020 ADMINSTRATION/COORDINATION
• Management
• Project Management
• Group Supervision
• Coordination Meetings/ Project & Client Meetings
• Project Procedures/ Training/ Team Building
• Job Scheduling/ Drawing Book/ Progress Reporting
• Plan check/ permit coordination
• Topographical and geotechnical survey review/coordination
• Responses to Design & Constructability Reviews/ QA Audits
• Project Closeout
060 ESTIMATES
• Professional Services ((Budget/Definitive?)
• Equipment/ Material (Preliminary/Budget/ Definitive?)
• Material Take Off to support estimates
150 PURCHASING
• Procurement Specifications if not under another WBS Code
• Material Take Off for procurement
• Requisitions for Equipment/ Materials/ Subcontracts/ Services
• Technical Bid Analysis
• Conforming/ Purchase Requisition
• Material Control Meetings
• Review of Vendor Data
• Shop Inspection or Witness of Testing
Form WD-SR004f1
(WBS) FOR DELIVERABLES/NON-DELIVERABLES- PAGE 2 OF 2
PIPING DEPARTMENT
500 Plot Plans and General Arrangement
510 Piping Sections
520 Piping Plans
521 U/G Piping Plans
522 Rack Piping Plans
523 Piping Layouts
524 Demolition (Plans, Photos or Isometrics)
530 Piping Isometric Drawings
532 Stress Analysis
542 Models (Physical or CAD)
551 Line List
552 Tie-In Activities
553 Specialty Item Activities
571 Piping-MTO
572 Piping-Specification
CIVIL/STRUCTURAL DEPARTMENT
601 Concrete Drawings and Calculations
602 Architectural/ Building Drawings and Calculations
603 Structural Steel Drawings and Calculations
604 Civil Drawings and Calculations
ELECTRICAL DEPARTMENT
700 Electrical Studies and Calculations
731 Single Line Diagrams
732 Electrical Plans
733 Electrical Details
734 Electrical Conduit/ Cable Schedules
737 Electrical Logic Diagrams