

On December 2, 1994, the DOTC issued Dept. Order No. 94-832 constituting the i. Proof of the availability of the project proponent and/or
Prequalification Bids and Awards Committee (PBAC) for the implementation of the NAIA IPT the consortium to provide the minimum amount of
III project. equity for the project; and

On March 27, 1995, then DOTC Secretary Jose Garcia endorsed the proposal of ii. a letter testimonial from reputable banks attesting that
AEDC to the National Economic and Development Authority (NEDA).A revised proposal, the project proponent and/or the members of the
however, was forwarded by the DOTC to NEDA on December 13, 1995. On January 5, 1996, consortium are banking with them, that the
the NEDA Investment Coordinating Council (NEDA ICC) — Technical Board favorably project proponent and/or the members are of good
endorsed the project to the ICC — Cabinet Committee which approved the same, subject financial standing, and have adequate resources.
to certain conditions, on January 19, 1996. On February 13, 1996, the NEDA passed Board
Resolution No. 2 which approved the NAIA IPT III Project. d. The basis for the prequalification shall be the proponent's
compliance with the minimum technical and financial
On June 7, 14, and 21, 1996, DOTC/MIAA caused the publication in two daily requirements provided in the Bid Documents and the IRR of
newspapers of an invitation for competitive or comparative proposals on AEDC's unsolicited the BOT Law. The minimum amount of equity shall be 30%
proposal, in accordance with Sec. 4-A of RA 6957, as amended. The alternative bidders of the Project Cost. CSaITD
were required to submit three (3) sealed envelopes on or before 5:00 p.m. of September
20, 1996. The first envelope should contain the Prequalification Documents, the second e. Amendments to the draft Concession Agreement shall be issued
envelope the Technical Proposal, and the third envelope the Financial Proposal of the from time to time. Said amendments shall only cover items
proponent. that would not materially affect the preparation of the
proponent's proposal.
On June 20, 1996, PBAC Bulletin No. 1 was issued, postponing the availment of
the Bid Documents and the submission of the comparative bid proposals. Interested firms On August 29, 1996, the Second Pre-Bid Conference was held where certain
were permitted to obtain the Request for Proposal Documents beginning June 28, 1996, clarifications were made. Upon the request of prospective bidder People's Air Cargo &
upon submission of a written application and payment of a non-refundable fee of Warehousing Co., Inc (Paircargo), the PBAC warranted that based on Sec. 11.6, Rule 11 of
P50,000.00 (US$2,000). the Implementing Rules and Regulations of the BOT Law, only the proposed Annual
Guaranteed Payment submitted by the challengers would be revealed to AEDC, and that
The Bid Documents issued by the PBAC provided among others that the proponent the challengers' technical and financial proposals would remain confidential. The PBAC also
must have adequate capability to sustain the financing requirement for the detailed clarified that the list of revenue sources contained in Annex 4.2a of the Bid Documents was
engineering, design, construction, operation, and maintenance phases of the project. The merely indicative and that other revenue sources may be included by the proponent, subject
proponent would be evaluated based on its ability to provide a minimum amount of equity to approval by DOTC/MIAA. Furthermore, the PBAC clarified that only those fees and
to the project, and its capacity to secure external financing for the project. charges denominated as Public Utility Fees would be subject to regulation, and those
charges which would be actually deemed Public Utility Fees could still be revised, depending
On July 23, 1996, the PBAC issued PBAC Bulletin No. 2 inviting all bidders to a on the outcome of PBAC's query on the matter with the Department of Justice.
pre-bid conference on July 29, 1996.
In September 1996, the PBAC issued Bid Bulletin No. 5, entitled "Answers to the
On August 16, 1996, the PBAC issued PBAC Bulletin No. 3 amending the Bid Queries of PAIRCARGO as Per Letter Dated September 3 and 10, 1996." Paircargo's queries
Documents. The following amendments were made on the Bid Documents: and the PBAC's responses were as follows:

a. Aside from the fixed Annual Guaranteed Payment, the proponent 1. It is difficult for Paircargo and Associates to meet the
shall include in its financial proposal an additional required minimum equity requirement as prescribed in Section 8.3.4
percentage of gross revenue share of the Government, as of the Bid Documents considering that the capitalization of each
follows: member company is so structured to meet the requirements and
needs of their current respective business undertaking/activities. In
i. First 5 years 5.0% order to comply with this equity requirement, Paircargo is requesting
PBAC to just allow each member of (sic) corporation of the joint
Venture to just execute an agreement that embodies a commitment challenger, Paircargo, had prequalified to undertake the project. The Secretary of the DOTC
to infuse the required capital in case the project is awarded to the approved the finding of the PBAC.
Joint Venture instead of increasing each corporation's current
authorized capital stock just for prequalification purposes. The PBAC then proceeded with the opening of the second envelope of the
Paircargo Consortium which contained its Technical Proposal.
In prequalification, the agency is interested in one's financial
capability at the time of prequalification, not future or potential On October 3, 1996, AEDC reiterated its objections, particularly with respect to
capability. Paircargo's financial capability, in view of the restrictions imposed by Section 21-B of
the General Banking Act and Sections 1380 and 1381 of the Manual Regulations for Banks
A commitment to put up equity once awarded the project is and Other Financial Intermediaries. On October 7, 1996, AEDC again manifested its
not enough to establish that "present" financial capability. However, objections and requested that it be furnished with excerpts of the PBAC meeting and the
total financial capability of all member companies of the Consortium, accompanying technical evaluation report where each of the issues they raised were
to be established by submitting the respective companies' audited addressed.
financial statements, shall be acceptable.
On October 16, 1996, the PBAC opened the third envelope submitted by AEDC
2. At present, Paircargo is negotiating with banks and other and the Paircargo Consortium containing their respective financial proposals. Both
institutions for the extension of a Performance Security to the joint proponents offered to build the NAIA Passenger Terminal III for at least $350 million at no
venture in the event that the Concessions Agreement (sic) is awarded cost to the government and to pay the government: 5% share in gross revenues for the
to them. However, Paircargo is being required to submit a copy of the first five years of operation, 7.5% share in gross revenues for the next ten years of
draft concession as one of the documentary requirements. Therefore, operation, and 10%.share in gross revenues for the last ten years of operation, in
Paircargo is requesting that they'd (sic) be furnished copy of the accordance with the Bid Documents. However, in addition to the foregoing, AEDC offered
approved negotiated agreement between the PBAC and the AEDC at to pay the government a total of P135 million as guaranteed payment for 27 years while
the soonest possible time. Paircargo Consortium offered to pay the government a total of P17.75 billion for the same
period. CSaITD
A copy of the draft Concession Agreement is included in the
Bid Documents. Any material changes would be made known to Thus, the PBAC formally informed AEDC that it had accepted the price proposal
prospective challengers through bid bulletins. However, a final version submitted by the Paircargo Consortium, and gave AEDC 30 working days or until November
will be issued before the award of contract. SECAHa 28, 1996 within which to match the said bid, otherwise, the project would be awarded to
Paircargo.
The PBAC also stated that it would require AEDC to sign Supplement C of the Bid
Documents (Acceptance of Criteria and Waiver of Rights to Enjoin Project) and to submit As AEDC failed to match the proposal within the 30-day period, then DOTC
the same with the required Bid Security. Secretary Amado Lagdameo, on December 11, 1996, issued a notice to Paircargo
Consortium regarding AEDC's failure to match the proposal.
On September 20, 1996, the consortium composed of People's Air Cargo and
Warehousing Co.,Inc. (Paircargo),Phil. Air and Grounds Services, Inc. (PAGS) and Security On February 27, 1997, Paircargo Consortium incorporated into Philippine
Bank Corp. (Security Bank) (collectively, Paircargo Consortium) submitted their competitive International Airport Terminals Co.,Inc. (PIATCO).
proposal to the PBAC. On September 23, 1996, the PBAC opened the first envelope
containing the prequalification documents of the Paircargo Consortium. On the following AEDC subsequently protested the alleged undue preference given to PIATCO and
day, September 24, 1996, the PBAC prequalified the Paircargo Consortium. reiterated its objections as regards the prequalification of PIATCO.

On September 26, 1996, AEDC informed the PBAC in writing of its reservations On April 11, 1997, the DOTC submitted the concession agreement for the second-
as regards the Paircargo Consortium, which include: pass approval of the NEDA-ICC,

a. The lack of corporate approvals and financial capability of On April 16, 1997, AEDC filed with the Regional Trial Court of Pasig a Petition for
PAIRCARGO; Declaration of Nullity of the Proceedings, Mandamus and Injunction against the Secretary
of the DOTC, the Chairman of the PBAC, the voting members of the PBAC and Pantaleon D.
b. The lack of corporate approvals and financial capability of PAGS; Alvarez, in his capacity as Chairman of the PBAC Technical Committee.

c. The prohibition imposed by RA 337, as amended (the General On April 17, 1997, the NEDA-ICC conducted an ad referendum to facilitate the
Banking Act) on the amount that Security Bank could legally approval, on a no-objection basis, of the BOT agreement between the DOTC and PIATCO.
invest in the project; As the ad referendum gathered only four (4) of the required six (6) signatures, the NEDA
merely noted the agreement.
d. The inclusion of Siemens as a contractor of the PAIRCARGO Joint
Venture, for prequalification purposes; and On July 9, 1997, the DOTC issued the notice of award for the project to PIATCO.

e. The appointment of Lufthansa as the facility operator, in view of On July 12, 1997, the Government, through then DOTC Secretary Arturo T. Enrile,
the Philippine requirement in the operation of a public utility. and PIATCO, through its President, Henry T. Go, signed the "Concession Agreement for the
Build-Operate-and-Transfer Arrangement of the Ninoy Aquino International Airport
The PBAC gave its reply on October 2, 1996, informing AEDC that it had Passenger Terminal III" (1997 Concession Agreement).The Government granted PIATCO
considered the issues raised by the latter, and that based on the documents submitted by the franchise to operate and maintain the said terminal during the concession period and
Paircargo and the established prequalification criteria, the PBAC had found that the to collect the fees, rentals and other charges in accordance with the rates or schedules
stipulated in the 1997 Concession Agreement. The Agreement provided that the concession On September 17, 2002, the workers of the international airline service providers,
period shall be for twenty-five (25) years commencing from the in-service date, and may claiming that they stand to lose their employment upon the implementation of the
be renewed at the option of the Government for a period not exceeding twenty-five (25) questioned agreements, filed before this Court a petition for prohibition to enjoin the
years. At the end of the concession period, PIATCO shall transfer the development facility enforcement of said agreements. 2
to MIAA.
On October 15, 2002, the service providers, joining the cause of the petitioning
On November 26, 1998, the Government and PIATCO signed an Amended and workers, filed a motion for intervention and a petition-in-intervention.
Restated Concession Agreement (ARCA).Among the provisions of the 1997 Concession
Agreement that were amended by the ARCA were: Sec. 1.11 pertaining to the definition of On October 24, 2002, Congressmen Salacnib Baterina, Clavel Martinez and
"certificate of completion";Sec. 2.05 pertaining to the Special Obligations of GRP; Sec. 3.02 Constantino Jaraula filed a similar petition with this Court. 3
(a) dealing with the exclusivity of the franchise given to the Concessionaire; Sec. 4.04
concerning the assignment by Concessionaire of its interest in the Development Facility; On November 6, 2002, several employees of the MIAA likewise filed a petition
Sec. 5.08 (c) dealing with the proceeds of Concessionaire's insurance; Sec. 5.10 with assailing the legality of the various agreements. 4
respect to the temporary take-over of operations by GRP; Sec. 5.16 pertaining to the taxes,
On December 11, 2002. another group of Congressmen, Hon. Jacinto V. Paras,
duties and other imposts that may be levied on the Concessionaire; Sec. 6.03 as regards
Rafael P. Nantes, Eduardo C. Zialcita, Willie B. Villarama, Prospero C. Nograles, Prospero
the periodic adjustment of public utility fees and charges; the entire Article VIII concerning
A. Pichay, Jr.,Harlin Cast Abayon and Benasing O. Macaranbon, moved to intervene in the
the provisions on the termination of the contract; and Sec. 10.02 providing for the venue
case as Respondents-Intervenors. They filed their Comment-In-Intervention defending the
of the arbitration proceedings in case a dispute or controversy arises between the parties
validity of the assailed agreements and praying for the dismissal of the petitions.
to the agreement.
During the pendency of the case before this Court, President Gloria Macapagal
Subsequently, the Government and PIATCO signed three Supplements to the
Arroyo, on November 29, 2002, in her speech at the 2002 Golden Shell Export Awards at
ARCA. The First Supplement was signed on August 27, 1999; the Second Supplement on
Malacañang Palace, stated that she will not "honor (PIATCO) contracts which the Executive
September 4, 2000; and the Third Supplement on June 22, 2001 (collectively,
Branch's legal offices have concluded (as) null and void." 5
Supplements).
Respondent PIATCO filed its Comments to the present petitions on November 7
The First Supplement to the ARCA amended Sec. 1.36 of the ARCA defining
and 27, 2002. The Office of the Solicitor General and the Office of the Government
"Revenues" or "Gross Revenues";Sec. 2.05 (d) of the ARCA referring to the obligation of
Corporate Counsel filed their respective Comments in behalf of the public respondents.
MIAA to provide sufficient funds for the upkeep, maintenance, repair and/or replacement
of all airport facilities and equipment which are owned or operated by MIAA; and further On December 10, 2002, the Court heard the case on oral argument. After the oral
providing additional special obligations on the part of GRP aside from those already argument, the Court then resolved in open court to require the parties to file simultaneously
enumerated in Sec. 2.05 of the ARCA. The First Supplement also provided a stipulation as their respective Memoranda in amplification of the issues heard in the oral arguments within
regards the construction of a surface road to connect NAIA Terminal II and Terminal III in 30 days and to explore the possibility of arbitration or mediation as provided in the
lieu of the proposed access tunnel crossing Runway 13/31; the swapping of obligations challenged contracts. CSaITD
between GRP and PIATCO regarding the improvement of Sales Road; and the changes in
the timetable. It also amended Sec. 6.01 (c) of the ARCA pertaining to the Disposition of In their consolidated Memorandum, the Office of the Solicitor General and the
Terminal Fees; Sec. 6.02 of the ARCA by inserting an introductory paragraph; and Sec. Office of the Government Corporate Counsel prayed that the present petitions be given due
6.02 (a) (iii) of the ARCA referring to the Payments of Percentage, Share in Gross course and that judgment be rendered declaring the 1997 Concession Agreement, the ARCA
Revenues. CSaITD and the Supplements thereto void for being contrary to theConstitution, the BOT Law and
its Implementing Rules and Regulations.
The Second Supplement to the ARCA contained provisions concerning the
clearing, removal, demolition or disposal of subterranean structures uncovered or On March 6, 2003, respondent PIATCO informed the Court that on March 4, 2003
discovered at the site of the construction of the terminal by the Concessionaire. It defined PIATCO commenced arbitration proceedings before the International Chamber of
the scope of works; it provided for the procedure for the demolition of the said structures Commerce, International Court of Arbitration (ICC) by filing a Request for Arbitration with
and the consideration for the same which the GRP shall pay PIATCO; it provided for time the Secretariat of the ICC against the Government of the Republic of the Philippines acting
extensions, incremental and consequential costs and losses consequent to the existence of through the DOTC and MIAA.
such structures; and it provided for some additional obligations on the part of PIATCO as
regards the said structures. In the present cases, the Court is again faced with the task of resolving
complicated issues made difficult by their intersecting legal and economic implications. The
Finally, the Third Supplement provided for the obligations of the Concessionaire Court is aware of the far reaching fall out effects of the ruling which it makes today. For
as regards the construction of the surface road connecting Terminals II and III. more than a century and whenever the exigencies of the times demand it, this Court has
never shirked from its solemn duty to dispense justice and resolve "actual controversies
Meanwhile, the MIAA which is charged with the maintenance and operation of the involving rights which are legally demandable and enforceable, and to determine whether
NAIA Terminals I and II, had existing concession contracts with various service providers or not there has been grave abuse of discretion amounting to lack or excess of
to offer international airline airport services, such as in-flight catering, passenger handling, jurisdiction." 6 To be sure, this Court will not begin to do otherwise today.
ramp and ground support, aircraft maintenance and provisions, cargo handling and
warehousing, and other services, to several international airlines at the NAIA. Some of We shall first dispose of the procedural issues raised by respondent PIATCO which
these service providers are the Miascor Group, DNATA-Wings Aviation Systems Corp.,and they allege will bar the resolution of the instant controversy.
the MacroAsia Group. Miascor, DNATA and MacroAsia, together with Philippine Airlines
(PAL),are the dominant players in the industry with an aggregate market share of 70%. Petitioners' Legal Standing to File
the present Petitions
a. G.R. Nos. 155001 and 155661 said contracts will be in force for the stipulated period, and thereafter, renewed so as to
allow each of the petitioning service providers to recoup their investments and obtain a
In G.R. No. 155001 individual petitioners are employees of various service reasonable return thereon.
providers 7 having separate concession contracts with MIAA and continuing service
agreements with various international airlines to provide in-flight catering, passenger Petitioning employees of various service providers at the NAIA Terminals I and II
handling, ramp and ground support, aircraft maintenance and provisions, cargo handling and of MIAA on the other hand allege that with the closure of the NAIA Terminals I and II
and warehousing and other services. Also included as petitioners are labor unions MIASCOR as international passenger terminals under the PIATCO Contracts, they stand to lose
Workers Union-National Labor Union and Philippine Airlines Employees Association, These employment.
petitioners filed the instant action for prohibition as taxpayers and as parties whose rights
and interests stand to be violated by the implementation of the PIATCO Contracts. The question on legal standing is whether such parties have "alleged such a
personal stake in the outcome of the controversy as to assure that concrete adverseness
Petitioners-Intervenors in the same case are all corporations organized and which sharpens the presentation of issues upon which the court so largely depends for
existing under Philippine laws engaged in the business of providing in-flight catering, illumination of difficult constitutional questions." 9 Accordingly, it has been held that the
passenger handling, ramp and ground support, aircraft maintenance and provisions, cargo interest of a person assailing the constitutionality of a statute must be direct and personal.
handling and warehousing and other services to several international airlines at the Ninoy He must be able, to show, not only that the law or any government act is invalid, but also
Aquino International Airport. Petitioners-Intervenors allege that as tax-paying international that he sustained or is in imminent danger of sustaining some direct injury as a result of
airline and airport-related service operators, each one of them stands to be irreparably its enforcement, and not merely that he suffers thereby in some indefinite way. It must
injured by the implementation of the PIATCO Contracts. Each of the petitioners-intervenors appear that the person complaining has been or is about to be denied some right or privilege
have separate and subsisting concession agreements with MIAA and with various to which he is lawfully entitled or that he is about to be subjected to some burdens or
international airlines which they allege are being interfered with and violated by respondent penalties by reason of the statute or act complained of. 10
PIATCO.
We hold that petitioners have the requisite standing. In the abovementioned
In G.R. No. 155661, petitioners constitute employees of MIAA and Samahang cases, petitioners have a direct and substantial interest to protect by reason of the
Manggagawa sa Paliparan ng Pilipinas — a legitimate labor union and accredited as the sole implementation of the PIATCO Contracts. They stand to lose their source of livelihood, a
and exclusive bargaining agent of all the employees in MIAA. Petitioners anchor their property right which is zealously protected by the Constitution. Moreover, subsisting
petition for prohibition on the nullity of the contracts entered into by the Government and concession agreements between MIAA and petitioners-intervenors and service contracts
PIATCO regarding the build-operate-and-transfer of the NAIA IPT III. They filed the petition between international airlines and petitioners-intervenors stand to be nullified or
as taxpayers and persons who have a legitimate interest to protect in the implementation terminated by the operation of the NAIA IPT III under the PIATCO Contracts. The financial
of the PIATCO Contracts. prejudice brought about by the PIATCO Contracts on petitioners and petitioners-intervenors
in these cases are legitimate interests sufficient to confer on them the requisite standing to
Petitioners in both cases raise the argument that the PIATCO Contracts contain file the instant petitions. CSaITD
stipulations which directly contravene numerous provisions of the Constitution, specific
provisions of the BOT Law and its Implementing Rules and Regulations, and public policy. b. G.R. No. 155547
Petitioners contend that the DOTC and the MIAA, by entering into said contracts, have
committed grave abuse of discretion amounting to lack or excess of jurisdiction which can In G.R. No. 155547, petitioners filed the petition for prohibition as members of
be remedied only by a writ of prohibition, there being no plain, speedy or adequate remedy the House of Representatives, citizens and taxpayers. They allege that as members of the
in the ordinary course of law. House of Representatives, they are especially interested in the PIATCO Contracts, because
the contracts compel the Government and/or the House of Representatives to appropriate
In particular, petitioners assail the provisions in the 1997 Concession Agreement funds necessary to comply with the provisions therein. 11 They cite provisions of the
and the ARCA which grant PIATCO the exclusive right to operate a commercial international PIATCO Contracts which require disbursement of unappropriated amounts in compliance
passenger terminal within the Island of Luzon, except those international airports already with the contractual obligations of the Government. They allege that the Government
existing at the time of the execution of the agreement. The contracts further provide that obligations in the PIATCO Contracts which compel government expenditure without
upon the commencement of operations at the NAIA IPT III, the Government shall cause appropriation is a curtailment of their prerogatives as legislators, contrary to the mandate
the closure of Ninoy Aquino International Airport Passenger Terminals I and II as of the Constitution that "[n]o money shall be paid out of the treasury except in pursuance
international passenger terminals. With respect to existing concession agreements between of an appropriation made by law." 12
MIAA and international airport service providers regarding certain services or operations,
the 1997 Concession Agreement and the ARCA uniformly provide that such services or Standing is a peculiar concept in constitutional law because in some cases, suits
operations will not be carried over to the NAIA IPT III and PIATCO is under no obligation to are not brought by parties who have been personally injured by the operation of a law or
permit such carry over except through a separate agreement duly entered into with any other government act but by concerned citizens, taxpayers or voters who actually sue
PIATCO. 8 in the public interest. Although we are not unmindful of the cases ofImus Electric
Co. v. Municipality of Imus 13 and Gonzales v. Raquiza 14 wherein this Court held that
With respect to the petitioning service providers and their employees, upon the appropriation must be made only on amounts immediately demandable, public interest
commencement of operations of the NAIA IPT III, they allege that they will be effectively demands that we take a more liberal view in determining whether the petitioners suing as
barred from providing international airline airport services at the NAIA Terminals I and II legislators, taxpayers and citizens have locus standi to file the instant
as all international airlines and passengers will be diverted to the NAIA IPT III. The petition.In Kilosbayan, Inc. v. Guingona, 15 this Court held "[i]n line with the liberal policy
petitioning service providers will thus be compelled to contract with PIATCO alone for such of this Court on locus standi,ordinary taxpayers, members of Congress, and even
services, with no assurance that subsisting contracts with MIAA and other international association of planters, and non-profit civic organizations were allowed to initiate and
airlines will be respected. Petitioning service providers stress that despite the very prosecute actions before this Court to question the constitutionality or validity of laws, acts,
competitive market, the substantial capital investments required and the high rate of fees, decisions, rulings, or orders of various government agencies or
they entered into their respective contracts with the MIAA with the understanding that the instrumentalities," 16 Further, "insofar as taxpayers' suits are concerned ...(this Court)
is not devoid of discretion as to whether or not it should be entertained." 17 As such justice would best be served if the trial court hears and adjudicates the case in asingle and
"...even if, strictly speaking, they [the petitioners] are not covered by the definition, it is complete proceeding.
still within the wide discretion of the Court to waive the requirement and so remove the
impediment to its addressing and resolving the serious constitutional questions It is established that petitioners in the present cases who have presented
raised." 18 In view of the serious legal questions involved and their impact on public legitimate interests in the resolution of the controversy are not parties to the PIATCO
interest, we resolve to grant standing to the petitioners. Contracts.Accordingly, they cannot be bound by the arbitration clause provided for in the
ARCA and hence, cannot be compelled to submit to arbitration proceedings. A speedy and
Other Procedural Matters decisive resolution of all the critical issues in the present controversy, including those raised
by petitioners, cannot be made before an arbitral tribunal.The object of arbitration is
Respondent PIATCO further alleges that this Court is without jurisdiction to review
precisely to allow an expeditious determination of a dispute. This objective would not be
the instant cases as factual issues are involved which this Court is ill-equipped to resolve.
met if this Court were to allow the parties to settle the cases by arbitration as there are
Moreover, PIATCO alleges that submission of this controversy to this Court at the first
certain issues involving non-parties to the PIATCO Contracts which the arbitral tribunal will
instance is a violation of the rule on hierarchy of courts. They contend that trial courts have
not be equipped to resolve.
concurrent jurisdiction with this Court with respect to a special civil action for prohibition
and hence, following the rule on hierarchy of courts, resort must first be had before the Now, to the merits of the instant controversy.
trial courts.
I
After a thorough study and careful evaluation of the issues involved, this Court is
of the view that the crux of the instant controversy involves significant legal questions.The Is PIATCO a qualified bidder?
facts necessary to resolve these legal questions are well established and, hence, need not Public respondents argue that the Paircargo Consortium, PIATCO's predecessor,
be determined by a trial court. was not a duly pre-qualified bidder on the unsolicited proposal submitted by AEDC as the
Paircargo Consortium failed to meet the financial capability required under the BOT Law and
The rule on hierarchy of courts will not also prevent this Court from assuming
the Bid Documents. They allege that in computing the ability of the Paircargo Consortium
jurisdiction over the cases at bar. The said rule may be relaxed when the redress desired
to meet the minimum equity requirements for the project, the entire net worth of Security
cannot be obtained in the appropriate courts or where exceptional and compelling
Bank, a member of the consortium, should not be considered.
circumstances justify availment of a remedy within and calling for the exercise of this
Court's primary jurisdiction. 19 PIATCO relies, on the other hand, on the strength of the Memorandum dated
October 14, 1996 issued by the DOTC Undersecretary Primitivo C. Cal stating that the
It is easy to discern that exceptional circumstances exist in the cases at bar that
Paircargo Consortium is found to have a combined net worth of P3,900,000,000.00,
call for the relaxation of the rule. Both petitioners and respondents agree that these cases
sufficient to meet the equity requirements of the project. The said Memorandum was in
are of transcendental importance as they involve the construction and operation of the
response to a letter from Mr. Antonio Henson of AEDC to President Fidel V. Ramos
country's premier international airport. Moreover, the crucial issues submitted for resolution
questioning the financial capability of the Paircargo Consortium on the ground that it does
are of first impression and they entail the proper legal interpretation of key provisions of
not have the financial resources to put up the required minimum equity of
the Constitution, the BOT Law and its Implementing Rules and Regulations. Thus,
P2,700,000,000.00. This contention is based on the restriction under R.A. No. 337, as
considering the nature of the controversy before the Court, procedural bars may be lowered
amended or the General Banking Act that a commercial bank cannot invest in any single
to give way for the speedy disposition of the instant cases.
enterprise in an amount more than 15% of its net worth. In the said Memorandum,
Legal Effect of the Commencement Undersecretary Cal opined:
of Arbitration Proceedings by
The Bid Documents, as clarified through Bid Bulletin Nos. 3
PIATCO
and 5, require that financial capability will be evaluated based on total
There is one more procedural obstacle which must be overcome. The Court is financial capability of all the member companies of the [Paircargo]
aware that arbitration proceedings pursuant to Section 10.02 of the ARCA have been filed Consortium. In this connection, the Challenger was found to have a
at the instance of respondent PIATCO. Again, we hold that the arbitration step taken by combined net worth of P3,926,421,242.00 that could support a
PIATCO will not oust this Court of its jurisdiction over the cases at bar. project costing approximately P13 Billion. CSaITD

In Del Monte Corporation-USA v. Court of Appeals, 20 even after finding that the It is not a requirement that the net worth must be
arbitration clause in the Distributorship Agreement in question is valid and the dispute "unrestricted." To impose that as a requirement now will be nothing
between the parties is arbitrable, this Court affirmed the trial court's decision denying less than unfair.
petitioner's Motion to Suspend Proceedings pursuant to the arbitration clause under the
contract. In so ruling, this Court held that as contracts produce legal effect between the The financial statement or the net worth is not the sole basis
parties, their assigns and heirs, only the parties to the Distributorship Agreement are bound in establishing financial capability. As stated in Bid Bulletin No. 3,
by its terms, including the arbitration clause stipulated therein. This Court ruled that financial capability may also be established by testimonial letters
arbitration proceedings could be called for but only with respect to the parties to the issued by reputable banks. The Challenger has complied with this
contract in question. Considering that there are parties to the case who are neither parties requirement.
to the Distributorship Agreement nor heirs or assigns of the parties thereto, this Court,
citing its previous ruling in Salas, Jr. v. Laperal Realty Corporation, 21 held that to tolerate To recap, net worth reflected in the Financial Statement
the splitting of proceedings by allowing arbitration as to some of the parties on the one should not be taken as the amount of the money to be used to answer
hand and trial for the others on the other hand would, in effect, result in multiplicity of the required thirty percent (30%) equity of the challenger but rather
suits, duplicitous procedure and unnecessary delay. 22 Thus, we ruled that the interest of to be used in establishing if there is enough basis to believe that the
challenger can comply with the required 30% equity. In fact, proof of
sufficient equity is required as one of the conditions for award of Paircargo's Audited Financial Statements as of 1993 and 1994 indicated that it
contract (Section 12.1 IRR of the BOT Law) but not for pre- had a net worth of P2,783,592,00 and P3,123,515,00 respectively. 26 PAGS' Audited
qualification (Section 5.4 of the same document). 23 Financial Statements as of 1995 indicate that it has approximately P26,735,700.00 to invest
as its equity for the project. 27 Security Bank's Audited Financial Statements as of 1995
Under the BOT Law, in case of a build-operate-and-transfer arrangement, the show that it has a net worth equivalent to its capital funds in the amount of
contract shall be awarded to the bidder "who, having satisfied the minimum financial, P3,523,504,377.00. 28
technical, organizational and legal standards" required by the law, has submitted the lowest
bid and most favorable terms of the project, 24 Further, the 1994 Implementing Rules and We agree with public respondents that with respect to Security Bank, the entire
Regulations of the BOT Law provide: amount of its net worth could not be invested in a single undertaking or enterprise, whether
allied or non-allied in accordance with the provisions of R.A. No. 337, as amended or
Section 5.4 Pre-qualification Requirements. the General Banking Act:
xxx xxx xxx Sec. 21-B. The provisions in this or in any other Act to the
c. Financial Capability: The project proponent must have contrary notwithstanding, the Monetary Board, whenever it shall
adequate capability to sustain the financing requirements for the deem appropriate and necessary to further national development
detailed engineering design, construction and/or operation and objectives or support national priority projects, may authorize a
maintenance phases of the project, as the case may be. For purposes commercial bank, a bank authorized to provide commercial banking
of pre-qualification, this capability shall be measured in terms of (i) services, as well as a government-owned and controlled bank, to
proof of the ability of the project proponent and/or the consortium to operate under an expanded commercial banking authority and by
provide a minimum amount of equity to the project, and (ii) a letter virtue thereof exercise, in addition to powers authorized for
testimonial from reputable banks attesting that the project proponent commercial banks, the powers of an Investment House as provided in
and/or members of the consortium are banking with them, that they Presidential Decree No. 129, invest in the equity of a non-allied
are in good financial standing, and that they have adequate undertaking,or own a majority or all of the equity in a financial
resources.The government agency/LGU concerned shall determine on intermediary other than a commercial bank or a bank authorized to
a project-to-project basis and before pre-qualification, the minimum provide commercial banking services; Provided, That (a) the total
amount of equity needed. (Italics supplied) investment in equities shall not exceed fifty percent (50%) of the net
worth of the bank; (b) the equity investment in any one enterprise
Pursuant to this provision, the PBAC issued PBAC Bulletin No. 3 dated August 16, whether allied or non-allied shall not exceed fifteen percent (15%) of
1996 amending the financial capability requirements for pre-qualification of the project the net worth of the bank;(c) the equity investment of the bank, or
proponent as follows: of its wholly or majority-owned subsidiary, in a single non-allied
undertaking shall not exceed thirty-five percent (35%) of the total
6. Basis of Pre-qualification equity in the enterprise nor shall it exceed thirty-five percent (35%)
of the voting stock in that enterprise; and (d) the equity investment
The basis for the pre-qualification shall be on the compliance in other banks shall be deducted from the investing bank's net worth
of the proponent to the minimum technical and financial requirements for purposes of computing the prescribed ratio of net worth to risk
provided in the Bid Documents and in the IRR of the BOT Law, R.A. assets.
No. 6957, as amended by R.A. 7718.
xxx xxx xxx
The minimum amount of equity to which the proponent's
financial capability will be based shall be thirty percent (30%) of the Further, the 1993 Manual of Regulations for Banks provides:
project cost instead of the twenty percent (20%) specified in Section
3.6.4 of the Bid Documents.This is to correlate with the required debt- SECTION X383. Other Limitations and Restrictions.— The
to-equity ratio of 70:30 in Section 2.01a of the draft concession following limitations and restrictions shall also apply regarding equity
agreement, The debt portion of the project financing should not investments of banks.
exceed 70% of the actual project cost.
a. In any single enterprise.— The equity investments of
Accordingly, based on the above provisions of law, the Paircargo Consortium or banks in any single enterprise shall not exceed at any time fifteen
any challenger to the unsolicited proposal of AEDC has to show that it possesses the percent (15%) of the net worth of the 'investing bank as defined in
requisite financial capability to undertake the project in the minimum amount of 30% of Sec. X106 and Subsec. X121.5. CSaITD
the project cost through (i) proof of the ability to provide a minimum amount of equity to
the project, and (ii) a letter testimonial from reputable banks attesting that the project Thus, the maximum amount that Security Bank could validly invest in the
proponent or members of the consortium are banking with them, that they are in good Paircargo Consortium is only P528,525,656.55, representing 15% of its entire net worth.
financial standing, and that they have adequate resources. The total net worth therefore of the Paircargo Consortium, after considering the maximum
amounts that may be validly invested by each of its members isP558,384,871.55 or only
As the minimum project cost was estimated to be US$350,000,000.00 or roughly 6.08% of the project cost,29 an amount substantially less than the prescribed minimum
P9,183,650,000.00, 25 the Paircargo Consortium had to show to the satisfaction of the equity investment required for the project in the amount of P2,755,095,000.00 or 30% of
PBAC that it had the ability to provide the minimum equity for the project in the amount of the project cost.
at least P2,755,095,000.00.
The purpose of pre-qualification in any public bidding is to determine, at the
earliest opportunity, the ability of the bidder to undertake the project. Thus, with respect
to the bidder's financial capacity at the pre-qualification stage, the law requires the Agreement included in the Bid Documents. They maintain that a substantial departure from
government agency to examine and determine the ability of the bidder to fund the entire the draft Concession Agreement is a violation of public policy and renders the 1997
cost of the project by considering the maximum amounts that each bidder may invest in Concession Agreement null and void.
the project at the time of pre-qualification.
PIATCO maintains, however, that the Concession Agreement attached to the Bid
The PBAC has determined that any prospective bidder, for the construction, Documents is intended to be a draft,i.e.,subject to change, alteration or modification, and
operation and maintenance of the NAIA IPT III project should prove that it has the ability that this intention was clear to all participants, including AEDC, and DOTC/MIAA. It argued
to provide equity in the minimum amount of 30% of the project cost, in accordance with further that said intention is expressed in Part C (6) of Bid Bulletin No. 3 issued by the PBAC
the 70:30 debt-to-equity ratio prescribed in the Bid Documents. Thus, in the case of which states:
Paircargo Consortium, the PBAC should determine the maximum amounts that each
member of the consortium may commit for the construction, operation and maintenance of 6. Amendments to the Draft Concessions Agreement
the NAIA IPT III project at the time of pre-qualification.With respect to Security Bank,
the maximum amount which may be invested by it would only be 15% of its net worth in Amendments to the Draft Concessions Agreement shall be
view of the restrictions imposed by the General Banking Act. Disregarding the investment issued from time to time. Said amendments shall only cover
ceilings provided by applicable law would not result in a proper evaluation of whether or items that would not materially affect the preparation of the
not a bidder is pre-qualified to undertake the project as for all intents and purposes, such proponent's proposal.
ceiling or legal restriction determines thetrue maximum amount which a bidder may invest
By its very nature, public bidding aims to protect the public interest by giving the
in the project.
public the best possible advantages through open competition. Thus:
Further, the determination of whether or not a bidder is pre-qualified to undertake
Competition must be legitimate, fair and honest. In the field
the project requires an evaluation of the financial capacity of the said bidder at the time
of government contract law, competition requires, not only bidding
the bid is submitted based on the required documents presented by the bidder. The PBAC
upon a common standard, a common basis, upon the same thing, the
should not be allowed to speculate on the future financial ability of the bidder to undertake
same subject matter, the same undertaking,' but also that it be
the project on the basis of documents submitted. This would open doors to abuse and
legitimate, fair and honest; and not designed to injure or defraud the
defeat the very purpose of a public bidding. This is especially true in the case at bar which
government. 31
involves the investment of billions of pesos by the project proponent. The relevant
government authority is duty-bound to ensure that the awardee of the contract possesses An essential element of a publicly bidded contract is that all bidders must be on
the minimum required financial capability to complete the project. To allow the PBAC to equal footing. Not simply in terms of application of the procedural rules and regulations
estimate the bidder's future financial capability would not secure the viability and integrity imposed by the relevant government agency, but more importantly, on the contract bidded
of the project. A restrictive and conservative application of the rules and procedures of upon. Each bidder must be able to bid on the same thing.The rationale is obvious. If the
public bidding is necessary not only to protect the impartiality and regularity of the winning bidder is allowed to later include or modify certain provisions in the contract
proceedings but also to ensure the financial and technical reliability of the project. It has awarded such that the contract is altered in any material respect, then the essence of fair
been held that: competition in the public bidding is destroyed. A public bidding would indeed be a farce if
after the contract is awarded, the winning bidder may modify the contract and include
The basic rule in public bidding is that bids should be
provisions which are favorable to it that were not previously made available to the other
evaluated based on the required documents submitted before and not
bidders. Thus:
after the opening of bids. Otherwise, the foundation of a fair and
competitive public bidding would be defeated. Strict observance of the It is inherent in public biddings that there shall be a fair
rules, regulations, and guidelines of the bidding process is the only competition among the bidders. The specifications in such biddings
safeguard to a fair, honest and competitive public bidding. 30 provide the common ground or basis for the bidders. The
specifications should, accordingly, operate equally or indiscriminately
Thus, if the maximum amount of equity that a bidder may invest in the project at
upon all bidders. 32
the time the bids are submitted falls short of the minimum amounts required to be put up
by the bidder, said bidder should be properly disqualified. Considering that at the pre- The same rule was restated by Chief Justice Stuart of the Supreme Court of
qualification stage, the maximum amounts which the Paircargo Consortium may invest in Minnesota:
the project fell short of the minimum amounts prescribed by the PBAC, we hold that
Paircargo Consortium was not a qualified bidder. Thus the award of the contract by the The law is well settled that where, as in this case, municipal
PBAC to the Paircargo Consortium, a disqualified bidder, is null and void. authorities can only let a contract for public work to the lowest
responsible bidder, the proposals and specifications therefore must be
While it would be proper at this juncture to end the resolution of the instant so framed as to permit free and full competition. Nor can they enter
controversy, as the legal effects of the disqualification of respondent PIATCO's predecessor into a contract with the best bidder containing substantial provisions
would come into play and necessarily result in the nullity of all the subsequent contracts beneficial to him, not included or contemplated in the terms and
entered by it in pursuance of the project, the Court feels that it is necessary to discuss in specifications upon which the bids were invited. 33
full the pressing issues of the present controversy for a complete resolution thereof.
In fact, in the PBAC Bid Bulletin No. 3 cited by PIATCO to support its argument
II that the draft concession agreement is subject to amendment, the pertinent portion of
Is the 1997 Concession Agreement valid? which was quoted above, the PBAC also clarified that "[s]aid amendments shall only cover
items that would not materially affect the preparation of the proponent's proposal."
Petitioners and public respondents contend that the 1997 Concession Agreement
is invalid as it contains provisions that substantially depart from the draft Concession
While we concede that a winning bidder is not precluded from modifying or (1) aircraft parking fees;
amending certain provisions of the contract bidded upon, such changes must not constitute
substantial or material amendments that would alter the basic parameters of the contract (2) aircraft tacking fees;
and would constitute a denial to the other bidders of the opportunity to bid on the same
terms.Hence, the determination of whether or not a modification or amendment of a (3) groundhandling fees;
contract bidded out constitutes a substantial amendment rests on whether the contract,
(4) rentals and airline offices;
when taken as a whole, would contain substantially different terms and conditions that
would have the effect of altering the technical and/or financial proposals previously (5) check-in counter rentals; and
submitted by other bidders. The alterations and modifications in the contract executed
between the government and the winning bidder must be such as to render such executed (6) porterage fees.
contract to be an entirely different contract from the one that was bidded upon.CSaITD
Under the 1997 Concession Agreement,fees which are subject to adjustment and
In the case of Caltex (Philippines),Inc. v. Delgado Brothers, Inc., 34 this Court effective upon MIAA approval are classified as "Public Utility Revenues" and include: 37
quoted with approval the ruling of the trial court that an amendment to a contract awarded
through public bidding, when such subsequent amendment was made without a new public (1) aircraft parking fees;
bidding, is null and void:
(2) aircraft tacking fees;
The Court agrees with the contention of counsel for the
plaintiffs that the due execution of a contract after public bidding is a (3) check-in counter fees; and
limitation upon the right of the contracting parties to alter or amend
it without another public bidding, for otherwise what would a public (4) Terminal Fees.
bidding be good for if after the execution of a contract after public The implication of the reduced number of fees that are subject to MIAA approval
bidding, the contracting parties may alter or amend the contract, or is best appreciated in relation to fees included in the second category identified above.
even cancel it, at their will? Public biddings are held for the protection Under the 1997 Concession Agreement,fees which PIATCO may adjust whenever it deems
of the public, and to give the public the best possible advantages by necessary without need for consent of DOTC/MIAA are "Non-Public Utility Revenues" and is
means of open competition between the bidders. He who bids or defined as "all other income not classified as Public Utility Revenues derived from operations
offers the best terms is awarded the contract subject of the bid, and of the Terminal and the Terminal Complex." 38Thus, under the 1997 Concession
it is obvious that such protection and best possible advantages to the Agreement, groundhandling fees, rentals from airline offices and porterage fees are no
public will disappear if the parties to a contract executed after public longer subject to MIAA regulation.
bidding may alter or amend it without another previous public
bidding. 35 Further, under Section 6.03 of the draft Concession Agreement;MIAA reserves the
right to regulate (1) lobby and vehicular parking fees and (2) other new fees and charges
Hence, the question that comes to fore is this: is the 1997 Concession Agreement that may be imposed by PIATCO. Such regulation may be made by periodic adjustment and
the same agreement that was offered for public bidding,i.e.,the draft Concession is effective only upon written approval of MIAA. The full text of said provision is quoted
Agreement attached to the Bid Documents? A close comparison of the draft Concession below:
Agreement attached to the Bid Documents and the 1997 Concession Agreement reveals
that the documents differ in at least two material respects: Section 6.03. Periodic Adjustment in Fees and
Charges.Adjustments in the aircraft parking fees, aircraft tacking
a. Modification on the Public fees, groundhandling fees, rentals and airline offices, check-in-
Utility Revenues and Non-Public counter rentals and porterage fees shall be allowed only once every
Utility Revenues that may be two years and in accordance with the Parametric Formula attached
collected by PIATCO hereto as Annex F. Provided that adjustments shall be made effective
The fees that may be, imposed and collected by PIATCO under the draft only after the written express approval of the MIAA. Provided, further,
Concession Agreement and the 1997 Concession Agreement may be classified into three that such approval of the MIAA, shall be contingent only on the
distinct categories: (1) fees which are subject to periodic adjustment of once every two conformity of the adjustments with the above said parametric
years in accordance with a prescribed parametric formula and adjustments are made formula. The first adjustment shall be made prior to the In-Service
effective only upon written approval by MIAA; (2) fees other than those included in the first Date of the Terminal.
category which may be adjusted by PIATCO whenever it deems necessary without need for
consent of DOTC/MIAA; and (3) new fees and charges that may be imposed by PIATCO The MIAA reserves the right to regulate under the foregoing
which have not been previously imposed or collected at the Ninoy Aquino International terms and conditions the lobby and vehicular parking fees and other
Airport Passenger Terminal I, pursuant to Administrative Order No. 1, Series of 1993, as new fees and charges as contemplated in paragraph 2 of Section 6.01
amended. The glaring distinctions between the draft Concession Agreement and the 1997 if in its judgment the users of the airport shall be deprived of a free
Concession Agreement lie in the types of fees included in each category and the extent of option for the services they cover. 39
the supervision and regulation which MIAA is allowed to exercise in relation thereto.
On the other hand, the equivalent provision under the 1997 Concession
For fees under the first category,i.e.,those which are subject to periodic Agreement reads:
adjustment in accordance with a prescribed parametric formula and effective only upon
Section 6.03 Periodic Adjustment in Fees, and Charges.
written approval by MIAA, the draft Concession Agreement includes the following: 36
xxx xxx xxx
(c) Concessionaire shall at all times be judicious in fixing in the draft Concession Agreement. Finally, the change in the currency stipulated for "Public
fees and charges constituting Non-Public Utility Revenues in order to Utility Revenues" under the 1997 Concession Agreement, except terminal fees, gives
ensure that End Users are not unreasonably deprived of PIATCO an added benefit which was not available at the time of bidding. aSTAIH
services. While the vehicular parking fee, porterage fee and
greeter/well wisher fee constitute Non-Public Utility Revenues of b. Assumption by the
Concessionaire, GRP may intervene and require Concessionaire to Government
explain and justify the fee it may set from time to time,if in the of the liabilities of PIATCO in
reasonable opinion of GRP the said fees have become exorbitant the event
resulting in the unreasonable deprivation of End Users of such of the latter's default thereof
services. 40 Under the draft Concession Agreement,default by PIATCO of any of its obligations
to creditors who have provided, loaned or advanced funds for the NAIA IPT III project does
Thus, under the 1997 Concession Agreement,with respect to (1) vehicular parking
not result in the assumption by the Government of these liabilities. In fact, nowhere in the
fee, (2) porterage fee and (3) greeter/well wisher fee, all that MIAA can do is to require
said contract does default of PIATCO's loans figure in the agreement. Such default does not
PIATCO to explain and justify the fees set by PIATCO. In the draft Concession
directly result in any concomitant right or obligation in favor of the Government.
Agreement,vehicular parking fee is subject to MIAA regulation and approval under the
second paragraph of Section 6.03 thereof while porterage fee is covered by the first However, the 1997 Concession Agreement provides:
paragraph of the same provision. There is an obvious relaxation of the extent of control
and regulation by MIAA with respect to the particular fees that may be charged by Section 4.04 Assignment.
PIATCO. CSaITD
xxx xxx xxx
Moreover, with respect to the third category of fees that may be imposed and
collected by PIATCO, i.e.,new fees and charges that may be imposed by PIATCO which have (b) In the event Concessionaire should default in the
not been previously imposed or collected at the Ninoy Aquino International Airport payment of an Attendant Liability, and the default has resulted in the
Passenger Terminal I, under Section 6.03 of the draft Concession Agreement MIAA has acceleration of the payment due date of the Attendant Liability prior
reserved the right to regulate the same under the same conditions that MIAA may regulate to its stated date of maturity, the Unpaid Creditors and Concessionaire
fees under the first category, i.e.,periodic adjustment of once every two years in accordance shall immediately inform GRP in writing of such default. GRP shall,
with a prescribed parametric formula and effective only upon written approval by MIAA. within one hundred eighty (180) Days from receipt of the joint written
However, under the 1997 Concession Agreement,adjustment of fees under the third notice of the Unpaid Creditors and Concessionaire, either (i) take over
category is not subject to MIAA regulation. the Development Facility and assume the Attendant Liabilities, or (ii)
allow the Unpaid Creditors, if qualified, to be substituted as
With respect to terminal fees that may be charged by PIATCO, 41 as shown concessionaire and operator of the Development Facility in
earlier, this was included within the category of "Public Utility Revenues" under the 1997 accordance with the terms and conditions hereof, or designate a
Concession Agreement.This classification is significant because under the 1997 Concession qualified operator acceptable to GRP to operate the Development
Agreement, "Public Utility Revenues" are subject to an "Interim Adjustment" of fees upon Facility, likewise under the terms and conditions of this Agreement;
the occurrence of certain extraordinary events specified in the agreement. 42 However, Provided that if at the end of the 180-day period GRP shall not have
under the draft Concession Agreement, terminal fees are not included in the types of fees served the Unpaid Creditors and Concessionaire written notice of its
that may be subject to "Interim Adjustment." 43 choice, GRP shall be deemed to have elected to take over the
Development Facility with the concomitant assumption of Attendant
Finally, under the 1997 Concession Agreement,"Public Utility Revenues," except Liabilities.
terminal fees, are denominated in US Dollars 44 while payments to the Government are in
Philippine Pesos. In the draft Concession Agreement,no such stipulation was included. By (c) If GRP should, by written notice, allow the Unpaid
stipulating that "Public Utility Revenues" will be paid to PIATCO in US Dollars while Creditors to be substituted as concessionaire, the latter shall form and
payments by PIATCO to the Government are in Philippine currency under the 1997 organize a concession company qualified to take over the operation
Concession Agreement, PIATCO is able to enjoy the benefits of depreciations of the of the Development Facility. If the concession company should elect
Philippine Peso, while being effectively insulated from the detrimental effects of exchange to designate an operator for the Development Facility, the concession
rate fluctuations. company shall in good faith identify and designate a qualified operator
acceptable to GRP within one hundred eighty (180) days from receipt
When taken as a whole, the changes under the 1997 Concession Agreement with of GRP's written notice. If the concession company, acting in good
respect to reduction in the types of fees that are subject to MIAA regulation and the faith and with due diligence, is unable to designate a qualified
relaxation of such regulation with respect to other fees are significant amendments that operator within the aforesaid period, then GRP shall at the end of the
substantially distinguish the draft Concession Agreement from the 1997 Concession 180-day period take over the Development Facility and assume
Agreement. The 1997 Concession Agreement, in this respect, clearly gives PIATCO more Attendant Liabilities.
favorable terms than what was available to other bidders at the time the contract was
bidded out.It is not very difficult to see that the changes in the 1997 Concession Agreement The term "Attendant Liabilities" under the 1997 Concession Agreement is defined
translate to direct and concrete financial advantages for PIATCO which were not available as:
at the time the contract was offered for bidding. It cannot be denied that under the 1997
Concession Agreement only "Public Utility Revenues" are subject to MIAA Attendant Liabilities refer to all amounts recorded and from
regulation. Adjustments of all other fees imposed and collected by PIATCO are entirely time to time outstanding in the books of the Concessionaire as owing
within its control.Moreover, with respect to terminal fees, under the 1997 Concession to Unpaid Creditors who have provided, loaned or advanced funds
Agreement, the same is further subject to "Interim Adjustments" not previously stipulated actually used for the Project,including all interests, penalties,
associated fees, charges, surcharges, indemnities, reimbursements In view of the above discussion, the fact that the foregoing substantial
and other related expenses, and further including amounts owed by amendments were made on the 1997 Concession Agreement renders the same null and
Concessionaire to its suppliers, contractors and sub-contractors. void for being contrary to public policy.These amendments convert the 1997 Concession
Agreement to an entirely different agreement from the contract bidded out or the draft
Under the above quoted portions of Section 4.04 in relation to the definition of Concession Agreement. It is not difficult to see that the amendments on (1) the types of
"Attendant Liabilities," default by PIATCO of its loans used to finance the NAIA IPT III fees or charges that are subject to MIAA regulation or control and the extent thereof and
project triggers the occurrence of certain events that leads to the assumption by the (2) the assumption by the Government, under certain conditions, of the liabilities of
Government of the liability for the loans.Only in one instance may the Government escape PIATCO directly translates concrete financial advantages to PIATCO that were previously
the assumption of PIATCO's liabilities, i.e.,when the Government so elects and allows a not available during the bidding process.These amendments cannot be taken as merely
qualified operator to take over as Concessionaire. However, this circumstance is dependent supplements to or implementing provisions of those already existing in the draft Concession
on the existence and availability of a qualified operator who is willing to take over the rights Agreement. The amendments discussed above present new terms and conditions which
and obligations of PIATCO under the contract, a circumstance that is not entirely within the provide financial benefit to PIATCO which may have altered the technical and financial
control of the Government. parameters of other bidders had they known that such terms were available.
Without going into the validity of this provision at this juncture, suffice it to state III
that Section 4.04 of the 1997 Concession Agreement may be considered a form of security
for the loans PIATCO has obtained to finance the project, an option that was not made Direct Government Guarantee
available in the draft Concession Agreement. Section 4.04 is an important amendment to Article IV, Section 4.04(b) and (c),in relation to Article 1.06, of the 1997
the 1997 Concession Agreement because it grants PIATCO a financial advantage or benefit Concession Agreement provides:
which was not previously made available during the bidding process.This financial
advantage is a significant modification that translates to better terms and conditions for Section 4.04 Assignment
PIATCO.
xxx xxx xxx
PIATCO, however, argues that the parties to the bidding procedure acknowledge
that the draft Concession Agreement is subject to amendment because the Bid Documents (b) In the event Concessionaire should default in the
permit financing or borrowing. They claim that it was the lenders who proposed the payment of an Attendant Liability,and the default resulted in the
amendments to the draft Concession Agreement which resulted in the 1997 Concession acceleration of the payment due date of the Attendant Liability prior
Agreement. to its stated date of maturity, the Unpaid Creditors and Concessionaire
shall immediately inform GRP in writing of such default. GRP shall
We agree that it is not inconsistent with the rationale and purpose of the BOT within one hundred eighty (180) days from receipt of the joint written
Law to allow the project proponent or the winning bidder to obtain financing for the project, notice of the Unpaid Creditors and Concessionaire, either (i) take over
especially in this case which involves the construction, operation and maintenance of the the Development Facility and assume the Attendant Liabilities,or (ii)
NAIA IPT III. Expectedly, compliance by the project proponent of its undertakings therein allow the Unpaid Creditors, if qualified to be substituted as
would involve a substantial amount of investment. It is therefore inevitable for the awardee concessionaire and operator of the Development facility in accordance
of the contract to seek alternate sources of funds to support the project. Be that as it may, with the terms and conditions hereof, or designate a qualified operator
this Court maintains that amendments to the contract bidded upon should always conform acceptable to GRP to operate the Development Facility, likewise under
to the general policy on public bidding if such procedure is to be faithful to its real nature the terms and conditions of this Agreement; Provided, that if at the
and purpose. By its very nature and characteristic, competitive public bidding aims to end of the 180-day period GRP shall not have served the Unpaid
protect the public interest by giving the public the best possible advantages through open Creditors and Concessionaire written notice of its choice, GRP shall be
competition. 45 It has been held that the three principles in public bidding are (1) the offer deemed to have elected to take over the Development Facility with
to the public; (2) opportunity for competition; and (3) a basis for the exact comparison of the concomitant assumption of Attendant Liabilities.
bids. A regulation of the matter which excludes any of these factors destroys the distinctive
character of the system and thwarts the purpose of its adoption. 46 These are the basic (c) If GRP, by written notice, allow the Unpaid Creditors to
parameters which every awardee of a contract bidded out must conform to, requirements be substituted as concessionaire, the latter shall form and organize a
of financing and borrowing notwithstanding. Thus, upon a concrete showing that, as in this concession company qualified to takeover the operation of the
case, the contract signed by the government and the contract awardee is an entirely Development Facility. If the concession company should elect to
different contract from the contract bidded, courts should not hesitate to strike down said designate an operator for the Development Facility, the concession
contract in its entirety for violation of public policy on public bidding. A strict adherence on company shall in good faith identify and designate a qualified operator
the principles, rules and regulations on public bidding must be sustained if only to preserve acceptable to GRP within one hundred eighty (180) days from receipt
the integrity and the faith of the general public on the procedure. of GRP's written notice. If the concession company, acting in good
faith and with due diligence, is unable to designate a qualified
Public bidding is a standard practice for procuring government contracts for public operator within the aforesaid period, then GRP shall at the end of the
service and for furnishing supplies and other materials. It aims to secure for the government 180-day period take over the Development Facility and assume
the lowest possible price under the most favorable terms and conditions, to curtail Attendant Liabilities.
favoritism in the award of government contracts and avoid suspicion of anomalies and it
places all bidders in equal footing. 47 Any government action which permits any substantial xxx xxx xxx
variance between the conditions under which the bids are invited and the contract executed
after the award thereof is a grave abuse of discretion amounting to lack or excess of Section 1.06. Attendant Liabilities
jurisdiction which warrants proper judicial action.
Attendant Liabilities refer to all amounts recorded and from xxx xxx xxx
time to time outstanding in the books of the Concessionaire as owing
to Unpaid Creditors who have provided, loaned or advanced funds (c) GRP agrees with Concessionaire (PIATCO) that it shall
actually used for the Project, including all interests, penalties, negotiate in good faith and enter into direct agreement with the
associated fees, charges, surcharges, indemnities, reimbursements Senior Lenders,or with an agent of such Senior Lenders (which
and other related expenses,and further including amounts owed by agreement shall be subject to the approval of the Bangko Sentral ng
Concessionaire to its suppliers, contractors and subcontractors. 48 Pilipinas),in such form as may be reasonably acceptable to both GRP
and Senior Lenders, with regard, inter alia, to the following
It is clear from the above-quoted provisions that Government, in the event that parameters:
PIATCO defaults in its loan obligations, is obligated to pay "all amounts recorded and from
time to time outstanding from the books" of PIATCO which the latter owes to its xxx xxx xxx
creditors. 49 These amounts include "all interests, penalties, associated fees, charges,
surcharges, indemnities, reimbursements and other related expenses." 50 This obligation (iv) If the Concessionaire [PIATCO] is in default under a
of the Government to pay PIATCO's creditors upon PIATCO's default would arise if the payment obligation owed to the Senior Lenders,and as a result thereof
Government opts to take over NAIA IPT III. It should be noted, however, that even if the the Senior Lenders have become entitled to accelerate the Senior
Government chooses the second option, which is to allow PIATCO's unpaid creditors operate Loans, the Senior Lenders shall have the right to notify GRP of the
NAIA IPT III, the Government is still at a risk of being liable to PIATCO's creditors should same, and without prejudice to any other rights of the Senior Lenders
the latter be unable to designate a qualified operator within the prescribed period. 51 In or any Senior Lenders' agent may have (including without limitation
effect, whatever option the Government chooses to take in the event of PIATCO's failure to under security interests granted in favor of the Senior Lenders),to
fulfill its loan obligations, the Government is still at a risk of assuming PIATCO's outstanding either in good faith identify and designate a nominee which is qualified
loans.This is due to the fact that the Government would only be free from assuming under sub-clause (viii)(y) below to operate the Development Facility
PIATCO's debts if the unpaid creditors would be able to designate a qualified operator within [NAIA Terminal 3] or transfer the Concessionaire's [PIATCO] rights
the period provided for in the contract. Thus, the Government's assumption of liability is and obligations under this Agreement to a transferee which is
virtually out of its control.The Government under the circumstances provided for in the qualified under sub-clause (viii) below;
1997 Concession Agreement is at the mercy of the existence, availability and willingness of
xxx xxx xxx
a qualified operator. The above contractual provisions constitute a direct government
guarantee which is prohibited by law. (vi) if the Senior Lenders, acting in good faith and using
reasonable efforts, are unable to designate a nominee or effect a
One of the main impetus for the enactment of the BOT Law is the lack of
transfer in terms and conditions satisfactory to the Senior Lenders
government funds to construct the infrastructure and development projects necessary for
within one hundred eighty (180) days after giving GRP notice as
economic growth and development. This is why private sector resources are being tapped
referred to respectively in (iv) or (v) above, then GRP and the Senior
in order to finance these projects. The BOT law allows the private sector to participate, and
Lenders shall endeavor in good faith to enter into any other
is in fact encouraged to do so by way of incentives, such as minimizing, the unstable flow
arrangement relating to the Development Facility [NAIA Terminal 3]
of returns, 52 provided that the government would not have to unnecessarily expend
(other than a turnover of the Development Facility [NAIA Terminal 3]
scarcely available funds for the project itself. As such, direct guarantee, subsidy and equity
to GRP) within the following one hundred eighty (180) days. If no
by the government in these projects are strictly prohibited. 53 This is but logical for if the
agreement relating to the Development Facility [NAIA Terminal 3] is
government would in the end still be at a risk of paying the debts incurred by the private
arrived at by GRP and the Senior Lenders within the said 180-day
entity in the BOT projects, then the purpose of the law is subverted.
period, then at the end thereof the Development Facility [NAIA
Section 2(n) of the BOT Law defines direct guarantee as follows: Terminal 3] shall be transferred by the Concessionaire [PIATCO] to
GRP or its designee and GRP shall make a termination payment to
(n) Direct government guarantee — An agreement whereby Concessionaire [PIATCO] equal to the Appraised Value (as hereinafter
the government or any of its agencies or local government units defined) of the Development Facility [NAIA Terminal 3] or the sum of
assume responsibility for therepayment of debt directly incurred by the Attendant Liabilities, if greater.Notwithstanding Section 8.01 (c)
the project proponent in implementing the project in case of a loan hereof, this Agreement shall be deemed terminated upon the transfer
default. of the Development Facility [NAIA Terminal 3] to GRP pursuant
hereto;
Clearly by providing that the Government "assumes" the attendant liabilities,
which consists of PIATCO's unpaid debts, the 1997 Concession Agreement provided for a xxx xxx xxx
direct government guarantee for the debts incurred by PIATCO in the implementation of
the NAIA IPT III project. It is of no moment that the relevant sections are subsumed under Section 1.06. Attendant Liabilities
the title of "assignment".The provisions providing for direct government guarantee which
Attendant Liabilities refer to all amounts in each case
is prohibited by law is clear from the terms thereof.
supported by verifiable evidence from time to time owed or which
The fact that the ARCA superseded the 1997 Concession Agreement did not cure may become owing by Concessionaire [PIATCO] to Senior Lenders or
this fatal defect. Article IV, Section 4.04(c),in relation to Article 1, Section 1.06, of the any other persons or entities who have provided, loaned, or advanced
ARCA provides: funds or provided financial facilities to Concessionaire [PIATCO] for
the Project [NAIA Terminal 3],including, without limitation, all
Section 4.04 Security principal, interest, associated fees, charges, reimbursements, and
other related expenses (including the fees, charges and expenses of
any agents or trustees of such persons or entities),whether payable should the conditions as set forth in the ARCA arise. This is a form of direct government
at maturity, by acceleration or otherwise, and further including guarantee.
amounts owed by Concessionaire [PIATCO] to its professional
consultants and advisers, suppliers, contractors and sub- The BOT Law and its implementing rules provide that in order for an unsolicited
contractors. 54 proposal for a BOT project may be accepted, the following conditions must first be met: (1)
the project involves a new concept in technology and/or is not part of the list of priority
It is clear from the foregoing contractual provisions that in the event that PIATCO projects, (2) no direct government guarantee, subsidy or equity is required, and (3) the
fails to fulfill its loan obligations to its Senior Lenders, the Government is obligated to government agency or local government unit has invited by publication other interested
directly negotiate and enter into an agreement relating to NAIA IPT III with the Senior parties to a public bidding and conducted the same. 56 The failure to meet any of the above
Lenders, should the latter fail to appoint a qualified nominee or transferee who will take the conditions will result in the denial of the proposal. It is further provided that the presence
place of PIATCO. If the Senior Lenders and the Government are unable to enter into an of direct government guarantee, subsidy or equity will "necessarily, disqualify a proposal
agreement after the prescribed period, the Government must then pay PIATCO, upon from being treated and accepted as an unsolicited proposal." 57 The BOT Law clearly and
transfer of NAIA IPT III to the Government, termination payment equal to the appraised strictly prohibits direct government guarantee, subsidy and equity in unsolicited proposals
value of the project or the value of the attendant liabilities whichever is greater.Attendant that the mere inclusion of a provision to that effect is fatal and is sufficient to deny the
liabilities as defined in the ARCA includes all amounts owed or thereafter may be owed by proposal. It stands to reason therefore that if a proposal can be denied by reason of the
PIATCO not only to the Senior Lenders with whom PIATCO has defaulted in its loan existence of direct government guarantee, then its inclusion in the contract executed after
obligations but to all other persons who may have loaned, advanced funds or provided any the said proposal has been accepted is likewise sufficient to invalidate the contract itself. A
other type of financial facilities to PIATCO for NAIA IPT III. The amount of PIATCO's debt prohibited provision, the inclusion of which would result in the denial of a proposal cannot,
that the Government would have to pay as a result of PIATCO's default in its loan obligations and should not, be allowed to later on be inserted in the contract resulting from the said
— in case no qualified nominee or transferee is appointed by the Senior Lenders and no proposal. The basic rules of justice and fair play alone militate against such an occurrence
other agreement relating to NAIA IPT III has been reached between the Government and and must not, therefore, be countenanced particularly in this instance where the
the Senior Lenders — includes, but is not limited to, "all principal, interest, associated fees, government is exposed to the risk of shouldering hundreds of million of dollars in debt.
charges, reimbursements, and other related expenses ...whether payable at maturity, by
acceleration or otherwise." 55 This Court has long and consistently adhered to the legal maxim that those that
cannot be done directly cannot be done indirectly. 58 To declare the PIATCO contracts valid
It is clear from the foregoing that the ARCA provides for a direct guarantee by the despite the clear statutory prohibition against a direct government guarantee would not
government to pay PIATCO's loans not only to its Senior Lenders but all other entities who only make a mockery of what the BOT Law seeks to prevent —which is to expose the
provided PIATCO funds or services upon PIATCO's default in its loan obligation with its government to the risk of incurring a monetary obligation resulting from a contract of loan
Senior Lenders.The fact that the Government's obligation to pay PIATCO's lenders for the between the project proponent and its lenders and to which the Government is not a party
latter's obligation would only arise after the Senior Lenders fail to appoint a qualified to — but would also render the BOT Law useless for what it seeks to achieve — to make
nominee or transferee does not detract from the fact that, should the conditions as stated use of the resources of the private sector in the "financing, operation and maintenance of
in the contract occur, the ARCA still obligates the Government to pay any and all amounts infrastructure and development projects" 59 which are necessary for national growth and
owed by PIATCO to its lenders in connection with NAIA IPT III. Worse, the conditions that development but which the government, unfortunately, could ill-afford to finance at this
would make the Government liable for PIATCO's debts is triggered by PIATCO's own default point in time.
of its loan obligations to its Senior Lenders to which loan contracts the Government was
never a party to. The Government was not even given an option as to what course of action IV
it should take in case PIATCO defaulted in the payment of its senior loans. The Government, Temporary takeover of business affected with public interest
upon PIATCO's default, would be merely notified by the Senior Lenders of the same and it
is the Senior Lenders who are authorized to appoint a qualified nominee or transferee. Article XII, Section 17 of the 1987 Constitution provides:
Should the Senior Lenders fail to make such an appointment, the Government is then
automatically obligated to "directly deal and negotiate" with the Senior Lenders regarding Section 17. In times of national emergency, when the public
NAIA IPT III. The only way the Government would not be liable for PIATCO's debt is for a interest so requires, the State may, during the emergency and under
qualified nominee or transferee to be appointed in place of PIATCO to continue the reasonable terms prescribed by it, temporarily take over or direct the
construction, operation and maintenance of NAIA IPT III. This "pre-condition",however, will operation of any privately owned public utility or business affected
not take the contract out of the ambit of a direct guarantee by the government as the with public interest.
existence, availability and willingness of a qualified nominee or transferee is totally out of
The above provision pertains to the right of the State in times of national
the government's control. As such the Government is virtually at the mercy of PIATCO (that
emergency, and in the exercise of its police power, to temporarily take over the operation
it would not default on its loan obligations to its Senior Lenders),the Senior Lenders (that
of any business affected with public interest. In the 1986 Constitutional Commission, the
they would appoint a qualified nominee or transferee or agree to some other arrangement
term "national emergency" was defined to include threat from external aggression,
with the Government) and the existence of a qualified nominee or transferee who is able
calamities or national disasters, but not strikes "unless it is of such proportion that would
and willing to take the place of PIATCO in NAIA IPT III.
paralyze government service." 60 The duration of the emergency itself is the determining
The proscription against government guarantee in any form is one of the policy factor as to how long the temporary takeover by the government would last. 61 The
considerations behind the BOT Law.Clearly, in the present case, the ARCA obligates the temporary takeover by the government extends only to the operation of the business and
Government to pay for all loans, advances and obligations arising out of financial facilities not to the ownership thereof. As such the government is not required to compensate the
extended to PIATCO for the implementation of the NAIA IPT III project should PIATCO private entity-owner of the said business as there is no transfer of ownership,whether
default in its loan obligations to its Senior Lenders and the latter fails to appoint a qualified permanent or temporary. The private entity-owner affected by the temporary takeover
nominee or transferee. This in effect would make the Government liable for PIATCO's loans cannot, likewise, claim just compensation for the use of the said business and its properties
as the temporary takeover by the government is in exercise of its police power and not of
its power of eminent domain.
Article V, Section 5.10 (c) of the 1997 Concession Agreement provides: Clearly, monopolies are not per se prohibited by the Constitution but may be
permitted to exist to aid the government in carrying on an enterprise or to aid in the
Section 5.10 Temporary Take-over of operations by GRP. performance of various services and functions in the interest of the public. 67 Nonetheless,
a determination must first be made as to whether public interest requires a monopoly. As
xxx xxx xxx monopolies are subject to abuses that can inflict severe prejudice to the public, they are
subject to a higher level of State regulation than an ordinary business undertaking.
(c) In the event the development Facility or any part thereof
and/or the operations of Concessionaire or any part thereof, become In the cases at bar, PIATCO, under the 1997 Concession Agreement and the
the subject matter of or be included in any notice, notification, or ARCA, is granted the "exclusive right to operate a commercial international passenger
declaration concerning or relating to acquisition, seizure or terminal within the Island of Luzon" at the NAIA IPT III. 68 This is with the exception of
appropriation by GRP in times of war or national emergency, GRP already existing international airports in Luzon such as those located in the Subic Bay
shall, by written notice to Concessionaire, immediately take over the Freeport Special Economic Zone ("SBFSEZ"), Clark Special Economic Zone ("CSEZ") and in
operations of the Terminal and/or the Terminal Complex. During such Laoag City. 69 As such, upon commencement of PIATCO's operation of NAIA IPT III,
take over by GRP, the Concession Period shall be suspended; Terminals 1 and 2 of NAIA would cease to function as international passenger terminals.
provided, that upon termination of war, hostilities or national This, however, does not prevent MIAA to use Terminals 1 and 2 as domestic passenger
emergency, the operations shall be returned to Concessionaire, at terminals or in any other manner as it may deem appropriate except those activities that
which time, the Concession period shall commence to run would compete with NAIA IPT III in the latter's operation as an international passenger
again. Concessionaire shall be entitled to reasonable compensation terminal. 70 The right granted to PIATCO to exclusively operate NAIA IPT III would be for
for the duration of the temporary take over by GRP, which a period of twenty-five (25) years from the In-Service Date 71 and renewable for another
compensation shall take into account the reasonable cost for the use twenty-five (25) years at the option of the government. 72 Both the 1997 Concession
of the Terminal and/or Terminal Complex, (which is in the amount at Agreement and the ARCA further provide that, in view of the exclusive right granted to
least equal to the debt service requirements of Concessionaire, if the PIATCO,the concession contracts of the service providers currently servicing Terminals 1
temporary take over should occur at the time when Concessionaire is and 2 would no longer be renewed and those concession contracts whose expiration are
still servicing debts owed to project lenders),any loss or damage to subsequent to the In-Service Date would cease to be effective on the said date. 73
the Development Facility, and other consequential damages. If the
parties cannot agree on the reasonable compensation of The operation of an international passenger airport terminal is no doubt an
Concessionaire, or on the liability of GRP as aforesaid, the matter shall undertaking imbued with public interest. In entering into a Build-Operate-and-Transfer
be resolved in accordance with Section 10.01 [Arbitration].Any contract for the construction, operation and maintenance of NAIA IPT III, the government
amount determined to be payable by GRP to Concessionaire shall be has determined that public interest would be served better if private sector resources were
offset from the amount next payable by Concessionaire to GRP. 62 used in its construction and an exclusive right to operate be granted to the private entity
undertaking the said project, in this case PIATCO. Nonetheless, the privilege given to
PIATCO cannot, by mere contractual stipulation, contravene the Constitutional PIATCO is subject to reasonable regulation and supervision by the Government through the
provision on temporary government takeover and obligate the government to pay MIAA, which is the government agency authorized to operate the NAIA complex, as well as
"reasonable cost for the use of the Terminal and/or Terminal Complex." 63 Article XII, DOTC, the department to which MIAA is attached. 74
section 17 of the 1987 Constitution envisions a situation wherein the exigencies of the times
necessitate the government to "temporarily take over or direct the operation of any This is in accord with the Constitutional mandate that a monopoly which is not
privately owned public utility or business affected with public interest." It is the welfare and prohibited must be regulated. 75 While it is the declared policy of the BOT Law to
interest of the public which is the paramount consideration in determining whether or not encourage private sector participation by "providing a climate of minimum government
to temporarily take over a particular business. Clearly, the State in effecting the temporary regulations," 76 the same does not mean that Government must completely surrender its
takeover is exercising its police power. Police power is the "most essential, insistent, and sovereign power to protect public interest in the operation of a public utility as a monopoly.
illimitable of powers." 64 Its exercise therefore must not be unreasonably hampered nor The operation of said public utility can not be done in an arbitrary manner to the detriment
its exercise be a source of obligation by the government in the absence of damage due to of the public which it seeks to serve. The right granted to the public utility may be exclusive
arbitrariness of its exercise. 65 Thus, requiring the government to pay reasonable but the exercise of the right cannot run riot. Thus, while PIATCO may be authorized to
compensation for the reasonable use of the property pursuant to the operation of the exclusively operate NAIA IPT III as an international passenger terminal, the Government,
business contravenes theConstitution. through the MIAA, has the right and the duty to ensure that it is done in accord with public
interest. PIATCO's right to operate NAIA IPT III cannot also violate the rights of third
V parties.
Regulation of Monopolies
Section 3.01(e) of the 1997 Concession Agreement and the ARCA provide:
A monopoly is "a privilege or peculiar advantage vested in one or more persons
or companies, consisting in the exclusive right (or power) to carry on a particular business 3.01 Concession Period
or trade, manufacture a particular article, or control the sale of a particular
commodity." 66 The 1987 Constitution strictly regulates monopolies,whether private or xxx xxx xxx
public, and even provides for their prohibition if public interest so requires. Article XII,
(e) GRP confirms that certain concession
Section 19 of the 1987 Constitution states:
agreements relative to certain services and operations currently being
Sec. 19. The state shall regulate or prohibit monopolies undertaken at the Ninoy Aquino International Airport passenger
when the public interest so requires. No combinations in restraint of Terminal I have a validity period extending beyond the In-Service
trade or unfair competition shall be allowed. Date.GRP through DOTC/MIAA, confirms that these services and
operations shall not be carried over to the Terminal and the
Concessionaire is under no legal obligation to permit such carry- Davide, Jr.,C.J.,Bellosillo, Ynares-Santiago, Sandoval-Gutierrez, Austria Martinez,
over except through a separate agreement duly entered into with Corona and Carpio Morales, JJ., concur.
Concessionaire. In the event Concessionaire becomes involved in any
litigation initiated by any such concessionaire or operator, GRP Vitug, J.,please see separate (dissenting) opinion
undertakes and hereby holds Concessionaire free and harmless on full
indemnity basis from and against any loss and/or any liability Panganiban, J.,please see separate opinion
resulting from any such litigation, including the cost of litigation and
Quisumbing and Azcuna, JJ.,concur with separate (dissenting) opinion of J. Vitug.
the reasonable fees paid or payable to Concessionaire's counsel of
choice, all such amounts shall be fully deductible by way of an offset Callejo, Sr.,J.,concurs with separate opinion of J. Panganiban.
from any amount which the Concessionaire is bound to pay GRP under
this Agreement. Carpio, J., took no part.

During the oral arguments on December 10, 2002, the counsel for the petitioners-
in-intervention for G.R. No. 155001 stated that there are two service providers whose
contracts are still existing and whose validity extends beyond the In-Service Date. One Separate Opinions
contract remains valid until 2008 and the other until 2010. 77

We hold that while the service providers presently operating at NAIA Terminal 1 VITUG, J.:
do not have an absolute right for the renewal or the extension of their respective contracts,
those contracts whose duration extends beyond NAIA IPT III's In-Service-Date should not This Court is bereft of jurisdiction to hear the petitions at bar.
be unduly prejudiced. These contracts must be respected not just by the parties thereto The Constitution provides that the Supreme Court shall exercise original jurisdiction over,
but also by third parties. PIATCO cannot, by law and certainly not by contract, render a among other actual controversies, petitions for certiorari, prohibition, mandamus, quo
valid and binding contract nugatory. PIATCO, by the mere expedient of claiming an warranto, and habeas corpus. 1 The cases in question, although denominated to be
exclusive right to operate, cannot require the Government to break its contractual petitions for prohibition, actually pray for the nullification of the PIATCO contracts and to
obligations to the service providers. In contrast to the arrastre and stevedoring service restrain respondents from implementing said agreements for being illegal and
providers in the case of Anglo-Fil Trading Corporation v. Lazaro 78 whose contracts consist unconstitutional.
of temporary hold-over permits, the affected service providers in the cases at bar, have a
valid and binding contract with the Government, through MIAA, whose period of effectivity, Section 2, Rule 65 of the Rules of Court states:
as well as the other terms and conditions thereof cannot be violated.
"When the proceedings of any tribunal, corporation, board,
In fine, the efficient functioning of NAIA IPT III is imbued with public interest. The officer or person, whether exercising judicial, quasi-judicial or
provisions of the 1997 Concession Agreement and the ARCA did not strip government, thru ministerial functions, are without or in excess of its or his jurisdiction,
the MIAA, of its right to supervise the operation of the whole NAIA complex, including NAIA or with grave abuse of discretion amounting to lack or excess of
IPT III. As the primary government agency tasked with the job, 79 it is MIAA's jurisdiction, and there is no appeal or any other plain, speedy and
responsibility to ensure that whoever by contract is given the right to operate NAIA IPT III adequate remedy in the ordinary course of law, a person aggrieved
will do so within the bounds of the law and with due regard to the rights of third parties thereby may file a verified petition in the proper court, alleging the
and above all, the interest of the public. facts with certainty and praying that judgment be rendered
commanding the respondent to desist from further proceedings in the
VI action or matter specified therein, or otherwise granting such
CONCLUSION incidental reliefs as law and justice may require."

In sum, this Court rules that in view of the absence of the requisite financial The rule is explicit. A petition for prohibition may be filed against a tribunal,
capacity of the Paircargo Consortium, predecessor of respondent PIATCO, the award by the corporation, board, officer or person, exercising judicial, quasi-judicial or ministerial
PBAC of the contract for the construction, operation and maintenance of the NAIA IPT III functions.What the petitions seek from respondents do not involve judicial, quasi-judicial
is null and void. Further, considering that the 1997 Concession Agreement contains material or ministerial functions. In prohibition, only legal issues affecting the jurisdiction of the
and substantial amendments, which amendments had the effect of converting the 1997 tribunal, board or officer involved may be resolved on the basis of undisputed facts. 2 The
Concession Agreement into an entirely different agreement from the contract bidded upon, parties allege, respectively, contentious evidentiary facts. It would be difficult, if not
the 1997 Concession Agreement is similarly null and void for being contrary to public policy. anomalous, to decide the jurisdictional issue on the basis of the contradictory factual
The provisions under Sections 4.04(b) and (c) in relation to Section 1.06 of the 1997 submissions made by the parties. 3 As the Court has so often exhorted, it is not a trier of
Concession Agreement and Section 4.04(c) in relation to Section 1.06 of the ARCA, which facts.
constitute a direct government guarantee expressly prohibited by, among others, the BOT
Law and its Implementing Rules and Regulations are also null and void. The Supplements, The petitions, in effect, are in the nature of actions for declaratory relief under
being accessory contracts to the ARCA, are likewise null and void. TcEaAS Rule 63 of the Rules of Court. The Rules provide that any person interested under a contract
may, before breach or violation thereof, bring an action in the appropriate Regional Trial
WHEREFORE, the 1997 Concession Agreement, the Amended and Restated Court to determine any question of construction or validity arising, and for a declaration of
Concession Agreement and the Supplements thereto are set aside for being null and void. his rights or duties thereunder. 4 The Supreme Court assumes no jurisdiction over petitions
for declaratory relief which are cognizable by regional trial courts. 5
SO ORDERED.
As I have so expressed in Tolentino vs. Secretary of Finance, 6 reiterated
in Santiago vs. Guingona, Jr., 7 the Supreme Court should not be thought of as having
been tasked with the awesome responsibility of overseeing the entire bureaucracy. The Court has, in the past, held that questions relating to gargantuan government
Pervasive and limitless, such as it may seem to be under the 1987 Constitution, judicial contracts ought to be settled without delay. 2 This holding applies with greater force to the
power still succumbs to the paramount doctrine of separation of powers. The Court may instant cases. Respondent Piatco is partly correct in averring that petitioners can obtain
not at good liberty intrude, in the guise of sovereign imprimatur, into every affair of relief from the regional trial courts via an action to annul the contracts.
government. What significance can still then remain of the time-honored and widely
acclaimed principle of separation of powers if, at every turn, the Court allows itself to pass Nevertheless, the unavoidable consequence of having to await the rendition and
upon at will the disposition of a co-equal, independent and coordinate branch in our system the finality of any such judgment would be a prolonged state of uncertainty that would be
of government. I dread to think of the so varied uncertainties that such an undue prejudicial to the nation, the parties and the general public. And, in light of the feared loss
interference can lead to. CSTDIE of jobs of the petitioning workers, consequent to the inevitable pretermination of contracts
of the petitioning service providers that will follow upon the heels of the impending opening
Accordingly, I vote for the dismissal of the petition. of NAIA Terminal III, the need for relief is patently urgent, and therefore, direct resort to
this Court through the special civil action of prohibition is thus justified. 3
PANGANIBAN, J.:
Contrary to Piatco's argument that the resolution of the issues raised in the
Petitions will require delving into factual questions, 4 I submit that their disposition
The five contracts for the construction and the operation of Ninoy Aquino ultimately turns on questions of law. 5 Further, many of the significant and relevant factual
International Airport (NAIA) Terminal III, the subject of the consolidated Petitions before questions can be easily addressed by an examination of the documents submitted by the
the Court, are replete with outright violations of law, public policy and the Constitution. The parties. In any event, the Petitions raise some novel questions involving the application of
only proper thing to do is declare them all null and void ab initio and let the chips fall where the amended BOT Law, which this Court has seen fit to tackle.
they may. Fiat iustitia ruat coelum.
Arbitration
The facts leading to this controversy are already well presented in the ponencia.I
shall not burden the readers with a retelling thereof. Instead, I will cut to the chase and Should the dispute be referred to arbitration prior to judicial recourse?
directly address the two sets of gut issues: Respondent Piatco claims that Section 10.02 of the Amended and Restated Concession
Agreement (ARCA) provides for arbitration under the auspices of the International Chamber
1. The first issue is procedural:Does the Supreme Court have original jurisdiction of Commerce to settle any dispute or controversy or claim arising in connection with the
to hear and decide the Petitions? Corollarily, do petitioners have locus standiand should this Concession Agreement, its amendments and supplements. The government disagrees,
Court decide the cases without any mandatory referral to arbitration? however, insisting that there can be no arbitration based on Section 10.02 of the ARCA,
since all the Piatco contracts are void ab initio.Therefore, all contractual provisions,
2. The second one is substantive in character: Did the subject contracts violate including Section 10.02 of the ARCA, are likewise void, inexistent and inoperative. To
the Constitution, the laws, and public policy to such an extent as to render all of them void support its stand, the government cites Chavez v. Presidential Commission on Good
and inexistent? Government: 6 "The void agreement will not be rendered operative by the parties' alleged
performance (partial or full) of their respective prestations. A contract that violates
My answer to all the above questions is a firm "Yes." the Constitution and the law is null and void ab initio and vests no rights and creates no
obligations. It produces no legal effect at all."
The Procedural Issue:
As will be discussed at length later, the Piatco contracts are indeed void in their
Jurisdiction, Standing and Arbitration
entirety; thus, a resort to the aforesaid provision on arbitration is unavailing. Besides,
Definitely and surely, the issues involved in these Petitions are clearly of petitioners and petitioners-in-intervention have pointed out that, even
transcendental importance and of national interest. The subject contracts pertain to the granting arguendo that the arbitration clause remained a valid provision, it still cannot bind
construction and the operation of the country's premiere international airport terminal — them inasmuch as they are not parties to the Piatco contracts. And in the final analysis, it
an ultramodern world-class public utility that will play a major role in the country's economic is unarguable that the arbitration process provided for under Section 10.02 of the ARCA, to
development and serve to project a positive image of our country abroad. The five build- be undertaken by a panel of three (3) arbitrators appointed in accordance with the Rules
operate-&-transfer (BOT) contracts, while entailing the investment of billions of pesos in of Arbitration of the International Chamber of Commerce, will not be able to address,
capital and the availment of several hundred millions of dollars in loans, contain provisions determine and definitively resolve the constitutional and legal questions that have been
that tend to establish a monopoly, require the disbursements of public funds sans raised in the Petitions before us.
appropriations, and provide government guarantees in violation of statutory prohibitions,
as well as other provisions equally offensive to law, public policy and the Constitution. Public Locus Standi
interest will inevitably be affected thereby. Given this Court's previous decisions in cases of similar import, no one will
seriously doubt that, being taxpayers and members of the House of Representatives,
Thus, objections to these Petitions, grounded upon (a) the hierarchy of courts,
Petitioners Baterina et al.,have locus standi to bring the Petition in GR No. 155547.
(b) the need for arbitration prior to court action, and (c) the alleged lack of sufficient
In Albano v. Reyes, 7 this Court held that the petitioner therein, suing as a citizen, taxpayer
personality, standing or interest, being in the main procedural matters, must now be set
and member of the House of Representatives, was sufficiently clothed with standing to
aside, as they have been in past cases. This Court must be permitted to perform its
bring the suit questioning the validity of the assailed contract. The Court cited the fact that
constitutional duty of determining whether the other agencies of government have acted
public interest was involved, in view of the important role of the Manila International
within the limits of the Constitution and the laws, or if they have gravely abused the
Container Terminal (MICT) in the country's economic development and the magnitude of
discretion entrusted to them. 1
the financial consideration. This, notwithstanding the fact that expenditure of public funds
Hierarchy of Courts was not required under the assailed contract.
In the cases presently under consideration, petitioners' personal and substantial The build-operate-and-transfer (BOT) project for the NAIA Passenger Terminal III
interest in the controversy is shown by the fact that certain provisions in the Piatco comes under the category of an "unsolicited proposal," which is the subject of Section 4-A
contracts create obligations on the part of government (through the DOTC and the MIAA) of the BOT Law. 10 The unsolicited proposal was originally submitted by the Asia's
to disburse public funds without prior congressional appropriations. Emerging Dragon Corporation (AEDC) to the Department of Transportation and
Communications (DOTC) and the Manila International Airport Authority (MIAA),which
Petitioners thus correctly assert that the injury to them has a twofold aspect: (1) reviewed and approved the proposal.
they are adversely affected as taxpayers on account of the illegal disbursement of public
funds; and (2) they are prejudiced qua legislators, since the contractual provisions The draft of the concession agreement as negotiated between AEDC and
requiring the government to incur expenditures without appropriations also operate as DOTC/MIAA was endorsed to the National Economic Development Authority (NEDA-
limitations upon the exclusive power and prerogative of Congress over the public purse. As ICC),which in turn reviewed it on the basis of its scope, economic viability, financial
members of the House of Representatives, they are actually deprived of discretion insofar indicators and risks; and thereafter approved it for bidding.
as the inclusion of those items of expenditure in the budget is concerned. To prevent such
encroachment upon the legislative privilege and obviate injury to the institution of which The DOTC/MIAA then prepared the Bid Documents, incorporating therein the
they are members, petitioners-legislators have locus standi to bring suit. negotiated Draft Concession Agreement, and published invitations for public bidding, i.e.,for
the submission of comparative or competitive proposals. Piatco's predecessor-in-interest,
Messrs. Agan et al and Lopez et al., are likewise taxpayers and thus possessed of the Paircargo Consortium, was the only company that submitted a competitive bid or price
standing to challenge the illegal disbursement of public funds. Messrs. Agan et al., in challenge.
particular, are employees (or representatives of employees) of various service providers
that have (1) existing concession agreements with the MIAA to provide airport services At this point, I must emphasize that the law requires the award of a BOT project
necessary to the operation of the NAIA and (2) service agreements to furnish essential to the bidder that has satisfied the minimum requirements; and met the technical, financial,
support services to the international airlines operating at the NAIA. organizational and legal standards provided in the BOT Law. Section 5 of this statute states:

On the other hand, Messrs. Lopez et al. are employees of the MIAA. These "Sec. 5. Public bidding of projects.- ...
petitioners (Messrs. Agan et al. and Messrs. Lopez et al.) are confronted with the prospect
of being laid off from their jobs and losing their means of livelihood when their employer- "In the case of a build-operate-and-transfer arrangement,
companies are forced to shut down or otherwise retrench and cut back on manpower. Such the contract shall be awarded to the bidder who, having satisfied the
development would result from the imminent implementation of certain provisions in the minimum financial, technical, organizational and legal standards
contracts that tend toward the creation of a monopoly in favor of Piatco, its subsidiaries required by this Act,has submitted the lowest bid and most favorable
and related companies. terms for the project, based on the present value of its proposed tolls,
fees, rentals and charges over a fixed term for the facility to be
Petitioners-in-intervention are service providers in the business of furnishing constructed, rehabilitated, operated and maintained according to the
airport-related services to international airlines and passengers in the NAIA and are prescribed minimum design and performance standards, plans and
therefore competitors of Piatco as far as that line of business is concerned. On account of specifications. ..." (Italics supplied.)
provisions in the Piatco contracts, petitioners-in-intervention have to enter into a written
contract with Piatco so as not to be shut out of NAIA Terminal III and barred from doing The same provision requires that the price challenge via public bidding "must be
business there. Since there is no provision to ensure or safeguard free and fair competition, conducted under a two-envelope/two-stage system: the first envelope to contain the
they are literally at its mercy. They claim injury on account of their deprivation of property technical proposal and the second envelope to contain the financial proposal." Moreover,
(business) and of the liberty to contract, without due process of law. the 1994 Implementing Rules and Regulations (IRR) provide that only those bidders that
have passed the prequalification stage are permitted to have their two envelopes reviewed.
And even if petitioners and petitioners-in-intervention were not sufficiently
clothed with legal standing, I have at the outset already established that, given its impact In other words, prospective bidders must prequalify by submitting their
on the public and on national interest, this controversy is laden with transcendental prequalification documents for evaluation; and only the pre-qualified bidders would be
importance and constitutional significance. Hence, I do not hesitate to adopt the same entitled to have their bids opened, evaluated and appreciated. On the other hand,
position as was enunciated in Kilosbayan v. Guingona Jr. 8 that "in cases of transcendental disqualified bidders are to be informed of the reason for their disqualification. This
importance, the Court may relax the standing requirements and allow a suit to prosper procedure was confirmed and reiterated in the Bid Documents, which I quote thus:
even when there is no direct injury to the party claiming the right of judicial review." 9 "Prequalified proponents will be considered eligible to move to second stage technical
proposal evaluation. The second and third envelopes of pre-disqualified proponents will be
The Substantive Issue: returned." 11

Violations of the Constitution and the Laws Aside from complying with the legal and technical requirements (track record or
experience of the firm and its key personnel),a project proponent desiring to prequalify
From the Outset, the Bidding must also demonstrate its financial capacity to undertake the project. To establish such
Process Was Flawed and Tainted capability, a proponent must prove that it is able to raise the minimum amount of equity
After studying the documents submitted and arguments advanced by the parties, required for the project and to procure the loans or financing needed for it. Section 5.4(c)
I have no doubt that, right at the outset, Piatco was not qualified to participate in the of the 1994 IRR provides:
bidding process for the Terminal III project, but was nevertheless permitted to do so. It
"Sec. 5.4. Prequalification Requirements.— To pre-qualify, a
even won the bidding and was helped along by what appears to be a series of collusive and
project proponent must comply with the following requirements:
corrosive acts.
xxx xxx xxx
"c. Financial Capability. The project proponent must have subject to the same guidelines, requirements and limitations. The desired result is to be
adequate capability to sustain the financing requirements for the able to determine the best offer or lowest bid, all things being equal.
detailed engineering design, construction, and/or operation and
maintenance phases of the project, as the case may be. For purposes Inasmuch as the Paircargo consortium did not possess the minimum equity
of prequalification, this capability shall be measured in terms of: equivalent to 30 percent of the minimum project cost, it should not have been prequalified
(i) proof of the ability of the project proponent and/or the consortium or allowed to participate further in the bidding. The Prequalification and Bidding Committee
to provide a minimum amount of equity to the project,and (ii) a letter (PBAC) should therefore not have opened the two envelopes of the consortium containing
testimonial from reputable banks attesting that the project proponent its technical and financial proposals; required AEDC to match the consortium's bid; 16 or
and/or members of the consortium are banking with them, that they awarded the Concession Agreement to the consortium's successor-in-interest, Piatco.
are in good financial standing, and that they have adequate
resources. The government Agency/LGU concerned shall determine As there was effectively no public bidding to speak of, the entire bidding process
on a project-to-project basis, and before prequalification, the having been flawed and tainted from the very outset, therefore, the award of the concession
minimum amount of equity needed. ...." (Italics supplied) to Paircargo's successor Piatco was void, and the Concession Agreement executed with the
latter was likewise void ab initio. For this reason, Piatco cannot and should not be allowed
Since the minimum amount of equity for the project was set at 30 percent 12 of to benefit from that Agreement. 17
the minimum project cost of US$350 million, the minimum amount of equity required of
any proponent stood at US$105 million. Converted to pesos at the exchange rate then of AEDC Was Deprived of the
P26.239 to US$1.00 (as quoted by the Bangko Sentral ng Pilipinas),the peso equivalent of Right to Match PIATCO's
the minimum equity was P2,755,095,000. Price Challenge
In DOTC PBAC Bid Bulletin No. 4 (par. 3),Undersecretary Cal declared that, for
However, the combined equity or net worth of the Paircargo consortium stood at purposes of matching the price challenge of Piatco, AEDC as originator of the unsolicited
only P558,384,871.55. 13 This amount was only slightly over 6 percent of the minimum proposal would be permitted access only to the schedule of proposed Annual Guaranteed
project cost and very much short of the required minimum equity, which was equivalent to Payments submitted by Piatco, and not to the latter's financial and technical proposals that
30 percent of the project cost. Such deficiency should have immediately caused the constituted the basis for the price challenge in the first place. This was supposedly in
disqualification of the Paircargo consortium. This matter was brought to the attention of the keeping with Section 11.6 of the 1994 IRR, which provides that proprietary information is
Prequalification and Bidding Committee (PBAC). to be respected, protected and treated with utmost confidentiality, and is therefore not to
form part of the bidding/tender and related documents.
Notwithstanding the glaring deficiency, DOTC Undersecretary Primitivo C. Cal,
concurrent chair of the PBAC, declared in a Memorandum dated 14 October 1996 that "the This pronouncement, I believe, was a grievous misapplication of the mentioned
Challenger (Paircargo consortium) was found to have a combined net worth of provision. The "proprietary information" referred to in Section 11.6 of the IRR pertains only
P3,926,421,242.00 that could support a project costing approximately P13 billion." To to the proprietary information of the originator of an unsolicited proposal, and not to those
justify his conclusion, he asserted: "It is not a requirement that the networth must be belonging to a challenger. The reason for the protection accorded proprietary information
`unrestricted.' To impose this as a requirement now will be nothing less than unfair." at all is the fact that, according to Section 4-A of the BOT Law as amended, a proposal
qualifies as an "unsolicited proposal" when it pertains to a project that involves "a new
He further opined, "(T)he networth reflected in the Financial Statement should
concept or technology," and/or a project that is not on the government's list of priority
not be taken as the amount of money to be used to answer the required thirty (30%)
projects.
percent equity of the challenger but rather to be used in establishing if there is enough
basis to believe that the challenger can comply with the required 30% equity. In fact, proof To be considered as utilizing a new concept or technology, a project must involve
of sufficient equity is required as one of the conditions for award of contract (Sec. 12.1 of the possession of exclusive rights (worldwide or regional) over a process; or possession of
IRR of the BOT Law) but not for prequalification (Sec. 5.4 of same document)." intellectual property rights over a design, methodology or engineering
concept. 18 Patently, the intent of the BOT Law is to encourage individuals and groups to
On the basis of the foregoing dubious declaration, the Paircargo consortium was
come up with creative innovations, fresh ideas and new technology. Hence, the significance
deemed prequalified and thus permitted to proceed to the other stages of the bidding
and necessity of protecting proprietary information in connection with unsolicited proposals.
process.
And to make the encouragement real, the law also extends to such individuals and groups
By virtue of the prequalified status conferred upon the Paircargo, Undersecretary what amounts to a "right of first refusal" to undertake the project they conceptualized,
Cal's findings in effect relieved the consortium of the need to comply with the financial involving the use of new technology or concepts, through the mechanism of matching a
capability requirement imposed by the BOT Law and IRR. This position is unmistakably and price challenge.
squarely at odds with the Supreme Court's consistent doctrine emphasizing the strict
A competing bid is never just any figure conjured from out of the blue; it is arrived
application of pertinent rules, regulations and guidelines for the public bidding process, in
at after studying economic, financial, technical and other, factors; it is likewise based on
order to place each bidder — actual or potential — on the same footing. Thus, it is
certain assumptions as to the nature of the business, the market potentials, the probable
unarguably irregular and contrary to the very concept of public bidding to permit a variance
demand for the product or service, the future behavior of cost items, political and other
between the conditions under which bids are invited and those under which proposals are
risks, and so on. It is thus self-evident that in order to be able to intelligently match a bid
submitted and approved.
or price challenge, a bidder must be given access to the assumptions and the calculations
Republic v. Capulong 14 teaches that if one bidder is relieved from having to that went into crafting the competing bid.
conform to the conditions that impose some duty upon it, that bidder is not contracting in
In this instance, the financial and technical proposals of Piatco would have
fair competition with those bidders that propose to be bound by all conditions. The essence
provided AEDC with the necessary information to enable it to make a reasonably informed
of public bidding is, after all, an opportunity for fair competition and a basis for the precise
matching bid. To put it more simply, a bidder unable to access the competitor's assumptions
comparison of bids. 15 Thus, each bidder must bid under the same conditions; and be
will never figure out how the competing bid came about; requiring him to "counter-propose" regulated scenario was likewise intended to discourage collusion and substantially reduce
is like having him shoot at a target in the dark while blindfolded. the opportunity for agents of government to abuse their discretion in the course of the
award process.
By withholding from AEDC the challenger's financial and technical proposals
containing the critical information it needed, Undersecretary Cal actually and effectively Despite the clear timetables set out in the IRR, several lengthy and still-
deprived AEDC of the ability to match the price challenge. One could say that AEDC did not unexplained delays occurred in the award process, as can be observed from the
have the benefit of a "level playing field." It seems to me, though, that AEDC was actually presentation made by the counsel for public respondents, 19 quoted hereinbelow:
shut out of the game altogether.
"11 Dec. 1996 — The Paircargo Joint Venture was informed
At the end of the day, the bottom line is that the validity and the propriety of the by the PBAC that AEDC failed to match and that negotiations
award to Piatco had been irreparably impaired. preparatory to Notice of Award should be commenced. This was
the decision to award that should have commenced the running of the
Delayed Issuance of the 7-day period to approve the Notice of Award, as per Section 9.1 of
Notice of Award Violated the IRR, or to submit the draft contract to the ICC for approval
the BOT Law and the IRR conformably with Section 9.2.
Section 9.5 of the IRR requires that the Notice of Award must indicate the time
"01 April 1997 — The PBAC resolved that a copy of the final
frame within which the winner of the bidding (and therefore the prospective awardee) shall
draft of the Concession Agreement be submitted to the NEDA for
submit the prescribed performance security, proof of commitment of equity contributions,
clearance on a no-objection basis. This resolution came more than 3
and indications of sources of financing (loans);and, in the case of joint ventures, an
months too late as it should have been made on the 20th of December
agreement showing that the members are jointly and severally responsible for the
1996 at the latest.
obligations of the project proponent under the contract.
"16 April 1997 — The PBAC resolved that the period of
The purpose of having a definite and firm timetable for the submission of the
signing the Concession Agreement be extended by 15 days.
aforementioned requirements is not only to prevent delays in the project implementation,
but also to expose and weed out unqualified proponents, who might have unceremoniously "18 April 1997 — NEDA approved the Concession
slipped through the earlier prequalification process, by compelling them to put their money Agreement. Again this is more than 3 months too late as the NEDA's
where their mouths are, so to speak. decision should have been released on the 16th of January 1997 or
fifteen days after it should have been submitted to it for review.
Nevertheless, this provision can be easily circumvented by merely postponing the
actual issuance of the Notice of Award, in order to give the favored proponent sufficient "09 July 1997 — The Notice of Award was issued to PIATCO.
time to comply with the requirements. Hence, to avert or minimize the manipulation of the Following the provisions of the IRR, the Notice of Award should have
post-bidding process, the IRR not only set out the precise sequence of events occurring been issued fourteen days after NEDA's approval, or the 28th of
between the completion of the evaluation of the technical bids and the issuance of the January 1997. In any case, even if it were to be assumed that the
Notice of Award, but also specified the timetables for each such event. Definite allowable release of NEDA's approval on the 18th of April was timely, the Notice
extensions of time were provided for, as were the consequences of a failure to meet a of Award should have been issued on the 9th of May 1997. In both
particular deadline. cases, therefore, the release of the Notice of Award occurred in a
decidedly less than timely fashion."
In particular, Section 9.1 of the 1994 IRR prescribed that within 30 calendar days
from the time the second-stage evaluation shall have been completed, the Committee must This chronology of events bespeaks an unmistakable disregard, if not disdain, by
come to a decision whether or not to award the contract and, within 7 days therefrom, the the persons in charge of the award process for the time limitations prescribed by the IRR.
Notice of Award must be approved by the head of agency or local government unit (LGU) Their attitude flies in the face of this Court's solemn pronouncement in Republic
concerned, and its issuance must follow within another 7 days thereafter. v. Capulong 20 that "strict observance of the rules, regulations and guidelines of the
bidding process is the only safeguard to a fair, honest and competitive public bidding."
Section 9.2 of the IRR set the procedure applicable to projects involving
substantial government undertakings as follows: Within 7 days after the decision to award From the foregoing, the only conclusion that can possibly be drawn is that the BOT
is made, the draft contract shall be submitted to the ICC for clearance on a no-objection law and its IRR were repeatedly violated with unmitigated impunity — and by agents of
basis. If the draft contract includes government undertakings already previously approved, government, no less! On account of such violation, the award of the contract to Piatco,
then the submission shall be for information only. which undoubtedly gained time and benefited from the delays, must be deemed null and
void from the beginning.
However, should there be additional or new provisions different from the original
government undertakings, the draft shall have to be reviewed and approved. The ICC has Further Amendments Resulted
15 working days to act thereon, and unless otherwise specified, its failure to act on the in a Substantially Different
contract within the specified time frame signifies that the agency or LGU may proceed with Contract, Awarded Without
the award. The head of agency or LGU shall approve the Notice of Award within seven days Public Bidding
of the clearance by the ICC on a no-objection basis, and the Notice itself has to be issued
within seven days thereafter. But the violations and desecrations did not stop there. After the PBAC made its
decision on December 11, 1996 to award the contract to Piatco, the latter negotiated
The highly regulated time-frames within which the agents of government were to changes to the Contract bidded out and ended up with what amounts to a substantially new
act evinced the intent to impose upon them the duty to act expeditiously throughout the contract without any public bidding.This Contract was subsequently further amended four
process, to the end that the project be prosecuted and implemented without delay. This more times through negotiation and without any bidding. Thus, the contract actually
executed between Piatco and DOTC/MIAA on July 12, 1997 (the Concession Agreement or 8. Under Section 8.07 of the DCA, the term attendant liabilities refers
"CA") differed from the contract bidded out (the draft concession agreement or "DCA") in to liabilities pertinent to NAIA Terminal III,such as payment
the following very significant respects: of lease rentals and performance of other obligations under
the Land Lease Agreement; the obligations under the
1. The CA inserted stipulations creating a monopoly in favor of Piatco Tenant Agreements; and payment of all taxes, fees, charges
in the business of providing airport-related services for and assessments of whatever kind that may be imposed on
international airlines and passengers. 21 NAIA Terminal III or parts thereof. But in Section 1.06 of
the CA, Attendant Liabilities refers to unpaid debts of
2. The CA provided that government is to answer for Piatco's unpaid Piatco:"All amounts recorded and from time to time
loans and debts (lumped under the term Attendant outstanding in the books of (Piatco) as owing to Unpaid
Liabilities) in the event Piatco fails to pay its senior Creditors who have provided, loaned or advanced funds
lenders. 22 actually used for the Project, including all interests,
penalties, associated fees, charges, surcharges,
3. The CA provided that in case of termination of the contract due to
indemnities, reimbursements and other related expenses,
the fault of government, government shall pay all expenses
and further including amounts owed by [Piatco] to its
that Piatco incurred for the project plus the appraised value
suppliers, contractors and subcontractors."
of the Terminal. 23
9. Per Sections 8.04 and 8.06 of the DCA, government may, on
4. The CA imposed new and special obligations on government,
account of the contractors breach,rescind the contract and
including delivery of clean possession of the site for the
select one of four options: (a) take over the terminal and
terminal; acquisition of additional land at the government's
assume all its attendant liabilities; (b) allow the contractor's
expense for construction of road networks required by
creditors to assign the Project to another entity acceptable
Piatco's approved plans and specifications; and assistance
to DOTC/MIAA; (c) pay the contractor rent for the facilities
to Piatco in securing site utilities, as well as all necessary
and equipment the DOTC may utilize; or (d) purchase the
permits, licenses and authorizations. 24
terminal at a price established by independent appraisers.
5. Where Section 3.02 of the DCA requires government to refrain Depending on the option selected, government may take
from competing with the contractor with respect to immediate possession and control of the terminal and its
the operation of NAIA Terminal III,Section 3.02(b) of the CA operations. Government will be obligated to compensate the
excludes and prohibits everyone,including government, contractor for the "equivalent or proportionate contract
from directly or indirectly competing with Piatco, with costs actually disbursed," but only where government is the
respect to the operation of, as well as operations in,NAIA one in breach of the contract. But under Section 8.06(a) of
Terminal III. Operations in is sufficiently broad to the CA, whether on account of Piatco's breach of contract or
encompass all retail and other commercial business its inability to pay its creditors, government is obliged to
enterprises operating within Terminal III, inclusive of the either (a) take over Terminal III and assume all of Piatco's
businesses of providing various airport-related services to debts or (b) permit the qualified unpaid creditors to be
international airlines, within the scope of the prohibition. substituted in place of Piatco or to designate a new operator.
And in the event of government's breach of contract, Piatco
6. Under Section 6.01 of the DCA, the following fees are subject to may compel it to purchase the terminal at fair market value,
the written approval of MIAA: lease/rental charges, per Section 8.06(b) of the CA.
concession privilege fees for passenger services, food
services, transportation utility concessions, groundhandling, 10. Under the DCA, any delay by Piatco in the payment of the
catering and miscellaneous concession fees, porterage fees, amounts due the government constitutes breach of
greeter/well-wisher fees, carpark fees, advertising fees, VIP contract. However, under the CA, such delay does not
facilities fees and others. Moreover, adjustments to the necessarily constitute breach of contract, since Piatco is
groundhandling fees, rentals and porterage fees are permitted to suspend payments to the government in order
permitted only once every two years and in accordance with to first satisfy the claims of its secured creditors, per Section
a parametric formula, per DCA Section 6.03. However, the 8.04(d) of the CA.
CA as executed with Piatco provides in Section 6.06 that all
It goes without saying that the amendment of the Contract bidded out (the DCA
the aforesaid fees, rentals and charges may be
or draft concession agreement) — in such substantial manner, without any public bidding,
adjusted without MIAA's approval or intervention. Neither
and after the bidding process had been concluded on December 11, 1996 — is violative of
are the adjustments to these fees and charges subject to or
public policy on public biddings, as well as the spirit and intent of theBOT Law. The whole
limited by any parametric formula. 25
point of going through the public bidding exercise was completely lost. Its very rationale
7. Section 1.29 of the DCA provides that the terminal fees, aircraft was totally subverted by permitting Piatco to amend the contract for which public bidding
tacking fees, aircraft parking fees, check-in counter fees and had already been concluded. Competitive bidding aims to obtain the best deal possible by
other fees are to be quoted and paid in Philippine pesos. But fostering transparency and preventing favoritism, collusion and fraud in the awarding of
per Section 1.33 of the CA, all the aforesaid fees save the contracts.That is the reason why procedural rules pertaining to public bidding demand strict
terminal fee are denominated in US Dollars. observance. 26
In a relatively early case, Caltex v. Delgado Brothers, 27 this Court made it clear public bidding will be destroyed — there will be no basis for an exact comparison between
that substantive amendments to a contract for which a public bidding has already been bids.
finished should only be awarded after another public bidding:
Moreover, Piatco misinterpreted the meaning behind PBAC Bid Bulletin No. 3. The
"The due execution of a contract after public bidding is a phrase amendments ... from time to time refers only to those amendments to the draft
limitation upon the right of the contracting parties to alter or amend concession agreement issued by the PBAC prior to the submission of the price challenge; it
it without another public bidding, for otherwise what would a public certainly does not include or permit amendments negotiated for and introduced after the
bidding be good for if after the execution of a contract after public bidding process, has been terminated.
bidding, the contracting parties may alter or amend the contract, or
even cancel it, at their will? Public biddings are held for the protection Piatco's Concession
of the public, and to give the public the best possible advantages by Agreement Was Further
means of open competition between the bidders. He who bids or offers Amended, (ARCA) Again
the best terms is awarded the contract subject of the bid, and it is Without Public Bidding
obvious that such protection and best possible advantages to the Not satisfied with the Concession Agreement, Piatco — once more without
public will disappear if the parties to a contract executed after public bothering with public bidding — negotiated with government for still more substantial
bidding may alter or amend it without another previous public changes. The result was the Amended and Restated Concession Agreement (ARCA)
bidding." 28 executed on November 26, 1998. The following changes were introduced:
The aforementioned case dealt with the unauthorized amendment of a contract 1. The definition of Attendant Liabilities was further amended with the
executed after public bidding; in the situation before us, the amendments were made also result that the unpaid loans of Piatco, for which government
after the bidding, but prior to execution. Be that as it may, the same rationale may be required to answer, are no longer limited to only
underlying Caltex applies to the present situation with equal force.Allowing the winning those loans recorded in Piatco's books or loans whose
bidder to renegotiate the contract for which the bidding process has ended is tantamount proceeds were actually used in the Terminal III project. 30
to permitting it to put in anything it wants. Here, the winning bidder (Piatco) did not even
bother to wait until after actual execution of the contract before rushing to amend it. 2. Although the contract may be terminated due to breach by Piatco,
Perhaps it believed that if the changes were made to a contract already won through bidding it will not be liable to pay the government any Liquidated
(DCA) instead of waiting until it is executed, the amendments would not be noticed or Damages if a new operator is designated to take over the
discovered by the public. operation of the terminal. 31
In a later case, Mata v. San Diego, 29 this Court reiterated its ruling as 3. The Liquidated Damages which government becomes liable for in
follows: IcaEDC case of its breach of contract were substantially
increased. 32
"It is true that modification of government contracts, after
the same had been awarded after a public bidding, is not allowed 4. Government's right to appoint a comptroller for Piatco in case the
because such modification serves to nullify the effects of the bidding latter encounters liquidity problems was deleted. 33
and whatever advantages the Government had secured thereby and
may also result in manifest injustice to the other bidders. This 5. Government is made liable for Incremental and Consequential
prohibition, however, refers to a change in vital and essential Costs and Losses in case it fails to comply or cause any third
particulars of the agreement which results in a substantially new party under its direct or indirect control to comply with the
contract." special obligations imposed on government. 34

Piatco's counter-argument may be summed up thus: There was nothing in the 6. The insurance policies obtained by Piatco covering the terminal are
1994 IRR that prohibited further negotiations and eventual amendments to the DCA even now required to be assigned to the Senior Lenders as
after the bidding had been concluded. In fact, PBAC Bid Bulletin No. 3 security for the loans; previously, their proceeds were to be
states: "[A]mendments to the Draft Concession Agreement shall be issued from time to used to repair and rehabilitate the facility in case of
time.Said amendments will only cover items that would not materially affect the preparation damage. 35
of the proponent's proposal."
7. Government bound itself to set the initial rate of the terminal fee,
I submit that accepting such warped argument will result in perverting the policy to be charged when Terminal III begins operations, at an
underlying public bidding. The BOT Law cannot be said to allow the negotiation of amount higher than US$20. 36
contractual stipulations resulting in a substantially new contract after the bidding process
and price challenge had been concluded. In fact, the BOT Law, in recognition of the time, 8. Government waived its defense of the illegality of the contract and
money and effort invested in an unsolicited proposal, accords its originator the privilege of even agreed to be liable to pay damages to Piatco in the
matching the challenger's bid. event the contract was declared illegal. 37

Section 4-A of the BOT Law specifically refers to a "lower price proposal" by a 9. Even though government may be entitled to terminate the ARCA
competing bidder; and to the right of the original proponent "to match the price" of the on account of breach by Piatco, government is still liable to
challenger. Thus, only the price proposals are in play. The terms, conditions and pay Piatco the appraised value of Terminal III or the
stipulations in the contract for which public bidding has been concluded are understood Attendant Liabilities, if the termination occurs before the In-
to remain intact and not be subject to further negotiation. Otherwise, the very essence of
Service Date. 38 This condition contravenes the BOT Government, Also Without
Lawprovision on termination compensation. Prior Public Bidding

10. Government is obligated to take the administrative action After Piatco had managed to breach the protective rampart of public bidding, it
required for Piatco's imposition, collection and application of recklessly went on a rampage of further assaults on the ARCA.
all Public Utility Revenues. 39No such obligation existed
The First Supplement Is
previously.
as Void as the ARCA
11. Government is now also obligated to perform and cause other In the First Supplement ("FS") executed on August 27, 1999, the following
persons and entities under its direct or indirect control to changes were made to the ARCA:
perform all acts necessary to perfect the security interests
to be created in favor of Piatco's Senior Lenders. 40 No such 1. The amounts payable by Piatco to government were reduced by
obligation existed previously. allowing additional exceptions to the Gross Revenues in
which government is supposed to participate. 45
12. DOTC/MIAA's right of intervention in instances where Piatco's
Non-Public Utility Revenues become exorbitant or excessive 2. Made part of the properties which government is obliged to
has been removed. 41 construct and/or maintain and keep in good repair are (a)
the access road connecting Terminals II and III — the
13. The illegality and unenforceability of the ARCA or any of its construction of this access road is the obligation of Piatco,
material provisions was made an event of default on the in lieu of its obligation to construct an Access Tunnel
part of government only,thus constituting a ground for connecting Terminals II and III; and (b) the taxilane and
Piatco to terminate the ARCA. 42 taxiway — these are likewise part of Piatco's obligations,
since they are part and parcel of the project as described in
14. Amounts due from and payable by government under the contract
Clause 1.3 of the Bid Documents. 46
were made payable on demand — net of taxes, levies,
imposts, duties, charges or fees of any kind except as 3. The MIAA is obligated to provide funding for the maintenance and
required by law. 43 repair of the airports and facilities owned or operated by it
and by third persons under its control. It will also be liable
15. The Parametric Formula in the contract, which is utilized to
to Piatco for the latter's losses, expenses and damages as
compute for adjustments/increases to the public utility
well as liability to third persons, in case MIAA fails to perform
revenues (i.e.,aircraft parking and tacking fees, check-in
such obligations. In addition, MIAA will also be liable for the
counter fee and terminal fee),was revised to permit Piatco
incremental and consequential costs of the remedial work
to input its more costly short-term borrowing rates instead
done by Piatco on account of the former's default. 47
of the longer-terms rates in the computations for
adjustments, with the end result that the changes will 4. The FS also imposed on government ten (10) "Additional Special
redound to its greater financial benefit. Obligations," including the following:
16. The Certificate of Completion simply deleted the successful (a) Working for the removal of the general aviation traffic
performance-testing of the terminal facility in accordance from the NAIA airport complex 48
with defined performance standards as a pre-condition for
government's acceptance of the terminal facility. 44 (b) Providing through MIAA the land required by Piatco for
the taxilane and one taxiway at no cost to
In sum, the foregoing revisions and amendments as embodied in the ARCA Piatco 49
constitute very material alterations of the terms and conditions of the CA, and give further
manifestly undue advantage to Piatco at the expense of government.Piatco claims that the (c) Implementing the government's existing storm drainage
changes to the CA were necessitated by the demands of its foreign lenders. However, no master plan 50
proof whatsoever has been adduced to buttress this claim.
(d) Coordinating with DPWH the financing, the
In any event, it is quite patent that the sum total of the aforementioned changes implementation and the completion of the
resulted in drastically weakening the position of government to a degree that seems quite following works before the In-Service Date: three
excessive, even from the standpoint of a businessperson who regularly transacts with banks left-turning overpasses (EDSA to Tramo St.,Tramo
and foreign lenders, is familiar with their mind-set, and understands what motivates them. to Andrews Ave.,and Manlunas Road to Sales
On the other hand, whatever it was that impelled government officials concerned to accede Ave.); 51 and a road upgrade and improvement
to those grossly disadvantageous changes, I can only hazard a guess. program involving widening, repair and
resurfacing of Sales Road, Andrews Avenue and
There is no question in my mind that the ARCA was unauthorized and illegal for Manlunas Road; improvement of Nichols
lack of public bidding and for being patently disadvantageous to government. Interchange; and removal of squatters along
Andrews Avenue. 52
The Three Supplements
Imposed New Obligations on
(e) Dealing directly with BCDA and the Phil. Air Force in By way of background, at the inception of and forming part of the NAIA Terminal
acquiring additional land or right of way for the III project was the proposed construction of an access tunnel crossing Runway 13/31, which
road upgrade and improvement program.53 would connect Terminal III to Terminal II. The Bid Documents in Section 4.1.2.3[B][i]
declared that the said access tunnel was subject to further negotiation; but for purposes of
5. Government is required to work for the immediate reversion to the bidding, the proponent should submit a bid for it as well. Therefore, the tunnel was
MIAA of the Nayong Pilipino National Park. 54 supposed to be part and parcel of the Terminal III project.
6. Government's share in the terminal fees collected was revised from However, in Section 5 of the First Supplement, the parties declared that the access
a flat rate of P180 to 36 percent thereof; together with tunnel was not economically viable at that time. In lieu thereof, the parties agreed that a
government's percentage share in the gross revenues of surface access road (now called the T2-T3 Road) was to be constructed by Piatco to connect
Piatco, the amount will be remitted to government in pesos the two terminals. Since it was plainly in substitution of the tunnel, the surface road
instead of US dollars. 55 This amendment enables Piatco to construction should likewise be considered part and parcel of the same project, and
benefit from the further erosion of the peso-dollar exchange therefore part of Piatco's obligation as well. While the access tunnel was estimated to cost
rate, while preventing government from building up its about P800 million, the surface road would have a price tag in the vicinity of about P100
foreign exchange reserves. million, thus producing significant savings for Piatco.
7. All payments from Piatco to government are now to be invoiced to Yet, the Third Supplement, while confirming that Piatco would construct the T2-
MIAA, and payments are to accrue to the latter's exclusive T3 Road, nevertheless shifted to government some of the obligations pertaining to the
benefit. 56 This move appears to be in support of the funds former, as follows:
MIAA advanced to DPWH.
1. Government is now obliged to remove at its own expense all
I must emphasize that the First Supplement is void in two respects. First,it is tenants, squatters, improvements and/or waste materials
merely an amendment to the ARCA, upon which it is wholly dependent; therefore, since on the site where the T2-T3 road is to be
the ARCA is void, inexistent and not capable of being ratified or amended, it follows that constructed. 58 There was no similar obligation on the part
the FS too is void, inexistent and inoperative. Second,even assumingarguendo that the of government insofar as the access tunnel was concerned.
ARCA is somehow remotely valid, nonetheless the FS, in imposing significant new
obligations upon government, altered the fundamental terms and stipulations of the ARCA, 2. Should government fail to carry out its obligation as above
thus necessitating a public bidding all over again. That the FS was entered into sans public described, Piatco may undertake it on government's behalf,
bidding renders it utterly void and inoperative. subject to the terms and conditions (including compensation
payments) contained in the Second Supplement. 59
The Second Supplement Is
Similarly Void and Inexistent 3. MIAA will answer for the operation, maintenance and repair of the
T2-T3 Road. 60
The Second Supplement ("SS") was executed between the government and Piatco
on September 4, 2000. It calls for Piatco, acting not as concessionaire of NAIA Terminal III The TS depends upon and is intended to supplement the ARCA as well as the First
but as a public works contractor, to undertake — in the government's stead — the clearing, Supplement, both of which are void and inexistent and not capable of being ratified or
removal, demolition and disposal of improvements, subterranean obstructions and waste amended. It follows that the TS is likewise void, inexistent and inoperative. And even if,
materials at the project site. 57 hypothetically speaking, both ARCA and FS are valid, still, the Third Supplement — imposing
as it does significant new obligations upon government — would in effect alter the terms
The scope of the works, the procedures involved, and the obligations of the
and stipulations of the ARCA in material respects, thus necessitating another public bidding.
contractor are provided for in Parts II and III of the SS. Section 4.1 sets out the
Since the TS was not subjected to public bidding, it is consequently utterly void as well. At
compensation to be paid, listing specific rates per cubic meter of materials for each phase
any rate, the TS created new monetary obligations on the part of government, for which
of the work — excavation, leveling, removal and disposal, backfilling and dewatering. The
there were no prior appropriations. Hence it follows that the same is void ab initio.
amounts collectible by Piatco are to be offset against the Annual Guaranteed Payments it
must pay government. In patiently tracing the progress of the Piatco contracts from their inception up to
the present, I noted that the whole process was riddled with significant lapses, if not
Though denominated as Second Supplement, it was nothing less than an entirely
outright irregularity and wholesale violations of law and public policy. The rationale of
new public works contract. Yet it, too, did not undergo any public bidding, for which reason
beginning at the beginning, so to speak, will become evident when the question of what to
it is also void and inoperative.
do with the five Piatco contracts is discussed later on.
Not surprisingly, Piatco had to subcontract the works to a certain Wintrack
In the meantime, I shall take up specific, provisions or changes in the contracts
Builders, a firm reputedly owned by a former high-ranking DOTC official. But that is another
and highlight the more prominent objectionable features.
story altogether.
Government Directly
The Third Supplement Is
Guarantees Piatco Debts
Likewise Void and Inexistent
Certainly the most discussed provision in the parties' arguments is the one
The Third Supplement ("TS"),executed between the government and Piatco on
creating an unauthorized, direct government guarantee of Piatco's obligations in favor of
June 22, 2001, passed on to the government certain obligations of Piatco as Terminal III
the lenders.
concessionaire, with respect to the surface road connecting Terminals II and III.
Section 4-A of the BOT Law as amended states that unsolicited proposals,such as effort (equally unsuccessful) to "enter into any other arrangement" with the government
the NAIA Terminal III Project, may be accepted by government provided inter aliathat no regarding the Terminal III facility, before government is required to make good on its
direct government guarantee, subsidy or equity is required.In short, such guarantee is guarantee. What is abundantly clear is the fact that, in the devious labyrinthine process
prohibited in unsolicited proposals. Section 2(n) of the same legislation defines direct detailed in the aforesaid section, it is entirely within the Senior Lenders' power, prerogative
government guarantee as "an agreement whereby the government or any of its agencies and control — exercisable via a mere refusal or inability to agree upon "a transferee" or
or local government units (will) assume responsibility for the repayment of debt directly "any other arrangement" regarding the terminal facility — to push the process forward to
incurred by the project proponent in implementing the project in case of a loan default." the ultimate contractual cul-de-sac, wherein government will be compelled to abjectly
surrender and make good on its guarantee of payment.
Both the CA and the ARCA have provisions that undeniably create such prohibited
government guarantee. Section 4.04 (c)(iv) to (vi) of the ARCA, which is similar to Section Piatco also argues that there is no proviso requiring government to pay the Senior
4.04 of the CA, provides thus: Lenders in the event of Piatco's default. This is literally true, in the sense that Section
4.04(c)(vi) of ARCA speaks of government making the termination payment to Piatco,not
"(iv) that if Concessionaire is in default under a payment to the lenders. However, it is almost a certainty that the Senior Lenders will already have
obligation owed to the Senior Lenders, and as a result thereof the made Piatco sign over to them, ahead of time, its right to receive such payments from
Senior Lenders have become entitled to accelerate the Senior Loans, government; and/or they may already have had themselves appointed its attorneys-in-fact
the Senior Lenders shall have the right to notify GRP of the same ...; for the purpose of collecting and receiving such payments.
(v) ...the Senior Lenders may after written notification to Nevertheless, as petitioners-in-intervention pointed out in their
GRP, transfer the Concessionaire's rights and obligations to a Memorandum, 61 the termination payment is to be made to Piatco, not to the lenders; and
transferee ...; there is no provision anywhere in the contract documents to prevent it from diverting the
proceeds to its own benefit and/or to ensure that it will necessarily use the same to pay off
(vi) if the Senior Lenders ...are unable to ...effect a transfer the Senior Lenders and other creditors, in order to avert the foreclosure of the mortgage
...,then GRP and the Senior Lenders shall endeavor ...to enter into and other liens on the terminal facility. Such deficiency puts the interests of government at
any other arrangement relating to the Development Facility. ...If no great risk. Indeed, if the unthinkable were to happen, government would be paying several
agreement relating to the Development Facility is arrived at by GRP hundreds of millions of dollars, but the mortgage liens on the facility may still be foreclosed
and the Senior Lenders within the said 180-day period, then at the by the Senior Lenders just the same.
end thereof the Development Facility shall be transferred by the
Concessionaire to GRP or its designee and GRP shall make a Consequently, the Piatco contracts are also objectionable for grievously failing to
termination payment to Concessionaire equal to the Appraised Value adequately protect government's interests. More accurately, the contracts would
(as hereinafter defined) of the Development Facility or the sum of the consistently weaken and do away with protection of government interests. As such, they
Attendant Liabilities, if greater ...." are therefore grossly lopsided in favor of Piatco and/or its Senior Lenders.
In turn, the term Attendant Liabilities is defined in Section 1.06 of the ARCA as While on this subject, it is well to recall the earlier discussion regarding a
follows: particularly noticeable alteration of the concept of "Attendant Liabilities." In Section 1.06 of
the CA defining the term, the Piatco debts to be assumed/paid by government were
"Attendant Liabilities refer to all amounts in each case qualified by the phrases recorded and from time to time outstanding in the books of the
supported by verifiable evidence from time to time owed or which may Concessionaire and actually used for the project.These phrases were eliminated from the
become, owing by Concessionaire to Senior Lenders or any other ARCA's definition of Attendant Liabilities.
persons or entities who have provided, loaned or advanced funds or
provided financial facilities to Concessionaire for the Project, Since no explanation has been forthcoming from Piatco as to the possible
including, without limitation, all principal, interest, associated fees, justification for such a drastic change, the only conclusion, possible is that it intends to
charges, reimbursements, and other related expenses (including the have all of its debts covered by the guarantee, regardless of whether or not they are
fees, charges and expenses of any agents or trustees of such persons disclosed in its books. This has particular reference to those borrowings which were
or entities),whether payable at maturity, by acceleration or otherwise, obtained in violation of the loan covenants requiring Piatco to maintain a minimum 70:30
and further including amounts owed by Concessionaire to its debt-to-equity ratio, and even if the loan proceeds were not actually used for the project
professional consultants and advisers, suppliers, contractors and sub- itself.
contractors."
This point brings us back to the guarantee itself. In Section 4.04(c)(vi) of ARCA,
Government's agreement to pay becomes effective in the event of a default by the amount which government has guaranteed to pay as termination payment is
Piatco on any of its loan obligations to the Senior Lenders, and the amount to be paid by the greater of either (i) the Appraised Value of the terminal facility or (ii) the aggregate of
government is the greater of either the Appraised Value of Terminal III or the aggregate the Attendant Liabilities. Given that the Attendant Liabilities may include practically any
amount of the moneys owed by Piatco — whether to the Senior Lenders or to other entities, Piatco debt under the sun, it is highly conceivable that their sum may greatly exceed the
including its suppliers, contractors and subcontractors. In effect, therefore, this agreement appraised value of the facility, and government may end up paying very much more than
already constitutes the prohibited assumption by government of responsibility for the real worth of Terminal III. (So why did government have to bother with public bidding
repayment of Piatco's debts in case of a loan default. In fine, a direct government anyway?)
guarantee.
In the final analysis, Section 4.04(c)(iv) to (vi) of the ARCA is diametrically at
It matters not that there is a roundabout procedure prescribed by Section odds with the spirit and the intent of the BOT Law. The law meant to mobilize private
4.04(c)(iv),(v) and (vi) that would require, first,an attempt (albeit unsuccessful) by the resources (the private sector) to take on the burden and the risks of financing the
Senior Lenders to transfer Piatco's rights to a transferee of their choice; and, second,an construction, operation and maintenance of relevant infrastructure and development
projects for the simple reason that government is not in a position to do so. By the same "(i) Failure of Concessionaire to finish the Works in all
token, government guarantee was prohibited, since it would merely defeat the purpose material respects in accordance with the Tender Design and the
and raison d'être of a build-operate-and-transfer project to be undertaken by the private Timetable;
sector.
(ii) Commission by Concessionaire of a material breach of
To the extent that the project proponent is able to obtain loans to fund the project, this Agreement ...;
those risks are shared between the project proponent on the one hand, and its banks and
other lenders on the other. But where the proponent or its lenders manage to cajol or (iii) ...a change in control of Concessionaire arising from the
coerce the government into extending a guarantee of payment of the loan obligations, the sale, assignment, transfer or other disposition of capital stock which
risks assumed by the lenders are passed right back to government. I cannot understand results in an ownership structure violative of statutory or
why, in the instant case, government cheerfully assented to re-assuming the risks of the constitutional limitations;
project when it gave the prohibited guarantee and thus simply negated the very purpose
of the BOT Law and the protection it gives the government. (iv) A pattern of continuing or repeated non-compliance,
willful violation, or non-performance of other terms and conditions
Contract Termination hereof which is hereby deemed a material breach of this Agreement
Provisions in the Piatco ..." 62
Contracts Are Void
As if that were not bad enough, the ARCA also inserted into Section 8.01 the
The BOT Law as amended provides for contract termination as follows: phrase "Subject to Section 4.04." The effect of this insertion is that in those instances where
government may terminate the contract on account of Piatco's breach, and it is nevertheless
"Sec. 7. Contract Termination.— In the event that a project required under the ARCA to make termination compensation to Piatco even though
is revoked, cancelled or terminated by the government through no unauthorized by law, such compensation is to be equivalent to the payment amount
fault of the project proponent or by mutual agreement, the guaranteed by government — either a) the Appraised Value of the terminal facility or (b)
Government shall compensate the said project proponent for its the aggregate of the Attendant Liabilities, whichever amount is greater!
actual expenses incurred in the project plus a reasonable rate of
return thereon not exceeding that stated in the contract as of the date Clearly, this condition is not in line with Section 7 of the BOT Law. That provision
of such revocation, cancellation or termination: Provided,That the permits a project proponent to recover the actual expenses it incurred in the prosecution
interest of the Government in this instances [sic] shall be duly insured of the project plus a reasonable rate of return not in excess of that provided in the contract;
with the Government Service Insurance System or any other or to be compensated for the equivalent or proportionate contract cost as defined in the
insurance entity duly accredited by the Office of the Insurance contract, in case the government is in default on certain major contractual obligations.
Commissioner: Provided, finally,That the cost of the insurance
coverage shall be included in the terms and conditions of the bidding Furthermore, in those instances where such termination compensation is
referred to above. authorized by the BOT Law, it is indispensable that the interest of government be duly
insured.Section 5.08 the ARCA mandates insurance coverage for the terminal facility; but
"In the event that the government defaults on certain major all insurance policies are to be assigned, and all proceeds are payable, to the Senior
obligations in the contract and such failure is not remediable or if Lenders. In brief, the interest being secured by such coverage is that of the Senior Lenders,
remediable shall remain unremedied for an unreasonable length of not that of government. This can hardly be considered compliance with law.
time, the project proponent/contractor may, by prior notice to the
concerned national government agency or local government unit In essence, the ARCA provisions on termination compensation result in another
specifying the turn-over date, terminate the contract. The project unauthorized government guarantee, this time in favor of Piatco.
proponent/contractor shall be reasonably compensated by the
Government for equivalent or proportionate contract cost as defined A Prohibited Direct Government Subsidy,
in the contract." Which at the Same Time Is an Assault
on the National Honor
The foregoing statutory provision in effect provides for the following limited
Still another contractual provision offensive to law and public policy is Section
instances when termination compensation may be allowed:
8.01(d) of the ARCA, which is a "bolder and badder" version of Section 8.04(d) of the CA.
1. Termination by the government through no fault of the project
It will be recalled that Section 4-A of the BOT Law as amended prohibits not only
proponent
direct government guarantees, but likewise a direct government subsidy for unsolicited
2. Termination upon the parties' mutual agreement proposals. Section 13.2. b. iii. of the 1999 IRR defines a direct government subsidy as
encompassing "an agreement whereby the Government ...will ...postpone any payments
3. Termination by the proponent due to government's default on due from the proponent."
certain major contractual obligations
Despite the statutory ban, Section 8.01 (d) of the ARCA provides thus:
To emphasize, the law does not permit compensation for the project proponent
when contract termination is due to the proponent's own fault or breach of contract. "(d) The provisions of Section 8.01(a) notwithstanding, and
for the purpose of preventing a disruption of the operations in the
This principle was clearly violated in the Piatco Contracts. The ARCA stipulates Terminal and/or Terminal Complex, in the event that at any time
that government is to pay termination compensation to Piatco even whentermination is Concessionaire is of the reasonable opinion that it shall be unable to
initiated by government for the following causes: meet a payment obligation owed to the Senior Lenders,
Concessionaire shall give prompt notice to GRP, through DOTC/MIAA I will now discuss the manner in which the Piatco Contracts offended
and to the Senior Lenders. In such circumstances, the Senior Lenders the Constitution.
(or the Senior Lenders' Representative) may ensure that after making
provision for administrative expenses and depreciation, the cash The Exclusive Right Granted to Piatco
resources of Concessionaire shall first be used and applied to meet all to Operate a Public Utility Is Prohibited
payment obligations owed to the Senior Lenders. Any excess cash, by the Constitution
after meeting such payment obligations, shall be earmarked for the While Section 2.02 of the ARCA spoke of granting to Piatco "a franchise to operate
payment of all sums payable by Concessionaire to GRP under this and maintain the Terminal Complex," Section 3.02(a) of the same ARCA granted to Piatco,
Agreement.If by reason of the foregoing GRP should be unable to for the entire term of the concession agreement, "the exclusive right to operate a
collect in full all payments due to GRP under this Agreement, then the commercial international passenger terminal within the Island of Luzon" with the exception
unpaid balance shall be payable within a 90-day grace period counted of those three terminals already existing 63 at the time of execution of the ARCA.
from the relevant due date, with interest per annum at the rate equal
to the average 91-day Treasury Bill Rate as of the auction date Section 11 of Article XII of the Constitution prohibits the grant of a "franchise,
immediately preceding the relevant due date. If payment is not certificate, or any other form of authorization for the operation of a public utility" that is
effected by Concessionaire within the grace period, then a spread of "exclusive in character."
five (5%) percent over the applicable 91-day Treasury Bill Rate shall
be added on the unpaid amount commencing on the expiry of the In its Opinion No. 078, Series of 1995, the Department of justice held that "the
grace period up to the day of full payment. When the temporary NAIA Terminal III which ...is a 'terminal for public use' is a public utility." Consequently,
illiquidity of Concessionaire shall have been corrected and the cash the constitutional prohibition against the exclusivity of a franchise applies to the franchise
position of Concessionaire should indicate its ability to meet its for the operation of NAIA Terminal III as well.
maturing obligations, then the provisions set forth under this Section
8.01(d) shall cease to apply. The foregoing remedial measures shall What was granted to Piatco was not merely a franchise, but an "exclusive right"
be applicable only while there remains unpaid and outstanding to operate an international passenger terminal within the "Island of Luzon." What this grant
amounts owed to the Senior Lenders." (Italics supplied) effectively means is that the government is now estopped from exercising its inherent
power to award any other person another franchise or a right to operate such a public
By any manner of interpretation or application, Section 8.01(d) of the ARCA utility, in the event public interest in Luzon requires it. This restriction is highly detrimental
clearly mandates the indefinite postponement of payment of all of Piatco's obligations to to government and to the public interest. Former Secretary of Justice Hernando B. Perez
the government, in order to ensure that Piatco's obligations to the Senior Lenders are paid expressed this point well in his Memorandum for the President dated 21 May 2002:
in full first. That is nothing more or less than the direct government subsidy prohibited by
the BOT Law and the IRR. The fact that Piatco will pay interest on the unpaid amounts owed "Section 3.02 on 'Exclusivity'
to government does not change the situation or render the prohibited subsidy any less
unacceptable. "This provision gives to PIATCO (the Concessionaire) the
exclusive right to operate a commercial international airport within
But beyond the clear violations of law, there are larger issues involved in the the Island of Luzon with the exception of those already existing at the
ARCA. Earlier, I mentioned that Section 8.01(d) of the ARCA completely eliminated the time of the execution of the Agreement, such as the airports at Subic,
proviso in Section 8.04(d) of the CA which gave government the right to appoint a financial Clark and Laoag City. In the case of the Clark International Airport,
controller to manage the cash position of Piatco during situations of financial distress. Not however, the provision restricts its operation beyond its design
only has government been deprived of any means of monitoring and managing the capacity of 850,000 passengers per annum and the operation of new
situation; worse, as can be seen from Section 8.01(d) above-quoted, the Senior Lenders terminal facilities therein until after the new NAIA Terminal III shall
have effectively locked in on the right to exercise financial controllership over Piatco and to have consistently reached or exceeded its design capacity of ten (10)
allocate its cash resources to the payment of all amounts owed to the Senior Lenders before million passenger capacity per year for three (3) consecutive years
allowing any payment to be made to government. during the concession period.

In brief, this particular provision of the ARCA has placed in the hands of foreign "This is an onerous and disadvantageous provision. It
lenders the power and the authority to determine how much (if at all) and when the effectively grants PIATCO a monopoly in Luzon and ties the hands of
Philippine government (as grantor of the franchise) may be allowed to receive from Piatco. government in the matter of developing new airports which may be
In that situation, government will be at the mercy of the foreign lenders. This is a situation found expedient and necessary in carrying out any future plan for an
completely contrary to the rationale of the BOT Law and to public policy. inter-modal transportation system in Luzon.

The aforesaid provision rouses mixed emotions — shame and disgust at the "Additionally, it imposes an unreasonable restriction on the
parties' (especially the government officials') docile submission and abject servitude and operation of the Clark International Airport which could adversely
surrender to the imperious and excessive demands of the foreign lenders, on the one hand; affect the operation and development of the Clark Special Economic
and vehement outrage at the affront to the sovereignty of the Republic and to the national Zone to the economic prejudice of the local constituencies that are
honor, on the other. It is indeed time to put an end to such an unbearable, dishonorable being benefited by its operation." (Italics supplied)
situation.
While it cannot be gainsaid that an enterprise that is a public utility may happen
The Piatco Contracts Unarguably to constitute a monopoly on account of the very nature of its business and the absence of
Violate Constitutional Injunctions competition, such a situation does not however constitute justification to violate the
constitutional prohibition and grant an exclusive franchise or exclusive right to operate a
public utility.
Piatco's contention that the Constitution does not actually prohibit monopolies is By way of background, two monopolies were actually created by the Piatco
beside the point. As correctly argued, 64 the existence of a monopoly by a public utility is contracts. The first and more obvious one refers to the business of operating an
a situation created by circumstances that do not encourage competition. This situation is international passenger terminal in Luzon,the business end of which involves providing
different from the grant of a franchise to operate a public utility, a privilege granted by international airlines with parking space for their aircraft, and airline passengers with the
government. Of course, the grant of a franchise may result in a monopoly. But making such use of departure and arrival areas, check-in counters, information systems, conveyor
franchise exclusive is what is expressly proscribed by the Constitution. systems, security equipment and paraphernalia, immigrations and customs processing
areas; and amenities such as comfort rooms, restaurants and shops.
Actually, the aforementioned Section 3.02 of the ARCA more than just guaranteed
exclusivity; it also guaranteed that the government will not improve or expand the facilities In furtherance of the first monopoly, the Piatco Contracts stipulate that the NAIA
at Clark — and in fact is required to put a cap on the latter's operations — until after Terminal III will be the only facility to be operated as an international passenger
Terminal III shall have been operated at or beyond its peak capacity for three consecutive terminal; 66 that NAIA Terminals I and II will no longer be operated as such; 67 and that
years. 65 As counsel for public respondents pointed out, in the real world where the rate no one (including the government) will be allowed to compete with Piatco in the operation
of influx of international passengers can fluctuate substantially from year to year, it may of an international passenger terminal in the NAIA Complex. 68 Given that, at this time,
take many years before Terminal III sees three consecutive years' operations at peak the government and Piatco are the only ones engaged in the business of operating an
capacity. The Diosdado Macapagal International Airport may thus end up stagnating for a international passenger terminal, I am not acutely concerned with this particular
long time. Indeed, in order to ensure greater profits for Piatco, the economic progress of a monopolistic situation.
region has had to be sacrificed.
There was however another monopoly within the NAIA created by the subject
The Piatco Contracts Violate contracts for Piatco — in the business of providing international airlines with the
the Time Limitation on Franchises following: groundhandling, in-flight catering, cargo handling, and aircraft repair and
maintenance services.These are lines of business activity in which are engaged many
Section 11 of Article XII of the Constitution also provides that "no franchise,
service providers (including the petitioners-in-intervention),who will be adversely affected
certificate or any other form of authorization for the operation of a public utility shall be . .
upon full implementation of the Piatco Contracts, particularly Sections 3.01(d)69 and
. for a longer period than fifty years." After all, a franchise held for an unreasonably long
(e) 70 of both the ARCA and the CA.
time would likely give rise to the same evils as a monopoly.
On the one hand, Section 3.02(a) of the ARCA makes Terminal III the only
The Piatco Contracts have come up with an innovative way to circumvent the
international passenger terminal at the NAIA, and therefore the only place within the NAIA
prohibition and obtain an extension. This fact can be gleaned from Section 8.03(b) of the
Complex where the business of providing airport-related services to international airlines
ARCA, which I quote thus:
may be conducted. On the other hand, Section 3.01(d) of the ARCA requires government,
"Sec. 8.03. Termination Procedure and Consequences of through the MIAA, not to allow service providers with expired MIAA contracts to renew or
Termination.— extend their contracts to render airport-related services to airlines. Meanwhile, Section
3.01(e) of the ARCA requires government, through the DOTC and MIAA, not to allow service
a) ... providers — those with subsisting concession agreements for services and operations being
conducted at Terminal I — to carry over their concession agreements, services and
b) In the event the Agreement is terminated pursuant to operations to Terminal III, unless they first enter into a separate agreement with
Section 8.01 (b) hereof, Concessionaire shall be entitled to collect the Piatco. ACaTIc
Liquidated Damages specified in Annex 'G'.The full payment by GRP
to Concessionaire of the Liquidated Damages shall be a condition The aforementioned provisions vest in Piatco effective and exclusive control over
precedent to the transfer by Concessionaire to GRP of the which service provider may and may not operate at Terminal III and render the airport-
Development Facility. Prior to the full payment of the Liquidated related services needed by international airlines. It thereby possesses the power to exclude
Damages, Concessionaire shall to the extent practicable continue to competition. By necessary implication, it also has effective control over the fees and charges
operate the Terminal and the Terminal Complex and shall be entitled that will be imposed and collected by these service providers.
to retain and withhold all payments to GRP for the purpose of
offsetting the same against the Liquidated Damages. Upon full This intention is exceedingly clear in the declaration by Piatco that it is "completely
payment of the Liquidated Damages, Concessionaire shall within its rights to exclude any party that it has not contracted with from NAIA Terminal
immediately transfer the Development Facility to GRP on 'as-is- III." 71
where-is' basis."
Worse, there is nothing whatsoever in the Piatco Contracts that can serve to
The aforesaid easy payment scheme is less beneficial than it first appears. restrict, control or regulate the concessionaire's discretion and power to reject any service
Although it enables government to avoid having to make outright payment of an obligation provider and/or impose any term or condition it may see fit in any contract it enters into
that will likely run into billions of pesos, this easy payment plan will nevertheless cost with a service provider. In brief, there is no safeguard whatsoever to ensure free and fair
government considerable loss of income, which it would earn if it were to operate Terminal competition in the service-provider sector.
III by itself. Inasmuch as payments to the concessionaire (Piatco) will be on "installment
In the meantime, and not surprisingly, Piatco is first in line, ready to exploit the
basis," interest charges on the remaining unpaid balance would undoubtedly cause the total
unique business opportunity. It announced 72 that it has accredited three groundhandlers
outstanding balance to swell. Piatco would thus be entitled to remain in the driver's seat
for Terminal III. Aside from the Philippine Airlines, the other accredited entities are the
and keep operating the terminal for an indefinite length of time.
Philippine Airport and Ground Services Globeground, Inc. ("PAGSGlobeground") and the
The Contracts Create Two Orbit Air Systems, Inc. ("Orbit").PAGSGlobeground is a wholly-owned subsidiary of the
Monopolies for Piatco Philippine Airport and Ground Services, Inc. or PAGS, 73 while Orbit is a wholly-owned
subsidiary of Friendship Holdings, Inc., 74 which is in turn owned 80 percent by
PAGS. 75 PAGS is a service provider owned 60 percent by the Cheng Family; 76 it is a prevent competition in the broad and general sense, or to control prices to the detriment
stockholder of 35 percent of Piatco 77 and is the latter's designated contractor-operator for of the public. In short, it is the concentration of business in the hands of a few. The material
NAIA Terminal III. 78 consideration in determining its existence is not that prices are raised and competition
actually excluded, but that power exists to raise prices or exclude competition when
Such entry into and domination of the airport-related services sector appear to desired." 83 (Italics supplied)
be very much in line with the following provisions contained in the First Addendum to the
Piatco Shareholders Agreement, 79 executed on July 6, 1999, which appear to constitute The Contracts Encourage Monopolistic Pricing, Too
a sort of master plan to create a monopoly and combinations in restraint of trade:
Aside from creating a monopoly, the Piatco contracts also give the concessionaire
"11. The Shareholders shall ensure: virtually limitless power over the charging of fees, rentals and so forth. What little
"oversight function" the government might be able and minded to exercise is less than
a. ... sufficient to protect the public interest, as can be gleaned from the following provisions:

b. That (Phil. Airport and Ground Services, Inc.) PAGS "Sec. 6.06. Adjustment of Non-Public Utility Fees and
and/or its designated Affiliates shall, at all times during the Charges
Concession Period, be exclusively authorized by (PIATCO) to
engage in the provision of ground-handling, catering and "For fees, rentals and charges constituting Non-Public Utility
fueling services within the Terminal Complex. Revenues, Concessionaire may make any adjustments it deems
appropriate without need for the consent of GRP or any government
c. That PAIRCARGO and/or its designated Affiliate shall, agency subject to Sec. 6.03(c)."
during the Concession Period, be the only entities authorized
to construct and operate a warehouse for all cargo handling Section 6.03(c) in turn provides:
and related services within the Site."
"(c) Concessionaire shall at all times be judicious in fixing
Precisely, proscribed by our Constitution are the monopoly and the restraint of fees and charges constituting Non-Public Utility Revenues in order to
trade being fostered by the Piatco Contracts through the erection of barriers to the entry ensure that End Users are not unreasonably deprived of services.
of other service providers into Terminal III. In Tatad v. Secretary of the Department of While the vehicular parking fee, porterage fee and greeter/wellwisher
Energy, 80 the Court ruled: fee constitute Non-Public Utility Revenues of Concessionaire, GRP
may require Concessionaire to explain and justify the fee it may set
". . . [S]ection 19 of Article XII of the Constitution . . . from time to time, if in the reasonable opinion of GRP the said fees
mandates: 'The State shall regulate or prohibit monopolies when the have become exorbitant resulting in the unreasonable deprivation of
public interest so requires. No combinations in restraint of trade or End Users of such services."
unfair competition shall be allowed.'
It will be noted that the above-quoted provision has no teeth, so the
"A monopoly is a privilege or peculiar advantage vested in concessionaire can defy the government without fear of any sanction. Moreover, Section
one or more persons or companies, consisting in the exclusive right 6.06 — taken together with Section 6.03(c) of the ARCA — falls short of the standard set
or power to carry on a particular business or trade, manufacture a by the BOT Law as amended, which expressly requires in Section 2(b) that the project
particular article, or control the sale or the whole supply of a particular proponent is "allowed to charge facility users appropriate tolls, fees, rentals and charges
commodity. It is a form of market structure in which one or only a not exceeding those proposed in its bid or as negotiated and incorporated in the
few firms dominate the total sales of a product or service. On the contract ...."
other hand, a combination in restraint of trade is an agreement or
understanding between two or more persons, in the form of a The Piatco Contracts Violate
contract, trust, pool, holding company, or other form of association, Constitutional Prohibitions
for the purpose of unduly restricting competition, monopolizing trade Against Impairment of Contracts
and commerce in a certain commodity, controlling its production, and Deprivation of Property Without
distribution and price, or otherwise interfering with freedom of trade Due Process
without statutory authority. Combination in restraint of trade refers Earlier, I discussed how Section 3.01(e) 84 of both the CA and the ARCA requires
to the means while monopoly refers to the end. government, through DOTC/MIAA, not to permit the carry-over to Terminal III of the
services and operations of certain service providers currently operating at Terminal I with
"xxx xxx xxx
subsisting contracts.
"Section 19, Article XII of our Constitution is anti-trust in
By the In-Service Date, Terminal III shall be the only facility to be operated as an
history and in spirit. It espouses competition. The desirability of
international passenger terminal at the NAIA; 85 thus, Terminals I and II shall no longer
competition is the reason for the prohibition against restraint of trade,
operate as such, 86 and no one shall be allowed to compete with Piatco in the operation of
the reason for the interdiction of unfair competition, and the reason
an international passenger terminal in the NAIA. 87 The bottom line is that, as of the In-
for regulation of unmitigated monopolies. Competition is thus the
Service Date, Terminal III will be the only terminal where the business of providing airport-
underlying principle of [S]ection 19, Article XII of our Constitution,. .
related services to international airlines and passengers may be conducted at all.
." 81

Gokongwei Jr. v. Securities and Exchange Commission 82 elucidates the criteria


to be employed: "A 'monopoly' embraces any combination the tendency of which is to
Consequently, government through the DOTC/MIAA will be compelled to cease into unless there is an appropriation therefor, the unexpended
honoring existing contracts with service providers after the In-Service Date, as they cannot balance of which, free of other obligations, is sufficient to cover the
be allowed to operate in Terminal III. proposed expenditure; and ...

In short, the CA and the ARCA obligate and constrain government to break its "Sec. 47. Certificate Showing Appropriation to Meet
existing contracts with these service providers. Contract.— Except in the case of a contract for personal service, for
supplies for current consumption or to be carried in stock not
Notably, government is not in a position to require Piatco to accommodate the exceeding the estimated consumption for three (3) months, or
displaced service providers, and it would be unrealistic to think that these service providers banking transactions of government-owned or controlled banks, no
can perform their service contracts in some other international airport outside Luzon. contract involving the expenditure of public funds by any government
Obviously, then, these displaced service providers are — to borrow a quaint expression agency shall be entered into or authorized unless the proper
— up the river without a paddle.In plainer terms, they will have lost their businesses accounting official of the agency concerned shall have certified to the
entirely, in the blink of an eye. officer entering into the obligation that funds have been duly
appropriated for the purpose and that the amount necessary to cover
What we have here is a set of contractual provisions that impair the obligation of the proposed contract for the current calendar year is available for
contracts and contravene the constitutional prohibition against deprivation of property expenditure on account thereof, subject to verification by the auditor
without due process of law. 88 concerned. The certificate signed by the proper accounting official and
the auditor who verified it, shall be attached to and become an
Moreover, since the displaced service providers, being unable to operate, will be
integral part of the proposed contract, and the sum so certified shall
forced to close shop, their respective employees — among them Messrs. Agan and Lopez
not thereafter be available for expenditure for any other purpose until
et al. — have very grave cause for concern, as they will find themselves out of employment
the obligation of the government agency concerned under the
and bereft of their means of livelihood. This situation comprises still another violation of
contract is fully extinguished."
the constitution prohibition against deprivation of property without due process.
Referring to the aforequoted provisions, this Court has held that "(I)t is quite
True, doing business at the NAIA may be viewed more as a privilege than as a
evident from the tenor of the language of the law that the existence of appropriations and
right. Nonetheless, where that privilege has been availed of by the petitioners-in-
the availability of funds are indispensable pre-requisites to or conditions sine qua non for
intervention service providers for years on end, a situation arises, similar to that
the execution of government contracts. The obvious intent is to impose such conditions as
in American Inter-fashion v. GTEB. 89 We held therein that a privilege enjoyed for seven
a priori requisites to the validity of the proposed contract." 93
years "evolved into some form of property right which should not be
removed . . . arbitrarily and without due process." Said pronouncement is particularly Notwithstanding the constitutional ban, statutory mandates and Jurisprudential
relevant and applicable to the situation at bar because the livelihood of the employees of precedents, the three Supplements to the ARCA, which were not approved by NEDA,
petitioners-intervenors are at stake. imposed on government the additional burden of spending public moneys without prior
appropriation.
The Piatco Contracts Violate
Constitutional Prohibition Against In the First Supplement ("FS") dated August 27, 1999, the following requirements
Deprivation of Liberty Without were imposed on the government:
Due Process
The Piatco Contracts by locking out existing service providers from entry into • To construct, maintain and keep in good repair and operating
Terminal III and restricting entry of future service providers, thereby infringed upon the condition all airport support services, facilities, equipment
freedom — guaranteed to and heretofore enjoyed by international airlines — to contract and infrastructure owned and/or operated by MIAA, which
with local service providers of their choice, and vice versa. are not part of the Project or which are located outside the
Site, even though constructed by Concessionaire —
Both the service providers and their client airlines will be deprived of the right to including the access road connecting Terminals II and III
liberty,which includes the right to enter into all contracts, 90 and/or the right to make a and the taxilane, taxiways and runways
contract in relation to one's business. 91
• To obligate the MIAA to provide funding for the upkeep,
By Creating New Financial Obligations for Government, Supplements to the ARCA maintenance and repair of the airports and facilities owned
Violate the Constitutional Ban on Disbursement of Public Funds Without Valid or operated by it and by third persons under its control in
Appropriation order to ensure compliance with international standards;
and holding MIAA liable to Piatco for the latter's losses,
Clearly prohibited by the Constitution is the disbursement of public funds out of expenses and damages as well as for the latter's liability to
the treasury, except in pursuance of an appropriation made by law. 92 The immediate third persons, in case MIAA fails to perform such obligations;
effect of this constitutional ban is that all the various agencies of government are in addition, MIAA will also be liable for the incremental and
constrained to limit their expenditures to the amounts appropriated by law for each fiscal consequential costs of the remedial work done by Piatco on
year; and to carefully count their cash before taking on contractual commitments. Giving account of the former's default.
flesh and form to the injunction of the fundamental law, Sections 46 and 47 of Executive
Order 292, otherwise known as the Administrative Code of 1987, provide as follows: • Section 4 of the FS imposed on government ten (10) "Additional
Special Obligations," including the following:
"Sec. 46. Appropriation Before Entering into Contract.— (1)
No contract involving the expenditure of public funds shall be entered
Ø Providing thru MIAA the land required by Piatco for the Conversely, failure to deliver on any of these obligations may conceivably result
taxilane and one taxiway, at no cost to Piatco in substantial prejudice to the concessionaire, to such an extent as to constitute a material
breach of the Piatco Contracts. Whereupon, the concessionaire may outrightly terminate
Ø Implementing the government's existing storm drainage the Contracts pursuant to Section 8.01(b)(i) and (ii) of the ARCA and seek payment of
master plan Liquidated Damages in accordance with Section 8.02(a) of the ARCA; or the concessionaire
may instead require government to pay the Incremental and Consequential Losses under
Ø Coordinating with DPWH the financing, implementation Section 1.23 of the ARCA. 94 The logical conclusion then is that the obligations in the
and completion of the following works before the Supplements are not to be performed on a best-efforts basis only, but are unarguably
In-Service Date: three left-turning overpasses mandatory in character.
(Edsa to Tramo St.,Tramo to Andrews Ave.,and
Manlunas Road to Sales Ave.) and a road upgrade Regarding MIAA's obligation to coordinate with the DPWH for the complete
and improvement program involving widening, implementation of the road upgrading and improvement program for Sales, Andrews and
repair and resurfacing of Sales Road, Andrews Manlunas Roads (which provide access to the Terminal III site) prior to the In-Service Date,
Avenue and Manlunas Road; improvement of it is essential to take note of the fact that there was a pressing need to complete the
Nichols Interchange; and removal of squatters program before the opening of Terminal III. 95 For that reason, the MIAA was compelled
along Andrews Avenue to enter into a memorandum of agreement with the DPWH in order to ensure the timely
completion of the road widening and improvement program. MIAA agreed to advance the
Ø Dealing directly with BCDA and the Philippine Air Force in total amount of P410.11 million to DPWH for the works, while the latter was committed to
acquiring additional land or right of way for the do the following:
road upgrade and improvement program
"2.2.8. Reimburse all advance payments to MIAA including
Ø Requiring government to work for the immediate but not limited to interest, fees, plus other costs of money within the
reversion to MIAA of the Nayong Pilipino National periods CY2004 and CY2006 with payment of no less than One
Park, in order to permit the building of the second Hundred Million Pesos (PhP100M) every year.
west parallel taxiway
"2.2.9. Perform all acts necessary to include in its CY2004
• Section 5 of the FS also provides that in lieu of the access tunnel, a to CY2006 budget allocation the repayments for the advances made
surface access road (T2-T3) will be constructed. This by MIAA, to ensure that the advances are fully repaid by CY2006. For
provision requires government to expend funds to purchase this purpose, DPWH shall include the amounts to be appropriated for
additional land from Nayong Pilipino and to clear the same reimbursement to MIAA in the "Not Needing Clearance" column of
in order to be able to deliver clean possession of the site to their Agency Budget Matrix (ABM) submitted to the Department of
Piatco, as required in Section 5(c) of the FS. Budget and Management."
On the other hand, the Third Supplement ("TS") obligates the government to It can be easily inferred, then, that DPWH did not set aside enough funds to be
deliver, within 120 days from date thereof, clean possession of the land on which the T2- able to complete the upgrading program for the crucially situated access roads prior to the
T3 Road is to be constructed. targeted opening date of Terminal III; and that, had MIAA not agreed to lend the P410
Million, DPWH would not have been able to complete the program on time. As a
The foregoing contractual stipulations undeniably impose on government the
consequence, government would have been in breach of a material obligation. Hence, this
expenditures of public funds not included in any congressional appropriation or authorized
particular undertaking of government may likewise not be construed as being for best-
by any other statute. Piatco however attempts to take these stipulations out of the ambit
efforts compliance only.
of Sections 46 and 47 of the Administrative Code by characterizing them as stipulations for
compliance on a "best-efforts basis" only. They also Infringe on the Legislative
Prerogative and Power Over the Public Purse
To determine whether the additional obligations under the Supplements may
really be undertaken on a best-efforts basis only, the nature of each of these obligations But the particularly sad thing about this transaction between MIAA and DPWH is
must be examined in the context of its relevance and significance to the Terminal III the fact that both agencies were maneuvered into (or allowed themselves to be maneuvered
Project, as well as of any adverse impact that may result if such obligation is not performed into) an agreement that would ensure delivery of upgraded roads for Piatco's benefit, using
or undertaken on time. In short, the criteria for determining whether the best-efforts basis funds not allocated for that purpose. The agreement would then be presented to Congress
will apply is whether the obligations are critical to the success of the Project and, as a done deal. Congress would thus be obliged to uphold the agreement and support it
accordingly, whether failure to perform them (or to perform them on time) could result in with the necessary allocations and appropriations for three years, in order to enable DPWH
a material breach of the contract. to deliver on its committed repayments to MIAA. The net result is an infringement on the
legislative power over the public purse and a diminution of Congress' control over
Viewed in this light, the "Additional Special Obligations" set out in Section 4 of the expenditures of public funds — a development that would not have come about, were it not
FS take on a different aspect. In particular, each of the following may all be deemed to play for the Supplements. Very clever but very illegal!
a major role in the successful and timely prosecution of the Terminal III Project: the
obtention of land required by PIATCO for the taxilane and taxiway; the implementation of EPILOGUE
government's existing storm drainage master plan; and coordination with DPWH for the
completion of the three left-turning overpasses before the In-Service Date, as well as What Do We Do Now?
acquisition and delivery of additional land for the construction of the T2-T3 access road. In the final analysis, there remains but one ultimate question, which I raised
during the Oral Argument on December 10, 2002: What do we do with the Piatco Contracts
and Terminal III? 96 (Feeding directly into the resolution of the decisive question is the finished — to bid out the operation of the facility under the same or analogous principles
other nagging issue: Why should we bother with determining the legality and validity of as build-operate-and-transfer projects. To be imposed, however, is the condition that the
these contracts, when the Terminal itself has already been built and is practically winning bidder must pay the builder of the facility a price fixed by government based
complete?) on quantum meruit;on the real, reasonable — not inflated — value of the built facility.

Prescinding from all the foregoing disquisition, I find that all the Piatco contracts, How the payment or series of payments to the builder, funders, investors and
without exception, are void ab initio,and therefore inoperative. Even the very process by contractors will be staggered and scheduled, will have to be built into the bids, along with
which the contracts came into being — the bidding and the award — has been riddled with the annual guaranteed payments to government. In this manner, this whole sordid mess
irregularities galore and blatant violations of law and public policy, far too many to ignore. could result in something truly beneficial for all, especially for the Filipino people.
There is thus no conceivable way, as proposed by some, of saving one (the original
Concession Agreement) while junking all the rest. WHEREFORE, I vote to grant the Petitions and to declare the subject contracts
NULL and VOID.
Neither is it possible to argue for the retention of the Draft Concession Agreement
(referred to in the various pleadings as the Contract Bidded Out) as the contract that should ||| (Agan, Jr. v. Philippine International Air Terminals Co., Inc., G.R. Nos. 155001,
be kept in force and effect to govern the situation, inasmuch as it was never executed by 155547 & 155661, [May 5, 2003], 450 PHIL 744-902)
the parties. What Piatco and the government executed was the Concession Agreement
which is entirely different from the Draft Concession Agreement.

Ultimately, though, it would be tantamount to an outrageous, grievous and


unforgivable mutilation of public policy and an insult to ourselves if we opt to keep in place
a contract — any contract — for to do so would assume that we agree to having Piatco
continue as the concessionaire for Terminal III.

Despite all the insidious contraventions of the Constitution, law and public policy
Piatco perpetrated, keeping Piatco on as concessionaire and even rewarding it by allowing
it to operate and profit from Terminal III — instead of imposing upon it the stiffest sanctions
permissible under the laws — is unconscionable.

It is no exaggeration to say that Piatco may not really mind which contract we
decide to keep in place. For all it may care, we can do just as well without one, if we only
let it continue and operate the facility.After all, the real money will come not from building
the Terminal, but from actually operating it for fifty or more years and charging whatever
it feels like, without any competition at all.This scenario must not be allowed to
happen. aATESD

If the Piatco contracts are junked altogether as I think they should be, should not
AEDC automatically be considered the winning bidder and therefore allowed to operate the
facility? My answer is a stone-cold 'No'.AEDC never won the bidding, never signed any
contract, and never built any facility. Why should it be allowed toautomatically step in and
benefit from the greed of another?

Should government pay at all for reasonable expenses incurred in the construction
of the Terminal? Indeed it should, otherwise it will be unjustly enriching itself at the expense
of Piatco and, in particular, its funders, contractors and investors — both local and foreign.
After all, there is no question that the State needs and will make use of Terminal III, it
being part and parcel of the critical infrastructure and transportation-related programs of
government.

In Melchor v. Commission on Audit, 97 this Court held that even if the contract
therein was void, the principle of payment by quantum meruit was found applicable, and
the contractor was allowed to recover the reasonable value of the thing or services
rendered (regardless of any agreement as to the supposed value),in order to avoid unjust
enrichment on the part of government. The principle of quantum meruit was likewise
applied in Eslao v. Commission on Audit, 98 because to deny payment for a building almost
completed and already occupied would be to permit government to unjustly enrich itself at
the expense of the contractor. The same principle was applied in Republic v. Court of
Appeals. 99

One possible practical solution would be for government — in view of the nullity
of the Piatco contracts and of the fact that Terminal III has already been built and is almost

Vous aimerez peut-être aussi