“Shift Order” indicator in customizing tcode OPU3 controls if the actual dates of the partially confirmed operations
are taken into account during a new scheduling run.
Prerequisite
1. Create a production order in tcode CO01 and release it. Scheduling is automatically executed.
Execute scheduling by clicking the scheduling icon in tcode CO02. Check the rescheduling result. The planned start
date was on 2015.6.2, now it starts on 2015.5.28, the actual dates when the partial confirmation was executed.
You can also check the dates in “Confirmed Dates” view. Start time is same as the actual confirmed dates.