ARULMIGU CHENNAKESAVAPERUMAL THIRUKOIL AT

YELAGIRI VILLAGE THIRUPATTUR TALUK VELLORE


DISTRICT
Name of work: RENOVATION OF THIRUKOIL
DETAILED ESTIMATE
Sl.
No. Description No L B D Qty

Dismantling and clearing away the debries such as weathering course and
tiles etc all complete
weathering course 1 x 1 3.63 3.61 3.63
1 x 1 3.33 1.50 3.33
1 x 1 6.80 6.80 6.80
say14.00sqm 13.76
Labour charges for dismantling and removing the existing stone structure
including numbering, labour charges for removing the stones and stacking for
reuse ,scafolding charges tools and plant charges etc all compete.

WALL STONES
outeallround
outer allround 1 x 1 42.29 0.95 40.18
outer allround 1 x 1 42.29 0.33 13.96
inside garbagraham 1 x 1 10.16 0.95 9.65
mugamandapam 1 x 1 6.06 0.95 5.76
mahamandapam 1 x 1 22.16 0.95 21.05
outside allround 1 x 1 21.72 1.09 23.67
inside 1 x 1 10.16 1.09 11.07
1 x 1 6.06 1.09 6.61
outside 1 x 1 20.58 1.41 29.02
inside 1 x 1 10.16 1.41 14.33
1 x 1 6.06 1.41 8.54
183.84 sqm or 1779.00 sft 183.84
PALLER 1 x 4 0.35 0.35 2.75 1.35
1.35 cum or 48.00 cft
POTHYAL 1 x 4 1.05 0.35 0.40 0.59
1 x 4 0.35 0.35 0.40 0.20
1 x 12 0.70 0.35 0.40 1.18
1.97 cum or 70.00 cft 1.97
UTHIRAM 1 x 4 7.05 0.40 0.45 5.08
1 x 12 3.00 0.40 0.45 6.48
say 11.56cum or 409 cft 11.56
Page 1
PAVUKKAL 1 x 1 4.05 4.03 16.32
1 x 1 3.81 2.21 8.42
mahamandapam 1 x 1 7.43 7.43 55.20
SAY 79.94 sqm or 860 sft 79.94
Earth work excavation in all classes of soils and sub soils and todepth as
may be directed except in hard rock, requiring blasting, including initial leads
and lifts and re-filling the sides of foundation, with excavated earth in 150mm
layers well watered rammed and consolidated, including depositing surplus earth
clearing and levelling the site, shoring shuttering baling out water wherever
necessary etc., complete complying with standard specification.

walls allround 1x 1 37.79 2.32 2.45 214.80


cross wall 1x 2 0.74 2.32 2.45 8.41
for pillers 1x 4 1.37 1.37 2.45 18.39
241.60
say 245.00 cum say 242.00
Supplying and filling in foundation, basement, etc with filling sand in
layers of not more than 15 cm thick well watered, rammed and consolidated etc.
complete complying with standard specification and as directed by the
departmental officers.

walls allround 1x 1 37.79 2.32 0.30 26.30


cross wall 1x 2 0.74 2.32 0.30 1.03
for pillers 1x 4 1.37 1.37 0.30 2.25
say 30.00 cum 29.58
Plain Cement concrete 1:5:10 (one cement five sand and ten aggregate)
using 40mm gauge hard granite broken stone jelly for foundation including cost
and conveyance of all materials labour for mixing,l aying, compacting, curing,
dewatering, side shuttering, wherever necessary including curing etc.,complete
complying with standard specification and as directed.

walls allround 1x 1 37.79 2.32 0.30 26.30


cross wall 1x 2 0.74 2.32 0.30 1.03
for pillers 1x 4 1.37 1.37 0.30 2.25
floring concrete karuvarai 1x 1 2.55 2.53 0.10 0.65
mugamandapam 1x 1 2.30 1.40 0.10 0.32
mahamandapam 1x 1 6.60 6.60 0.10 4.36
say 35.00 cum 34.91
Random Rubble masonry work in CM 1:5 ( One of cement and five of
sand) Using selected stones and bond stones in foundation and basement
including dewatering wherever necessary proper setting, curing etc., complete in
all respects complying with relevant standard Specifications.

Page 2
1st footing walls allround 1x 1 37.79 2.32 0.45 39.45
cross wall 1x 2 0.74 2.17 0.45 1.45
for pillers 1x 4 1.37 1.37 0.45 3.38

2 ndfooting walls allround 1x 1 37.79 2.02 34.35


0.45
cross wall 1x 2 1.04 1.87 0.45 1.75
for pillers 1x 4 1.07 1.07 0.45 2.06

3rd footing walls allround 1x 1 37.79 1.72 29.25


0.45
cross wall 1x 2 1.34 1.57 0.45 1.89
for pillers 1x 4 0.77 0.77 0.45 1.07

4th footing walls allround 1x 1 37.79 1.42 24.15


0.45
cross wall 1x 2 1.99 1.07 0.45 1.92
for pillers 1x 4 0.47 0.47 0.45 0.40
1x 4 0.47 0.47 0.45 0.40
say 142.00 cum 141.52
supplying of new stones like pavukkal, uthiram, pothoyal etc including cost
and conveyace etc all complete

outer allround 1 x 1 42.29 0.75 0.33 10.47


or 370cft
Refixing the cut stones in its original position including charges for tools and
plants labour charges for pointing with lime morter etc all complete
wall stones old
outer allround 1 x 1 42.29 0.95 40.18
outer allround 1 x 1 42.29 0.33 13.96
inside garbagraham 1 x 1 10.16 0.95
9.65

mugamandapam 1 x 1 6.06 0.95 5.76


mahamandapam 1 x 1 22.16 0.95 21.05
outside allround 1 x 1 21.72 1.09 23.67
inside 1 x 1 10.16 1.09 11.07
1 x 1 6.06 1.09 6.61
outside 1 x 1 20.58 1.41 29.02
inside 1 x 1 10.16 1.41 14.33
1 x 1 6.06 1.41 8.54
183.84
1779sft
wall stones new 1 x 1 42.29 0.75 0.33 10.47
370.00
Page 3
piller 1 x 4 0.35 0.35 2.75 1.35
48.00
pothiyal 1 x 4 1.05 0.35 0.40 0.59
1 x 4 0.35 0.35 0.40 0.20
1 x 12 0.70 0.35 0.40 1.18
1.97
70.00
uthiram 1 x 4 7.05 0.40 0.45 5.08
1 x 12 3.00 0.40 0.45 6.48
11.56
409cft
pavukkal 1 x 1 4.05 4.03 16.32
1 x 1 3.81 2.21 8.42
mahamandapam 1 x 1 7.43 7.43 55.20
79.94
say 860.00
RR masonry in cm 1:1:4 using rrstones and boulders including cost and
conveyance of all materials , labour charges for laying etc all complete.

Brick work in following Cement Mortar using best quality II class Ground
moulded bricks size 9" x 4-3/8" x 2-3/4" for foundation and basement including
curing, etc., complete complying with standard specifiction.

parapet wall 1 x 1 18.40 0.23 0.30 5.52


1 x 1 27.32 0.23 0.90 24.59
30.11
say 13.80
Providing Weathering Course with Broken brick jelly and lime mortar in
ratio 32:12.5 by volume including beating with wooden beater over roof slab
including laying, consolidating,finishing etc.,complete.

weathering course 1 x 1 3.33 1.50 0.30 1.00


1 x 1 6.80 6.80 0.30 2.04
say 3.1 cum 3.04
Finishing the Top of Roof with One course of machine Pressed Tiles 200 x
200 x 20mm in C.M.1 : 3 - 12mm thick mixed with Water Proofing
Compound,Red oxide and pointing with same mortar etc.,

Page 4
overweathering course 1 x 1 3.33 1.50 3.33

1 x 1 6.80 6.80 6.80


say 10.2sqm 10.13
Plastering with Cement Mortar 1:5 (One cement and Five sand), 12mm
thick in all floors including curing etc. complete complying with standard
specification and as directed by the departmental officers.

parapet inside 1x 1 7.70 0.50 3.85


1x 1 26.40 0.90 23.76
27.61
say 28.00
Brick work in combination morter in ratio 1:1:5 following Cement Mortar
using best quality II class Ground moulded bricks size 9" x 4-3/8" x 2-3/4" for
gopuram including curing, etc., complete complying with standard specifiction.

for gopuram 1x 1 10.10 0.85 1.20 12.12


1x 1 7.50 0.80 1.45 10.88
1x 1 6.13 0.80 2.00 12.26
1x 1 4.60 0.80 0.65 2.99
1x 1 1.50 1.50 0.45 0.68
38.93
or 1375cft
Providing vargapuchu over of vimanam /gopuram in combination morter
1:1:4 including shaping the mugapathram ,mahanasi koodu and all ornamental
worksto proper shape by embedding broken bricks ,rough plastering in ccm
1:1:4 and finishing with ornamental plastering and nayam theervai labour
charges ,lifting of materials , cost and conveyance of materials, curing etc all
comlete

gopuram 1 x 1 12.44 1.20 14.93


1 x 1 10.53 1.45 15.27
1 x 1 8.63 2.00 17.26
1 x 1 6.71 0.65 4.36
1 x 1 3.84 0.50 1.92
1 x 1 19.30 0.30 5.79
1 x 1 28.40 0.90 25.56
parapet outer 1 x 1 28.20 0.35 9.87
1 x 1 24.20 0.35 8.47
103.43
say 105.00 or 1130.00

Page 5
Providing new sudai vigraham in vimanam /rajagopuram with GI rod to
suitable dia shaping the broken brick in cm 1:3 and finishing to reqd shape with
cm 1:3 including cost and conveyance etc all complete as specification

over outer wall 1x 4 4


over outer gopuram 1x 12 12
16.00
Supplying and manufacturing and fixing in position of MS grill for
window ,ventilator including cost and conveyance of materials labour charges
for fixing in position etc all complete
in gopuram 2x 3 0.60 0.90 3.24
entrance gate 1x 1 1.20 2.20 2.64
5.88
5.88sqm*25kg/sqm =147kg say 150kg

Finishing the top of flooring in cm 1:4 20mm thick including neat


finishing curing etc all complete
floor finishing karuvarai 1x 1 2.55 2.53 6.45
mugamandapam 1x 1 2.30 1.40 3.22
mahamandapam 1x 1 6.60 6.60 43.56
53.23
say 54.00
Painting two coats of newly plastered wall surface with water based
exterior emulsion paint of first class quality and of approved colour over a
priming coat including thorough scrapping, clean removal of dirt, and including
necessary plaster of paris putty, wherever required etc., complete complying
with standard specification.

plastering area 105+28=133 133.00

add for sudai 17.00


150.00
12
Painting new iron work with two finishing coats of synthetic enamel
ready mixed paint of approved quality and colour in all floors including the cost
of paint etc., complete complying with standard specification. (The make,
quality and colour of paint should be got approved by the Executive Engineer
before use on works.)

in gopuram 2x 3 0.60 2.00 0.90 3.24


entrance gate 1x 1 1.20 2.00 2.20 2.64
5.88
Page 6
say 6.00
provision for labour welfare fund ls
provision for GST @ 12% ls
Provision for centage charges ls
provision for unforseen items ls

Page 7
Page 8
ARULMIGU CHENNAKESAVAPERUMAL THIRUKOIL AT
YELAGIRI VILLAGE THIRUPATTUR TALUK VELLORE
DISTRICT
Name of work: RENOVATION OF THIRUKOIL
ABSTRACT ESTIMATE
S.NoQty Unit Description of Work Rate Per Amount
Dismantling and clearing away the debries such as weathering
course and tiles etc all complete
17.9 sqm 23.80 sqm 426.02
Labour charges for dismantling and removing the existing stone
structure including numbering, labour charges for removing the stones
and stacking for reuse ,scafolding charges tools and plant charges etc all
compete.

1779 sft a) wall stones 50.00 sft 88,950.00


48 cft b) piller 50.00 cft 2,400.00
70 cft c) pothiyal 50.00 cft 3,500.00
408 cft d) uthiram 50.00 cft 20,400.00
860 sft e) pavukkal 50.00 sft 43,000.00

1 Earth work excavation in all classes of soils and sub soils and
todepth as may be directed except in hard rock, requiring blasting,
including initial leads and lifts and re-filling the sides of foundation,
with excavated earth in 150mm layers well watered rammed and
consolidated, including depositing surplus earth clearing and
levelling the site, shoring shuttering baling out water wherever
necessary etc., complete complying with standard specification.

242.00 Cum 128.47 Cum 31,089.74


2 Supplying and filling in foundation, basement, etc with filling
sand in layers of not more than 15 cm thick well watered, rammed and
consolidated etc. complete complying with standard specification and
as directed by the departmental officers.

30.00 Cum 535.11 Cum 16,053.30

Page 9
3 Plain Cement concrete 1:5:10 (one cement five sand and ten
aggregate) using 40mm gauge hard granite broken stone jelly for
foundation including cost and conveyance of all materials labour for
mixing,l aying, compacting, curing, dewatering, side shuttering,
wherever necessary including curing etc.,complete complying with
standard specification and as directed.

35.00 3058.15 Cum 107,035.25


Random Rubble masonry work in CM 1:5 ( One of cement and
five of sand) Using selected stones and bond stones in foundation and
basement including dewatering wherever necessary proper setting,
curing etc., complete in all respects complying with relevant standard
Specifications.

142.00 3059.90 434,505.80


supplying of new stones like pavukkal, uthiram, pothoyal etc
including cost and conveyace etc all complete
370.00 cft 300.00 111,000.00
Refixing the cut stones in its original position including charges for
tools and plants labour charges for pointing with lime morter etc all
complete

1779 a) wall stones old 100.00 177,900.00


370.00 new 250.00 92,500.00
48 b) piller 100.00 4,800.00
70 c) pothiyal 100.00 7,000.00
409 d) uthiram 100.00 40,900.00
860 e) pavukkal 100.00 86,000.00
Brick work in following Cement Mortar using best quality II
class Ground moulded bricks size 9" x 4-3/8" x 2-3/4" for foundation
and basement including curing, etc., complete complying with standard
specifiction.
13.90 4943.86 68,719.65
Providing Weathering Course with Broken brick jelly and lime
mortar in ratio 32:12.5 by volume including beating with wooden beater
over roof slab including laying, consolidating, finishing etc.,complete.

3.1 3322.14 10,298.63


Finishing the Top of Roof with One course of machine Pressed
Tiles 200 x 200 x 20mm in C.M.1 : 3 - 12mm thick mixed with Water
Proofing Compound,Red oxide and pointing with same mortar etc.,

Page 10
10.2 520.70 5,311.14
Plastering with Cement Mortar 1:5 (One cement and Five sand),
12mm thick in all floors including curing etc. complete complying with
standard specification and as directed by the departmental officers.

28 sqm 134.55 3,767.40


Brick work in following Cement Mortar1:4 using best quality II
class Ground moulded stock bricks size 9" x 4-3/8" x 2-3/4" including
all varivargam ,moulds sthambam ,mugabathram,kooduand all
ornamental works including cost and conveyance of materials curing,
etc., complete complying with standard specifiction.

39 5025.96 196,012.44
Providing vargapuchu over of vimanam /gopuram in
combination morter 1:1:4 including shaping the mugapathram
,mahanasi koodu and all ornamental worksto proper shape by
embedding broken bricks ,rough plastering in ccm 1:1:4 and finishing
with ornamental plastering and nayam theervai labour charges ,lifting
of materials , cost and conveyance of materials, curing etc all comlete

1130 sft 75.35 85,145.50


Providing new sudai vigraham in vimanam /rajagopuram with GI
rod to suitable dia shaping the broken brick in cm 1:3 and finishing to
reqd shape with cm 1:3 including cost and conveyance etc all complete
as specification

16 0.00
Painting two coats of newly plastered wall surface with water
based exterior emulsion paint of first class quality and of approved
colour over a priming coat including thorough scrapping, clean removal
of dirt, and including necessary plaster of paris putty, wherever required
etc., complete complying with standard specification.

150.00 160.00 24000.00


Supplying and manufacturing and fixing in position of MS grill for
window ,ventilator including cost and conveyance of materials labour
charges for fixing in position etc all complete

150 kg 78.20 11,730.00

Page 11
Finishing the top of flooring in cm 1:4 20mm thick including neat
finishing curing etc all complete

54 269.45 14,550.30
Painting new iron works such as gate, steel doors windows
ventilators with two coats of approved quality and color of synthetic
enamel paint over the existing red oxide primer in all floor etc,
complete complying with standard specifications.

6.00 88.20 529.20


1,687,524.38
13 provision for labour welfare fund ls

14 provision for GST @ 12%

15 Provision for centage charges

16 provision for unforseen items ls


SAY 1,700,000.00

Page 12
Page 13
#REF!

DETAILED ESTIMATE
Sl.
No Description No L B D Qty Unit
.
1 Earth work excavation for foundation in all classes of soils and sub soils and todepth as may be
directed except in hard rock, requiring blasting, including infinal leads and lifts and re-filling the
sides of foundation, with excavated earth in 150mm layers well watered rammed and consolidated,
including depositing surplus earth clearing and levelling the site, shoring shuttering baling out water
wherever necessary etc., complete complying with standard specification.

Column footing 1 x 18 2.20 2.20 2.10 182.95

Circular column 1 x 2 2.20 2.20 2.10 20.33

Stub column 1 x 32 1.10 1.10 1.35 52.27

Grade beam: A1 to J1, A2 to j2 8 x 2 1.40 0.50 0.60 6.72

A1-A2,B1-B2,C1-C2,D1-D2,E1-E2,F1-
9 x 2 2.35 0.50 0.65 13.75
F2,G1-G2,H1-H2,J1-J2

Bet Stub columns A1 To J1, a2 TO J2 2 x 7 2.50 0.40 0.75 10.50

B1 to C1 1 x 2 1.05 0.40 0.75 0.63

J1 to outer column 1 x 1 0.75 0.40 0.75 0.23

for cross wall @ A1,A2,B1,B2 1 x 4 1.11 0.40 0.75 1.33

J1 to J2 stub column 1 x 2 4.20 0.40 0.75 2.52

Cross wall bet ween Kitchen- store 1 x 1 3.20 0.40 0.75 0.96

Cross wall bet ween Kitchen- store 1 x 1 3.20 0.40 0.75 0.96

Cross wall bet ween pantry - RO plant 1 x 1 3.20 0.40 0.75 0.96

Front of hand wash 1 x 2 3.24 0.50 0.65 2.11

Portico sides 1 x 2 3.15 0.50 0.65 2.05

Bettween circular column 1 x 1 2.60 0.50 0.65 0.85

Cross wall at LPG 1 x 2 1.23 0.50 0.75 0.92

Front of hand wash 1 x 2 4.04 0.50 0.65 2.63


Add extra 2.33
Total 305.00 Cum

Page 14
Sl.
No Description No L B D Qty Unit
.
2 Supplying and filling in foundation, basement, etc with filling sand in layers of not more than 15 cm
thick well watered, rammed and consolidated etc. complete complying with standard specification
and as directed by the departmental officers.

Annadhana koodam 1 x 1 7.50 19.72 0.15 22.19

Pantry 1 x 1 5.27 1.65 0.15 1.30

Kitchen 1 x 1 5.27 7.04 0.15 5.57

RO plant 1 x 1 2.00 1.42 0.15 0.43

store 1 x 1 2.00 3.37 0.15 1.01

utensil store 1 x 1 2.00 3.44 0.15 1.03

utensil wash 1 x 1 1.50 3.44 0.15 0.77

Hand wash Passage 1 x 2 2.40 3.37 0.15 2.43

Passage 1 x 2 21.67 1.20 0.15 7.80

LPG 1 x 1 3.00 1.20 0.15 0.54

Service corridor 1 x 2 5.33 1.20 0.15 1.92

Front of hand wash 1 x 2 4.04 1.20 0.15 1.45

Portico 1 x 1 4.64 4.27 0.15 2.97


Sundries 2.59
Total 52.00 Cum

3 Refilling with excavated earth other than sand with an initial head load of 100 mts. and depositing the
earth as shown by the departmental officers in layers of not more than 15 cm thick well rammed,
watered and consolidated etc. complete complying with standard specification.

Annadhana koodam 1 x 1 7.50 19.72 0.35 51.77

Pantry 1 x 1 5.27 1.65 0.35 3.04

Kitchen 1 x 1 5.27 7.04 0.35 12.99

RO plant 1 x 1 2.00 1.42 0.35 0.99

store 1 x 1 2.00 3.37 0.35 2.36

utensil store 1 x 1 2.00 3.44 0.25 1.72

Utensil wash 1 x 1 1.50 3.44 0.25 1.29

Hand wash Passage 1 x 2 2.40 3.37 0.35 5.66

Page 15
Sl.
No Description No L B D Qty Unit
.
Passage Ramp 2 x 0.5 9.30 1.20 0.18 2.01

passage 2 x 1 5.10 1.20 0.35 4.28

Service corridor 1 x 1 5.33 1.20 0.25 1.60


2.29
Total 90.00 Cum
4 Cement concrete 1:5:10 (one cement five sand ten aggregate) using 40mm gauge hard granite broken
stone jelly for foundation including cost and conveyance of all materials labour for mixing,l aying,
compacting, curing, dewatering, side shuttering, wherever necessary including curing etc.,complete
complying with standard specification and as directed.

Column footings 1 x 18 2.20 2.20 0.08 6.97

Circular column 1 x 2 2.20 2.20 0.08 0.77

Stupbcolumn 1 x 32 1.10 1.10 0.08 3.10

Grade beam: A1 to J1, A2 to j2 8 x 2 3.30 0.50 0.08 2.11

A1-A2,B1-B2,C1-C2,D1-D2,E1-E2,F1-
9 x 2 3.63 0.50 0.08 2.61
F2,G1-G2,H1-H2,J1-J2

Stub column A1 To J1, a2 TO J2 7 x 2 3.37 0.40 0.08 1.51

B1 to C1 1 x 2 2.14 0.40 0.08 0.14

J1 to outer column 1 x 2 1.20 0.40 0.08 0.08

for cross wall @ A1,A2,B1,B2 1 x 4 2.10 0.40 0.08 0.27

J1 to J2 stup column 1 x 2 5.33 0.40 0.08 0.34

Cross wall bet ween Kitchen- store 1 x 1 3.44 0.40 0.08 0.11

Cross wall bet ween Kitchen- store 1 x 1 3.37 0.40 0.08 0.11

Cross wall bet ween pantry - RO plant 1 x 1 3.37 0.40 0.08 0.11

Frond of hand wash 1 x 2 3.24 0.50 0.08 0.26

Portico sides 1 x 2 3.07 0.50 0.08 0.25

Between circular column 1 x 1 3.97 0.45 0.08 0.14

Cross wall at LPG 1 x 2 1.23 0.50 0.08 0.10

Flooring: 0.00

Annadhana koodam 1 x 1 7.50 19.72 0.10 14.79

Page 16
Sl.
No Description No L B D Qty Unit
.
Pantry 1 x 1 5.27 1.65 0.10 0.87

Kitchen 1 x 1 5.27 7.04 0.10 3.71

RO plant 1 x 1 2.00 1.42 0.10 0.28

store 1 x 1 2.00 3.37 0.10 0.67

utensil store 1 x 1 2.00 3.44 0.10 0.69

Utensil wash 1 x 1 1.50 3.44 0.10 0.52

Hand wash Passage 1 x 2 2.40 3.37 0.10 1.62

Passage 1 x 2 21.67 1.20 0.10 5.20

LPG 1 x 1 3.00 1.20 0.10 0.36

Service corridor 1 x 2 5.33 1.20 0.10 1.28

hand wash flooring 1 x 2 4.04 1.20 0.10 0.97

Portico 1 x 1 4.64 4.27 0.10 1.98


Add extra 1.08
Total 53.00 Cum

5 Supplying and erecting steel centering including necessary supports for plane surfaces for Reinforced
Cement Concrete works such as column footings, column pedestals, plinth beams, grade beams,
staircase steps, etc. which require only nominal strutting using mild steel sheets of size 90cm x 60cm
and 10 BG stiffened with welded mild steel angles of size 25mm x 25mm x 3 mm for boarding, laid
over silver oak joists of size 10cm x 6.5cm spaced at about 75cm centre to centre or at suitable
intervals etc. complete in all floors complying with standard specifcation. (Payment for centering
shall be given after the concrete is laid)

Column /footing, Grade beam Etc

Rectungalar column-Circular columns -


1 x 20 8.00 0.30 48.00
- Footing sides

Pedestal 1 x 20 2.00 0.15 6.00

Stub column footing sides 1 x 32 3.60 0.20 23.04

Pedestal 1 x 32 1.40 0.15 6.72

Grade beam: 0.00

A1 to J1, A2 to j2 8 x 4 3.30 0.30 31.68

Page 17
Sl.
No Description No L B D Qty Unit
.
A1-A2,B1-B2,C1-C2,D1-D2,E1-E2,F1-
9 x 4 3.63 0.35 45.74
F2,G1-G2,H1-H2,J1-J2

Stub column A1 To J1, a2 TO J2 2 x 14 3.37 0.30 28.31

B1 to C1,B2,C2 2 x 2 2.14 0.30 2.57

J1 to outer column 1 x 2 1.20 0.30 0.72

for cross wall @ A1,A2,B1,B2 4 x 2 2.10 0.30 5.04

J1 to J2 stup column 2 x 2 5.33 0.30 6.40


Cross wall bet ween Kitchen- utensil
1 x 2 3.44 0.30 2.06
store
Cross wall bet ween Kitchen- store 1 x 2 3.37 0.30 2.02

Cross wall bet ween pantry - RO plant 1 x 2 3.37 0.30 2.02

pantry - RO plant 2 x 2 1.20 0.30 1.44

Front of hand wash 2 x 2 3.37 0.30 4.04

Portico sides 2 x 2 3.07 0.30 3.68

Portico front sides 1 x 2 3.97 0.35 2.78

front of hand wash 1 x 2 4.64 0.30 2.78

Cross wall at LPG 2 x 2 1.23 0.30 1.48


Sundries 3.47
Total 230.00 Sqm

6 Providing form work for centring the soffits of all reinforcement cement concrete surfaces
M.S.Sheets of 90 x 60cm x 10 gauge stiffened with welded M.S angle of size 25x25x3mm laid over
silver oak joints of size 10cm x 6.50cm spaced at about 90cm centre to centre and supported by
casurina props of 10cm to 13 cm dia spaced at 75cm centre to centre complying with standard
specification and as directed.

A
For plane surfaces such as Rcc Roof slab, beams,Lintels,bet blocks,landing slab, portico slab, beeams
etc.,

Sill beam: Sides - W 2 x 2 2.40 0.10 0.96

W1 10 x 2 2.10 0.10 4.20


Utensil Wash, store, KW 2 x 2 2.10 - 0.10 0.84
Kitchen KW 1 x 2 3.30 - 0.10 0.66

Page 18
Sl.
No Description No L B D Qty Unit
.
LINTEL: A1 to J1, A2 to J2 2 x 16 3.30 - 0.30 31.68
A1-B1,A2-B2 hand wash 2 x 2 3.83 0.30 4.60
Cross walls 4 x 2 2.40 0.30 5.76

A1-A2,G1-G2,J1-J2 3 x 2 7.50 - 0.30 13.50

H2-J2 Stub columns 1 x 2 3.30 - 0.30 1.98

Wall between kitchen, utensil


1 x 2 8.69 0.15 2.61
store,kitchen-store - RO- PLANT

Wall between kitchen, utensil store,-


2 x 2 2.00 0.15 1.20
store - RO- PLANT

Utensil wash walls 2 x 2 1.50 - 0.15 0.90

LPG sides walls 2 x 2 1.20 - 0.15 0.72

Front walls 1 x 2 3.90 0.15 1.17

Beam: Cantilever beam at columns for


sunshade:
C1,D1,E1,F1,G1,C2,D2,E2,F2,G2
10 x 2 1.19 0.18 4.28
SIDES
Front sides 10 x 1 0.23 0.18 0.41
ROOF BEAMS:
A1 to J1, A2 to J2 sides 4 x 8 3.30 - 0.30 31.68

A1-A2,B1-B2,C1-C2,D1-D2,E1-E2,F1-
9 x 2 7.50 0.45 60.75
F2,G1-G2,H1-H2,J1-J2

Roof slab Bottom:


Annadhana koodam 1 x 1 7.50 19.72 147.90
Pantry 1 x 1 5.27 1.65 8.70
R.O Plant 1 x 1 2.00 1.42 2.84
Kitchen 1 x 1 5.27 7.04 37.10
Store 1 x 1 2.00 3.37 6.74
Utensil store 1 x 1 2.00 3.44 6.88
LPG 1 x 1 1.20 3.00 3.60
Hand wash 1 x 2 2.40 3.37 16.18
Roof slab: Sides A1 - J1, A2-J2 1 x 2 29.10 0.15 8.73

J1 - J2 1 x 2 8.50 0.15 2.55

LPG 1 x 2 3.90 0.15 1.17

Page 19
Sl.
No Description No L B D Qty Unit
.
,, ,, 2 x 2 1.20 0.15 0.72

Hand wash 2 x 2 2.63 0.15 1.58

Cross walls 1 x 2 1.20 0.15 0.36

Front of hand wash 1 x 2 4.04 0.15 1.21

Portico bottom 1 x 1 4.50 4.20 18.90

Roof beam portico sides 2 x 2 4.20 0.45 7.56

Portico front 1 x 2 4.50 0.45 4.05

Roof slab sides allround 1 x 1 12.90 0.15 1.94

3.40

450.00 Sqm
B) FOR COLUMN AND SUNSHADE:
Column up to basement 1 x 18 1.60 1.85 53.28

Circular column 1 x 2 0.94 1.85 3.48

Stub column up to ground level 1 x 32 0.92 0.75 22.08

Columns A1 to J1, A2 TO J2 up to roof 1 x 18 1.60 3.60 103.68

Stub columns: A1,B1,A2,B2 2 x 3 0.92 2.70 14.90


From G.L lintel
Circular column 1 x 2 3.14 0.30 3.60 6.78
Sunshade: B1 TO TO H2 H1, B2 1 x 2 21.90 1.43 62.63
front side 1 x 2 21.90 0.12 5.26
sunshade kitchen bottom 1 x 1 5.43 0.60 3.26
,, @ Hand wash 1 x 2 2.90 0.60 3.48
Service corridor roof 1 x 1 5.43 1.43 7.76
Front side 1 x 1 5.43 0.12 0.65

2.76

290.00 Sqm

c)
Curved centeing for kodungai:

Portico sides 1 x 2 4.20 0.90 7.56


Front 1 x 1 5.10 0.90 4.59
0.85
13.00 Sqm

Page 20
Sl.
No Description No L B D Qty Unit
.
7 Reinforced Cement Concrete 1:11/2:3 (one cement,One and half course sand and Three broken stone)
using 20mm 'size of hard broken granite stone for all RCC works using machine for mixing concrete
excluding cost of steel, fabrication of reinforcement, centering, and shuttering and placing the grills
in position etc., complete complying with standard specification.

a) For foundation and Basement:


Column + Circular column footing 1 x 20 2.00 2.00 0.30 24.00

(2.00x2.00)+
Sloped portion 1 x 20 0.25 10.60
(0.40x0.60)/2
Pedestal 1 x 20 0.40 0.60 0.15 0.72
Column up to basement 1 x 18 0.30 0.50 1.85 5.00

Circular column 1 x 2 (3.14 x 0.30/4) 1.85 0.26

Stub column footing 1 x 32 0.90 0.90 0.20 5.18

(0.90 x 0.90 )+
Sloped portion 1 x 32 0.15 2.21
(0.35 x 0.35)/2

Pedestal 1 x 32 0.35 0.35 0.15 0.59

Stub column 1 x 32 0.23 0.23 0.45 0.76

Grade beam- A1 TO H1 , A2 - J2 1 x 15 3.30 0.23 0.30 3.42

H1-J1 1 x 1 3.30 0.45 0.30 0.45

A1-A2,B1-B2,C1-C2,D1-D2,E1-E2,F1-
1 x 9 7.50 0.23 0.35 5.43
F2,G1-G2,H1-H2,J1-J2

Stub column A1-J1,A2J2 2 x 7 3.37 0.23 0.30 3.26

B1-C1 1 x 2 1.46 0.23 0.30 0.20

J1 to outer wall 1 x 1 1.20 0.23 0.30 0.08

For cross wall A1,A2,B1,B2 hand wash 1 x 4 2.10 0.23 0.30 0.58

J1 to J2 Stub column(Service corridor) 1 x 2 5.33 0.23 0.30 0.74


Cross wall bwtween Kitchen- utensil
1 x 1 3.44 0.23 0.30 0.24
store
Cross wall bwtween Kitchen- store 1 x 1 3.37 0.23 0.30 0.23

Cross wall between panatry Ro plant 1 x 1 3.37 0.23 0.30 0.23

Front of hand wash @ portico sides 1 x 2 1.20 0.23 0.30 0.17

,, ,, 1 x 2 4.04 0.23 0.30 0.56

Grade beam : Portico sides 1 x 2 3.07 0.30 0.30 0.55

Page 21
Sl.
No Description No L B D Qty Unit
.
Grade beam between circular column 1 x 1 3.97 0.23 0.30 0.27

Grade beam cross wall between LPG 1 x 2 1.23 0.45 0.30 0.33

1.94

68.00 Cum
B) Above Basement level up to 3.60m
height:

Column - up to roof A1 To J1 A2 To J2 1 x 18 0.30 0.50 3.60 9.72

Circular column 1 x 2 3.14x0.302/4 3.60 0.51

Stub column - A1,B1,A2,B2, from G.L


1 x 4 0.23 0.23 2.70 0.57
To Lintel
Sill beam - W 1 x 2 2.40 0.23 0.10 0.11

W1 1 x 10 2.10 0.23 0.10 0.48

Utensil wash , store - KW 1 x 2 2.10 0.23 0.10 0.10

Kitchen KW 1 x 1 3.30 0.23 0.10 0.08

LINTEL: A1 to J1, A2 to J2 2 x 8 3.30 0.23 0.30 3.64

A1-B1,A2-B2 Stub column 1 x 2 3.83 0.23 0.30 0.53

cross wall 1 x 4 2.40 0.23 0.30 0.66

A1 to A2,G1 to G2, J1 to J2 1 x 3 7.50 0.23 0.30 1.55

H2-J2 Stup column 1 x 1 3.30 0.23 0.30 0.23

Wall between Kitchen - utenseel store


1 x 1 8.69 0.23 0.15 0.30
Kitchen store,pantry -Ro plant

Wall between utensil store - store-store


1 x 2 2.00 0.23 0.15 0.14
-Ro plant
Utensil wash walls 1 x 2 1.50 0.23 0.15 0.10

L P G side wall 1 x 2 1.20 0.45 0.15 0.16

Front wall : 1 x 1 3.90 0.45 0.15 0.26

Beam: Cantilever beam at columns for sunshade:

C1, D1, E1, F1, G1, C2, D2, E2, F2, G2 1 x 10 1.19 0.23 0.18 0.49

Sunshade: B1 to H1, B2 to H2 1 x 2 21.90 1.43 0.12 7.52

Page 22
Sl.
No Description No L B D Qty Unit
.
kitchen 1 x 1 5.43 0.60 0.07 0.21

sunshade @ handwash 1 x 2 2.40 0.60 0.07 0.19


Service corridor 1 x 1 5.43 1.43 0.12 0.93
Roof beam : A1 - J1, A2-J2,sides 2 x 8 3.30 0.23 0.30 3.64
A1-A2, B1-B2,C1-C2, D1-D2, E1-E2,
1 x 9 7.50 0.30 0.45 9.11
F1-F2, G1-G2, H1-H2, J1-J2
Roof slab: Annadhana koodam 1 x 1 7.50 19.72 0.15 22.19
Pantry 1 x 1 5.27 1.65 0.15 1.30
Ro plant 1 x 1 2.00 1.42 0.15 0.43
Kitchen 1 x 1 5.27 7.04 0.15 5.57
store 1 x 1 2.00 3.37 0.15 1.01
Utensil store 1 x 1 2.00 3.44 0.15 1.03
LPG 1 x 1 1.20 3.00 0.15 0.54
hand wash 1 x 2 2.40 3.37 0.15 2.43
Portico roof beam :
Sides 1 x 2 4.20 0.23 0.45 0.87
Front 1 x 1 4.50 0.23 0.45 0.47
Portico roof slab 1 x 1 4.80 4.50 0.15 3.24
Portico Kodungai allround 1 x 1 17.10 0.90 0.10 1.54
1.15
83.00 Cum

8 Supplying, fabricating and placing in position Mild Steel / Ribbed Tor Steel grills for all RCC works
as per design given including cost of steel and G.I. binding wire in all floors etc. complete complying
with standard specification. (Contractor has to make his own arrangements for the supply of steel
and binding wire)

Footings 43.30 x 75 Kg / Cum 3247.50


Grade beam, 16.74 x 100 Kg / Cum 1674.00
Columns 16.25 x 225 Kg / Cum 3656.25
Lintel 9.00 x 150 Kg / Cum 1350.00
Beam 13.62 x 250 Kg / Cum 3405.00
Sill beam,roof slab,Kodungai 51.82 x 100 Kg / Cum 5182.00
Add Extra 85.25
Total 18600.00 kg
Total 186.00 QTL

Brick work in following Cement Mortar 1:6 using best quality II class Ground moulded bricks size
9
9" x 4-3/8" x 2-3/4" for including curing, etc., complete complying with standard specifiction.

Page 23
Sl.
No Description No L B D Qty Unit
.
a) Foundation and basement:

A1-H1 1 x 7 3.30 0.23 0.90 4.78


A2-J2 1 x 8 3.30 0.23 0.90 5.46
A1-A2,J1-J2,G1-G2,H1-H2 1 x 4 7.50 0.23 0.90 6.21
Wall between kitchen - utensil store 1 x 1 3.44 0.23 0.90 0.71
Kitchen - store 1 x 1 3.37 0.23 0.90 0.70
pantry - Ro Plant 1 x 1 1.42 0.23 0.90 0.29
Utensil wash - Cross wall 1 x 2 1.43 0.23 0.90 0.59
LPG - wall H1 -J1 1 x 1 3.30 0.45 0.90 1.34
Cross wall 1 x 2 1.20 0.45 0.90 0.97
Front wall 1 x 1 3.30 0.23 0.90 0.68
Hand wash side wall 1 x 2 3.37 0.23 0.90 1.40
Cross wall 2 x 2 2.40 0.23 0.90 1.99
B1 to H1, B2 to H2 6 x 2 3.30 0.23 0.90 8.20
,, ,, 2 x 2 1.65 0.23 0.90 1.37
service corridor 1 x 1 11.35 0.23 0.90 2.35
Cross wall 1 x 2 1.20 0.23 0.90 0.50
Portico : A1 to Circular column, A2 to
circular column 1 x 2 6.00 0.23 0.45 1.24
Wall between to circular column 1 x 1 4.50 0.23 0.45 0.47
Entrence steps:

I st step 1 x 1 3.20 1.20 0.15 0.58


II nd step 1 x 1 2.60 0.90 0.15 0.35
III rd step 1 x 1 2.00 0.60 0.15 0.18
Service corridor steps:

I st step 1 x 1 1.20 0.23 0.15 0.04


II nd step 1 x 1 1.20 0.23 0.15 0.04
III rd step 1 x 1 1.20 0.23 0.15 0.04

1.52
Page 24
Sl.
No Description No L B D Qty Unit
. Cu
42.00 m
Above basement level up to 3.60m
B)
height:
A1 to H1 1 x 7 3.30 0.23 3.30 17.53
A2 to H2 1 x 8 3.30 0.23 3.30 20.04
D/F lintel beams 1 x 15 3.30 0.23 0.30 -3.42
A1-A2,G1-G2,H1-H2,J1-J2 1 x 4 7.50 0.23 3.15 21.74
Wall between - Kitchen - utensil store 1 x 1 3.44 0.23 3.60 2.85
Kitchen - store 1 x 1 3.37 0.23 3.60 2.79
Pantry - Ro plant 1 x 1 1.42 0.23 3.60 1.18
Utensil wash - cross wall 1 x 2 1.43 0.23 3.30 2.17
LPG wall - H1-J1 1 x 1 3.30 0.45 3.30 4.90
Cross wall 1 x 2 1.20 0.45 3.30 3.56
Front wall 1 x 1 3.30 0.23 3.30 2.50
Stub column A1-B1,A2-B2 1 x 2 3.37 0.23 2.10 3.26
Cross wall 2 x 2 2.40 0.23 2.10 4.64
B1-D1, B2-D2 Passage 2 x 1 7.20 0.23 0.15 0.50

D1-F1 , D2-F2 ramp 0.15+


2 x 1 7.20 0.23 0.60/2 1.24
F1 - H1, F2-H2 passage 2 x 1 7.20 0.20 0.60 1.73
Service corridor 1 x 1 5.67 0.23 0.50 0.65
,, ,, 1 x 1 5.67 0.23 0.15 0.20
Cross wall 1 x 1 1.43 0.23 0.15 0.05
Deductions:
Window W 1 x 2 1.80 0.23 1.65 -1.37
Window W1 1 x 10 1.50 0.23 1.65 -5.69
Window KW 1 x 3 1.50 0.23 1.20 -1.24
M.D 1 x 1 2.00 0.23 2.40 -1.10
D 1 x 2 1.50 0.23 2.40 -1.66
D1 1 x 2 1.20 0.23 2.40 -1.32
D2 1 x 2 1.00 0.23 2.40 -1.10
C.G 1 x 1 3.00 0.23 2.40 -1.66
Hand wash open 2 x 2 1.00 0.23 2.40 -2.21
Jolly 2 x 4 1.50 0.23 1.65 -4.55
1.79
Page 25
Sl.
No Description No L B D Qty Unit
. Cu
68.00 m
Brick masonry in CM 1:4, using best quality II class Ground moulded bricks size 9" x 4-3/8" x 2-3/4
including all vaarivargams, moulds, sthambams, mukhapathramsa, koodu, nasi and all ornamental
birck work complete, all pancharams, agarais, karnrakoodus, etc., forming core wlls of
10
Rajagopurams/vimanams complete including cost and conveyance of all materials including cement,
all the labour charges including marking pathies shaping of the bricks, lifting of all the materials to
required hts curing and all extra for working in hts etc., complete – 100cft.

Parapet wall all round : 1 x 1 73.20 0.23 0.75 12.63


0.37 Cu
13.00 m

11 Special ceiling plastering and finishing the exposed surface of all RCC items of work such as slabs,
beams, sunshades, facia, canopy slab, staircase waist slab, landing slab etc., with Cement Mortar 1:3
(One Cement and Three Sand) 10mm thick including hacking the surfaces, providing cement mortar
nosing, beading for sunshades, staircases, steps, landing slabs and curing, etc., in all floors complying
with standard specification and as directed by the departmental officers

Qty item no 6a 450.00


Qty item no 6b 290.00
Kodungai 6c 13x2 26.00
3.99
Total qty 770.00 Sqm

12 Plastering with Cement Mortar 1:5 (One cement and Five sand), 12mm thick in all floors including
curing etc. complete complying with standard specification and as directed by the departmental
officers.

For basement (Brick work Qty/0.23x1)


42.00 / 0.23 1.00 182.60
Item no 7
Item no 8 68.00 / 0.23 2.00 591.30

Parepet wall Brick work 13.00 / 0.23 2.00 113.04


Add extra 3.06
Total 890.00 Sqm

13 Providing Weathering Course Concrete to an average thickness of 8cm with20mm size Broken brick
jelly in lime mortar over roof slab including laying, consolidating,finishing etc.,complete.

Top roof of slab 1 x 1 7.50 28.64 0.08 17.18


For Splashing 1 x 0.5 72.28 0.15 0.15 0.81
For portico 1 x 1.0 4.20 4.20 0.08 1.41
For Splashing 1 x 1 16.80 0.15 0.15 0.38
Sundries 1.22
Total 21.00 Cum

Page 26
Sl.
No Description No L B D Qty Unit
.
14 Finishing the Top of Roof with One course of machine Pressed Tiles 200 x 200 x 20mm in C.M.1 : 3
- 12mm thick mixed with Water Proofing Compound,Red oxide and pointing with same mortar etc.,

Top roof of slab 1 x 1 7.50 28.64 - 214.80


For flashing 1 x 1 72.28 0.20 14.46
For portico 1 x 1.0 4.20 4.20 17.64
For Splashing 1 x 1 16.80 0.20 3.36
Sundries 1.74
Total 252.00 Sqm

15 Paving the floor with kota stone slab of size 600 x 600 of 18 / 20mm (un-polished) in all floors laid in
of cement mortor 1:3 (one cement three sand), 20mm thick and pointed with colour cement neatly
including polishing with polishing stone and oxalic acid etc., so as to perfectly smooth and glossy and
including hire charges for polishing machine and power consumption charges etc. The kota stone
slabs and other materials to be used shall be got approved by the Executive Engineer concerned
before use on work, etc., complete as per standard speicification.

Annadhana koodam flooring 1 x 1 7.50 19.72 147.90


Kitchen 1 x 1 5.27 7.04 37.10
Pantry 1 x 1 5.27 1.65 8.70
Utensil store 1 x 1 2.00 3.44 6.88
Utensil wash 1 x 1 1.50 3.44 5.16
store 1 x 1 2.00 3.37 6.74
Ro plant 1 x 1 2.00 1.42 2.84
LPG 1 x 1 1.20 3.00 3.60
Service corridor 1 x 1 1.43 5.67 8.11
hand wash 1 x 2 2.40 3.37 16.18
Sundries 1.79
Total 245.00 Sqm

16
Paving the floor with concrete anti-skid tiles(Eurocon) to Required shape and design of 20mm thick
of approved quality and colour laid in Cement Mortar 1:3 (One Cement and Three sand) 20mm thick
and pointed with white cement mixed with colouring pigment at the rate of 0.40 Kg. / sq.m., curing,
etc., complete complying with standard specification and as directed by the departmental officers.
(The make and brand of the tiles should be got approved by Executive Engineer before use on works)

Passage 1 x 2 21.37 1.43 61.12


Front of hand wash 1 x 2 4.04 1.20 9.70
Portico 1 x 1 4.50 4.20 18.90
Service corridor 1 x 1 5.67 1.43 8.11
Sundries 2.17
Total 100.00 Sqm

17 Supplying and fixing of best quality 110mm Dia PVC rain water pipes including cost and conveyance
of all materials and labour charges for fixing in position etc., complete.

Page 27
Sl.
No Description No L B D Qty Unit
.
From Main Building 4 x 2 5.20 - - 41.60

Hand wash 1 x 2 3.00 - - 6.00

Portico 1 x 2 5.20 - - 10.40


Sundries 2.00
Total 60.00 Rm

18 supplying and fixing of Teak wood frames 127 x 76mm size as per standard specifications.
For D 1.00 x 2.00 5.70 0.13 0.08 0.11
For D1 1.00 x 2.00 5.40 0.13 0.08 0.10
For D2 1.00 x 2.00 5.20 0.13 0.08 0.10
sundries 0.09
0.40 cum

19 Supplying and fixing of Flush door shutter using Teak wood frame of size 127mm x 76mm and
Door shutters Single leaf in position using 35mm thick solid core Flush shutters with teak play on
both sides with teak wood lipping alround including cost and labour for fixing the hold fasts and
furniture fittings etc.,complete as directed by the departmental officers complying with standard
specification.
Double leaf shutter:
Single leaf shutter: D 1 x 2 1.50 2.10 6.30
D1- Door 1 x 2 1.20 2.10 5.04
D2- Door 1 x 2 1.00 2.10 4.20
1.46
17.00 Sqm
20
Supply and fixing of Teak Wood glazed window with outer frames of size 3" x 21/2" and shutter
frames of size 21/2"x11/2" and glass panels of 4mm thick. M.S grill shall be fixed to the frames @
30Kg/m2. The rate includes cost of materials manufacutering and fixing at site.

W- Window 1 x 2 1.80 1.30 4.68


W1- Window 1 x 10 1.50 1.30 19.50
K-W 1 x 4 1.50 1.20 7.20
1.62
33.00 Sqm

Page 28
Sl.
No Description No L B D Qty Unit
.
21 Supplying and fixing mild steel grill for windows and hand rails etc complete., including cost
conveyance of all materials and fixing in position including priming coat etc complete with standard
specifications.
Window grill Item no 19 1 x 33 33.00
At 20 kg for Sqm 660.00 Kg
For hand rails at cooridor 1 x 2 22.00 0.80 35.20
At 25Kg for Sqm 880.00 Kg
10.00
68.20 1550.00 Kg

22 Painting two coats with cement paint of first class quality and approved colour, including priming
coat and through scrapping and clean removal of dirt etc., complete as per standared specification.

Roof slab Bottom:


Annadhana koodam 1 x 1 7.50 19.72 147.90
Pantry 1 x 1 5.27 1.65 8.70
R.O Plant 1 x 1 2.00 1.42 2.84
Kitchen 1 x 1 5.27 7.04 37.10
Store 1 x 1 2.00 3.37 6.74
Utensil store 1 x 1 2.00 3.44 6.88
LPG 1 x 1 1.20 3.00 3.60
Hand wash 1 x 2 2.40 3.37 16.18
A1-A2,B1-B2,C1-C2,D1-D2,E1-E2,F1-
9 x 2 7.50 0.45 60.75
F2,G1-G2,H1-H2,J1-J2
Sunshade: B1 TO TO H2 H1, B2 1 x 2 21.90 1.43 62.63
front side 1 x 2 21.90 0.12 5.26
sunshade kitchen bottom 1 x 1 5.43 0.60 3.26
,, @ Hand wash 1 x 2 2.90 0.60 3.48
Service corridor roof 1 x 1 5.43 1.43 7.76
6.92
Total 380.00 Sqm

23 Painting two coats of newly plastered wall surface with water based exterior emulsion paint of first
class quality and of approved colour over a priming coat including thorough scrapping, clean removal
of dirt, and including necessary plaster of paris putty, wherever required etc., complete complying
with standard specification.

Pleastering in CM 1:5 890.00


Pleastering in CM 1:3 770.00
D/F cement painting 380.00
D/F Dadooing quantity 165.00
5.00
Total 1120.00 Sqm

Page 29
Sl.
No Description No L B D Qty Unit
.
24
Painting new wood work with two finishing coats of synthetic enamel ready mixed paint of approved
quality and colour over one coat priming coat in all floors including the cost of primer etc., complete
complying with standard specification. (The make, quality and colour of paint should be got
approved by the Executive Engineer before use on works.)

D 1 x 2 1.50 2.20 2.10 13.86


D1 1 x 2 1.20 2.20 2.10 11.09
D2 1 x 2 1.00 2.20 2.10 9.24
W 1 x 2 1.80 1.00 1.30 4.68
W1 1 x 10 1.50 1.00 1.30 19.50
Kw 1 x 4 1.50 1.00 1.20 7.20
4.43
70.00 Sqm

Painting new iron works such as gate, steel doors windows ventilators with two coats of approved
quality and color of synthetic enamel paint over the existing red oxide primer in all floor etc,
25 complete complying with standard specifications.
W- Window 1 x 2 1.80 1.00 1.30 4.68
W1- Window 1 x 10 1.50 1.00 1.30 19.50
K-W 1 x 4 1.50 1.00 1.20 7.20
For hand rails at cooridor 1 x 2 22.00 1.00 0.80 35.20
3.42
70.00 Sqm

Page 30
Sl.
No Description No L B D Qty Unit
.
26 Dadooing walls with following best approved quality, white / colour glazed tiles of following sizes
set in Cement Mortar 1:2 (One Cement and Two sand) 10mm thick and pointing the joints with white
cement mixed with colouring pigments at the rate of 0.40 Kg. / sq.m. neatly in all floors, curing, etc.,
complying with standard specification and as directed by the departmental officers.

Annadhana koodam & pantry& Ro Plant 1 x 1 57.88 2.10 121.55

Wall between Pantry Ro plant 1 x 2 1.42 2.10 5.96

Wall between Pantry Ro plant 1 x 1 0.23 2.10 0.48


(-) MD 1 x 1 2.00 2.10 -4.20
(-) W 1 x 2 1.80 1.30 -4.68
(-) W1 1 x 10 1.50 1.30 -19.50
(-) D1 1 x 2 1.20 2.10 -5.04
(-) D 1 x 1 1.50 2.10 -3.15
Door sides 4 x 2 0.18 2.10 3.02

Kitchen 1 x 1 24.62 2.10 51.70


(-) D 1 x 2 1.50 2.10 -6.30
(-) D2 1 x 1 1.00 2.10 -2.10
(-) KW 1 x 2 1.50 1.20 -3.60
Hand wash 1 x 2 6.37 2.10 26.75
Sundries 4.09
Total 165.00 Sqm

27 Provision for ornamental Main door L.S


28 Provision for cub board and plat form
arrangements in kitchen L.S

29 provision for Rain water harvesting


arrangements L.S

30 provision for pavement and drain


arrangement L.S

31
Provisions for Electrical
arrangements7.5%
32 Provisions for Water supply
arrangements 5%
33 Provisions for LPG connection,
furniture and fly roof gate arrangements. L.S

34 Provision for advertisement charges L.S


35 provision for Photograph and L.S
36 documentation charges
Provisions for Centage charges @ 2% L.S

Page 31
Sl.
No Description No L B D Qty Unit
.
37 Provisions for Labour Welfare Scheme
L.S
1.00%
38 Provision for P.S.Charges and
L.S
Unforeseen items

Page 32
ARULMIGU CHENNAKESAVAPERUMAL THIRUKOIL AT
YELAGIRI VILLAGE TIRUPATTUR TALUK VELLORE DISTRICT
LEAD STATEMENT
Dist
anc
Sl. Source of Lead
Material e Unit Cost Total
No. Supply Charges
(Km
1 Cement At site s) MT 5530.00 5530.00

2 Steel At site MT 44190.00 44190.00

3 Sand for mortor Jami 47 cu.m. 168.00 366.85 534.85


kulithirai
4 Sand for filling Jami 47 cu.m. 168.00 366.85 534.85
kulithirai
5 Rough Stone pasalikuttai 20 cu.m. 413.00 178.50 591.50

6 Bond Stone pasalikuttai 20 cu.m. 595.00 595.00

7 HGB 40mm ISS metal pasalikuttai 20 cu.m. 929.00 178.50 1107.50

8 HGB 25mm ISS metal pasalikuttai 20 cu.m. 799.00 178.50 977.50

8 HGB 20mm ISS metal pasalikuttai 20 cu.m. 1293.00 178.50 1471.50

9 HGB 10-12mm ISS metal pasalikuttai 20 cu.m. 1041.50 178.50 1220.00

11 HGB 6-10mm ISS metal pasalikuttai 20 cu.m. 740.50 178.50 919.00

10 Country bricks of size Adiyur 14 1000 5130.00 109.00 5239.00


83/4" x 41/4" x 23/4" Nos.

5 II Class Table Moulded Adiyur 12 1000 6100.00 158.36 6258.36


Chamber Burnt Bricks of Nos.
size
6 9"
II xClass
41/2" xTable
3" Moulded 12 1000 6810.00 158.36 6968.36
Chamber Burnt Bricks of Nos.
size
9" x 43/8" x 23/4"

11
11 II Class Ground Moulded Adiyur 12 1000 5925.00 158.36 6083.36
Chamber Burnt Bricks of Nos.
size
9" x 43/8" x 23/4"
12 Brick jelly 40mm Adiyur 12 cu.m. 635.00 77.32 712.32

13 Brick jelly 20mm Adiyur 12 cu.m. 707.00 77.32 784.32

14 Gravel Local 1 cu.m. 188.00 9.62 197.62

15 Shell lime Pollachi 350 cu.m. 1248.00 1425.20 2673.20

16 Slacked lime Pollachi 350 cu.m. 919.00 1425.20 2344.20

17 Pressed tiles Thiruppathur 7 1000 10400.00 75.74 10475.74


200x200x20mm Nos
Certificate shall be issued to the effect that the lead particulars furnished above are correct to
the best of his knowledge and belief and the rates adopted are based on the current Schedule
of Rates for the year 2018-2019.

12
ARULMIGU CHENNAKESAVAPERUMAL THIRUKOIL AT
YELAGIRI VILLAGE TIRUPATTUR TALUK AND VELLORE
DISTRICT
Name of work : RENOVATION OF THIRUKOIL
DATA
Sl. Qty. Unit Description Rate in Per Amount in
No. rupees rupees
SUB DATA
1 CEMENT MORTAR 1:2
720.00 KG Cement 5530.00 MT 3981.60
1.00 cu.m. Sand for morter 534.85 cu.m. 534.85
1.00 cu.m. Mixing charges 65.90 cu.m. 65.90
Rate for 1 cu.m. 4582.35
2 CEMENT MORTAR 1:3
480.00 KG Cement 5530.00 MT 2654.40
1.00 cu.m. Sand for morter 534.85 cu.m. 534.85
1.00 cu.m. Mixing charges 65.90 cu.m. 65.90
Rate for 1 cu.m. 3255.15
3 CEMENT MORTAR 1:4
360.00 KG Cement 5530.00 MT 1990.80
1.00 cu.m Sand for morter 534.85 cu.m. 534.85
1.00 .cu.m Mixing charges 65.90 cu.m. 65.90
. Rate for 1 cu.m. 2591.55
4 CEMENT MORTAR 1:5
288.00 KG Cement 5530.00 MT 1592.64
1.00 cu.m. Sand for morter 534.85 cu.m. 534.85
1.00 cu.m. Mixing charges 65.90 cu.m. 65.90
Rate for 1 cu.m. 2193.39
6 COMBINATION MORTAR 1:1:4
360.00 KG Cement 5530.00 MT 1990.80
1.00 cu.m. Sand for morter 534.85 cu.m. 534.85
1.00 cu.m. Mixing charges 65.90 cu.m. 65.90
0.25 cu.m. Lime 2673.20 cu.m. 668.30
1.00 cu.m. Grinding charges 210.40 cu.m. 210.40
2.00 KG Gallnut 80.00 cu.m. 160.00
1.00 KG Jaggery 50.00 cu.m. 50.00
Rate for 1 cu.m. 3680.25
1 Earth work excavation for foundation in all soils and sub-soils and to
full depth as may be directed except in rock requiring blasting inclusive of
shoring shuttering, bailing out water wherever necessary and depositing the
surplus earth within the compound in places shown by the departmental
officers with an initial lead of 10 mts and initial lift of 2 mts. and clearing and
levelling the site, etc., complete complying with standard specification.

Note: The cost of earth work excavation shall be calculated


based on the classifications of soils furnished in the trial pit
details appended with the estimates

1.00 cu.m. Earth work excavation 63.60 cu.m. 63.60


1.00 cu.m. Add 100% extra 63.60 cu.m. 63.60
0.33 cu.m. Refilling with 20.27 cu.m. 6.69
excavated earth
Rate for 1 cu.m. 133.89
2 Supplying and filling in foundation, basement, etc with filling sand in
layers of not more than 15 cm thick well watered, rammed and consolidated
etc. complete complying with standard specification and as directed by the
departmental officers.

1.00 cu.m. Cost of filling sand 517.31 cu.m. 517.31


1.00 cu.m. Refilling charges 19.50 cu.m. 19.50
Rate for 1 cu.m. 536.81
Cement Concrete 1:5:10 (One Cement, five sand and ten hard broken
stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation
including dewatering wherever necessary and laid in layers of not more than
15 cm thick well rammed, consolidated and curing etc. complete complying
with standard specification

9.00 cu.m. Broken stone Jelly - 1107.50 cu.m. 9967.50


4.50 cu.m. 40mm
Cementsize
mortar (1:4) 2591.55 cu.m. 11661.98
1.80 Nos. Mason II Class 567.00 Each 1020.60
17.70 Nos. Mazdoor I Class 508.00 Each 8991.60
14.10 Nos. Mazdoor II Class 320.00 Each 4512.00
Total for 10 cu.m. 36153.68
Rate for 1 cu.m. 3615.40
RR masonry in cm 1:5 using selected stones and bond in foundation
and basement including dewatering wherever necessary, proper setting , curing
etc all complete coplying with relavant standard specifications.
10.00 cu.m. Rough stone 563.33 cu.m. 5633.30
1.00 cu.m. Bond stone 567.00 cu.m. 567.00
3.40 cu.m. cm1:5 2193.39 cu.m. 7457.53
7.10 Nos. mason 1st class 567.00 Each 4025.70
10.60 Nos. mason 2nd class 508.00 Each 5384.80
14.10 Nos. Mazdoor I class 355.00 Each 5005.50
14.10 Nos Mazdoor II class 320.00 Each 4512.00
Rate for 10 Cum 32585.83
3258.60
11 Brick work in following Cement Mortar using best quality II class
Ground moulded bricks size 9" x 4-3/8" x 2-3/4" for foundation and basement
including curing, etc., complete complying with standard specifiction.

A In Cement Mortar 1:5


1300.00 Nos. Ground moulded bricks 6968.36 1000 Nos. 9058.87
9"x4-3/8"x2-3/4"

0.708 cu.m. Cement mortar 1:5 2193.39 cu.m. 1552.92


1.00 Nos. Mason I Class 567.00 Each 567.00
3.00 Nos. Mason II Class 508.00 Each 1524.00
2.00 Nos. Mazdoor I Class 355.00 Each 710.00
6.00 Nos. Mazdoor II Class 320.00 Each 1920.00
Total for 100 cft (or) 2.83168 cu.m. 15332.79
Rate for 1 cu.m. 5414.75
Rate for 1 cu.m.:
a For foundation & 5414.75 5414.75
b basement
In Ground floor 5414.75 44.80 5459.55
c In First floor 5459.55 90.30 5549.85
d In Second floor 5549.85 90.30 5640.15
e In Third floor 5640.15 90.30 5730.45
f In Fourth floor 5730.45 90.30 5820.75
g In Fifth floor 5820.75 90.30 5911.05
C In Cement Mortar 1:3
1300.00 Nos. II class table moulded 6968.36 1000 9058.87
bricks 9"x4-3/8"x2-
3/4"
0.708 cu.m. Cement mortar 1:3 3255.15 cu.m. 2304.65
1.00 Nos. Mason I Class 567.00 Each 567.00
3.00 Nos. Mason II Class 508.00 Each 1524.00
2.00 Nos. Mazdoor I Class 355.00 Each 710.00
6.00 Nos. Mazdoor II Class 320.00 Each 1920.00
Total for 100 cft (or) 2.83168 cu.m. 16084.51
Rate for 1 cu.m. 5680.25
Rate for 1 cu.m.:
a For foundation & 5680.25 5680.25
b basement
In Ground floor 5680.25 44.80 5725.05
c In First floor 5725.05 90.30 5815.35
d In Second floor 5815.35 90.30 5905.65
e In Third floor 5905.65 90.30 5995.95
f In Fourth floor 5995.95 90.30 6086.25
11 Special ceiling plastering and finishing the exposed surface of all RCC
items of work such as slabs, beams, sunshades, facia, canopy slab, staircase
waist slab, landing slab etc., with Cement Mortar 1:3 (One Cement and Three
Sand) 10mm thick including hacking the surfaces, providing cement mortar
nosing, beading for sunshades, staircases, steps, landing slabs and curing, etc.,
in all floors complying with standard specification and as directed by the
departmental officers

0.10 cu.m. Cement mortar 1:3 3255.15 cu.m. 325.52


1.10 Nos. Mason I Class 567.00 Each 623.70
1.10 Nos. Mazdoor I Class 355.00 Each 390.50
1.10 Nos. Mazdoor II Class 320.00 Each 352.00
Total for 10 sq.m. 1691.72
Rate for 1 sq.m. 169.20
12 Plastering with Cement Mortar 1:5 (One cement and Five sand), 12mm
thick in all floors including curing etc. complete complying with standard
specification and as directed by the departmental officers.
0.14 cu.m. Cement mortar 1:5 2193.39 cu.m. 307.07
1.10 Nos. Mason I Class 567.00 Each 623.70
0.50 Nos. Mazdoor I Class 355.00 Each 177.50
1.10 Nos. Mazdoor II Class 320.00 Each 352.00
Total for 10 sq.m. 1460.27
Rate for 1 sq.m. 146.05
13 Weathering course in brick jelly lime concrete using broken brick
jelly of size 20mm uniform gauge in pure slaked lime (no sand to be used) to
the proportion of brick jelly to lime being 32:12.5 by volume and laid over the
RCC roof slab in a single layer of required slope and finished by beating the
concrete with wooden beaters of approved pattern, keeping the surface
constantly wet by sprinkling lime jaggery water, etc., complete as per standard
specification and as directed by the deparmental officers.

12.80 cu.m. Brick Jelly (20mm 712.32 cu.m. 9117.70


5.00 cu.m. gauge)
Slaked lime 2673.20 cu.m. 13366.00
1.80 Nos. Mason I Class 567.00 Each 1020.60
17.70 Nos. Mazdoor I Class 355.00 Each 6283.50
14.10 Nos. Mazdoor II Class 320.00 Each 4512.00
LS Sundries for wooden LS 133.66
beaters, lime
Total for 10 cu.m. jaggery 34433.46
water Rate for 1 cu.m. 3443.40
a In foundation & 3443.40
b basement
For Ground floor 3443.40 61.84 3505.24
c For First floor 3505.24 82.10 3587.34
d For Second floor 3587.34 82.10 3669.44
e For Third floor 3669.44 82.10 3751.54
f For Fourth floor 3751.54 82.10 3833.64
g For Fifth floor 3833.64 82.10 3915.74
14 Finishing the top of roof with one course of machine pressed tiles of size
200mm x 200mm x 20mm of approved quality set in Cement Mortar 1:3 (One
Cement and Three Sand) 12mm thick mixed with water proofing compound
conforming to ISS at 2% by weight of cement used and the joints pointed
neatly to full depth of tiles with the same cement mortar mixed with red oxide
and water proofing compound including curing etc., complete complying with
standard specification and as directed by the departmental officers

Sub-Data for Pointing


with Cement Mortar
0.04 cu.m. Cement Mortar 1:3 3255.15 cu.m. 130.21
1:3
0.384 Kg Water Proofing 43.20 Kg 16.59
2.20 Nos. Compound
Mason II Class 508.00 Each 1117.60
0.50 Nos. Mazdoor I Class 355.00 Each 177.50
1.10 Nos. Mazdoor II Class 320.00 Each 352.00
LS Add for red oxide etc., 6.51
Total for 10 sq.m. 1800.41
Rate for 1 sq.m. 180.04
Main Data
250.00 Nos. Pressed Tiles of 2344.20 1000 586.05
200mm x 200mm x
20mm
0.12 cu.m. Cement Mortar 1:3 3255.15 cu.m. 390.62
10.00 sq.m. Pointing with Cement 180.04 sq.m. 1800.41
1.152 Kg Mortar
Water 1:3 Proofing 43.20 Kg 49.77
1.10 Compound
Nos. Mason I Class 567.00 Each 623.70
2.10 Nos. Mason II Class 508.00 Each 1066.80
2.20 Nos. Mazdoor I Class 355.00 Each 781.00
1.10 Nos. Mazdoor II Class 320.00 Each 352.00
Total for 10 sq.m. 5650.34
Rate for 1 sq.m. 565.10
21 Supplying and fixing mild steel grill Gate including cost conveyance of
all materials and fixing in position including priming coat etc complete with
standard specifications.
As per S.S.R s.no 161 /
P-21
As per S.S.R s.no 168 / 65.00 Kg 65.00
P-32 13.20 Kg 13.20
Rate for 1 Kg 78.20
43 Plastering with Cement Mortar 1:4 (One cement and Four sand), 20mm
thick in all floors including curing etc. complete complying with standard
specification and as directed by the departmental officers.

0.22 cu.m. Cement mortar 1:5 2193.39 cu.m. 482.55


2.20 Nos. Mason I Class 567.00 Each 1247.40
0.50 Nos. Mazdoor I Class 355.00 Each 177.50
3.20 Nos. Mazdoor II Class 320.00 Each 1024.00
Total for 10 sq.m. 2931.45
Rate for 1 sq.m. 293.15
22 Supplying and painting the walls with two coats of cement paint over one
coat of cement primer as instructed by the departmental officers including
preparation of surface curing, etc., complete in all floors complying with
standard specifications (The colour and shade of the cement paint shall be got
approved by the Executive Engineer before use of work).

For basic one coat of


primer with cement
paint
10.00 sq.m. Cleaning the plastered 4.20 sq.m. 42.00
1.80 Kg surface
Cement Paint 46.20 Kg 83.16
0.25 Nos. Painter I Class 454.00 Each 113.50
0.25 Nos. Mazdoor I Class 355.00 Each 88.75
0.40 Nos. Mazdoor II Class 320.00 Each 128.00
LS Sundries for brushes, LS 4.16
etc.
Rate for 10 sq.m. 459.57
Rate for 1 sq.m. 46.00
For finishing two coats
3.23 Kg Cement Paint 42.04 Kg 135.79
0.50 Nos. Painter I Class 454.00 Each 227.00
0.50 Nos. Mazdoor I Class 355.00 Each 177.50
0.80 Nos. Mazdoor II Class 320.00 Each 256.00
LS Sundries for brushes, LS 13.58
etc.
Rate per 10 sq.m. 809.87
Rate per 1 sq.m. 81.00
Main Data
1.00 sq.m. Basic one coat of 46.00 46.00
primer with cement
paint
1.00 sq.m. For finishing two coats 81.00 81.00
with cement paint
Rate per 1 sq.m. 127.00
14 Painting new iron works such as steel doors, windows, ventilators,
window bars, balustrades etc., with two coats of best approved first quality and
colour of synthetic enamel paint over the existing red oxide priming coat in all
floors excluding cost of priming coat etc., complete complying with standard
specification. (The make, quality and colour of paint should be got approved
by the Executive Engineer before use on works.)

Main data
2.22 Litre Ready mixed enamel 211.00 Litre 468.42
1.10 Nos. paint
Painter I Class 454.00 Each 499.40
l.s Sundries for brushes, 2.18
soap, putty, etc.

Total for 10 sq.m. 970.00


Rate for 1 sq.m. 97.00
13 Painting two coats of newly plastered wall surface with water based
exterior emulsion paint of first class quality and of approved colour over a
priming coat including thorough scrapping, clean removal of dirt, and
including necessary plaster of paris putty, wherever required etc., complete
complying with standard specification.

10.00 sq.m. Cleaning the plastered 4.20 sq.m. 42.00


1.40 Litre surface
water based exterior 274.00 Litre 383.60
0.98 Litre emulsion
Primer paint 136.50 Litre 133.77
Nos. Painter I Class 454.00 Each #VALUE!
LS Sundries for brushes, LS 4.83
sand paper, plaster of
paris putty, etc.
Total for 10 sq.m. #VALUE!
Rate for 1 sq.m. #VALUE!
15 Providing vargapoochu over the core walls of vimanam/ gopuram with
CM 1:1:4 complete including shaping the mukapathiram, maha nasi, koou all
ornamaental works to proper shape by embedding broken bricks or shaped
chiseled bricks rough plastering with cement mortar 1:4 and finishing with
final ornamental plastering and nayam threervai including cost and
conveyance of all matrials labour therefore , lifting of materials all working in
heights curing with water etc. compltete including all extra for folding and
including clearing the debris from vimanam/ gopuram.

for kalkaram of
vimanam/ gopurams
shaping in vargams

8.00 Nos. Ground moulded bricks 6046.10 1000 Nos. 48.37


9'x4-3/8"x2-3/4"

1.000 Cft Combination mortar cu.m. 0.00


1:1:4
2.00 Nos. Silpi vargapoochu I 310.00 Each 620.00
class
vargapoochu
0.350 cu.m. Combination mortar 3680.25 cu.m. 1288.09
1:1:4
4.00 Nos. Silpi vargapoochu I 1000.00 Each 4000.00
class
3.00 Nos. Silpi vargapoochu II 1000.00 Each 3000.00
class
4.00 Nos. Asst silpi 800.00 Each 3200.00
4.00 Nos. Mazdoor I Class 355.00 Each 1420.00
2.00 Nos. Mazdoor II Class 320.00 Each 640.00
nayam theervai
0.06 cu.m. sand 534.85 cu.m. 31.02
0.06 cu.m. screening of sand 10.00 cu.ft 0.60
35.00 kg cement 5530.00 Mt 193.55
3.00 Nos. Silpi vargapoochu I 1000.00 Each 3000.00
class
1.00 Nos. Mazdoor helper I Class 355.00 Each 355.00

curing wastages of 3.37


materials clearing
debris etc.,
rate for 100sqft 17800.00
rate for 1sqft 178.00
5906.08 ###

5257.60 1.11

### 0.70

369.13 ### 10.00

545.60 7896.00

308.27 ###
1223.00

SI 9

0.70

10.00
32586.45

0.85061
5.00
PAINTING ONE COATS OVER OLD

IRON WORKS WITH IIND CLASS

Lit READY MIX #REF! Lit #REF!

nos PAINTER I #REF! nos #REF!

Sqm Thorouh sc 3.55 Sqm 35.50

SUNDRIESLS 1.90

RATE #VALUE!
PER SQM

WOOD WORKS WITH IIND CLASS

SYNTHETIC ENAMEL PAINT

nos PAINTER I #REF! nos #REF! #REF!

Sqm Thorouh sc 3.80 Sqm 38.00


ARULMIGU CHENNAKESAVAPERUMAL THIRUKOIL AT
YELAGIRI VILLAGE TIRUPATTUR TALUK VELLORE
DISTRICT
NAME OF WORK: RENOVATION OF THIRUKOIL
ARULMIGU CHENNAKESAVAPERUMAL THIRUKOIL is about 7km from
jolarpet junction and about 10 km from tirupattur town. This thirukoil is about 300
years of old constructed with stone work

The ground level is above the sannathy floor level and hence the rain water
enters in to the sannathy during rainy seasons. Hence it disturbes the devotees during
puja times. Now a doner come to renovate this thirukoil at his own expenditure. Further
the local peoples are also intrusted in constucting a GOPURAM over moolavar
sannathy. The temple autharities have disided to renovate the thirukoil after getting
permission from the department.
The following provisions are made in this estimate
Provision is given for dismantling the existing weathering course and tiles with
parapet wall
Provision is given for Documenting the stone structure,Numbering ,removing
and stacking for reuse such as wall stones piller pavukkal etc
Provision is given for earth work excavation for foundation, sand filling and
foundation concrete 1:5:10 using 40 mm metal
Provision is given for laying Rrmasonry in cm 1:4 using selected stones
Provision is given for refixing the existing wall stones , piller, pothiyal ,uthiram,
pavukkal in its original position
Provision is given for raising wall height to additional ht of 1' 03/4" with new stones
Provision is also given for constucting gopuram with varga brick work and
vargapoochu to have temple structure
Provision is also given for painting the thirukoil with exterior water based
emulsion over vargapoochu and plastering
The estimate is prepared based on current sheduled of rate for the year 2017-18.
The estimate amount worksout to Rs .The estimate proposal my be
approved