Vous êtes sur la page 1sur 81

RINCIAN BIAYA

PEKERJAAN REHABILITASI CATHODIC PROTECTION PLTGU BELAWAN


PT PLN (Persero) UNIT PELAKSANA PEMBANGKITAN BELAWAN

HARGA SATUAN JUMLAH HARGA


No. URAIAN PEKERJAAN SATUAN JUMLAH
(Rp) (Rp)

A MATERIAL LIST unit 6 377,369,315 2,264,215,890


Transformer Rectifier Spesifikasi :
1
Type : Manual Setting
- Cooling : Air Cooled (Pendinginan Udara )
- Input AC: : 3 phase, 380VAC, 50 Hz, Output: 250 Amp-50 V
- Casing : SS 304, Outdoor Type : IP 43
unit
2 Servis Transformer Rectifier : 14 32,565,526 455,917,364
"
Pembersihan Transformer Rectifier : penggantian Diode, fuse, manual Volt meter, Amp
meter dan Lampu, Pengencangan mur baut, pengecekan kabel kabel, Pengecatan Casing
3 Transformer Rectifier Oil : type Shell S2ZUI drum 3 25,791,896 77,375,688
4 Oeepwell Groundbed dengan kedalaman 75 m
A. MMO String Anode unit 72 65,782,363 4,736,330,136
Consist of 6 Pes MMO anode dimension 1" x 1m c/w 150m leghth of 1 x 35 sq.mm
HMWPE cable
B. Material for Deepwell Anode lnstalation (1 hole- 75 meter each), adalah :
Steel Pipe Casing 8" dia non schedule Pcs 900 4,559,174 4,103,256,600
Loresco SC-3 Coke Breeze backsfill 501bs/bag Bag 1080 2,051,628 2,215,758,240
Anode Centralizer ( u-clamp) Pcs 950 521,049 494,996,550
Nylon Rope meter 6000 19,539 117,234,000
Breather pipa PVC dia 1" @4m length meter 1450 104,210 151,104,500
Cover for casing pipe Pcs 72 325,655 23,447,160
5 DeepWeld Groundbed dengan kedalaman 30m
A. MMO String Anode unit 4 54,710,083 218,840,332
Consist of 5 Pes MMO anode dimension 1" x 1m c/w 100m leghth of 1 x 35 sq.mm
HMWPE cable
B. Material for Deepwell Anode lnstalation (1 hole- 30 meter each), total 8 unit adalah :
Steel Pipe Casing 8" dia non schedule Pcs 20 4,559,174 91,183,480
Loresco SC-3 Coke Breeze backsfill 501bs/bag Bag 120 2,051,628 246,195,360
Anode Centralizer ( u-clamp) Pcs 96 521,049 50,020,704
Nylon Rope meter 300 19,539 5,861,700
Breather pipa PVC dia 1" @4m length meter 300 104,210 31,263,000
Cover for casing pipe Pcs 8 325,655 2,605,240
6 Mixed Metal Oxide Anode, Dimension 1" x 1m c/w cable HMWPE
Length cable : 100m ( 10 pes), size 25sq.mm unit 10 13,677,521 136,775,210
Length cable : 50m ( 5 pes), size 16sq.mm unit 5 6,187,450 30,937,250
7 FRP (Fiber Rainforced Plastic) Support Dimension : 1" x 1200mm set 15 5,861,794 87,926,910
Positive SS 304 Juction Box, Casing : S/S 304, 2mm, Dimension : 400 x 300 x 200 (with 17,585,384
8 unit 20 351,707,680
10 terminals)
9 Cable, Cable XLPE/PVC 1 x 70sq mm meter 3800 182,367 692,994,600
10 Cast Almunium Test Point, c/w 2 5 Terminal with 3" dia conduit 6ft long unit 76 6,513,103 494,995,828
11 Permanent Cu/CuS04 unit 80 7,815,726 625,258,080
12 Galvanized Conduit dia 1" x 4m btg 1,000 390,786 390,786,000
Accesories Conduit (Eibow,Sock) lot 4 65,131,053 260,524,212
13 Almunium Anode Type ICS 70 AWB, Net Weight : 7kg, Gross Weight: 7,3 kg Pcs 68 2,605,242 177,156,456
14 Almunium Anode Type ICS 40 AWB, Net Weight : 4kg, Gross Weight: 4,4 kg Pcs 400 1,302,621 521,048,400
Almunium Anode special design for condesor, Nb: Dimensi sesuai anode eksiting, jumlah 850 97,696
15 Kg 83,002,522
anode tergantung dimensi
Almunium Anode special design for condesor by pass pipe, Nb: Dimensi sesuai anode 97,696
16 Kg 330 32,278,758
eksiting, jumlah anode tergantung dimensi
17 AC Power 3 x 10 sq.mm meter 500 280,064 140,032,000
18 Miscellanous item (Nut, Bolt, Tape) lot 1 49,499,600 49,499,600

B ENGINEERING AND INSTALLATION WORK


1 Design Engineering Lot 1 468,932,037 468,932,037
2 Transportasi Material to site Lot 1 130,262,104 130,262,104
3 Mob-Demob personil & Equipment Lot 1 78,157,263 78,157,263
4 Biaya Akomodasi & Transportasi at site Lot 1 78,157,263 78,157,263
5 Biaya lnstalasi Material & Perbaikan -
- Biaya Bar Hole 8" @75meter hole 72 35,170,768 2,532,295,296
- Biaya Bar Hole 8" @30meter hole 4 26,052,421 104,209,684
- lnstalasi T/R unit 8 11,072,279 88,578,232
- lnstalasi ICCP system unit 76 15,631,453 1,187,990,428
- lnstalasi juction box unit 20 3,256,554 65,131,080
- lnstalasi Test Point meter 76 3,256,553 247,498,028
- Penggalian kabel dan lnstalasi Meter 4300 130,262 560,126,600
- lnstalasi Almunium Anode Pes 208 4,559,174 948,308,192
6 Biaya Testing & Commisioning Lot 1 390,794,823 390,794,823
7 Biaya Dokumentasi & Final Report Lot 1 195,393,156 195,393,156

JUMLAH 26,436,363,636
PPN 10% 2,643,636,364
Total 29,080,000,000

500
PEKERJAAN REHABILITASI CATHODIC PROTECTION PLTG
PT PLN (Persero) UNIT PELAKSANA PEMBANGKITAN
Faktor Berat untuk Keseluruhan Proye

Project : Pekerjaan Rehabilitasi Cothodic Protection PLTGU


Date :
Revision :0

NO. DESKRIPSI

1 ENGINEERING

2 PROCUREMENT

3 CONSTRUCTION AND INSTALLATION

4 COMMISSIONING AND ACCEPTANCE

5 DOCUMENTATION AND FINAL REPORT

TOTAL
ASI CATHODIC PROTECTION PLTGU BELAWAN
UNIT PELAKSANA PEMBANGKITAN BELAWAN
rat untuk Keseluruhan Proyek

BOBOT BERAT
HARGA
(%)

Rp 468,932,037 1.77%

Rp 18,904,612,086 71.51%

Rp 6,476,631,534 24.50%

Rp 390,794,823 1.48%

Rp 195,393,156 0.74%

Rp 26,436,363,636.00 100.00%
PEKERJAAN REHABILITASI CATHODIC PROTECTION PLTGU B

NO ITEM DESCRIPTION

Effective Date
1. ENGINEERING
Design Engineering

Special Design Anode for Condensor (Sacraficial Anode)

Transformer Rectifier

ICCP & Deepweld, Cable & Bore Hole Layout

Junction Box & Miscelaneous

2. PROUREMENT
Spesial Design Anode for Condensor

15

16

ICCP & Deepweld Groundbed

11
New Transformer Rectifier and Service

Junction Box and Miscellaneous Item

10

17

18

Cable

12.a

12.b

Almunium Anode

13

14

3. CONSTRUCTION
Genaral
Transportasi Material to site

Mob-Demob personil & Equipment

Biaya Akomodasi & Transportasi at site

Servis Transformer Rectifier :

2 Servis Transformer Rectifier :

Construction and Installation

Drill 8" for 75 meters

Drill 8" for 30 meters

Instalasi & servis Transformer Rectifier (T/R)

Instalasi of ICCP System

Instalasi Junction Box

Instalasi Test Point

Instalasi kabel

Instalasi Almunium Anode

4. COMMISSIONING AND ACCEPATNCE


Testing & Commisioning

5. DOCUMENTATION AND FINAL REPORT

Dokumentasi & Final Report

TOTAL
N REHABILITASI CATHODIC PROTECTION PLTGU BELAWAN

ITEM DESCRIPTION

sign Engineering

Special Design Anode for Condensor (Sacraficial Anode)

Transformer Rectifier

ICCP & Deepweld, Cable & Bore Hole Layout

Junction Box & Miscelaneous

REMENT
Spesial Design Anode for Condensor

Almunium Anode special design for condesor

Almunium Anode special design for condesor by pass pipe

ICCP & Deepweld Groundbed

Deepwell Groundbed dengan kedalaman 75 m

DeepWeld Groundbed dengan kedalaman 30m

Permanent Cu/CuS04
New Transformer Rectifier and Service

Transformer Rectifier Spesifikasi :

Transformer Rectifier Oil : type Shell S2ZUI

Junction Box and Miscellaneous Item

Positive SS 304 Juction Box, Casing : S/S 304, 2mm, Dim : 400 x 300 x 200 (with 10 terminals)

Cast Almunium Test Point, c/w 2 5 Terminal with 3" dia conduit 6ft long

FRP (Fiber Rainforced Plastic) Support Dim : 1" x 1200mm

AC Power 3 x 10 sq.mm

Miscellanous item (Nut, Bolt, Tape)

Mixed Metal Oxide Anode, Dimension 1" x 1m c/w cable HMWPE

Cable, Cable XLPE/PVC 1 x 70sq mm

Galvanized Conduit dia 1" x 4m

Accesories Conduit (Eibow,Sock)

Almunium Anode

Almunium Anode Type ICS 70 AWB, Net Weight : 7kg, Gross Weight: 7,3 kg

Almunium Anode Type ICS 40 AWB, Net Weight : 4kg, Gross Weight: 4,4 kg

TRUCTION
Transportasi Material to site

Mob-Demob personil & Equipment

Biaya Akomodasi & Transportasi at site

vis Transformer Rectifier :

Servis Transformer Rectifier :

nstruction and Installation

Drill 8" for 75 meters

Drill 8" for 30 meters

Instalasi & servis Transformer Rectifier (T/R)

Instalasi of ICCP System

Instalasi Junction Box

Instalasi Test Point

Instalasi kabel

Instalasi Almunium Anode

MISSIONING AND ACCEPATNCE


Testing & Commisioning

MENTATION AND FINAL REPORT

Dokumentasi & Final Report

TOTAL
: PERIOD 26-MAY-2019
Year 2018

18-Nov

25-Nov

2-Dec
WF Sub-WF Actual Week
(%) (%) Progress

Week No. 1 2 3

1.77% Plan 0.01% 0.01%


Actual 0.11%
0.44% Plan 0.01% 0.01%
0.40% Actual 0.11%
0.22% Plan
0.00% Actual
0.55% Plan
0.39% Actual
0.55% Plan
0.00% Actual

0.44% Plan
Actual
0.31% Plan
0.03% Actual
0.12% Plan
0.01% Actual
49.60% Plan
Actual
44.79% Plan
3.34% Actual
2.44% Plan
0.12% Actual
2.37% Plan
0.24% Actual
8.86% Plan
Actual
8.56% Plan
0.00% Actual
0.29% Plan
0.03% Actual
4.25% Plan
Actual
1.33% Plan
0.13% Actual
1.87% Plan
0.19% Actual
0.33% Plan
0.03% Actual
0.53% Plan
0.05% Actual
0.19% Plan
0.09% Actual
5.72% Plan
Actual
0.63% Plan
0.06% Actual
2.62% Plan
0.26% Actual
1.48% Plan
0.15% Actual
0.99% Plan
0.10% Actual
2.64% Plan
Actual
0.67% Plan
0.37% Actual
1.97% Plan
1.08% Actual

1.08% Plan
Actual
0.49% Plan
0.01% Actual
0.30% Plan
0.15% Actual
0.30% Plan
0.07% Actual

1.72% Plan
Actual
1.72% Plan
0.00% Actual

21.69% Plan
Actual
9.58% Plan
0.00% Actual
0.39% Plan
0.00% Actual
0.34% Plan
0.00% Actual
4.49% Plan
0.00% Actual
0.25% Plan
0.00% Actual
0.94% Plan
0.00% Actual
2.12% Plan
0.00% Actual
3.59% Plan
2.06% Actual

1.48% Plan
Actual
1.48% Plan
0.00% Actual

0.74% Plan
Actual
0.74% Plan
0.00% Actual

Earn. 0.00% 0.01% 0.01%

Plan Actual
Cum. 0.00% 0.01% 0.02%
100% 100% 9.38%
Earn. 0.00% 0.00% 0.11%
Cum. 0.00% 0.00% 0.11%
2018

16-Dec

23-Dec

30-Dec

13-Jan

20-Jan
9-Dec

6-Jan
4 5 6 7 8 9 10

0.02% 0.02% 0.03% 0.03% 0.06% 0.06% 0.08%


0.24%
0.02% 0.02% 0.03% 0.03% 0.03% 0.03% 0.04%
0.24%
0.00% 0.00% 0.01% 0.01% 0.01% 0.01% 0.02%

0.01% 0.01% 0.02%


0.02% 0.02% 0.03% 0.03% 0.06% 0.06% 0.08%
0.04% 0.06% 0.09% 0.13% 0.19% 0.24% 0.32%
0.00% 0.00% 0.24% 0.00% 0.00% 0.00% 0.00%
0.11% 0.11% 0.35% 0.35% 0.35% 0.35% 0.35%
`
10-Mar
10-Feb

17-Feb

24-Feb
27-Jan

3-Mar
3-Feb

11 12 13 14 15 16 17

0.08% 0.12% 0.12% 0.17% 0.09% 0.13% 0.09%


0.09% 0.06%
0.04% 0.05% 0.05% 0.09%

0.02% 0.02% 0.02% 0.03% 0.03% 0.04%

0.02% 0.03% 0.03% 0.04% 0.04% 0.05% 0.05%


0.09% 0.06%
0.01% 0.01% 0.02% 0.02% 0.03% 0.03%

0.07% 0.07% 0.07% 0.07%

0.07% 0.07% 0.07% 0.07%

0.07% 0.07% 0.07% 0.07%


0.40% 0.40%

0.39% 0.39%

0.01% 0.01%
0.08% 0.08%

0.08% 0.08%
0.08% 0.12% 0.12% 0.25% 0.16% 0.68% 0.64%
0.41% 0.52% 0.64% 0.88% 1.05% 1.73% 2.37%
0.00% 0.09% 0.00% 0.00% 0.00% 0.00% 0.06%
0.35% 0.44% 0.44% 0.44% 0.44% 0.44% 0.50%
17-Mar

24-Mar

31-Mar

14-Apr

21-Apr

28-Apr
7-Apr
18 19 20 21 22 23 24

0.11% 0.11% 0.16% 0.05% 0.06% 0.06% 0.11%


0.06%

0.06% 0.06% 0.11%


0.06%
0.04% 0.04% 0.05% 0.05% 0.06% 0.06% 0.11%

0.07% 0.07%

0.07% 0.07%

0.07% 0.07%

3.73% 3.73% 5.80% 5.80% 11.67%

3.73% 3.73% 5.60% 5.60% 11.20%

0.20% 0.20% 0.31%

0.17%
0.40% 0.60% 0.60% 0.60% 0.81% 0.81% 1.41%

0.39% 0.58% 0.58% 0.58% 0.78% 0.78% 1.36%

0.01% 0.02% 0.02% 0.02% 0.03% 0.03% 0.05%

0.23%

0.10%

0.13%

0.05% 0.05% 0.07% 0.07% 0.09%

0.05% 0.05% 0.07% 0.07% 0.09%

0.05% 0.05% 0.07% 0.07% 0.10%

0.05% 0.05% 0.07% 0.07% 0.10%

0.01% 0.02% 0.02% 0.03% 0.04% 0.06%


0.004% 0.004% 0.01% 0.01% 0.01% 0.01%

0.01% 0.01% 0.02% 0.02% 0.04%

0.002% 0.002% 0.004% 0.004% 0.01% 0.01%

0.08% 0.12% 0.12% 0.12% 0.16% 0.16% 0.27%

0.08% 0.12% 0.12% 0.12% 0.16% 0.16% 0.27%


0.66% 0.91% 4.72% 4.62% 7.00% 7.01% 13.94%
3.03% 3.93% 8.66% 13.28% 20.28% 27.29% 41.23%
0.00% 0.00% 0.00% 0.00% 0.06% 0.00% 0.00%
0.50% 0.50% 0.50% 0.50% 0.55% 0.55% 0.55%
12-May

19-May

26-May
5-May

2-Jun

9-Jun
25 26 27 28 29 30

0.00% 0.23% 0.00%

0.00% 0.04% 0.00%

0.00% 0.00% 0.00%

0.00% 0.19% 0.00%

0.00% 0.00% 0.00%

0.04% 0.00%

0.03% 0.00%

0.01% 0.00%
15.41% 0.86% 1.07% 0.34% 0.51% 0.68%
3.70% 0.00%
14.93%
3.34% 0.00%
0.31% 0.61% 0.81%
0.12% 0.00%
0.17% 0.25% 0.25% 0.34% 0.51% 0.68%
0.24% 0.00%

71.78%
1.41% 1.41%
0.03% 0.00%
1.36% 1.36% 71.78%
0.00% 0.00%
0.05% 0.05% 9-Jun; 70.36%
0.03% 0.00%
0.23% 0.42% 0.42% 0.57% 0.80% 1.07%
0.13% 0.37% 0.00%
0.10% 0.14% 0.14% 0.19% 0.29% 0.38%
0.13% 0.00%
0.13% 0.20% 0.20% 0.27% 0.40% 0.53%
0.19% 0.00%
0.02% 0.02% 0.04% 0.04% 0.05%
0.03% 0.00% 0.00%
0.04% 0.04% 0.06% 0.06% 0.08%
0.05% 0.00%
0.01% 0.01% 0.02% 0.02% 0.03%
0.09% 0.00% 0.00%
0.14% 0.37% 0.19% 0.28% 0.28% 0.37%
0.57% 0.00%
0.14% 0.18%
0.06% 0.00%
0.19% 0.19% 0.28% 0.28% 0.37%
0.26% 0.00%

0.15% 0.00%

0.10% 0.00%
0.14% 0.19%
0.66% 0.66% 0.13% 0.00%
0.14% 0.19%
0.17% 0.17% 0.03% 0.00%

0.49% 0.49% 0.10% 0.00%

0.07% 0.03% 0.04% 0.04% 0.04% 0.05%


0.23% 0.00% 0.00%
0.02% 0.02% 0.02% 0.02% 0.02% 0.03%
0.01% 0.00% 0.00%
0.04%
0.15% 0.00% 0.00%
0.01% 0.01% 0.01% 0.01% 0.01% 0.02%
0.07% 0.00% 0.00%

0.27% 0.27%

0.27% 0.27%

0.08% 0.08% 0.14% 0.14% 0.14% 0.58%


1.86% 0.21% 0.00% 0.00%
0.08% 0.08% 0.14% 0.14% 0.14% 0.42%

0.16%

1.86% 0.21% 0.00% 0.00%

9.38%
9.38%

17.75% 3.64% 1.85% 1.37% 1.77% 2.75%


58.98% 62.62% 64.47% 65.84% 67.61% 70.36%
2.52% 1.22% 5.08% 0.00% 0.00% 0.00%
3.07% 4.29% 9.38% 9.38% 9.38% 9.38%
31
16-Jun

71.78%
32
23-Jun

33

30-Jun
34

7-Jul
2019

35

14-Jul
36

21-Jul
71.78%

9-Jun; 70.36%

0.22% 0.30%

0.07% 0.10%

0.11% 0.15%

0.04% 0.05%

0.56% 0.95% 0.21% 0.31% 0.31% 0.62%

0.56% 0.75%

0.12% 0.12% 0.18% 0.18% 0.37%

0.08% 0.00% 0.04% 0.00% 0.12%

0.14% 0.14% 0.21% 0.21% 0.28%

0.14% 0.14% 0.21% 0.21% 0.28%

0.05% 0.06% 0.06% 0.06% 0.06% 0.07%


0.03% 0.04% 0.04% 0.04% 0.04% 0.04%

0.02% 0.02% 0.02% 0.02% 0.02% 0.03%

0.58% 0.80% 0.80% 1.03% 1.03% 1.21%

0.42% 0.56% 0.56% 0.70% 0.70% 0.85%

0.16% 0.24% 0.24% 0.32% 0.32% 0.37%

9.38%
9.38%

1.42% 2.26% 1.21% 1.60% 1.60% 2.18%


71.78% 74.04% 75.24% 76.85% 78.45% 80.63%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
9.38% 9.38% 9.38% 9.38% 9.38% 9.38%
37
28-Jul

38
4-Aug

39

11-Aug
40

18-Aug
41

25-Aug
42

1-Sep
0.82%

0.49%

0.08%

0.42% 0.56%

0.42% 0.56%

0.07% 0.07%
0.04% 0.04%

0.03% 0.03%

1.44% 1.61% 1.72% 1.80% 1.97% 0.85%

0.85% 0.99% 0.99% 0.99% 0.96%

0.05% 0.07%

0.03% 0.05%

0.37% 0.40% 0.40% 0.48% 0.48% 0.27%

0.22% 0.22% 0.34% 0.34% 0.45% 0.45%


2.75% 2.24% 1.72% 1.80% 1.97% 0.85%
83.38% 85.63% 87.35% 89.15% 91.12% 91.97%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
9.38% 9.38% 9.38% 9.38% 9.38% 9.38%
43
8-Sep

44
15-Sep

45

22-Sep
46

29-Sep
47

6-Oct
48

13-Oct
1.11% 1.15% 0.13% 0.05% 0.06% 0.22%

0.10% 0.17%

0.07% 0.08% 0.10%

0.27%

0.03% 0.05% 0.06% 0.11%

0.12%

0.67% 0.90%
1.11% 1.15% 0.13% 0.05% 0.06% 0.22%
93.08% 94.23% 94.36% 94.41% 94.47% 94.70%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
9.38% 9.38% 9.38% 9.38% 9.38% 9.38%
49
20-Oct

50
27-Oct

51
3-Nov
52

10-Nov
53

17-Nov
54

24-Nov
0.18% 0.23% 0.54% 0.20% 0.20% 0.33%

0.18% 0.23% 0.41%

0.13% 0.20% 0.20% 0.33%


0.18% 0.23% 0.54% 0.20% 0.20% 0.33%
94.87% 95.11% 95.65% 95.85% 96.05% 96.38%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
9.38% 9.38% 9.38% 9.38% 9.38% 9.38%
55
1-Dec

56
8-Dec

57
15-Dec
58

22-Dec
59

29-Dec
60

5-Jan
0.15%
0.15%

0.33% 0.40% 0.40% 0.13%

0.33% 0.40% 0.40% 0.13%

1.48%
1.48%

0.25% 0.25%

0.25% 0.25%

0.33% 0.40% 0.40% 1.76% 0.25% 0.25%


96.71% 97.11% 97.50% 99.26% 99.51% 99.75%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
9.38% 9.38% 9.38% 9.38% 9.38% 9.38%
61
12-Jan

62
19-Jan

63
26-Jan
2020

64

2-Feb
65

9-Feb
66

16-Feb

80%
90%
100%
70%

60%

50%

40%
40%

30%

20%

10%
0.25%

0.25%
0%
0.25% 0.00% 0.00% 0.00% 0.00% 0.00%
100.0% 100.0% 100.0% 100.0% 100.0% 100.0%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
9.38% 9.38% 9.38% 9.38% 9.38% 9.38%
23-Feb

67

100%

90%

80%
70%

60%

50%

40%
40%

30%

20%

10%
0%
0.00%
100.0%
0.00%
9.38%
PEKERJAAN REHABILITASI CA
PT PLN (Persero) UNI
SUMMARY
PERIOD : 1
Contract No. : 047.Pj/KIT.03.02UIKSBU/2018
Date : 16-Jun-19
Amand. : 0
Revision : 0

WP Code Work Description

1 ENGINEERING

2 PROCUREMENT

3 CONSTRUCTION AND INSTALLATION

PT SHAFTINDO ENERGI Page 60 of 81


WP Code Work Description

4 COMMISSIONING AND ACCEPATNCE

5 DOCUMENTATION AND FINAL REPORT

TOTAL

CONTRACTOR
Prepared by,

( )
PT SHAFTINDO ENERGI Page 61 of 81
TASI CATHODIC PROTECTION PLTGU BELAWAN
o) UNIT PELAKSANA PEMBANGKITAN BELAWAN
MMARY WEEKLY PROGRESS
RIOD : 10 June - 16 June 2019

Plan Progress Actual Progress


Overall Weight
(%) Cumm Last Cumm This Cumm Last
This Period This Period
Period Period Period

1.77% 100.00% 0.00% 100.00% 44.38% 0.00%

71.51% 91.23% 1.10% 92.33% 8.80% 0.00%

24.50% 13.65% 2.58% 16.23% 9.36% 0.00%

PT SHAFTINDO ENERGI Page 62 of 81


Plan Progress Actual Progress
Overall Weight
(%) Cumm Last Cumm This Cumm Last
This Period This Period
Period Period Period

1.48% 0.00% 0.00% 0.00% 0.00% 0.00%

0.74% 0.00% 0.00% 0.00% 0.00% 0.00%

100.00% 70.36% 1.42% 71.78% 9.38% 0.00%

COMPANY
Approved by,

PT SHAFTINDO ENERGI Page 63 of 81


Plan Progress Actual Progress
Overall Weight
(%) Cumm Last Cumm This Cumm Last
This Period This Period
Period Period Period
Rep's Site Compa

PT SHAFTINDO ENERGI Page 64 of 81


BELAWAN
N BELAWAN

Actual Progress Variance

Cumm This Cumm This


Period Period

44.38% -55.63%

8.80% -83.53%

9.36% -6.87%

PT SHAFTINDO ENERGI Page 65 of 81


Actual Progress Variance

Cumm This Cumm This


Period Period

0.00% 0.00%

0.00% 0.00%

9.38% -62.40%

Approved by,

PT SHAFTINDO ENERGI Page 66 of 81


Actual Progress Variance

Cumm This Cumm This


Period Period
Rep's Site Company

PT SHAFTINDO ENERGI Page 67 of 81


PEKERJAAN REHABILIT
PT PLN (Persero) U
BREAKDO
PERI

No. Uraian Pekerjaan

REHABILITASI CATHODIC PROTECTION PLTGU BELAWAN


1 ENGINEERING
1.1 Design Engineering
Special Design Anode for Condensor (Sacraficial Anode)
Transformer Rectifier
ICCP & Deepweld, Cable & Bore Hole Layout
Junction Box & Miscelaneous

2 PROCUREMENT
2.1 Spesial Design Anode for Condensor
15 Almunium Anode special design for condesor
16 Almunium Anode special design for condesor by pass pipe
2.2 ICCP & Deepweld Groundbed
4 Deepwell Groundbed dengan kedalaman 75 m
5 DeepWeld Groundbed dengan kedalaman 30m
11 Permanent Cu/CuS04
2.3 New Transformer Rectifier and Service
1 Transformer Rectifier Spesifikasi :
3 Transformer Rectifier Oil : type Shell S2ZUI
2.4 Junction Box and Miscellaneous Item
Positive SS 304 Juction Box, Casing : S/S 304, 2mm, Dimension : 400 x 300
8
x 200 (with 10 terminals)
10 Cast Almunium Test Point, c/w 2 5 Terminal with 3" dia conduit 6ft long
7 FRP (Fiber Rainforced Plastic) Support Dimension : 1" x 1200mm
17 AC Power 3 x 10 sq.mm
18 Miscellanous item (Nut, Bolt, Tape)
2.5 Cable
6 Mixed Metal Oxide Anode, Dimension 1" x 1m c/w cable HMWPE
9 Cable, Cable XLPE/PVC 1 x 70sq mm
12 Galvanized Conduit dia 1" x 4m
Accesories Conduit (Eibow,Sock)
2.6 Almunium Anode
13 Almunium Anode Type ICS 70 AWB, Net Weight : 7kg, Gross Weight: 7,3 kg
14 Almunium Anode Type ICS 40 AWB, Net Weight : 4kg, Gross Weight: 4,4 kg

3 CONSTRUCTION AND INSTALLATION


3.1 General
B2 Transportasi Material to site
B3 Mob-Demob personil & Equipment
B4 Biaya Akomodasi & Transportasi at site
3.2 Servis Transformer Rectifier :
Pembersihan Transformer Rectifier : penggantian Diode, fuse, manual Volt
2 meter, Amp meter dan Lampu, Pengencangan mur baut, pengecekan kabel
kabel, Pengecatan Casing
3.3 Construction and Installation
B5a Drill 8" for 75 meters
B5b Drill 8" for 30 meters
B5c Instalasi & servis Transformer Rectifier (T/R)
B5d Instalasi of ICCP System
B5e Instalasi Junction Box
B5f Instalasi Test Point
B5g Instalasi kabel
B5h Instalasi Almunium Anode

4 COMMISSIONING AND ACCEPATNCE


4.1 Testing & Commisioning

5 DOCUMENTATION AND FINAL REPORT


5.1 Dokumentasi & Final Report
RJAAN REHABILITASI CATHODIC PROTECTION PLTGU BELAWAN
PLN (Persero) UNIT PELAKSANA PEMBANGKITAN BELAWAN
BREAKDOWN DETAIL WEEKLY PROGRESS
PERIOD : 10 June - 16 June 2019

Plan Progress
Estimated Overall Weight Sub Weight
Value (IDR) Factor (%) Factor (%) Cumm Last Cumm This
This Period
Period Period

26,436,363,636 100.00% 100.00% 70.36% 1.42% 71.78%


468,932,037 1.77% 100.00% 100.00% 0.00% 100.00%
468,932,037 1.77% 100.00% 100.00% 0.00% 100.00%
117,233,009 0.44% 25.00% 100.00% 0.00% 100.00%
58,616,505 0.22% 12.50% 100.00% 0.00% 100.00%
146,541,262 0.55% 31.25% 100.00% 0.00% 100.00%
146,541,262 0.55% 31.25% 100.00% 0.00% 100.00%

18,904,612,086 71.51% 100.00% 91.23% 1.10% 92.33%


115,281,280 0.44% 100.00% 100.00% 0.00% 100.00%
83,002,522 0.31% 72.00% 100.00% 0.00% 100.00%
32,278,758 0.12% 28.00% 100.00% 0.00% 100.00%
13,113,355,082 49.60% 100.00% 100.00% 0.00% 100.00%
11,842,127,186 44.79% 90.31% 100.00% 0.00% 100.00%
645,969,816 2.44% 4.93% 100.00% 0.00% 100.00%
625,258,080 2.37% 4.77% 100.00% 0.00% 100.00%
2,341,591,578 8.86% 100.00% 100.00% 0.00% 100.00%
2,264,215,890 8.56% 96.70% 100.00% 0.00% 100.00%
77,375,688 0.29% 3.30% 100.00% 0.00% 100.00%
1,124,162,018 4.25% 100.00% 87.66% 5.29% 92.95%

351,707,680 1.33% 31.29% 100.00% 0.00% 100.00%


494,995,828 1.87% 44.03% 100.00% 0.00% 100.00%
87,926,910 0.33% 7.82% 50.00% 21.43% 71.43%
140,032,000 0.53% 12.46% 50.00% 21.43% 71.43%
49,499,600 0.19% 4.40% 50.00% 21.43% 71.43%
1,512,017,272 5.72% 100.00% 34.01% 9.82% 43.83%
167,712,460 0.63% 11.09% 100.00% 0.00% 100.00%
692,994,600 2.62% 45.83% 50.00% 21.43% 71.43%
390,786,000 1.48% 25.85% 0.00% 0.00% 0.00%
260,524,212 0.99% 17.23% 0.00% 0.00% 0.00%
698,204,856 2.64% 100.00% 25.37% 0.00% 25.37%
177,156,456 0.67% 25.37% 100.00% 0.00% 100.00%
521,048,400 1.97% 74.63% 0.00% 0.00% 0.00%

6,476,631,534 24.50% 100.00% 13.65% 2.58% 16.23%


286,576,630 1.08% 100.00% 41.09% 4.55% 45.64%
130,262,104 0.49% 45.45% 37.75% 6.25% 44.00%
78,157,263 0.30% 27.27% 50.00% 0.00% 50.00%
78,157,263 0.30% 27.27% 37.75% 6.25% 44.00%
455,917,364 1.72% 100.00% 100.00% 0.00% 100.00%
455,917,364 1.72% 100.00% 100.00% 0.00% 100.00%

5,734,137,540 21.69% 100.00% 5.42% 2.69% 8.10%


2,532,295,296 9.58% 44.16% 10.59% 4.41% 15.00%
104,209,684 0.39% 1.82% 0.00% 0.00% 0.00%
88,578,232 0.34% 1.54% 0.00% 0.00% 0.00%
1,187,990,428 4.49% 20.72% 3.57% 3.57% 7.14%
65,131,080 0.25% 1.14% 0.00% 0.00% 0.00%
247,498,028 0.94% 4.32% 0.00% 0.00% 0.00%
560,126,600 2.12% 9.77% 0.00% 0.00% 0.00%
948,308,192 3.59% 16.54% 0.00% 0.00% 0.00%

390,794,823 1.48% 100.00% 0.00% 0.00% 0.00%


390,794,823 1.48% 100.00% 0.00% 0.00% 0.00%

195,393,156 0.74% 100.00% 0.00% 0.00% 0.00%


195,393,156 0.74% 100.00% 0.00% 0.00% 0.00%
Actual Progress Variance
Cumm Last Cumm This Cumm This 16-Jun-19
This Period
Period Period Period

9.38% 0.00% 9.38% -62.40%


44.38% 0.00% 44.38% -55.63%
44.38% 0.00% 44.38% -55.63%
90.00% 0.00% 90.00% -10.00%
0.00% 0.00% 0.00% -100.00%
70.00% 0.00% 70.00% -30.00%
0.00% 0.00% 0.00% -100.00%

8.80% 0.00% 8.80% -83.53%


10.00% 0.00% 10.00% -90.00%
10.00% 0.00% 10.00% -90.00%
10.00% 0.00% 10.00% -90.00%
7.45% 0.00% 7.45% -92.55%
7.46% 0.00% 7.46% -92.54%
4.80% 0.00% 4.80% -95.20%
10.00% 0.00% 10.00% -90.00%
0.33% 0.00% 0.33% -99.67%
0.00% 0.00% 0.00% -100.00%
10.00% 0.00% 10.00% -90.00%
11.76% 0.00% 11.76% -81.19%

10.00% 0.00% 10.00% -90.00%


10.00% 0.00% 10.00% -90.00%
10.00% 0.00% 10.00% -61.43%
10.00% 0.00% 10.00% -61.43%
50.00% 0.00% 50.00% -21.43%
10.00% 0.00% 10.00% -33.83%
10.00% 0.00% 10.00% -90.00%
10.00% 0.00% 10.00% -61.43%
10.00% 0.00% 10.00% 10.00%
10.00% 0.00% 10.00% 10.00%
55.00% 0.00% 55.00% 29.63%
55.00% 0.00% 55.00% -45.00%
55.00% 0.00% 55.00% 55.00%

9.36% 0.00% 9.36% -6.87%


21.33% 0.00% 21.33% -24.30%
1.93% 0.00% 1.93% -42.07%
50.00% 0.00% 50.00% 0.00%
25.00% 0.00% 25.00% -19.00%
0.00% 0.00% 0.00% -100.00%
0.00% 0.00% 0.00% -100.00%

9.51% 0.00% 9.51% 1.40%


0.00% 0.00% 0.00% -15.00%
0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% -7.14%
0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00%
57.48% 0.00% 57.48% 57.48%

0.00% 0.00% 0.00% 0.00%


0.00% 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00%


0.00% 0.00% 0.00% 0.00%
KONSORSIUM PT KURNIA PURNAMATAMA –
PT TANEX MAKMUR PRIMAJAYA – PT SHAFTINDO ENERGI
PT. PLN (Persero)
V V Unit Induk Pembangkitan Sumatera Bagian Utara
P P
C C Rehabilitasi Cathodic Protection PLTGU Belawan

DAFTAR DOKUMEN
Nomor Dokumen Ukuran
No. Judul Dokumen Hal
EQP. No. REQ. No. Rev Kertas

DESIGN ENGINEERING
1 Special Design Anode for Condensor (Sacraficial Anode)
047.PJ/UIKSBU2018/KSO-SACP E Kalkulasi SACP Pada Area Condensor dan Water Intake Blok I A4 5

047.PJ/UIKSBU2018/KSO-SACP E Kalkulasi SACP Pada Area Condensor dan Water Intake Blok II A4 5

047.PJ/UIKSBU2018/KSO-SACP E Gambar Installasi SACP Pada Condensor dan Water Intake di Blok I A3 6

047.PJ/UIKSBU2018/KSO-SACP E Gambar Installasi SACP Pada Condensor dan Water Intake di Blok II A3 6

2 Transformer Rectifier
Gambar panel Arrangement Transformer Rectifier A4
Gambar Panel Wiring Transformer Rectifier A3

3 ICCP & Deepweld, Cable & Bore Hole Layout dan Junction Box
047.PJ/UIKSBU2018/KSO-ICPP Kalkulasi Anoda Impress Current A4 2
KONSORSIUM PT KURNIA PURNAMATAMA –
PT TANEX MAKMUR PRIMAJAYA – PT SHAFTINDO ENERGI
PT. PLN (Persero)
V V Unit Induk Pembangkitan Sumatera Bagian Utara
P P
C C Rehabilitasi Cathodic Protection PLTGU Belawan

DAFTAR DOKUMEN
Nomor Dokumen Ukuran
No. Judul Dokumen Hal
EQP. No. REQ. No. Rev Kertas

047.PJ/UIKSBU2018/KSO-ICPP E Gambar Layout Titik Bor dan Jalur Kabel A3 12

047.PJ/UIKSBU2018/KSO-ICPP A Gambar Detail Installasi Ground Bed MMO A3 3


047.PJ/UIKSBU2018/KSO-ICPP A Gambar Installasi Test Point dan Junction Box A3 2
4 Certificate & Procedure
047.PJ/UIKSBU/2018/KSO-COM Sertifikat Keaslian Material A4
047.PJ/UIKSBU/2018/KSO-PR Prosedur A4
Standar Instalasi A4
Standar Pengoperasian A4
Standar Perawatan A4
Nomor : 047.PJ/KSO-DL-01
Tanggal : 02-June-2019

Lokasi : Belawan

Progress
Jumlah Overall
Total Progress
Doc's Weight IFR IFA IFC
Aktual
IFR IFA IFC 50% 30% 20% 100.00%

15 100.00% 42.67%
4 26.67% 90.00%
28-Nov-18 13-Dec-18 03-May-19 1 6.67% 100% 100% 100% 100.00%
25-Apr-19 04-Jan-19
17-Jan-19
25-Apr-19
28-Nov-18 13-Dec-18 1 6.67% 100% 100% 0% 80.00%
25-Apr-19 04-Jan-19
12-Dec-18 19-Dec-18 03-May-19 1 6.67% 100% 100% 100% 100.00%
25-Apr-19 04-Jan-19
16-Jan-19
12-Dec-18 19-Dec-18 1 6.67% 100% 100% 0% 80.00%
25-Apr-19 16-Jan-19

2 13.33% 0.00%
1 6.67% 0% 0% 0% 0.00%
1 6.67% 0% 0% 0% 0.00%

4 26.67% 70.00%
1 6.67% 0% 0% 0% 0.00%
Nomor : 047.PJ/KSO-DL-01
Tanggal : 02-June-2019

Lokasi : Belawan

Progress
Jumlah Overall
Total Progress
Doc's Weight IFR IFA IFC
Aktual
IFR IFA IFC 50% 30% 20% 100.00%
07-Feb-19 14-Feb-19 1 6.67% 100% 100% 0% 80.00%
20-Feb-19
22-Feb-19
07-Mar-19
24-Mar-19 08-May-19 15-May-19 1 6.67% 100% 100% 100% 100.00%
08-Apr-19 02-May-19 15-May-19 1 6.67% 100% 100% 100% 100.00%
5 33.33% 0.00%
1 6.67% 0% 0% 0% 0.00%
1 6.67% 0% 0% 0% 0.00%
1 6.67% 0% 0% 0% 0.00%
1 6.67% 0% 0% 0% 0.00%
1 6.67% 0% 0% 0% 0.00%
PROCUREMENT MASTER SCHEDULE
PROJECT: Rehabilitasi Cathodic Protection
CLIENT: PLTU Belawan
CONTRACTOR: KOS KPI-Tanex-PTSE
CONTRACT NO.: 047.Pj/KIT.03.02UIKSBU/2018
CUT OF DATE: 16-Jun-19

PURCHASE ORDER SHIPMENT FROM VENDOR INSPECTION

No. URAIAN PEKERJAAN SATUAN JUMLAH PO PLAN


ETD ATD ACTUAL
NUMBER (SCH)

A MATERIAL LIST
1 Transformer Rectifier Spesifikasi : unit 6
Type : Manual Setting
- Cooling : Air Cooled (Pendinginan Udara )
- Input AC: : 3 phase, 380VAC, 50 Hz, Output: 250 Amp-50 V
- Casing : SS 304, Outdoor Type : IP 43
unit
2 Servis Transformer Rectifier : 14
"
Pembersihan Transformer Rectifier : penggantian Diode, fuse, manual Volt meter, Amp meter dan Lampu,
Pengencangan mur baut, pengecekan kabel kabel, Pengecatan Casing

3 Transformer Rectifier Oil : type Shell S2ZUI drum 3 PO-168


4 Oeepwell Groundbed dengan kedalaman 75 m
A. MMO String Anode unit 72 PO-172

Consist of 6 Pes MMO anode dimension 1" x 1m c/w 150m leghth of 1 x 35 sq.mm HMWPE cable

B. Material for Deepwell Anode lnstalation (1 hole- 75 meter each), adalah :


Steel Pipe Casing 8" dia non schedule Pcs 900 PO-170
Loresco SC-3 Coke Breeze backsfill 501bs/bag Bag 1080
Anode Centralizer ( u-clamp) Pcs 950
Nylon Rope meter 6000
Breather pipa PVC dia 1" @4m length meter 1450
Cover for casing pipe Pcs 72
5 DeepWeld Groundbed dengan kedalaman 30m
A. MMO String Anode unit 4 PO-172

Consist of 5 Pes MMO anode dimension 1" x 1m c/w 100m leghth of 1 x 35 sq.mm HMWPE cable

B. Material for Deepwell Anode lnstall (1 hole- 30 meter each), total 8 unit adalah :
Steel Pipe Casing 8" dia non schedule Pcs 20 PO-170
Loresco SC-3 Coke Breeze backsfill 501bs/bag Bag 120
Anode Centralizer ( u-clamp) Pcs 96
Nylon Rope meter 300
Breather pipa PVC dia 1" @4m length meter 300
Cover for casing pipe Pcs 8
6 Mixed Metal Oxide Anode, Dimension 1" x 1m c/w cable HMWPE
Length cable : 100m ( 10 pes), size 25sq.mm unit 10 PO-172
Length cable : 50m ( 5 pes), size 16sq.mm unit 5 PO-172
7 FRP (Fiber Rainforced Plastic) Support Dimension : 1" x 1200mm set 15 P0-004 03-May-19

8 Positive SS 304 Juction Box, Casing : S/S 304, 2mm, Dimension : 400 x 300 x 200 (with 10 terminals) unit 20 PO-167
9 Cable, Cable XLPE/PVC 1 x 70sq mm meter 3800 PO-166
10 Cast Almunium Test Point, c/w 2 5 Terminal with 3" dia conduit 6ft long unit 76 PO-167
11 Permanent Cu/CuS04 unit 80 PO-173
12 Galvanized Conduit dia 1" x 4m btg 1,000 PO-169
Accesories Conduit (Eibow,Sock) lot 4 PO-169
68 PO-122 &
13 Almunium Anode Type ICS 70 AWB, Net Weight : 7kg, Gross Weight: 7,3 kg Pcs 03-May-19 04-May-19 08-May-19 09-May-19
PO-164
400 PO-122 &
14 Almunium Anode Type ICS 40 AWB, Net Weight : 4kg, Gross Weight: 4,4 kg Pcs 03-May-19 04-May-19 08-May-19 09-May-19
PO-164
Almunium Anode special design for condesor, Nb: Dimensi sesuai anode eksiting, jumlah anode tergantung 850
15 dimensi Kg PO-162

Almunium Anode special design for condesor by pass pipe, Nb: Dimensi sesuai anode eksiting, jumlah anode 330
16 Kg PO-162
tergantung dimensi
17 AC Power 3 x 10 sq.mm meter 500 PO-165
18 Miscellanous item (Nut, Bolt, Tape) lot 1 PO-171 03-May-19 04-May-19 08-May-19 09-May-19
T MASTER SCHEDULE (PMS)

INSPECTION RECEIVED AT SITE Item Achievement Progress Achievement


STATUS Overall Overall
Weight PO Issued Shipment Receive at Site Inspection Progress
ACCEPTED/ ETA ATA PO Issued Shipment Receive at Site Inspection
NOT ACCEPTED 10% 40% 20% 30%

100% 68.58% 1.93% 1.93% 1.93% 8.60%


11.70% - 30-Dec-99 - 30-Dec-99 0.00% 0.00% 0.00% 0.00% 0.00%

2.35% - 30-Dec-99 - 30-Dec-99 0.00% 0.00% 0.00% 0.00% 0.00%

0.40% PO-168 30-Dec-99 - 30-Dec-99 100.00% 0.00% 0.00% 0.00% 10.00%

24.46% PO-172 30-Dec-99 - 30-Dec-99 100.00% 0.00% 0.00% 0.00% 10.00%

21.19% PO-170 30-Dec-99 - 30-Dec-99 100.00% 0.00% 0.00% 0.00% 10.00%


11.44% - 30-Dec-99 - 30-Dec-99 0.00% 0.00% 0.00% 0.00% 0.00%
2.56% - 30-Dec-99 - 30-Dec-99 0.00% 0.00% 0.00% 0.00% 0.00%
0.61% - 30-Dec-99 - 30-Dec-99 0.00% 0.00% 0.00% 0.00% 0.00%
0.78% - 30-Dec-99 - 30-Dec-99 0.00% 0.00% 0.00% 0.00% 0.00%
0.12% - 30-Dec-99 - 30-Dec-99 0.00% 0.00% 0.00% 0.00% 0.00%

1.13% PO-172 30-Dec-99 - 30-Dec-99 100.00% 0.00% 0.00% 0.00% 10.00%

0.47% PO-170 30-Dec-99 - 30-Dec-99 100.00% 0.00% 0.00% 0.00% 10.00%


1.27% - 30-Dec-99 - 30-Dec-99 0.00% 0.00% 0.00% 0.00% 0.00%
0.26% - 30-Dec-99 - 30-Dec-99 0.00% 0.00% 0.00% 0.00% 0.00%
0.03% - 30-Dec-99 - 30-Dec-99 0.00% 0.00% 0.00% 0.00% 0.00%
0.16% - 30-Dec-99 - 30-Dec-99 0.00% 0.00% 0.00% 0.00% 0.00%
0.01% - 30-Dec-99 - 30-Dec-99 0.00% 0.00% 0.00% 0.00% 0.00%

0.71% PO-172 30-Dec-99 - 30-Dec-99 100.00% 0.00% 0.00% 0.00% 10.00%


0.16% PO-172 30-Dec-99 - 30-Dec-99 100.00% 0.00% 0.00% 0.00% 10.00%
0.45% P0-004 30-Dec-99 - 30-Dec-99 100.00% 0.00% 0.00% 0.00% 10.00%

1.82% PO-167 30-Dec-99 - 30-Dec-99 100.00% 0.00% 0.00% 0.00% 10.00%


3.58% PO-166 30-Dec-99 - 30-Dec-99 100.00% 0.00% 0.00% 0.00% 10.00%
2.56% PO-167 30-Dec-99 - 30-Dec-99 100.00% 0.00% 0.00% 0.00% 10.00%
3.23% PO-173 30-Dec-99 - 30-Dec-99 100.00% 0.00% 0.00% 0.00% 10.00%
2.02% PO-169 30-Dec-99 - 30-Dec-99 100.00% 0.00% 0.00% 0.00% 10.00%
1.35% PO-169 30-Dec-99 - 30-Dec-99 100.00% 0.00% 0.00% 0.00% 10.00%
PO-122 &
Accepted 07-May-19 08-May-19 0.92% 04-May-19 09-May-19 08-May-19 100.00% 50.00% 50.00% 50.00% 55.00%
PO-164

PO-122 &
Accepted 07-May-19 08-May-19 2.69% 04-May-19 09-May-19 08-May-19 100.00% 50.00% 50.00% 50.00% 55.00%
PO-164

0.43% PO-162 30-Dec-99 - 30-Dec-99 100.00% 0.00% 0.00% 0.00% 10.00%

0.17% PO-162 30-Dec-99 - 30-Dec-99 100.00% 0.00% 0.00% 0.00% 10.00%

0.72% PO-165 30-Dec-99 - 30-Dec-99 100.00% 0.00% 0.00% 0.00% 10.00%


Accepted 07-May-19 08-May-19 0.26% PO-171 04-May-19 09-May-19 08-May-19 50.00% 50.00% 50.00% 50.00% 50.00%

Vous aimerez peut-être aussi