WORK BREAKDOWN STRUCTURE (WBS)

FOR DELIVERABLES AND NON-DELIVERABLES


PAGE 1 0F 2

020 ADMINSTRATION/COORDINATION
• Management
• Project Management
• Group Supervision
• Coordination Meetings/ Project & Client Meetings
• Project Procedures/ Training/ Team Building
• Job Scheduling/ Drawing Book/ Progress Reporting
• Plan check/ permit coordination
• Topographical and geotechnical survey review/coordination
• Responses to Design & Constructability Reviews/ QA Audits
• Project Closeout

050 FIELD SUPPORT


• Field Verification Trips (Design Phase)
• Field Support (Construction Phase)
• As-Built Drawing Revision

060 ESTIMATES
• Professional Services ((Budget/Definitive?)
• Equipment/ Material (Preliminary/Budget/ Definitive?)
• Material Take Off to support estimates

120 SQUAD CHECKS


• Of Other Department Deliverables
• Of Other Department Vendor Documents

150 PURCHASING
• Procurement Specifications if not under another WBS Code
• Material Take Off for procurement
• Requisitions for Equipment/ Materials/ Subcontracts/ Services
• Technical Bid Analysis
• Conforming/ Purchase Requisition
• Material Control Meetings
• Review of Vendor Data
• Shop Inspection or Witness of Testing

PROCESS/ PROJECT ENGINEERING ACTIVITIES


210 Conceptual Activities and Simulations
211 Process Support-Permitting
212 Process Flow Diagram Development
222 P & ID Development/ Review
261 Operating Manual Preparation
262 Process Reports
270 Process-Equipment Specification Development
280 Process HAZOP Review
285 Engineering Support by Process

Form WD-SR004f1
(WBS) FOR DELIVERABLES/NON-DELIVERABLES- PAGE 2 OF 2

MECHANICAL/ PROCESS EQUIPMENT


3XX Major Equipment ( where XX is the two digit number type of equipment)
350 Equipment List Preparation and Maintenance
365 Vessel Drawings
367 Mechanical Drawings
380 Materials Engineering
590 3 D Modeling

PIPING DEPARTMENT
500 Plot Plans and General Arrangement
510 Piping Sections
520 Piping Plans
521 U/G Piping Plans
522 Rack Piping Plans
523 Piping Layouts
524 Demolition (Plans, Photos or Isometrics)
530 Piping Isometric Drawings
532 Stress Analysis
542 Models (Physical or CAD)
551 Line List
552 Tie-In Activities
553 Specialty Item Activities
571 Piping-MTO
572 Piping-Specification

CIVIL/STRUCTURAL DEPARTMENT
601 Concrete Drawings and Calculations
602 Architectural/ Building Drawings and Calculations
603 Structural Steel Drawings and Calculations
604 Civil Drawings and Calculations

ELECTRICAL DEPARTMENT
700 Electrical Studies and Calculations
731 Single Line Diagrams
732 Electrical Plans
733 Electrical Details
734 Electrical Conduit/ Cable Schedules
737 Electrical Logic Diagrams

CONTROL SYSTEMS DEPARTMENT


800 Instrument Calculations/ Specifications/ Purchasing
811 Instrument Loop Diagrams
812 Instrument Location Plans
813 Instrument Installation Details
814 Instrument Wiring Diagrams
815 Instrument DCS Drawings
820 Instrument Index/ Summary
830 Instrument Panels/ Consoles
841 Instrument Distributed/ Digital Control System
842 Instrument Configuration/ Programming