Académique Documents
Professionnel Documents
Culture Documents
FOR
Jan, 2006
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
GENERAL CONTENTS
1
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
TECHNICAL DOCUMENTS
FOR
2
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
CONTENTS
CHAPTER 1 GENERAL
CHAPTER 6 SUGGESTION
3
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
4
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
1. Chapter 1 General
Code for Design and Construction for Cast in-situ Pile in Port
Engineering (JTJ248-2001)
1
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
Engineering (JTJ285-2000)
and geological information in the plant site area and information about
015-01
the long term. The design satisfys the requirement of 800000T/y coal in
phase-I, with provision for future expansion in the long term. A 5000T
wharf including unloading platform and 500m near shore jetty will be
2
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
According to the throughput in short and long term, and the different
type of coal transport vessels, the following coal handling process is
proposed. The process system includes the ship unloading system and
the conveyor belt system. The handling process is as follows:
5000T barge => wharf conveyor belt => trestle bridge conveyor belt =>
EAT04 transfer machine room.
Phase I:
The 5000T barge sails to the 5000T wharf to unload the coal by coal
unloading equipment on the dock. The on-dock unloading equipment is
3
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
two gantry cranes with hopper, having 10.5m gauge and 16t lifting
capacity. The hopper is equipped on the crane as the receiving
equipment. Underneath the hopper a vibrating feeder is equipped to
transfer the coal to the horizontal conveyor belt mounted on the crane,
then to the conveyor belt on the dock.
Phase II:
The 5000T wharf will be equipped with 2 additional gantry cranes with
hoppers to satisfy the unloading requirement.
On the 5000T wharf, two rails for gantry crane will be laid, with the
distance of 2.5m between the front edge of the wharf and the outside
track. The width of the wharf is 15m.
The design scope of the conveyor belt system is from the ship unloader
to the EAT04 transfer engine room at the land terminal. Single line
conveyor belt is used. For phase I, the conveyor belt capacity is 750T/h,
band width 1,200mm, speed 4.8m/s, with 1 berth. For phase II, the
conveyor belt capacity is 1500T/h, band width 1,200mm, speed 4.8m/s,
with 1 additional berth.
4
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
Table 2-1
Table 2-2
5
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
(m)
6
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
The wharf platform is 185m long, 15m wide (partially 20m wide). The
operation room and substation are positioned on the platform, with 1
mooring dolphin at each end of the wharf. A trestle bridge and an approach
levee are arranged between the platform and the land terminal. The trestle
bridge is approximately 500m long and the approach levee 90m long. The
trestle bridge and approach levee are 6m wide, with a conveyor belt and a
inspection path.
The top elevation of wharf platform and mooring dolphin is 7.0m. The land
terminal elevation is 3.5m for the approach levee. The trestle bridge and the
approach levee is linked up by a slope.
Wind: ≤ class 6
Crosswind: H4%≤1.0m, T≤ 6s
7
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
The tentative operation days are estimated at 280 days per year.
The natural water depth in the deep sea satisfies the shipping and berthing
requirement. To further facilitate the berthing operation, a light is set on top
of the mooring dolphin at either end of the wharf.
Table 3-2
No. Item 5000T wharf
8
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
Wave factors in front of the wharf, which may happen once every 50 years:
9
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
The sand layer on the natural rock surface of this project is about 5~10m.
Therefore, the steel pipe piles of this project shall be cast-in-place piles
embedded in the rock.
4.3.1 Wharf
The Φ1200mm steel pipe piles are used for the operating platform, and the
space interval between piers is about 20m. After completion of the
foundation, the reinforced concrete pile caps are cast in place, on top of
which are laid the reinforced concrete box girders. 450kN mooring dolphin
is setup on the 5000T wharf. DA-B500H rubber fenders are used for 5000T
wharf. Railing, and other accessory facilities will be provided accordingly.
Nine Ф800m steel pipe piles are driven for each mooring dolphin, on top of
which a reinforced concrete pier is cast in place. On the platform are set the
dolphin and railing.
The operating platform is connected to the shore through the steel trestle
bridge. The steel trestle bridge is about 70m in each span, and 6m in breadth.
The Ф800mm steel pipe piles are used as the foundation piles of the bridge
piers, and on top of the piles the reinforced concrete pier is cast in place.
The approach levee is a slant riprap levee structure. 10~100kg block stones
are used as the exterior protective covering blocks. At the back of the blocks
10
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
the 2-piece ragstones, mixed inverted filtering layer, and earthwork fabric
are laid to prevent loss of backfilled sand.
11
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
The range of this design includes the trestle bridge, the electric
equipment of the handling process system on the platform of the
unloading wharf, and the accessory power supply and lighting facilities
of this process system. The power source from which the inlet power
line is drawn for power supply to this project is not in the scope of this
project design.
Two-way 6.3KV, 3 phase power supply and distribution cable line are
provided by the power plant. The low-voltage power distribution
voltage is designed to be 4-wire, 50Hz, 0.4/0.23KV.
The cable is laid mainly in the cable tray, partially buried through the
steel conduit.
12
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
The road lights are used for outdoor lighting on the road, and the lights
on the platform are used for lighting along the line of the belt conveyor
trestle bridge. The average illumination intensity is 10LX.
All the shells of electric equipment and the metal conduits of this
project should be well grounded and protected with zero line
connection. The copper rod is used as the grounded pole and the
galvanized flat steel is used as the earth line, where it is embedded in
concrete, the earth line will be of galvanized steel.
1. Water Source
The power plant provides water supply to the wharf and approach levee.
The water quality should accord with the requirement of local hyginic
standard for drinking water. The water supply to this project comes
from the water supply pipeline of the power plant, and the hydraulic
pressure at the connecting point is ≥0.5Mpa.
13
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
2. Water Demand
The water supply points include the water supply points for the ship, for
dedusting spray at the hopper of the ship unloader, for flushing the
wharf surface and the floor of the transfer machine house. The
maximum daily water consumption is about 800m3.
The water supply pipeline is devided into two systems: one system is
for dedusting and domestic water system; another is for fire control.
The water supply pipeline of the dedusting and fire control system is
laid along the belt conveyor support frames through the galvanized
steel pipes of DN250. The flushing stations are set up at the interval of
about 30m, and two sets of flushing stations are set on each level of the
transfer machine house. The water supply for spraying on the ship
unloading hopper on the wharf is offered through rapid connectors. The
domestic water supply is provided through the galvanized steel pipeline
of DN200, laid along the belt conveyor support frames. There are five
cocks on the wharf for water supply to the barges.
5.2.2 Drainage
The early-stage rainwater and flushing water on the wharf surface, and
the flushing water on the floor of the transfer house are drained through
the open channel to the sedimentation basin of wastewater containing
coal, treated through the coal-containing wastewater treatment facility
of the power plant, and then recycled for use after the treated water is
up to the standard.
14
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
5.2.3 Fire-fighting
The biggest fire control object is the transfer houses; the water-use level
for fire control is 30 L/sec.(The volume of indoor fire control water is
10L/s; the volume of outdoor fire control water is 20L/s.) The fire
extinguishing time is two hours. One-time water consumption volume
for fire control is 216m3. The fire control water supply pipeline is
independant, and the galvanized steel pipes are used for this purpose.
The pipeline is laid along the belt conveyor support frames.The fire
hydrant boxs are set indoor at the interval of 50m on the wharf, trestle
bridge and approach levee. Two fire hydrant boxes are available on
each level of the transfer house.
Support from the fire fighting house of the power plant is considered as
a reinforcement.
5.3.1 General
15
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
equipment in operation.
The central control room (CCR) set on the wharf is the control center to
control the unloading process equipment, dedusting spray equipment,
and mobile hopper equipment of the wharf and coal transmission
system, to connect the equipment of coal transmission programmed
control system of the power plant through process control network
system, and to compose the automatic control system of the coal
unloading and belt conveyor system of the whole wharf.
The control system uses the design of the industrial network structure.
The control network equipment mainly include the programmable logic
controller (PLC) of the system, the Computer-vision Graphics
Processor (CGP), belt scale, and control network server. The optical
cable is used for transmission of the control network. The control
system can perform the functions of automatic start and stop. The
operating flow equipment pictures, the on-site operating status, the
handling amount, the operation and breakdown status of various
equipment can be monitored through CGP in CCR. It mainly fulfills the
tasks of various equipment control, system operation, display and
monitoring of flow pictures, and production information management
16
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
in the production process flow. The operation data are saved according
to classification. In accordance with the control requirement of the
transmission process equipment, a real-time control system network is
composed of the PLC remote control substations set up respectively in
the wharf CCR and near the head of 2# belt conveyor, the mobile
hopper PLC single units, and the central control system. It is uniformly
coordinated and controlled by the CCR operator. CGP can
automatically generate corresponding forms of equipment failure and
operational management through the data via PLC transmission.
The control system is divided into CCR automatic control mode and
on-site manual operating mode by the machine side. In automatic
operating mode, the control room operator starts the belt conveyor
system and send normal start signal to each traveling hopper equipment
PLC through the CGP mouse (or operating keyboard), after it is
confirmed that the selected flow equipment is in normal condition and
the downstream equipment have been started. Then the flow equipment
are started in sequence in material counter-flow direction. When the
flow stops normally, the flow equipment stop in sequence in material
flow direction. In emergency breakdown, all the system equipment stop
on the line and failure signal is simultaneously sent out to each
traveling hopper and other equipment in the system, and stop
immediately.
When the system is in operation, the status signals of all the flow
equipment, traveling hopper, dusting spray, flow belt conveyor, and
other equipment can be displayed on the CGP screen of CCR.
17
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
(1) The emergency cord switches set on the two sides of the belt conveyor;
(2) The off-tracking switches set at the head and tail and in the middle of the
belt conveyor;
(4) The belt tearing detector set at the planking point of the belt conveyor;
18
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
To enable the CCR operator to timely and accurately know about the
overall practical production situation on the operating site, safely and
rationally make dispatch management, and timely make communication
with the on-site operators, it is planned to set up cameras of the
industrial TV monitoring system on the wharf, and in the transfer
machine house to monitor the on-site operating condition and guarantee
the safety and reliability of the transmission system.
In accordance with the different types of the control system signals, the
control cable, signal screening cable and optical cable are used for the
control system. The screened cable is used for analog signal
transmission; the optical cable is used in the trunk network of the
control network and computer management system. All the selected
cables should meet the requirement for signal transmission distance and
high anti-interference performance.
The control cable is laid mainly on the cable tray along the belt
conveyor line. The steel duct and flexible metal hose are partially used
when the cable is connected to the equipment. The cable is drawn from
the central control room and then laid overhead on the cable tray or
through cable trench to the users.
19
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
6. Chapter 6 Suggestion
20
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
CONTENTS
CHAPTER 1 GENERAL
CHAPTER 6 SUGGESTION
21
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
22
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
1. Chapter 1 General
The coal-fired power plant wharf project is located 12km west of Puttalam.
The power plant phase-I project is of 1×300MW capacity, and total installed
capacity is 3x300MW in the long term.
In order to satisfy the coal handling requirement of the power plant, the
design is made according to available hydrological and meteorologic
information and relevant survey and study result. The scope of design
includes handling process, layout, marine structure, water supply and
drainage, fire fighting, powr supply & lighting, and control system. The
transfer machine house is at the tip of the land area, which is the designed
demarcation point of the plant area.
23
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
Code for Design and Construction for Cast in-situ Pile in Port
Engineering (JTJ248-2001)
Engineering (JTJ285-2000)
015-01
A 20000DWT wharf and near shore jetty ( length: 1000 m) for 20000DWT
common bulk cargo vessel is proposed.
24
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
20000DWT bulk cargo vessel => 20000DWT wharf => wharf conveyor belt
=> levee conveyor belt => EAT04 transfer machine room.
Phase I: 20000DWT common bulk cargo vessel transports the coal to the
20000DWT wharf to unload the coal by coal unloading equipment on the
25
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
Phase II: The 20000DWT wharf will be equipped with additional gantry
cranes to satisfy the unloading requirement.
On the 20000DWT wharf, two rails for gantry crane will be laid, with the
distance of 2.5m between the front edge of the wharf and the outside track.
The width of the wharf is 15m.
The design scope of the conveyor belt system is from the ship unloader to
the EAT04 transfer engine room at the land terminal. Single line conveyor
belt is used. For phase I, the conveyor belt capacity on the trestle bridge is
500T/h, band width 1,200mm, speed 4.8m/s, with 1 berth. For phase II, the
conveyor belt capacity is 1500T/h, band width 1,200mm, speed 4.8m/s, with
no additional berth added.
26
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
Table 2-3
Table 2-4
27
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
(m)
20000
Bulk carrier 164 25 13.5 9.8
(17500~22500)
This plan is for the 20000DWT common bulk cargo vessel and the
20000DWT wharf. The scope of construction in phase I comprises 1 No.
20000DWT berths (in phase II and III no additional berth is needed).
According to available information, during southwest monsoon season,
under the relatively bad wave and ocean current condition, the sand dune on
the sea bed along the coast line shifts mainly within the -6.0 isobath line,
whilst the sand shifting beyond the -6.0 isobath line is insignificant. In order
28
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
to reduce the total investment, the wharf is located beyond the -6.0m
bathymetric line. The 245º azimuth of wharf is adapted according to relevant
wave observation results and analysis statistics. The bottom elevation of the
front edge of the berth is -11.5m.
The wharf platform is 160m long, 15m wide (partially 20m wide). The
operation room and substation are positioned on the platform, with 1
mooring dolphin at each end of the wharf. A trestle bridge and an approach
levee are arranged between the platform and the land terminal. The trestle
bridge is approximately 1000m long and the approach levee 90m long. The
trestle bridge and approach levee are 6m wide, with a conveyor belt and a
inspection path.
The top elevation of wharf platform and mooring dolphin is 7.0m. The land
terminal elevation is 3.5m for the approach levee. The trestle bridge and the
approach levee is linked up by a slope.
A channel is excavated on the seabed between the wharf and the -12.0
isobath line. The channel is approximately 2000m long, 130m wide. The
turning point for the 20000DWT vessel is located in front of the wharf. To
facilitate the turning around of the vessel, the turning point area has a
diameter of 492m, 3 times of the vessel body length. The bottom elevation
of the channel is -11.5m, same as that of the front edge of wharf platform
and the turning point.
Wind: ≤ class 6
29
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
Wave:
The tentative operation days are estimated at 300 days per year.
For 20000DWT wharf, apart from setting up a light on top of the mooring
dolphin at either end of the wharf, 8 fairway buoys are erected along the
channel and the turning area to further facilitate the shipping operation.
Table 3-2
No. Item 20000DWT wharf
30
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
equipment
31
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
Wave factors in front of the wharf, which may happen once every 50
years:
32
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
The sand layer on the natural rock surface of this project is about
5~10m. Therefore, the steel pipe piles of this project shall be cast-in-
place piles embedded in the rock.
4.3.1 Wharf
The Φ1200mm steel pipe piles are used for the operating platform, and
the space interval between piers is about 20m. After completion of the
foundation, the reinforced concrete pile caps are cast in place, on top
of which are laid the reinforced concrete box girders. 750kN bollard is
setup on the wharf. SUC1450H rubber fenders are used for the wharf.
Railing, and other accessory facilities will be provided accordingly.
Nine Ф800m steel pipe piles are driven for each mooring dolphin, on
top of which a reinforced concrete pier is cast in place. On the platform
are set the dolphin and railing.
33
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
34
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
The range of this design includes the trestle bridge, the electric
equipment of the handling process system on the platform of the
unloading wharf, and the accessory power supply and lighting facilities
of this process system. The power source from which the inlet power
line is drawn for power supply to this project is not in the scope of this
project design.
Two-way 6.3KV, 3 phase power supply and distribution cable line are
provided by the power plant. The low-voltage power distribution
voltage is designed to be 4-wire, 50Hz, 0.4/0.23KV.
The cable is laid mainly in the cable tray, partially buried through the
steel conduit.
35
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
The road lights are used for outdoor lighting on the road, and the lights
on the platform are used for lighting along the line of the belt conveyor
trestle bridge. The average illumination intensity is 10LX.
All the shells of electric equipment and the metal conduits of this
project should be well grounded and protected with zero line
connection. The copper rod is used as the grounded pole and the
galvanized flat steel is used as the earth line, where it is embedded in
concrete, the earth line will be of galvanized steel.
1. Water Source
The power plant provides water supply to the wharf and approach
levee. The water quality should accord with the requirement of local
hyginic standard for drinking water. The water supply to this project
comes from the water supply pipeline of the power plant, and the
hydraulic pressure at the connecting point is ≥0.5Mpa.
2. Water Demand
36
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
The water supply points include the water supply points for the ship,
for dedusting spray at the hopper of the ship unloader, for flushing
the wharf surface and the floor of the transfer machine house. The
maximum daily water consumption is about 800m3.
The water supply pipeline is devided into two systems: one system
is for dedusting and domestic water system; another is for fire
control. The water supply pipeline of the dedusting and fire control
system is laid along the belt conveyor support frames through the
galvanized steel pipes of DN250. The flushing stations are set up at
the interval of about 30m, and two sets of flushing stations are set
on each level of the transfer machine house. The water supply for
spraying on the ship unloading hopper on the wharf is offered
through rapid connectors. The domestic water supply is provided
through the galvanized steel pipeline of DN200, laid along the belt
conveyor support frames. There are five cocks on the wharf for
water supply to the barges.
5.2.2 Drainage
5.2.3 Fire-fighting
37
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
The biggest fire control object is the transfer houses; the water-use
level for fire control is 30 L/sec.(The volume of indoor fire control
water is 10L/s; the volume of outdoor fire control water is 20L/s.)
The fire extinguishing time is two hours. One-time water
consumption volume for fire control is 216m3. The fire control
water supply pipeline is independant, and the galvanized steel pipes
are used for this purpose. The pipeline is laid along the belt
conveyor support frames.The fire hydrant boxs are set indoor at the
interval of 50m on the wharf, trestle bridge and approach levee.
Two fire hydrant boxes are available on each level of the transfer
house.
5.3.1 General
38
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
The central control room (CCR) set on the wharf is the control
center to control the unloading process equipment, dedusting spray
equipment, and mobile hopper equipment of the wharf and coal
transmission system, to connect the equipment of coal transmission
programmed control system of the power plant through process
control network system, and to compose the automatic control
system of the coal unloading and belt conveyor system of the whole
wharf.
39
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
The control system is divided into CCR automatic control mode and
on-site manual operating mode by the machine side. In automatic
operating mode, the control room operator starts the belt conveyor
system and send normal start signal to each traveling hopper
equipment PLC through the CGP mouse (or operating keyboard),
after it is confirmed that the selected flow equipment is in normal
condition and the downstream equipment have been started. Then
the flow equipment are started in sequence in material counter-flow
direction. When the flow stops normally, the flow equipment stop
in sequence in material flow direction. In emergency breakdown, all
the system equipment stop on the line and failure signal is
simultaneously sent out to each traveling hopper and other
equipment in the system, and stop immediately.
When the system is in operation, the status signals of all the flow
40
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
(1) The emergency cord switches set on the two sides of the belt
conveyor;
(2) The off-tracking switches set at the head and tail and in the middle
of the belt conveyor;
(4) The belt tearing detector set at the planking point of the belt
conveyor;
41
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
The control cable is laid mainly on the cable tray along the belt
conveyor line. The steel duct and flexible metal hose are partially
used when the cable is connected to the equipment. The cable is
drawn from the central control room and then laid overhead on the
cable tray or through cable trench to the users.
42
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
43
Puttalam 1X300MW Coal-Fired Power Plant
Port Part-Volume 3
6. Chapter 6 Suggestion
44