Académique Documents
Professionnel Documents
Culture Documents
The number of joints and associated internal continuation and back-up structure, plus any gussets
or brackets that are to be subjected to NDT may be determined by the Owner and ABS with
consultation of the records and NDT results of previous surveys.
Results of NDT are to be maintained as a permanent record of the drilling unit, and be readily
available to the attending Surveyors during subsequent periodical surveys of the hull.
5.7.4 Hull Thickness Measurement
See 7-2-5/5.1.4.
5.7.5 Corrosion Control
The requirements of 7-2-5/5.3.5 are to be complied with.
5.7.6 Lightship Displacement (2015)
The requirements of 7-2-5/5.3.6 are to be complied with.
146 ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2018
Part 7 Surveys
Chapter 2 Surveys After Construction
Section 5 Special Periodical Surveys 7-2-5
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2018 147
Part 7 Surveys
Chapter 2 Surveys After Construction
Section 5 Special Periodical Surveys 7-2-5
FIGURE 5
CVI and NDT during SPS Hull No. 2 of SEDUs (2014)
SPS #2
CVI and NDT may include areas in way of 2 bays above the leg-spudcan connection as
deemed necessary by the Surveyor.
CVI – Surfaces are to be cleaned for a meaningful examination.
NDT – To be examined by MPI or ACFM.
Port Leg
Fwd Leg
CVI CVI
NDT
NDT
Stbd Leg
CVI NDT
The leg-spudcan connections CVI At least one leg-spudcan connection
are to be subjected to (chosen at random) from each leg
extensive examination. should be examined.
NDT
148 ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2018
Part 7 Surveys
Chapter 2 Surveys After Construction
Section 5 Special Periodical Surveys 7-2-5
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2018 149
Part 7 Surveys
Chapter 2 Surveys After Construction
Section 5 Special Periodical Surveys 7-2-5
FIGURE 6
CVI and NDT during SPS Hull No. 3 of SEDUs (2014)
SPS #3
CVI and NDT is to include areas in way of 2 bays above the leg-spudcan connections.
CVI – Surfaces are to be cleaned for a meaningful examination.
NDT – To be examined by MPI or ACFM.
Port Leg
Fwd Leg
CVI CVI
150 ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2018
Part 7 Surveys
Chapter 2 Surveys After Construction
Section 5 Special Periodical Surveys 7-2-5
7.7 Special Periodical Survey – Hull No. 4 and Subsequent Special Surveys
7.7.1 General Visual Inspection (GVI)
The requirements of 7-2-5/7.1.1 are to be complied with.
7.7.2 Close Visual Inspection (CVI)
The requirements of 7-2-5/7.5.2 are to be complied with.
7.7.3 Nondestructive Testing (NDT)
The requirements of 7-2-5/7.5.3 are to be complied with.
7.7.4 Hull Thickness Measurement
See 7-2-5/7.1.4.
7.7.5 Corrosion Control
The requirements of 7-2-5/7.3.5 are to be complied with.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2018 151
Part 7 Surveys
Chapter 2 Surveys After Construction
Section 5 Special Periodical Surveys 7-2-5
TABLE 1
Thickness Gauging Requirements for Surface-Type Units (2017)
Special Periodical Survey Special Periodical Survey Special Periodical Survey Special Periodical Survey
Number 1 Number 2 Number 3 Number 4
1) Suspect areas throughout 1) Suspect areas throughout 1) Suspect areas throughout 1) Suspect areas throughout
the unit. the unit. the unit. the unit.
2) (2012) One transverse 2) (2012) Two girth belts of 2) (2012) A minimum of
section of deck plating deck, bottom and side three girth belts of deck,
abreast the moon pool plating abreast the moon bottom, side, and
opening within the pool and one hatch longitudinal-bulkhead
amidships 0.6L, together opening within the plating in way of the moon
with internals in way as amidships 0.6L together pool and other areas within
deemed necessary. Where with internals in way as the amidships 0.6L, together
unit is configured with deemed necessary. Where with internals in way
side ballast tanks, the unit is configured with (including in perimeter
plating and internals of the side ballast tanks, the ballast tanks, where fitted
tanks are also to be gauged plating and internals of the in way of belts).
in way of the section tanks to be gauged in way 3) Moon pool boundary
chosen. of the required belts, bulkhead plating.
3) Moon pool boundary Remaining internals in
ballast tanks to be gauged 4) Internals in forepeak and
bulkhead plating. after peak tanks as deemed
as deemed necessary.
necessary.
3) Moon pool boundary
bulkhead plating. 5) Lowest strake of all
transverse bulkheads in
4) Internal in forepeak tank hold spaces. Remaining
as deemed necessary. bulkhead plating to be
gauged as deemed
necessary.
6) All plates in two wind and
water strakes, port and
starboard, full length.
7) All exposed main deck
plating full length and all
exposed first-tier super-
structure deck plating
(poop, bridge and
forecastle decks).
8) All keel plates full length
plus additional bottom
plating as deemed
necessary by the Surveyor,
particularly in way of
cofferdams and machinery
spaces.
9) Duct keel or pipe tunnel
plating or pipe tunnel
plating and internals as
deemed necessary.
10) (2017) Plating of seachests.
Shell plating in way of
overboard discharges as
considered necessary by
the attending Surveyor.
Notes:
1 With reference to ballasting history and arrangement and condition of coatings, tanks and specific thickness gauging
locations should be selected which will provide the best representative sampling of areas likely to be most exposed
to corrosion effect.
2 Gauging requirements noted may be modified as deemed necessary or appropriate by the Surveyor if the structure
remains effectively protected against corrosion by a permanent type special coating.
3 In any case where excessive wastage is evident, additional gaugings may be required.
152 ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2018
Part 7 Surveys
Chapter 2 Surveys After Construction
Section 5 Special Periodical Surveys 7-2-5
TABLE 2
Thickness Gauging Requirements for Column-Stabilized Units (2017)
Special Periodical Survey Special Periodical Survey Special Periodical Survey Subsequent Special Periodical
Number 1 Number 2 Number 3 Survey
1) Suspect areas throughout 1) Suspect areas throughout 1) Suspect areas throughout 1) Suspect areas throughout
the unit. the unit. the unit. the unit.
2) Columns and bracings 2) Representative gaugings 2) Representative gaugings, 2) Comprehensive gaugings,
where wastage is evident of columns and bracings throughout, of special and throughout, of special and
in Splash Zone. in Splash Zone together primary application primary application
with internals in way as structures. structures.
deemed necessary. 3) 1 girth belt of each of 2 3) 1 girth belt of each of one-
3) Special and primary columns and 2 bracings in half of the columns and
application structure Splash Zone together with bracings in Splash Zone
where wastage is evident. internals in way as and internals in way as
deemed necessary. deemed necessary (i.e.,
4) Chain locker internals as gauge half of the unit’s
deemed necessary. columns and bracings in
Splash Zone).
5) Lower hulls in way of
mooring lines where 4) Chain locker internals as
wastage is evident. deemed necessary.
6) 1 girth belt of each lower 5) Lower hulls in way of
hull between one set of mooring lines where
columns. wastage is evident.
6) 1 girth belt of each lower
hull between one set of
columns.
7) Representative gaugings
of substructure of drilling
derrick.
8) (2017) Plating of seachests.
Shell plating in way of
overboard discharges as
considered necessary by
the attending Surveyor.
Notes:
1 With reference to the ballasting history and arrangement and condition of coatings, tanks and specific thickness
gauging locations should be selected which will provide the best representative sampling of areas likely to be most
exposed to corrosion effect.
2 Gauging requirements noted may be modified as deemed necessary or appropriate by the Surveyor if the structure
remains effectively protected against corrosion by a permanent type special coating.
3 In any case where excessive wastage is evident, additional gaugings may be required.
4 Structure application designations (special, primary, secondary) are defined in Section 3-1-4.
5 (2012) Splash Zone is to be considered as the structural area that has been periodically in and out of the water
when the unit was at its operating depth, most of the time during the past five-year period. Based on operational
record of the unit, additional zones may also be gauged.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2018 153
Part 7 Surveys
Chapter 2 Surveys After Construction
Section 5 Special Periodical Surveys 7-2-5
TABLE 3
Thickness Gauging Requirements for Self-Elevating Units (2017)
Special Periodical Survey Special Periodical Survey Special Periodical Survey Special Periodical Survey
Number 1 Number 2 Number 3 Number 4
1) Suspect areas throughout 1) Suspect areas throughout 1) Suspect areas throughout 1) Suspect areas throughout
the unit (particular attention the unit. the unit. the unit.
to be paid to the legs in 2) Legs in way of Splash 2) Representative gaugings, 2) Comprehensive gaugings,
way of the Splash Zone). Zone. throughout, of special and throughout, of special and
3) Primary application primary application primary application
structures where wastage structures. structures.
is evident. 3) Leg well structure. 3) Leg well structure.
4) Representative gaugings 4) Representative gaugings 4) Representative gaugings
of upper hull deck and of deck, bottom, and side of deck, bottom, and side
bottom plating and shell plating of hull and shell plating of hull and
internals of one preload mat. mat.
(ballast) tank. 5) Representative gaugings 5) Substructure of derrick as
of upper hull deck and deemed necessary.
bottom plating and 6) Representative gaugings
internals of at least two of internals of all preload
preload (ballast) tanks. (ballast) tanks.
7) (2017) Plating of seachests.
Shell plating in way of
overboard discharges as
considered necessary by
the attending Surveyor.
Notes:
1 With reference to the operating history and arrangement and condition of coatings, specific thickness gauging locations
should be selected which will provide the best representative sampling of areas likely to be most exposed to corrosion
effect.
2 Gauging requirements noted may be modified as deemed necessary or appropriate by the Surveyor if the structure
remains effectively protected against corrosion by a permanent type special coating.
3 In any case where excessive wastage is evident, additional gaugings may be required.
4 Structural application designation (special, primary, secondary) are defined in Section 3-1-4.
5 (2012) Splash Zone is to be considered as the structural area that has been periodically in and out of the water when
the unit was at its operating depth, most of the time during the past five-year period. Based on operational record
of the unit, additional zones may also be gauged.
154 ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2018
Part 7 Surveys
Chapter 2 Surveys After Construction
Section 5 Special Periodical Surveys 7-2-5
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2018 155
Part 7 Surveys
Chapter 2 Surveys After Construction
Section 5 Special Periodical Surveys 7-2-5
156 ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2018
Part 7 Surveys
Chapter 2 Surveys After Construction
Section 5 Special Periodical Surveys 7-2-5
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2018 157
Part 7 Surveys
Chapter 2 Surveys After Construction
Section 5 Special Periodical Surveys 7-2-5
• Fire main systems are to be examined and tested, as applicable, particularly to verify that; fire pumps,
including their relief valves (if fitted), fire main piping together with associated hydrants, hoses and
nozzles, and international shore connection remain in satisfactory condition. Pressure and operational
tests of the fire main system, as required by the Rules, are to be carried out.
• Additional fixed fire fighting systems, such as those using gas smothering, foam, fixed pressure water
spraying, and systems protecting helicopter decks are to be examined and tested, and to be proven
satisfactory.
• Portable and semi-portable fire extinguishers and sand (where provided) are to be examined, all portable
soda-acid and foam extinguishers are to be serviced, and all dry chemical and CO2 extinguishers are to
be weighed and recharged, as necessary, and proven satisfactory.
• Fireman’s outfits, consisting of a breathing apparatus, a lifeline, a safety lamp, an axe, nonconductive
boots and gloves, a rigid helmet and protective clothing complying with the requirements of the Rules
are to be examined, and verified as to be easily accessible and ready for use, and stored in separate
positions so that a fire in one location would not block access to both outfits.
• Fire detection system and its alarms, general alarms system, mud tank level alarms, ventilation system
alarms, and gas detection system and its alarms, are to be examined and tested, and proven satisfactory.
13.11 Outfitting
A general examination of following outfitting items is to be made in order that the Surveyor may be satisfied
as to its efficient state. The following items are to be especially proven in compliance with the Rules:
• Means of escape
• Means of access and egress
• Guards and rails
• Emergency control stations
• Arrangements in machinery spaces
• Segregation of fuel oil purifiers
• Rotary table area
• Fire precautions in machinery spaces
158 ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2018
Part 7 Surveys
Chapter 2 Surveys After Construction
Section 5 Special Periodical Surveys 7-2-5
At Special Survey No. 1, the items listed above are to be examined as far as practicable to the Surveyor’s
satisfaction. If considered necessary, any items in question are to be examined by an effective crack detection
method.
At Special Periodical Survey No. 2 and subsequent Special Periodical Surveys, the leg jacking system is to
be examined in the presence of the Surveyor by the original equipment manufacturer or other third party
inspector mutually agreeable to the owner and the Surveyor.
ABS RULES FOR BUILDING AND CLASSING MOBILE OFFSHORE DRILLING UNITS . 2018 159