Académique Documents
Professionnel Documents
Culture Documents
ork Order No # :
Length Width
S.No Discription Unit Qty Sides
(Ft) (Ft)
4 1227.073 374.11
Extra Dismantling of Watch Towers
a Back New Tower no 01 Dismanting
i Wall 1 6
ii Wall 1 6
iii Column of Wall 1 1.5
iv Roof Shed 1 9.5
v Back Wall 1 6.5
b Back Old Tower no 02 Dismantling
i Walls 2 6
ii Boundray Wall 1 12.5
iii Boundary Wall 1 13.5
iv Roof Shed 2 9.5 2
c Old Tower no 04 Near Water Tank
i Walls 2 6
ii Roof Shed 2 9.5 2
1.02 Excavtion
1 Watch Tower Footing 2 11 11
2 Boundary Wall
Page 1 of 72
itle of Project : : Misc C
ork Order No # :
Length Width
S.No Discription Unit Qty Sides
(Ft) (Ft)
ii Double Column 19 5.17 5.17
Deduction
i Double Column 19 5.17 2
ii Single Column 90 4.67 2
1.06 CC 1:4:8
1 1) Watch Tower for Footing 2 11 11
2
Watch Tower no 01 for Plitnth Protection
i 2 9.5 3.25
ii 1 9.33 3.25
Page 2 of 72
itle of Project : : Misc C
ork Order No # :
Length Width
S.No Discription Unit Qty Sides
(Ft) (Ft)
3
Watch Tower no 03 for Plitnth Protection
i 1 9.5 3.25
ii 1 9.33 3.25
4 Double Column Footing 19 5.17 5.17
5 Single Column Footing 89 4.67 4.67
6 Extra 1:4:8 for Trunch Nala 1 6.33 3.67
1.07 CC 1:3:6
1
Boundary Wall (N+S+W)
i South side 1 408.26 0.75
ii West Side 1 536.993 0.75
2 North Side 1 154.82 0.75
Back Side Wall with New Watch tower no 01 Railway
3
Side
i 1 394.33 0.75
ii 1 6 0.75
4 For New Watch Tower Flooring 2 7.5 7.5
1.08 CC 1:2:4
Footing
Single Column Footing 89 4 4
Double Column 19 4.67 4.67
Columns
Column Footing to Top Beam 127 1 1.5
4 Plinth Beam
i South side 1 400.8 0.75
ii West Side 1 522.0 0.75
iii North Side 1 154.8 0.75
5 Tie Beam
i South side 1 393.3 0.75
ii West Side 1 522.0 0.75
iii North Side 1 128.8 0.75
6 Coping Beam
i South side 1 393.3 1
Page 3 of 72
itle of Project : : Misc C
ork Order No # :
Length Width
S.No Discription Unit Qty Sides
(Ft) (Ft)
ii West Side 1 522.0 1
iii North Side 1 128.8 1
7 Extra For Trunch Nala
i Bed for water crossing 1 6.5 3
9
9) Extra for Watch Tower Changing
a
Railway and Back Wall Corner Watch Tower no 01
i Footing for Column 1 4 4
ii Column 1 0.75 0.75
iii Corner Column 1 1 1.5
iv 2 X 2 6.5 0.75
1st Roof Beam and 2nd Roof Beams
v 2 6 0.75
vi Slab 1st 1 6.5 7.5
vii Slab 2nd 1 6.5 9
Watch Tower Near Water Tank no 04
b
i 1st and 2nd Roof Beams 4 X 2 4.75 0.75
ii 2 13.5 0.75
iii 2 12.5 0.75
iv 1st Slabs 1 13.5 5.5
v 1 7.5 5.5
vi 2nd Slabs 1 15.5 5.5
vii 1 9.5 5.5
c
Watch Tower no 02 School and Back Old Tower
i Columns 3 Nos 3 1.5 1
ii 1st and 2nd Roof Beams 4 X 2 4.75 0.75
Page 4 of 72
itle of Project : : Misc C
ork Order No # :
Length Width
S.No Discription Unit Qty Sides
(Ft) (Ft)
iii 2 13.5 0.75
iv 2 12.5 0.75
v 1st Slabs 1 13.5 5.5
vi 1 7.5 5.5
vii 2nd Slabs 1 15.5 5.5
viii 1 9.5 5.5
d Stair Footing 2 3.5 3
1.09 DPC
1 South side 1 400.8 0.75
i West Side 1 522.0 0.75
ii North Side 1 154.8 0.75
Page 5 of 72
itle of Project : : Misc C
ork Order No # :
Length Width
S.No Discription Unit Qty Sides
(Ft) (Ft)
i Back Side Wall 1 6 0.75
ii Sides and Front Walls 3 6 0.75
iii Due to Changing
a Side Boundary Wall 1 6 0.75
b Back Side Rebrick Work of Wall 1 5.5 0.75
6
Back Wall and School Side Wall Corner Watch Tower 02
i School Side Wall 1 11.5 0.75
ii Back Side Wall 1 10.5 0.75
iii Short Wall 2 4.75 0.75
Page 6 of 72
itle of Project : : Misc C
ork Order No # :
Length Width
S.No Discription Unit Qty Sides
(Ft) (Ft)
Sft 2 55.75
Sft 3 56
Page 7 of 72
itle of Project : : Misc C
ork Order No # :
Length Width
S.No Discription Unit Qty Sides
(Ft) (Ft)
School Side Wall Beam Bottom Side
6 1 592.58
9 1 441.33
Back Side Wall Beam Bottom Side
10 Column Sides Plaster 2 X 109 0.75
11 All Column Top Plaster 109 0.75 0.75
b Watch Tower
Back & Railway Side Corner Watch Tower no 01 Plaster
1
b
Watch Tower no 03 of School and Front Wall Coners
i Out Side Wall Plaster 2 7.5
ii Out Side Wall Plaster 2 7.5
iii Inside Wall Plaster 4 6
iv 1st and 2nd Roof Plaster 2 6 6
v 1st Roof Top Plaster 1 6 6
Page 8 of 72
itle of Project : : Misc C
ork Order No # :
Length Width
S.No Discription Unit Qty Sides
(Ft) (Ft)
vi 1st Roof Beam Plaster Inside 2 6
vii Column Plaster 4 0.75
viii Tie Beam Sides Plaster 2 X 2 7.5
ix Tie Beam Top & Bottom 2 X 2 7.5 0.75
x Plinth Beam Plaster 2 7.5
xi Floor Plaster 1 7.5 6.75
xii Back Wall Inside Plaster 2 7.5
xiii Shed Plaster Sides 2 9
ix 1 9 1.5
x 2 10
xi 1 7.5 1.5
Watch Tower no 04 of Front and Railway Side Wall
c
Coners
i Both Side Wall Plaster 2 13.5
ii Both Side Wall Plaster 2 12.5
iii Both Wall Both Side Plaster 2 X 2 5.5
iv 1st and 2nd Roof Plaster 2 13.5 5.5
v 2 7 5.5
vi 1st Roof Top Plaster 1 13.5 5.5
vii 1 7 5.5
ix Shed Plaster 2 5.5
x 2 5.5 1.5
d
Watch Tower no 02 of Back and School Side Wall Coners
i Both Side Wall Plaster 2 13.5
ii Both Side Wall Plaster 2 12.5
iii Both Wall Both Side Plaster 2 X 2 5.5
iv 1st and 2nd Roof Plaster 2 13.5 5.5
v 2 7 5.5
vi 1st Roof Top Plaster 1 13.5 5.5
vii 1 7 5.5
viii Shed Plaster 2 5.5
ix 2 5.5 1.5
Page 9 of 72
itle of Project : : Misc C
ork Order No # :
Length Width
S.No Discription Unit Qty Sides
(Ft) (Ft)
Page 10 of 72
itle of Project : : Misc C
ork Order No # :
Length Width
S.No Discription Unit Qty Sides
(Ft) (Ft)
ii Both Wall Outside 2 6.5
Watch Tower no 03 of School and Front Wall Corners
c
1.18
P/A Plastic Emulsion Watch Tower Paint
1
1-Back & Railway Side Corner Watch Tower Paint no 01
i Inside Wall Paint 2 6
ii 1st and 2nd Roof Paint 2 6 6
2 DUE TO CHANGING PAINT
i Wall Insides 1 7.5
Page 11 of 72
itle of Project : : Misc C
ork Order No # :
Length Width
S.No Discription Unit Qty Sides
(Ft) (Ft)
ii Wall Insides 2 6.5
iii 1st 2nd Roof 2 6.5 6
Watch Tower of School and Front Wall Corners 03
3
4
Watch Tower of Front and Railway Side Wall Corners 04
i Both Wall Insiede Paint 1 13.5
ii Both Wall Inside Paint 1 12.5
iii Both Wall Inside Paint 2 X 2 5.5
iv 1st and 2nd Roof Paint 2 13.5 5.5
v 2 7 5.5
5
Watch Tower of Back and School Side WallL Corners 02
i Both Wall Insiede Paint 1 13.5
ii Both Wall Inside Paint 1 12.5
iii Both Wall Inside Paint 2 X 2 5.5
iv 1st and 2nd Roof Paint 2 13.5 5.5
v 2 7 5.5
Mtr Mtr
Page 12 of 72
itle of Project : : Misc C
ork Order No # :
Length Width
S.No Discription Unit Qty Sides
(Ft) (Ft)
ii Single Footing -top 89 4 4 4
Columns
i Single 89 1 5 1
ii Double 19 1 7 1
vii 90 X 2 1 1
viii 90 X 2 1.5 1
3 For 1:3:6
i Front Wall With Watch Tower 2 163.5
ii 2 12.5
iii School Side Wall 2 592.58
iv Back Wall With Railway Side 2 441.33
v 2 7.5
Mtr
Page 13 of 72
itle of Project : : Misc C
ork Order No # :
Length Width
S.No Discription Unit Qty Sides
(Ft) (Ft)
Page 14 of 72
nt Sheet
Pakistan State Oil Company Limited
National Technical Services
Misc Civil Works at Quetta
Date :
Height Nos /
Ft3 Ft2 Ft M3 M2 M Kg
(Ft) Job
11 5007.86 465.41
11 6588.923 612.35
11 1901.02 176.67
8.5 51 4.74
6 36 3.35
6 9 0.84
2 19 1.77
4.5 29.25 2.72
7 84 7.81
6 75 6.97
6 81 7.53
38 3.53
7 84 7.81
38 3.53
Total Dismantling 1305.02
4 968 27.407
4 101.28 2.867
Page 15 of 72
Misc Civil Works at Quetta
Date :
Height Nos /
Ft3 Ft2 Ft M3 M2 M Kg
(Ft) Job
5.33 2706.84 76.637
0.5 15 0.425
Total Excavtion 403.535
1 29.04 0.822
2.17 525.14 14.868
Page 16 of 72
Misc Civil Works at Quetta
Date :
Height Nos /
Ft3 Ft2 Ft M3 M2 M Kg
(Ft) Job
2 612.39 17.3383
2 805.4895 22.8055
2 232.23 6.575
2 591.495 16.747
2 9 0.255
0.17 19.125 0.541
Total 1:3:6 64.2619
21 4000.50 113.264
Page 17 of 72
Misc Civil Works at Quetta
Date :
Height Nos /
Ft3 Ft2 Ft M3 M2 M Kg
(Ft) Job
0.5 260.9965 7.389
0.5 64.41 1.824
1 213.4178 6.042
0.75 106.515 3.016
1.33 95.76 2.711
1 72 2.039
1.5 24 0.680
23.67 13.314375 0.377
8 12 0.340
1 19.5 0.552
1 9 0.255
0.5 24.375 0.690
0.5 29.25 0.828
1 28.5 0.807
1 20.25 0.573
1 18.75 0.531
0.5 37.125 1.051
0.5 20.625 0.584
0.5 42.625 1.207
0.5 26.125 0.740
Page 18 of 72
Misc Civil Works at Quetta
Date :
Height Nos /
Ft3 Ft2 Ft M3 M2 M Kg
(Ft) Job
1 20.25 0.573
1 18.75 0.531
0.5 37.125 1.051
0.5 20.625 0.584
0.5 42.625 1.207
0.5 26.125 0.740
0.5 10.5 0.297
Total 1:2:4 331.919
300.57
391.49 36.38
116.12 10.79
4.5 0.42
9 0.84
Total DPC 48.43
58.5 5.44
22.5 2.09
29.25 2.72
20.25 1.88
Total Plinth Protection 12.13
14 120.75 3.42
14 110.25 3.12
6.5 46.3125 1.31
Page 19 of 72
Misc Civil Works at Quetta
Date :
Height Nos /
Ft3 Ft2 Ft M3 M2 M Kg
(Ft) Job
15.16 68.22 1.93
7 94.5 2.68
14 120.75 3.42
14 110.25 3.12
6.5 46.3125 1.31
18.00 117.00
18.50 1054.50
18.33 1012.73
18.17 1017.24
19.13 1079.03
18.96 1050.76
18.59 1022.18
17.92 1015.33
17.33 740.86
17.54 644.60
17.54 967.51
17.54 974.87
18.84 1042.14
19.63 1087.62
18.08 971.80
18.08 1013.98
18.08 1012.48
18.08 1020.07
Page 20 of 72
Misc Civil Works at Quetta
Date :
Height Nos /
Ft3 Ft2 Ft M3 M2 M Kg
(Ft) Job
18.08 2015.92
18.08 3037.44
17.79 945.72
17.83 990.99
17.83 692.34
: #VALUE!
18.54 1056.87
18.50 1022.21
18.42 1031.32
18.67 1053.36
18.83 1043.56
18.75 1031.25
18.25 1034.23
17.67 755.39
18.25 670.71
18.25 1006.70
18.25 1014.37
18.30 1012.72
17.25 956.08
17.45 937.76
17.45 978.46
17.45 977.01
17.45 984.34
17.45 1945.30
17.45 2931.04
18.58 987.71
18.38 1021.37
18.38 713.56
18.09 1465.18
1043.07
63.50
229.02
Page 21 of 72
Misc Civil Works at Quetta
Date :
Height Nos /
Ft3 Ft2 Ft M3 M2 M Kg
(Ft) Job
Page 22 of 72
Misc Civil Works at Quetta
Date :
Height Nos /
Ft3 Ft2 Ft M3 M2 M Kg
(Ft) Job
1 12 1.12
8.5 25.5 2.37
1.33 39.9 3.71
22.5 2.09
2 30 2.79
50.625 4.70
8.5 127.5 11.85
0.5 9 0.84
13.5 1.25
0.5 10 0.93
11.25 1.05
135 12.55
0.00
0.00
74.25 6.90
38.5 3.58
Page 23 of 72
Misc Civil Works at Quetta
Date :
Height Nos /
Ft3 Ft2 Ft M3 M2 M Kg
(Ft) Job
0.00
81 7.53
0.00
0.00
74.25 6.90
38.5 3.58
Total Water Proofing 41.03
20 150 13.94
9.5 213.75 19.87
8 16 1.49
1 12 1.12
3.33 9.99 0.93
1.33 39.9 3.71
22.5 2.09
2 30 2.79
8.5 63.75 5.92
0.5 9 0.84
27 2.51
0.5 10 0.93
11.25 1.05
20 150 13.94
Page 24 of 72
Misc Civil Works at Quetta
Date :
Height Nos /
Ft3 Ft2 Ft M3 M2 M Kg
(Ft) Job
8 104 9.67
20 300 27.88
9.5 142.5 13.24
8 96 8.92
1 12 1.12
8.5 25.5 2.37
1.33 39.9 3.71
22.5 2.09
2 30 2.79
8.5 127.5 11.85
0.5 9 0.84
13.5 1.25
0.5 10 0.93
11.25 1.05
20 270 25.09
20 250 23.23
8 88 8.18
0.5 5.5 0.51
16.5 1.53
12 162 15.06
12 150 13.94
8 96 8.92
72 6.69
20 150 13.94
Page 25 of 72
Misc Civil Works at Quetta
Date :
Height Nos /
Ft3 Ft2 Ft M3 M2 M Kg
(Ft) Job
8 104 9.67
78 7.25
8 192 17.84
72 6.69
20 270 25.09
20 250 23.23
8 176 16.36
148.5 13.80
77 7.16
20 7.85 39.25
8 7.85 19.15
18.8 343.66
3.39 72.23
3.39 68.18
49.74 300.38
Total of Installation of Steel Ladders 842.86
80 7.43
200 18.59
152.16 14.14
2136.00 198.51
Page 26 of 72
Misc Civil Works at Quetta
Date :
Height Nos /
Ft3 Ft2 Ft M3 M2 M Kg
(Ft) Job
5696.00 529.37
513.00 47.68
1539.00 143.03
445.00
133.00
4400.29
180 16.73
270 25.09
2 654 60.78
2 50 4.65
2 2370.32 220.29
2 1765.32 164.06
2 30 2.79
Total Bitumen PB-4 1453.14
421 128.32
580 176.70
148 44.98
Total 1148 349.99177
1
1 205
1 290
1 70.05
Total 565
Page 27 of 72
Misc Civil Works at Quetta
Date :
Height Nos /
Ft3 Ft2 Ft M3 M2 M Kg
(Ft) Job
149.8
400
149.8
20
105.2
2
3
3
10
6
2
2
2
Page 28 of 72
NTS
1 Watch Tower
Footing main bar T/B & Both way 1/2" 6" 23 4 12.75 1173 0.302 354.246 kg 9" 9"
11'-3"
11'-6"
2
Vertical Bar Long for Column 5/8" 4 4 9.75 156 0.472 73.632 kg
up to Plinth beam 8'-9''
1'-00''
Prepared By ;Hafiz
NTS
Prepared By ;Hafiz
NTS
6''
3 Plinth Beam
bootom& Top 1/2" 5 4 9.75 195 0.302 58.89 kg 1'-3" 1'-3"
7'-3''
6"
4 Vertical Bar Long for Column
up to 1st Roof 5/8" 4 4 12.5 200 0.472 94.4 kg
12'-3"
6"
5 Bracing Beam
Bottom&Top 5/8'' 6" 12 4 12.75 612 0.472 288.864 kg 4'' 4''
7'-3"
Rings for Bracing Beam 3/8'' 6'' 12 4 2.5 48 0.17 8.16 kg 6" 3"
Prepared By ;Hafiz
NTS
6"
Prepared By ;Hafiz
NTS
6 1st Roof Beam 5/8'' 6" 3 4 9.75 117 0.472 55.224 kg 1'-3'' 1'-3''
Bottom Bar
7'-3"
1st Roof Beam 1/2'' 6" 2 4 9.75 78 0.302 23.556 kg 1'-3'' 1'-3''
Top Bar
1'
10 Vertical Steel For Door Slab Wall
1/2'' 4'' 7 2 2.5 35 0.302 10.57 kg
2.5
M.S Chairs
1/2'' 1 4 3 3.5 42 0.302 12.684 kg 1' 1'
3'' 3''
1'
11 Vertical Bar Long for Column
up to 2nd roof bean 5/8" 4 4 15.33 245.28 0.472 115.7722 kg
14'-4"
Prepared By ;Hafiz
NTS
Prepared By ;Hafiz
NTS
6''
Lintel Beam
12
1/2" 4 4 6 96 0.302 28.992 kg
6'
3''
7'-3''
6"
Prepared By ;Hafiz
NTS
10'-6"
M.S Chairs
1/2'' 1 4 3 3.5 42 0.302 12.684 kg 1' 1'
3'' 3''
1'
15 Extra bars all sides
3/8" 6" 4 21 8.33 699.72 0.17 118.9524 kg 4" 8'
10'-3"
17 Extra bars all Cornors bars
3/8" 6" 4 4 9 144 0.17 24.48 kg
9'
1940.162
Prepared By ;Hafiz
Misc. Civil Works at Quetta Depot (PO# 4110020110)
M/s.National Technical Services
Services
Sub Total
Add PST 6%
Total
Sub Total
Add PST 8%
Total
Material
2 CABLE 4 C-6 sq.mm PVC/PVC 400.00 M 854.50
3 CABLE 1 C-6 sq.mm PVC/PVC 20 M 170.90
4 CONDUIT GI 1"dia (M G) 100 M 256.41
5 Distribution Board 2 SET 64,957.26
6 Deformed Steel Bars 31,100.00 KG 94.02
7 Miscellaneous Steel structure 1,000.00 KG 106.82
8 Miscellaneous Steel structure 2,500.00 KG 106.84
9 Miscellaneous Steel structure 250 KG 106.84
10 Barbed Wire size12SWG 405 M 854.70
Sub Total
Add GST 17%
Total -B
Grand Total
2nd R/Bill Paid
Total
B Services
Payable SST
110)
5,048,648.56 5,048,648.56
403,891.88 403,891.88
5,452,540.45 5,452,540.45
17,766,195.47 17,766,073.54
14,785.73 14,779.64
745,309.94 745,309.94
403,891.88 403,891.88
18,930,183.02 18,930,054.99
4,171,579.02 3,698,961.05
709,168.43 628,823.38
4,880,747.45 4,327,784.43
#REF!
#REF!
Amount excluding Amount Including
GST
GST GST
#REF!
#REF!
#REF!
Misc. Civil Works at Quetta Depot (PO# 4110020110)
M/s.National Technical Services
Services
Sub Total
Add PST 6%
Total
Sub Total
Add PST 8%
Total
Material
2 CABLE 4 C-6 sq.mm PVC/PVC 400.00 M 854.50
3 CABLE 1 C-6 sq.mm PVC/PVC 20 M 170.90
4 CONDUIT GI 1"dia (M G) 100 M 256.41
5 Distribution Board 2 SET 64,957.26
6 Deformed Steel Bars 31,100.00 KG 94.02
7 Miscellaneous Steel structure 1,000.00 KG 106.82
8 Miscellaneous Steel structure 2,500.00 KG 106.84
9 Miscellaneous Steel structure 250 KG 106.84
10 Barbed Wire size12SWG 405 M 854.70
Sub Total
Add GST 17%
Total -B
Grand Total
2nd R/Bill Paid
A GST invoice
Total
B Services
Payable SST
0)
5,095,049.71 5,048,648.56
407,603.98 403,891.88
5,502,653.69 5,452,540.45
24,487,573.79 17,766,073.54
14,785.73 14,779.64
1,145,808.57 745,309.94
407,603.98 403,891.88
26,055,772.06 18,930,054.99
QTY- GR Done in
last R/Bill
4,171,579.02 3,698,961.05
709,168.43 628,823.38
4,880,747.45 4,327,784.43
8,752,861.80 986,186.30
30,936.52
866,222.55
F/Bill QTY-
Total QTY- GR to be Balance Qty for GR & GI Reservation #
GR to be done done PO Qty
400.00 400.00 - 400.00
20.00 20.00 - 20.00
100.00 100.00 - 100.00
2.00 2.00 - 2.00
29,000.00 - 2,100.00 -
1,000.00 137.93 - 137.93
202.41 (753.00) 2,297.59 (753.00)
- - 250.00 -
400.00 - 5.00 -
#REF!
#REF!
#REF!
7,766,675.50
986186.3
#REF!
#REF!
119,451.63
-90
119,361.63
Misc. Civil Works at Quetta Depot (PO# 4110020110)
M/s.National Technical Services
Work Order
S.No. Item Rate Unit
Qty
Services
1.01 Dismantling 1,000.00 M2 201.33
1.02 Excavation 700 M3 56.74
1.03 Backfilling 175.00 M3 0.001
1.04 Earthfilling 500.00 M3 0.00
1.05 Stone Soling 3,000.00 M3 6.86
1.06 CC 1:4:8 7,500.00 M3 5
1.07 CC 1:3:6 10,000.00 M3 0.001
1.08 RCC 1:2:4 15,000.00 M3 0
1.09 P/L DPC 1,000.00 M2 0.00
1.10 P/L Plinth Protection 1,300.00 M2 0.001
1.11 Installation of Deformed Steel Bars 20.00 KG 0.001
1.12 Block/Brick Masonry 11,000.00 M3 0.001
1.13 P/A Plaster 1/2" thick 500.00 M2 0.001
1.14 P/A Plaster 3/4" thick 600.00 M2 0.001
1.15 Roof Water Proofing 1,500.00 M2 0.001
1.16 P/A Enamel Paint 325.00 M2 0.001
1.17 P/A Weather Shield Paint 420.00 M2 0.001
1.18 P/a Plastic Emulsion Paint 425.00 M2 0.001
1.19 Installation of Steel Ladder 75.00 KG 0.001
1.20 UPVC Pipe 700.00 M 0.001
1.21 Aluminium Windows 13,500.00 M2 0.001
1.22 Bitumen PB-4 375 M2 0.001
1.23 Solid Flush Door 10,000.00 M2 0.001
1.24 Steel Chohkat 1,200.00 M 0.001
1.25 Installation of Barbed Wire 200.00 M 0.001
1.26 Installation of Angle Iron 70.00 KG 0.001
1.27 PVC/Vapor barrier polyethene sheet 200 M2 0.001
1.28 Fabrication&Installation of Steel Gate 100.00 KG 0.001
1.29 Termite Proofing 300.00 M2 0.001
1.30 Excavation for Cables 700.00 M3 0.001
1.31 Laying of Cables 100.00 M 0.001
1.32 Backfilling for Cables 700.00 M3 0.001
1.33 Laying of Cable 50.00 M 0.001
1.34 Installation of GI Pipe 200.00 M 0.001
1.35 Installation of DB 12,000.00 JOB 0.001
1.36 Wiring for 5A 3pin Switch Socket 2,800.00 EA 0.00
1.37 P/I 20A TP MCB 5KA 2,800.00 EA 0.001
1.38 Wiring for Single Light Point 2,000.00 EA 0.001
1.39 Wiring from Distribution Board 2,000.00 EA 0.001
1.40 Bracket Fan 18" dia 15,000.00 EA 0.001
1.41 Light 2,300.00 EA 0.001
1.42 Energy Savers 1,500.00 EA 0.001
Sub-Total
ST 5%
Total(Services)
Services
11.01 Dismantling 990.57 M2 778.584
11.02 Excavation 693.40 M3 313.26
11.03 Backfilling 173.35 M3 220
11.04 Earthfilling 495.28 M3 20
11.05 Stone Soling 2,971.70 M3 43.14
11.06 CC 1:4:8 7,429.25 M3 45.47
11.07 CC 1:3:6 9,905.66 M3 60
11.08 RCC 1:2:4 14,858.49 M3 380
11.09 P/L DPC 990.57 M2 105
11.10 P/L Plinth Protection 1,287.74 M2 20
11.11 Installation of Deformed Steel Bars 19.81 KG 31,100.00
11.12 Block/Brick Masonry 10,896.23 M3 400.00
11.13 P/A Plaster 1/2" thick 495.28 M2 150
11.14 P/A Plaster 3/4" thick 594.34 M2 4,560
11.15 Roof Water Proofing 1,485.85 M2 21
11.16 P/A Enamel Paint 321.93 M2 25
11.17 P/A Weather Shield Paint 416.04 M2 4,560
11.18 P/a Plastic Emulsion Paint 420.99 M2 30
11.19 Installation of Steel Ladder 74.29 KG 1,000.00
11.20 UPVC Pipe 693.40 M 14
11.21 Aluminium Windows 13,372.64 M2 20
11.22 Bitumen PB-4 371.46 M2 1,475
11.23 Solid Flush Door 9,905.66 M2 4
11.24 Steel Chohkat 1,188.68 M 11
11.25 Installation of Barbed Wire 198.11 M 405
11.26 Installation of Angle Iron 69.34 KG 2,500.00
11.27 PVC/Vapor barrier polyethene sheet 198.11 M2 12
11.28 Fabrication&Installation of Steel Gate 99.06 KG 250
11.29 Termite Proofing 297.17 M2 50
11.30 Excavation for Cables 693.40 M3 70
11.31 Laying of Cables 99.06 M 400
11.32 Backfilling for Cables 693.40 M3 70
11.33 Laying of Cable 49.53 M 20
11.34 Installation of GI Pipe 198.11 M 100
11.35 Installation of DB 11,886.79 JOB 2
11.36 Wiring for 5A 3pin Switch Socket 2,773.58 EA 2
11.37 P/I 20A TP MCB 5KA 2,773.58 EA 2
11.38 Wiring for Single Light Point 1,981.13 EA 6
11.39 Wiring from Distribution Board 1,981.13 EA 6
11.40 Bracket Fan 18" dia 14,858.49 EA 3
11.41 Light 2,278.30 EA 2
11.42 Energy Savers 1,485.85 EA 2
Sub-Total
ST 6%
Total(Services)
Sub-Total
ST 8%
Sub Total (Services)
Sub Total Services
ST 5%
ST 6%
ST 8%
Total Services
SUPPLY OF MATERIALS
2 CABLE 4 C-6 sq.mm PVC/PVC 854.50 M 400.00
3 CABLE 1 C-6 sq.mm PVC/PVC 170.90 M 20
4 CONDUIT GI 1"dia (M G) 256.41 M 100
5 Distribution Board 64,957.26 SET 2
6 Deformed Steel Bars 94.02 KG 31,100.00
7 Miscellaneous Steel structure 106.82 KG 1,000.00
8 Miscellaneous Steel structure 106.84 KG 2,500.00
9 Miscellaneous Steel structure 106.84 KG 250
10 Barbed Wire size12SWG 854.70 M 405
Sub-Total
GST 17%
Total (Materials)
- 352 342,223.59
- 97 66,014.25
- 50 8,506.99
- 20 9,722.16
- 10 29,166.69
- 20 145,833.43
- 20 194,444.44
- 100 1,458,333.28
- 40 38,889.04
- 20 25,277.86
- 9576 186,187.59
- 140 1,497,222.71
- 150 72,916.22
- 962 561,167.02
- 42 61,250.04
- 67 21,169.88
- 2490 1,016,755.53
- 215 88,836.69
- 845 61,612.55
- 0.1 68.06
- 0.1 1,312.50
- 275 100,259.81
- 5 48,611.11
- 12 14,000.01
- 365 70,971.07
- 765 52,062.78
- 0.1 19.44
- 0.1 9.72
- 0.1 29.17
- 150 102,083.89
- 400 38,890.22
- 150 102,083.89
- 20 972.26
- 106 20,610.78
- 2 23,333.33
- 3 8,166.65
- 3 8,166.65
- 10 19,444.42
- 6 11,666.65
- 2 29,166.67
- 2 4,472.22
- 2 2,916.67
- 6,544,847.92
- 523,587.83
- 7,068,435.76
19,392,524.08 19,269,623.48
14,785.73 14,785.73
1,145,808.57 745,743.66
- 523,587.83
20,553,118.38 20,553,740.71
4,171,579.02 4,167,519.07
709,168.43 708,478.24
4,880,747.45 4,875,997.31
25,433,865.83 25,429,738.02