Vous êtes sur la page 1sur 78

Sports Complex Phase-VI, DHA, Lahore Cantt.

GROUNDS & INTERNAL WORKS


CIVIL WORKS - Rate Analysis

Civil Works
1- EARTH WORKS
BOQ REF Excavation for foundations for walls and columns in all kind of soil and back filling the excavated
# 1.1 material including breaking clods, watering, compaction in layers not exceeding 9" in depth to full
compaction, dressing and disposal of surplus excavated stuff complete as per drawings,
EXCAVATION WORK
Unit / Cft.
S.# Description Qty Unit Rate Amount
LABOUR
1
Labour cost of excavation i/c dressing 1 Cft. 7 7.00
2 Shafting of Material 1 Cft. 2 2.00
Total 9.00

Labour 9.00

Sub Total (a) 9.00

Add 25 % Overhead Charges 25 2.25

Sub Total (b) 2.25

Grand Total 11.25

Rate /Cft. Rs. = 11.25

Civil Works
1- EARTH WORKS
BOQ REF Supply earth from approved sources including digging, loading and unloading and filling
# 1.2 including dressing, watering and consolidation by ramming in layers not exceeding 9" in depth to
full compaction complete as per drawings, specification and as directed by the Engineer Incharge.
EARTH FILLING
Unit / Cft.
S.# Description Qty Unit Rate Amount
LABOUR & MATERIAL
1 Supplying of Earth Material Only 1 Cft. 15 15.00
2 Water 2 ltr 0.15 0.30
3 Labor for filling & Spreading 1 Cft. 2.7 2.70
4 Labor for Watering & Compaction 1 Cft. 1.25 1.25
Total 19.25

Labour 19.25

Sub Total (a) 19.25

Add 25 % Overhead Charges 25 4.81

Sub Total (b) 4.81


Grand Total 24.06

Rate /Cft. Rs. = 24.06


Civil Works
2- TERMITE CONTROL TREATMENT
BOQ REF Providing, mixing and spraying anti termite solution Biflex, Mirage (5% SC) or approved
# 2.1 equivalent mixed with water, as per manufacturer's specification etc complete as per drawings,
specification and as directed by the Engineer Incharge.
Unit / Sft.
S.# Description Qty Unit Rate Amount
LABOUR & MATERIAL
1 Termite
Labour and Material Cost 1 Sft.. 10 10.00
Water ( 1 Liter TERMICURE+ 250
Liter water cover Area 540 Sft.) 0.46 ltr 0.25 0.12
Sub Total (a) 10.12

Add 25 % Overhead Charges 25 2.53

Sub Total (b) 2.53

Grand Total 12.64

Rate /Sft. Rs. = 13

Civil Works
3- PLAIN & REINFORCED CONCRETE
BOQ REF Providing and laying 1:4:8 cement concrete mix using Chenab sand and graded stone ballast 2" and
# 3.1 down gauge in foundations/under floor including leveling, compacting and curing etc complete as
per drawings, specification and as directed by the Engineer Incharge.
P.C.C 1:4:8
Unit % Cft.
S.# Description Qty Unit Rate Amount
MATERIAL
1 Cement OPC 9.48 Bags 510 4834.80
2 Sand (Chenab) 47.4 Cft. 25 1185.00
3 Crush Margla 94.8 Cft. 64 6067.20
Total 12087.00
Add 5% Wastage 5 604.35
Total 12691.35
LABOUR
1 Labour Charges 100 Cft. 20 2000.00

Total 2000.00

Material 12691.35
Labour 2000.00
Sub Total (a) 14691.35

Add 25 % Overhead Charges 25 3672.84

Sub Total (b) 3672.84

Grand Total 18364.19

Rate / Unit Cft. 183.64

Rate /Cft. Rs. = 184

Civil Works
3- PLAIN & REINFORCED CONCRETE
BOQ REF Providing and laying reinforced cement concrete using graded stone crush 3/4" and down gauge
# 3.2 having a minimum works cylinder crushing strength of 3000 psi at 28 days with a mix not leaner
than 1:2:4 in Foundations, Plinth/footing beams of required section including form work and its
R.C.C 1:2:4 in Footing
Unit per Cft.
S.# Description Unit Qty Rate Amount
MATERIAL
1 Cement Bag 0.18 510.00 89.76
2 Chenab Sand Cft. 0.22 25.00 5.50
3 Lawarncepur Sand Cft. 0.22 55.00 12.10
4 Margala Crush Cft. 0.88 64.00 56.32
5 Diesel Liter 0.12 116.75 14.01
6 Water for Mixing and curing Liter 64.00 0.10 6.40
Total 184.09
LABOUR
1 Labour for Processing Cft. 1.00 17.00 17.00
2 Labour for Laying Cft. 1.00 12.00 12.00
3 Labour for curing Cft. 1.00 2.00 2.00
4 Add Pump and Transit Mixer charges
Cft. 1.00 14.16 14.16
(@ 500 per CUM)
Total 229.25
SHUTTERING
1 Cost of Shuttering Sft. 1.14 40.00 45.60
Total 274.85
Add 5 % Wastage 5.61
Total 280.46
Add Overheads @ 25% 70.12
Grand Total 350.58
Complete Rate Cft. 350.58

Rate /Cft. Rs. = 351

Civil Works
3- PLAIN & REINFORCED CONCRETE
BOQ REF Providing and laying reinforced cement concrete using graded stone crush 3/4" and down gauge
# 3.3 having a minimum works cylinder crushing strength of 4000 psi at 28 days with a mix not leaner
than 1:1-1/2:3 in Columns and pillars of required section including form work and its removal,
R.C.C 1:1 1/2:3
Unit per Cft.
S.# Description Unit Qty Rate Amount
MATERIAL
1 Cement Bag 0.23 510.00 114.75
2 Chenab Sand Cft. 0.22 25.00 5.50
3 Lawarncepur Sand Cft. 0.22 55.00 12.10
4 Margala Crush Cft. 0.88 64.00 56.32
5 Diesel Liter 0.12 116.75 14.01
6 Water for Mixing and curing Liter 64.00 0.10 6.40
Total 209.08
LABOUR
1 Labour for Processing Cft. 1.00 17.00 17.00
2 Labour for Laying Cft. 1.00 12.00 12.00
3 Labour for curing Cft. 1.00 2.00 2.00
4 Add Pump and Transit Mixer charges
Cft. 1.00 14.16 14.16
(@ 500 per CUM)
Total 254.24
SHUTTERING
1 Cost of Shuttering Sft. 1.14 45.00 51.30
Total 305.54
Add 5 % Wastage 5.86
Total 311.40
Add Overheads @ 25% 77.85
Grand Total 389.26
Complete Rate Cft. 389.26

Rate /Cft. Rs. = 389

Civil Works
3- PLAIN & REINFORCED CONCRETE
BOQ REF Providing and laying reinforced cement concrete using graded stone crush 3/4" and down gauge
# 3.4 having a minimum works cylinder crushing strength of 3000 psi at 28 days with a mix not leaner
than 1:2:4 in plinth beams including form work and its removal, compacting and curing etc
R.C.C 1:2:4 in Retaining Wall
Unit per Cft.
S.# Description Unit Qty Rate Amount
MATERIAL
1 Cement Bag 0.18 510.00 89.76
2 Chenab Sand Cft. 0.22 25.00 5.50
3 Lawarncepur Sand Cft. 0.22 55.00 12.10
4 Margala Crush Cft. 0.88 64.00 56.32
5 Diesel Liter 0.12 116.75 14.01
6 Water for Mixing and curing Liter 64.00 0.10 6.40
Total 184.09
LABOUR
1 Labour for Processing Cft. 1.00 17.00 17.00
2 Labour for Laying Cft. 1.00 12.00 12.00
3 Labour for curing Cft. 1.00 2.00 2.00
4 Add Pump and Transit Mixer charges
Cft. 1.00 14.16 14.16
(@ 500 per CUM)
Total 229.25
SHUTTERING
1 Cost of Shuttering Sft. 1.14 50.00 57.00
Total 286.25
Add 5 % Wastage 5.61
Total 291.86
Add Overheads @ 25% 72.97
Grand Total 364.83
Complete Rate Cft. 364.83

Rate /Cft. Rs. = 365

Civil Works
3- PLAIN & REINFORCED CONCRETE
BOQ REF Providing and laying reinforced cement concrete using graded stone crush 3/4" and down gauge
# 3.5 having a minimum works cylinder crushing strength of 3000 psi at 28 days with a mix not leaner
than 1:2:4 in Slab, Beams, slab, steps, lintels, shelves & Parapet of required section including form
R.C.C 1:2:4 In Slab
Unit per Cft.
S.# Description Unit Qty Rate Amount
MATERIAL
1 Cement Bag 0.18 510.00 89.76
2 Chenab Sand Cft. 0.22 25.00 5.50
3 Lawarncepur Sand Cft. 0.22 55.00 12.10
4 Margala Crush Cft. 0.88 64.00 56.32
5 Diesel Liter 0.12 116.75 14.01
6 Water for Mixing and curing Liter 64.00 0.10 6.40
Total 184.09
LABOUR
1 Labour for Processing Cft. 1.00 17.00 17.00
2 Labour for Laying Cft. 1.00 12.00 12.00
3 Labour for curing Cft. 1.00 2.00 2.00
4 Add Pump and Transit Mixer charges
Cft. 1.00 14.16 14.16
(@ 500 per CUM)
Total 229.25
SHUTTERING
1 Cost of Shuttering Sft. 1.14 50.00 57.00
Total 286.25
Add 5 % Wastage 5.61
Total 291.86
Add Overheads @ 25% 72.97
Grand Total 364.83
Complete Rate Cft. 364.83

Rate /Cft. Rs. = 365

Civil Works
3- PLAIN & REINFORCED CONCRETE
BOQ REF Providing and laying 2" thick Cement concrete mix 1:2:4 using graded stone crush 3/4" and down
# 3.6 gauge as base layer under floor including the cost of cement slurry etc complete as per drawings,
specification and as directed by the Engineer Incharge.
P.C.C 1:2:4 Under Floor
Unit per Sft.
S.# Description Unit Qty Rate Amount
MATERIAL
1 Cement ( 6.54 Bag / CUM) 1Cft./6 x . Bag
02832 x 6.54 = 0.04 0.04 510.00 20.40
2 Chenab Sand (0.03*1.25*2 = 0.75) Cft. 0.08 25.00 2.00
3 Margalla Crush Cft. 0.15 64.00 9.86
4 Diesel Liter 0.03 116.75 3.50
5 Water for Mixing and curing Liter 8.00 0.20 1.60
LABOUR
1 Labour for Processing and Laying Sft. 1.00 20.00 20.00
2 Labour for curing Sft. 1.00 2.00 2.00
Total 59.36
Add 5% Wastage 1.05
Total 60.41
Add overheads @ 25% 15.10
Total 75.51
Complete Rate Sft. 75.51

Rate /Sft. Rs. = 76

Civil Works
3- PLAIN & REINFORCED CONCRETE
BOQ REF Providing and laying 2" thick Plain Cement Concrete 1:2:4 top finish for plinth protection,
# 3.7 including 1 1/2" wide & 1/4" thick Marble divider at 2'.6" c/c complete as per drawings,
specification and as directed by the Engineer Incharge.
P.C.C 1:2:4 On Plinth Protection
Unit per Sft.
S.# Description Unit Qty Rate Amount
MATERIAL
1 Cement ( 6.54 Bag / CUM) 1Cft./6 X . Bag
02832 X 6.54 = 0.03 0.03 510.00 15.30
2 Chenab Sand (0.03*1.25*2 = 0.75) Cft. 0.08 25.00 2.00
3 Margalla Crush Cft. 0.15 64.00 9.86
4 Marble Patti Rft. 0.12 5.00 0.60
5 Diesel Liter 0.03 116.75 3.50
6 Water for Mixing and curing Liter 8.00 0.20 1.60
LABOUR
1 Labour for Processing and Laying Sft. 1.00 20.00 20.00
2 Labour for curing Sft. 1.00 2.00 2.00
Total 54.86
Add 5% Wastage 1.03
Total 55.89
Add overheads @ 25% 13.97
Total 69.86
Complete Rate Sft. 69.86

Rate /Sft. Rs. = 70

Civil Works
4- REINFORCEMENT
BOQ REF Providing and laying deformed steel reinforcement bars with minimum yield stress of 60,000 psi
# 4.1 including the cost of straightening, cutting, bending, placing in position at any level and height,
binding with 16 SWG gauge wire, wastage, removal of rust and chairs etc. complete as per
DEFORM STEEL GRADE 60
Unit %0 Kgs
S.# Description Unit Qty Rate Amount
MATERIAL
1 Cost of Steel kg 1.00 77.00 77.00
2 Cost of Binding Wire kg 0.01 125.00 1.25
3
Cost of preapring and laying of spacers kg 1.00 1.30 1.30
LABOUR
1 Labour for cutting, binding, bending
kg 1.00 7.00 7.00
and placing
Total 86.55
Add 5 % for Wastage 3.91
Total 90.46
Add Overheads @ 25% 22.62
Grand Total 113.08
Complete Rate Kg 113.08

Rate /Kg Rs. = 113

Civil Works
5- Damp Proofing
BOQ REF Providing and laying 1-1/2" thick damp proof course with cement concrete 1:2:4 cast insitu using
# 5.1 graded screened bajri of 3/4" and down gauge i/c compacting, curing, form work and its removal
etc. complete with applying a coat of hot bitumen using 35 lbs. per hundred square feet (1.71
Damp Proofing
Unit per Sft.
S.# Description Unit Qty Rate Amount
MATERIAL

1 Cement OPC Bags 2.5 510 1275.00


2 Sand (Chenab) Cft. 5.5 25 137.50
3 Crush Cft. 11 64 704.00
4 Bitumen Kgs 8 80 640.00
Total 2756.50
Add 5% Wastage 5 137.83
Total 2894.33
LABOUR
1 Labour Sft. 100 15 1500.00
2 Labour for Bitumen Sft. 100 2 200.00
3 Form Work Sft. 100 2.5 250.00
Total 1950.00

Sub Total (a) 4844.33

Add Overheads @ 25% 25 1211.08


Total 6055.41
Grand Total 6055.41

Rate / Unit Sft. 60.55

Rate /Sft. Rs. = 61

Civil Works
5- Damp Proofing
BOQ REF Providing damp proof course on vertical surface with 3/4" thick cement plaster 1:4 mixed with any
# 5.2 approved water proofing agent i/c curing etc complete as per drawings, specification and as
directed by the Engineer Incharge.
Damp Proofing
Unit per Sft.
S.# Description Unit Qty Rate Amount
MATERIAL

1 Cement OPC Bags 1.14 510 581.40


2 Sand (Chenab) Cft. 5.5 25 137.50
3 Kerosene Oil ltr 3.63 130 471.90
4 Brush each 0.2 50 10.00
6 Bitumen Kgs 16.5 80 1320.00
Total 2520.80
Add 5% Wastage 5 126.04
Total 2646.84
LABOUR
1 Labour Sft. 100 15 1500.00
2 Labour for Bitumen Sft. 100 2 200.00
Total 1700.00

Sub Total (a) 4346.84

Add 25 % 25 1086.71
Total 5433.55
Grand Total 5433.55

Rate / Unit Sft. 54.34


Rate /Sft. Rs. = 54

Civil Works
6- Brick Masonary
BOQ REF Providing and laying first class burnt brick masonry set in cement mortar 1:5 in straight or curved
# 6.1 wall including scaffolding, raking out joints and curing etc in foundation etc. complete as per
drawings, specification and as directed by the Engineer Incharge.
BRICK WORK 1:5 In Foundation
Unit per Cft.
S.# Description Unit Qty Rate Amount
MATERIAL
Cement Bag 0.04 510.00 20.40
Chenab Sand Cft. 0.30 25.00 7.50
Bricks each 13.50 8.00 108.00
Diesel Liter 0.02 116.75 2.34
Water for Mixing and curing Liter 48.00 0.10 4.80
LABOUR
Labour Cft. 1.00 30.00 30.00
Labour for curing Cft. 1.00 1.14 1.14
Total 174.18
Add 5 % for Wastage 6.34
Total 180.51
Add Overheads @ 25% 45.13
Grand Total 225.64
Complete Rate Cft. 225.64

Rate /Cft. Rs. = 226

Civil Works
6- Brick Masonary
BOQ REF Providing and laying first class burnt brick masonry set in cement mortar 1:5 in straight or curved
# 6.2 wall including scaffolding, raking out joints and curing etc in super structure complete as per
drawings, specification and as directed by the Engineer Incharge.

Brick Work Super Structure ratio c/s (1:5)


Unit per Cft.
S.# Description Unit Qty Rate Amount

MATERIAL
Cement Bag 0.04 510.00 20.40
Chenab Sand Cft. 0.30 25.00 7.50
Bricks each 13.50 8.00 108.00
Diesel Liter 0.02 116.75 2.34
1/4" dia wall Ties Kg 0.25 55.00 13.75
Water for Mixing and curing Liter 48.00 0.10 4.80
LABOUR
Labour Cft. 1.00 30.00 30.00
Labour for curing Cft. 1.00 1.14 1.14
Total 187.93
Add 5 % for Wastage 7.02
Total 194.95
Add Overheads @ 25% 48.74
Grand Total 243.69
Complete Rate Cft. 243.69
Rate /Cft. Rs. = 244

Civil Works
6- Brick Masonary
BOQ REF Providing and laying first class burnt brick masonry set in cement mortar 1:3 in straight or curved
# 6.3 wall including scaffolding, raking out joints and curing etc in super structure complete as per
drawings, specification and as directed by the Engineer Incharge.
Brick Work Super Structure ratio c/s (1:3) 4-1/2" thick
Unit per Sft.
S.# Description Unit Qty Rate Amount
MATERIAL
1 Cement Bag 0.03 510.00 15.30
2 Chenab Sand Cft. 0.11 25.00 2.75
3 Bricks each 4.95 8.00 39.60
4 Water for Mixing and curing Liter 15.00 0.10 1.50
LABUOR
1 Labour Sft. 1.00 35.00 35.00
2 Labour for curing Sft. 1.00 0.81 0.81
Total 94.96
Add 5 % for Wastage 2.35
Total 97.31
Add Overheads @ 25% 24.33
Grand Total 121.63
Complete Rate Sft. 121.63

Rate /Sft. Rs. = 122

Civil Works
7-Cement Plaster
BOQ REF 1/2" thick Cement plaster 1:3 on soffit of ceiling, cantilever slabs, sides and soffit of beams etc
# 7.1 including making edges, smooth with steel trowel, corners, and curing etc. with ordinary portland
cement complete as per drawings, specification and as directed by the Engineer Incharge.

1/2" thick c/s Plaster 1:3


Unit per Sft.
S.# Description Unit Qty Rate Amount
MATERIAL
1 Cement Bag 0.01 510.00 4.08
2 Sand Chenab Cft. 0.03 25.00 0.85
Diesel Liter 0.02 116.75 2.34
Water for Mixing and curing Liter 8.00 0.10 0.80
LABOUR
Labour for Plastering Sft. 1.00 20.00 20.00
Labour for curing Sft. 1.00 0.50 0.50
Total 28.57
Scaffolding Sft. 1.00 0.52 0.52
Total 29.09
Add 5 % for Wastage 0.24
Total 29.33
Add Overheads @ 25% 7.33
Grand Total 36.66
Complete Rate Sft. 36.66

Rate /Sft. Rs. = 37


Civil Works
7-Cement Plaster
BOQ REF Cement plaster 1:4 on walls and columns etc including making edges, smooth with steel trowel,
# 7.2 (a) corners, and curing etc. on Internal surfaces with ordinary portland cement complete as per
drawings, specification and as directed by the Engineer Incharge.

1/2" thick c/s Plaster 1:4


Unit %Sft.
S.# Description Qty Unit Rate Amount
MATERIAL
1 Cement Bag 0.0070 510.00 3.57
2 Sand Chenab Cft. 0.0360 25.00 0.90
Diesel Liter 0.0200 116.75 2.34
Water for Mixing and curing Liter 8.0000 0.10 0.80
LABOUR
Labour for Plastering Sft. 1.0000 20.00 20.00
Labour for curing Sft. 1.0000 0.50 0.50
Total 28.11
Scaffolding Sft. 1.0000 0.52 0.52
Total 28.63
Add 5 % for Wastage 0.24
Total 28.86
Add Overheads @ 25% 7.22
Grand Total 36.08
Complete Rate Sft. 36.08

Rate /Sft. Rs. = 36

Civil Works
8-CARPENTRY AND JOINERY
BOQ REF Providing and fixing 1½" (40 mm) thick deodar wood panelled or panelled and glazed, doors with
# 8.1 M.S Pressed frame, lacker polish, Lock, Door closer, hinges, tower bolt etc. complete as per
drawings, specifications and as directed by the Engineer Incharge. (Basic cost of the lock is Rs.
1600)

1-1/2" thick solid Door


Unit 24.50 Sft.
S.# Description Unit Qty Rate Amount
MATERIAL
1 Steel frame 16 SWG 10" x 2" Rft. 17.5 220 3850.00
2 Concrete Sft. 2.25 300 675.00
3 Hold Fast Each 3 20 60.00
4 hinges Each 3 30 90.00
5 Partal i/c wastage Cft. 1.25 1400 1750.00
6 Lipping Rft. 17.5 16 280.00
7 Commercial Ply Rft. 56 26 1456.00
8 Lacquered Polish Sft. 24.5 25 612.50
8 Tower bolt Each 2 85 170.00
9 Handle Each 1 75 75.00
10 Lock Each 1 1750 1750.00
11 Architrave Rft. 17.5 20 350.00
12 Door Closer Each 1 1250 1250.00
Total 12368.50
LABOUR
1 Labour Charges for making for steel
chowkat . Each 1 250 250.00
2 Labour Charges for fixing for steel
chowkat . Sft. 17.5 20 350.00
3
Labour Charges for making for door. Each 1 750 750.00
4 Labour charges for fixing door Sft. 17.5 30 525.00
Total 1875.00

Sub Total (a) 14243.50

Add 25% Overhead charges 25 3560.88


Sub Total (B) 17804.38

Grand Total 17804.38

Rate / Unit Sft. 726.71

Rate /Sft. Rs. = 727

Civil Works
8-CARPENTRY AND JOINERY
BOQ REF Providing, making and fixing in position full height cabinets 24" deep consisting of solid deodar
# 8.2 wooden 2"x1" frame and 3/4" thick both side laminated MDF for cabinet box, shelves, leafs etc.
Lipped with deodar wood in design pattern with approved hardware i.e. Locks, hinges, handles,
catchers, hanging rods with brackets etc. including spirit/lacquered polish of approved shade to all
exposed wooden surfaces. Complete as per drawings, specifications and as directed by the
Engineer Incharge.

Full Height Cabinet 24" Deep


Unit 42 Sft.
S.# Description Unit Qty Rate Amount
MATERIAL
1 Deodar Wood i/c wastage Cft. 0.75 4500 3375.00
2 MDF 3/4" thick Sft. 106 43 4558.00
3 Full Hinges Inch 168 8 1344.00
4 Lipping Rft. 40 16 640.00
5 Commercial Ply Rft. 42 26 1092.00
6 Lacquered Polish Sft. 20 25 500.00
7 Handle Each 2 85 170.00
8 Lock Each 2 150 300.00
9 Catcher Each 2 8 16.00
10 Nuts & Bolts L.S 1 1000 1000.00
Total 12995.00
LABOUR
1 Labour for making & fixing Sft. 42 175 7350.00

Total 7350.00

Sub Total (a) 20345.00

Add 25% Overhead charges 25 5086.25


Sub Total (B) 25431.25

Grand Total 25431.25

Rate / Unit Sft. 605.51

Rate /Sft. Rs. = 606


Civil Works
9-ALUMINUM WORKS
BOQ REF Providing and fixing all types of glazed aluminium windows, vantilator of anodized bronze colour
# 9.1 partly fixed and party sliding using deluxe section of Ms. Alco/Pakistan Cables or other approved
manufacturer having Frame of size 100mm x 20mm and leaf frame sections of 50mm x 20mm, all
of 1.6mm thickness i/c 5mm thick imported tempered tinted glass with rubber gasket using
approved standard latches, hardware etc., complete as per drawings, specification and as directed
by the Engineer Incharge.

Aluminum Window
Unit 27 Sft.
S.# Description Qty Unit Rate Amount
MATERIAL
1 1.6 mm Chowket Frame 20 mm x 100
mm i/c wastage 23.1 Rft. 180 4158.00
2 Leaf Frame Section 20 mm x 50 mm 26.4 Rft. 195 5148.00
3 Rubber gasket 29.15 Rft. 3 87.45
4 Imported Tinted glass 27 Sft. 75 2025.00
6 Latches of matching shade 1 Nos 60 60.00
7 Cost of hardware L.S 500.00
9 Aluminum wire Netting with frame 13.5 Sft. 120 1620.00

Total 13598.45
LABOUR
1 Aluminum Technician 2 Nos 800 1600.00
2 Carriage Cooly 3 Nos 500 1500.00
3 Carriage charges L.S 300.00
4 Labour for Fixing for glass 27 Sft. 15 405.00

Total 3805.00

Sub Total (a) 17403.45

Add 25% Overhead charges 25 4350.86


Total 21754.31

Grand Total 21754.31

Rate / Unit Sft. 805.72

Rate /Sft. Rs. = 806

Civil Works
10- FLOOR & WALL FINISH
BOQ REF Providing and laying Granite Tiles (Master) Full Body Premium Quality on Flooring 12"x12" of
# 10.1 approved make and shade jointing with matching color pigments and bedding over 3/4" cement
sand mortar 1:3 including Finishing and curing etc. complete as per drawings, specifications and
as directed by the Engineer Incharge.

Granite Tile Flooring


Unit %Sft.
S.# Description Qty Unit Rate Amount
MATERIAL
1 Granite tile 16" x 16" 100 Sft. 130 13000.00
2 Cement OPC 2.55 Bags 510 1300.50
3 White Cement & Pigment 0.45 Bags 780 351.00
4 Sand chenab 4.5 Cft. 25 112.50
Total 14764.00
Add 5% Wastage 5 738.20
Total 15502.20

LABOUR
1 Labour Charges 100 Sft. 35 3500.00

Total 3500.00

Sub Total (a) 19002.20

Add 25% Overhead charges 25 4750.55


Total 23752.75

Grand Total 23752.75

Rate / Unit Sft. 237.53

Rate /Sft. Rs. = 238

Civil Works
10- FLOOR & WALL FINISH
BOQ REF Providing & Laying 4" high Granite Tile (Master) skirting with cement sand plaster (1:3) filling the
# 10.2 joints with matching color pigment, complete as per the drawings, specifications and as directed by
the Engineer Incharge.

Granite Tile Skirting


Unit %Sft.
S.# Description Qty Unit Rate Amount
MATERIAL
1 Granite Tile 16" x 5" 100 Sft. 130 13000.00
2 Cement OPC 2.04 Bags 510 1040.40
3 White Cement & Pigment 0.45 Bags 780 351.00
4 Sand chenab 4.5 Cft. 25 112.50
Total 14503.90
Add 5 % Wastage 5 725.20
Total 15229.10

LABOUR
1 Labour Charges 100 Sft. 30 3000.00

Total 3000.00

Sub Total (a) 18229.10

Add 25% Overhead charges 25 4557.27


Total 22786.37

Grand Total 22786.37

Rate / Unit Sft. 227.86

Rate /Sft. Rs. = 228

Civil Works
10- FLOOR & WALL FINISH
BOQ REF Providing and laying floor of tiles (matte finish ) 8" x 8" of Master or equivalent of approved
# 10.3 color including jointing and washing the tiles with cement slurry with matching color pigment and
curing etc. complete as per drawings, specification and as directed by the Engineer Incharge.
Matte Finish Tile on floor
Unit %Sft.
S.# Description Qty Unit Rate Amount
MATERIAL
1 Matt Tile 8" x 8" 100 Sft. 79 7900.00
2 Cement OPC 3/4" thick 1:3 Slurry 1.45 Bags 510 739.50
3 White Cement & Pigment 0.45 Bags 780 351.00
4 Sand chenab 6.35 Cft. 25 158.75
Total 9149.25
Add 3% Wastage 3 274.48
Total 9423.73
LABOUR
1 Labour Charges 100 Sft. 35 3500.00

Total 3500.00

Sub Total (a) 12923.73

Add 25% Overhead charges 25 3230.93


Total 16154.66

Grand Total 16154.66

Rate / Unit Sft. 161.55

Rate /Sft. Rs. = 162

Civil Works
10- FLOOR & WALL FINISH
BOQ REF Providing and laying glazed tiles 12” x 8” of Master or equivalent of approved color in dado
# 10.4 including jointing and washing the tiles with white cement slurry, with matching color pigment,
curing and cleaning etc complete as per drawings, specification and as directed by the Engineer
Glazed Tile
Unit %Sft.
S.# Description Qty Unit Rate Amount
MATERIAL
1 Glazed Tile 12"x 8" 100 Sft. 79 7900.00
2 Cement OPC 3/4" thick 1:4 1.27 Bags 510 647.70
3 Cement Slurry 1.45 Bags 510 739.50
4 White Cement & Pigment 0.45 Bags 780 351.00
5 Sand chenab 6.35 Cft. 25 158.75
Total 9796.95
Add 5% Wastage 5 489.85
Total 10286.80
LABOUR
1 Labour Charges 100 Sft. 35 3500.00

Total 3500.00

Sub Total (a) 13786.80

Add 25% Overhead charges 25 3446.70


Total 17233.50
Grand Total 17233.50

Rate / Unit Sft. 172.33

Rate /Sft. Rs. = 172

Civil Works
10- FLOOR & WALL FINISH
BOQ REF Providing and fixing 3/4" thick pre-polished Boticina marble windows sill laid with cement sand
# 10.5 plaster including round gola on both sides, complete as per the drawings, specifications and as
directed by the Engineer Incharge.
3/4" Thick Booticina marble slab ( Window sills)
Unit %Sft.
S.# Description Qty Unit Rate Amount
MATERIAL
1 Booticina Marble Slab i/c finishing ,
polishing 100 Sft. 225 22500.00
2 Cement OPC 3/4" thick 1:5 1.27 Bags 510 647.70
3 Cement Slurry 1.45 Bags 510 739.50
4 White Cement & Pigment 0.45 Bags 780 351.00
5 Sand chenab 6.35 Cft. 25 158.75
Total 24396.95
Add 5% Wastage 5 1219.85
Total 25616.80
LABOUR
1 Labour Charges 100 Sft. 35 3500.00

Total 3500.00

Sub Total (a) 29116.80

Add 25% Overhead charges 25 7279.20


Total 36396.00

Grand Total 36396.00

Rate / Unit Sft. 363.96

Rate /Sft. Rs. = 364

Civil Works
10- FLOOR & WALL FINISH
BOQ REF Providing and laying Blue Pearl granite 3/4" thick as required on floor/stair ( tread and riser ) and
# 10.6 on counters top as required, with gola etc. complete as per drawings, specification and as directed
by the Engineer Incharge.

3/4" Thick Blue Pearl Granite marble slab on (Treads,Risers,Entrance Steps)


Unit %Sft.
S.# Description Qty Unit Rate Amount
MATERIAL
1 Pre polished 3/4" Thick Blue Pearl
Granite marble 100 Sft. 725 72500.00

Total 72500.00
Add 5% Wastage 5 3625.00
Total 76125.00
LABOUR
1
Labour Charges i/c Cutting & Fixing 100 Sft. 35 3500.00

Total 3500.00

Sub Total (a) 79625.00

Add 25% Overhead charges 25 19906.25


Total 99531.25

Grand Total 99531.25

Rate / Sft. 995.31

Rate /Each Rs. = 995

Civil Works
10- FLOOR & WALL FINISH
BOQ REF Providing & Laying 4" high Pearl Blue skirting with cement sand plaster (1:3) filling the joints
# 10.7 with matching color pigment, complete as per the drawings, specifications and as directed by the
Engineer Incharge.
4" high Pearl Blue skirting
Unit %Sft.
S.# Description Qty Unit Rate Amount
MATERIAL
1 Pearl Blue marble skirting 100 Sft. 550 55000.00
2 Cement Slurry 1.45 Bags 510 739.50
3 White Cement & Pigment 0.45 Bags 780 351.00

Total 56090.50
Add 5% Wastage 5 2804.53
Total 58895.03
LABOUR
1 Labour Charges 100 Sft. 25 2500.00

Total 2500.00

Sub Total (a) 61395.03

Add 25% Overhead charges 25 15348.76


Total 76743.78

Grand Total 76743.78

Rate / Unit Sft. 767.44

Rate / Unit Rft. 383.72

Rate /Rft. Rs. = 384

Civil Works
11-WATER PROOFING & EXP. JOINT FILLING
BOQ REF Providing and laying hot bitumen on roof of 34 lbs per 100 Sft. finished with washed coarse sand
# 11.1 complete as per drawings, specification and as directed by the Engineer Incharge.
Hot Bitumen
Unit %Sft.
S.# Description Qty Unit Rate Amount
MATERIAL
1 Hot Bitumen 15.42 Kgs 108 1665.36
2 Sand 6 Cft. 12 72.00

Total 1737.36
LABOUR
1 Labour Charges 100 Sft. 3 300.00

Total 300.00

Sub Total (a) 2037.36

Add 25% Overhead charges 25 509.34


Total 2546.70

Grand Total 2546.70

Rate / Sft. 25.47

Say Rs. 25

Rate /Sft. Rs. = 25

Civil Works
11-WATER PROOFING & EXP. JOINT FILLING
BOQ REF Providing and laying single layer of polythene sheet of 500 gauge on roof for water proofing laid
# 11.2 complete as per drawings, specification and as directed by the Engineer Incharge.
Polythene Sheet
Unit %Sft.
S.# Description Qty Unit Rate Amount
MATERIAL
1 Polythene Sheet 100 Sft. 5 500.00

Total 500.00
Add 5% Wastage 5 25.00
Total 525.00
LABOUR
1 Labour Charges 100 Sft. 1 100.00

Total 100.00

Sub Total (a) 625.00

Add 25% Overhead charges 25 156.25


Total 781.25

Grand Total 781.25

Rate / Unit Sft. 7.81

Rate /Sft. Rs. = 8


Civil Works
11-WATER PROOFING & EXP. JOINT FILLING
BOQ REF Providing and laying 1st class burnt clay tiles of 9”x4½”x1½” size grouted with 1:3 cement mortar
# 11.3 over 4” thick puddled earth compacted and smooth finished to slope mixed with bhoosa @ 1seer of
bhoosa for 1Cft. of puddled earth in ground floor including flush pointing on the tiles work with
Roof Tile
Unit %Sft.
S.# Description Qty Unit Rate Amount
MATERIAL
1
40 Cft. 8 320.00
New Earth Filling i/c for mud plaster
2 Mud Plaster mix bhoosa 8 kgs 4 32.00
3 Brick Tile 360 Each 9 3240.00
3 Cement for Grouting 2.25 Bags 510 1147.50
3 Sand Chenab 8 Cft. 25 200.00

Total 4939.50
Add 5% Wastage 5 246.98
Total 5186.48
LABOUR
1 Earth Shifting, laying & Mud plaster
mixing 40 Cft. 10 400.00
2 Labour Charges i/c Tile fixing ,
grouting & pointing 100 Sft. 20 2000.00

Total 2000.00

Sub Total (a) 7186.48

Add 25% Overhead charges 25 1796.62


Total 8983.09

Grand Total 8983.09

Rate / Unit Sft. 89.83

Rate /Sft. Rs. = 90

Civil Works
11-WATER PROOFING & EXP. JOINT FILLING
BOQ REF Providing and laying Jambolon board 1.5" thick complete as per drawings, specification and as
# 11.4 directed by the Engineer Incharge.
Jambolon board 1.5" thick
Unit %Sft.
S.# Description Qty Unit Rate Amount
MATERIAL
1 Jambolon board 1.5" thick 100 Sft. 180 18000

Total 18000.00
Add 5% Wastage 5 900.00
Total 18900.00
LABOUR
2 Labour Charges i/c Laying 100 Sft. 15 1500.00
Total 1500.00

Sub Total (a) 20400.00

Add 25% Overhead charges 25 5100.00


Total 25500.00

Grand Total 25500.00

Rate / Unit Sft. 255.00

Rate /Sft. Rs. = 255

Civil Works
12- PAINTING
BOQ REF Providing and laying three coats of plastic emulsion paint of ICI or Burger or equivalent of
# 12.1 approved shade including surface preperation, primer coat, filling, cutting etc. Complete as per
drawings, specification and as directed by the Engineer Incharge.
Plastic Emulsion Paint
Unit % Sft.
S.# Description Qty Unit Rate Amount
MATERIAL
1 Paint ICI (Plastic Emulsion) 100 Sft. 19 1990.00
2 Primer Coat / filling 100 Sft. 5 500.00

Total 2490.00
LABOUR
1 Sand paper , rubbing Stone 100 Sft. 6 600.00

Total 600.00

Sub Total (a) 3090.00

Add 25% Overhead charges 25 772.50


Total 3862.50

Grand Total 3862.50

Rate / Unit Sft. 38.63

Rate /Sft. Rs. = 39

Civil Works
14- PAINTING
BOQ REF Providing and Applying three coats of Graffito paint on external walls of approved shade on
# 12.2 plastered surface. Complete as per drawings, specification and as directed by the Engineer
Incharge.

Graffito paint
Unit % Sft.
S.# Description Qty Unit Rate Amount
MATERIAL
1 Sandex base / under coat for filling
depressions consisting of Acrylic resin
1212 and D 18, Iron oxide colours,
Natural marble quartz,water etc with
ruler.
On Plastered Surface for 150Sft. 0.5 Bag 550 275.00
2 Sandex uper coat with suitable
thickness consisting of Acrylic resin
1212 and D 18, Iron oxide colours,
Natural marble quartz, water etc with
Grain Garmala.
On Plastered Surface for 150Sft. 3 Bag 450 1350.00

Total 1625.00
Add 5% Wastage 5 81.25
Total 1706.25
LABOUR
1 Labour Charges 100 Sft. 10 1000.00

Total 1000.00

Sub Total (a) 2706.25

Add 25% Overhead charges 25 676.56


Total 3382.81

Grand Total 3382.81

Rate / Unit Sft. 33.83

Rate /Sft. Rs. = 34

Civil Works
13-MISCELLANEOUS
BOQ REF Providing and fixing uPVC pipes rainwater down pipe of required dia. including all necessary
# 13.1 accessories with bolts and nuts fixed in cement concrete 1:2:4 complete as per drawings,
specification and as directed by the Engineer Incharge. 4" dia

u.PVC pipe 4" dia Rain water


Unit %Rft.
S.# Description Qty Unit Rate Amount
MATERIAL
1- 4" Dia Pipe 100 Rft. 180 18000.00
2- Fitting bend, socket (60% of Pipe 10800.00
3 Jointing Solution 100 Rft. 3 300.00

Total 29100.00
LABOUR
1 Labour Charges 100 Rft. 35 3500.00

Total 3500.00

Material 29100.00
Labour 3500.00
Sub Total (a) 32600.00

Add 25% Overhead charges 25 8150.00


Sub Total (b) 8150.00

Grand Total 40750.00

Say. Rate / Unit Rft. 408

Rate /Rft. Rs. = 408

Civil Works
15-MISCELLANEOUS
BOQ REF Providing and laying 1:2:4 cement concrete khurras 2" thick, 2' x 2' size on roof including finishing
# 13.2 with cement plaster 1:4 curing etc. complete in all respects as directed by the Engineer Incharge
Incharge or according to the specification of drawing and as approved by the consultant.
Khurras on Roof
Unit /Each
S.# Description Qty Unit Rate Amount
MATERIAL
1 Cement 0.204 Bags 510 104.04
2 Sand 0.55 Cft. 25 13.75
3 Crush 1.25 Cft. 64 80.00

Total 197.79
Add 5% Wastage 5 9.89
Total 207.68
LABOUR
1 Labour Charges 1 Each 500 500.00

Total 500.00

Material 207.68
Labour 500.00
Sub Total (a) 707.68

Add 25% Overhead charges 25 176.92

Sub Total (b) 176.92

Grand Total 884.60

Say. Rate / Unit Each 885

Rate /Cft. Rs. = 885

Civil Works
6- CAR PARKING PAVEMENT
BOQ REF Construction of Hard Standing / PCC Car Parking Floor consisting of well-compacted earth with
# 14.1 power road roller of 15 tonn in 4 layers over 6" thick Sub Base Material of Stone Product (NLC
Standared) over 3" thick PCC 1:2:4 with First Class brick on edge pattern 4ft x 4ft complete as per
drawing, design and as instructed by the Engineer Incharge.

1/2" thick c/s Plaster 1:4


Unit Per Sft.
S.# Description Qty Unit Rate Amount
Unit Taken for Analysis = 4'x4'=16 Sft
MATERIAL
1 Earth Filling i/c 95% Compaction with
power road ruller
.= 16 x 4 = 64 Cft. 64 Cft. 24.06 1540.00
2 Sub Base Material of Stone Product
(NLC Standared) i/c Compaction with
power road ruller 100%.
.= 16 x 0.5 = 8 Cft. 8 Cft. 106.00 848.00
3 PCC 1:2:4
.= 3.25x3.25 x0.25 = 2.64 cft 2.64 Cft. 230.00 607.20
4 Brick on Edge Soling in 1:3 c/s morter.

.= 16 x 0.75 = 12 Sft. 12 Sft 80.00 960.00


Total 3955.20

Rate Per Sft = 3955.2 /16 = 247.2


Complete Rate 247 Per Sft.

Rate /Sft. Rs. = 247

Civil Works
7- Jogging Track Top Finish
BOQ REF Providing & Laying 1" Stone Dust over 3" gravel 1/2" pure layer over 2" sand filling over
# 15.1 compacted earth complete as per drawing, design and as specified by the Engineer Incharge.
1/2" thick c/s Plaster 1:4
Unit Per Sft.
S.# Description Qty Unit Rate Amount
Unit Taken for Analysis = 10'x8'=80 Sft
MATERIAL
1 Sand filling
.= 80 x 0.17 = 13.6 Cft. 13.6 Cft. 25.00 340.00
2 Gravel 1/2" Pure
.= 80 x 0.25 = 20 Cft. 20 Cft. 55.00 1100.00
4 Stone Dust
.= 80 x 0.08= 6.4 Cft. 6.4 Cft. 50.00 320.00
Total 1760.00
Add 5% Wastage 88.00
Total 1848.00
LABOUR
Labour for laying ,dressing ,watering
ramming complete. 80 Sft 25.00 2000.00
Total 3848.00
Add 25 % (C.P +O.H .C) 962.00
Net Total 4810.00
Rate Per Sft = 4810 /80 = 60.12
Complete Rate 60 Per Sft.

Rate /Sft. Rs. = 60

Civil Works
19- RAIN WATER DISPOSAL
BOQ REF Providing and laying Gravel 1.5" to 2" gauge Under Rain water 12" dia pipe
# 19.2
1/2" thick c/s Plaster 1:4
Unit Per Cft.
S.# Description Qty Unit Rate Amount
MATERIAL
2 Gravel 1.5" to 2" gauge. 100 Cft 55.00 5500.00
Total 5500.00
Add 5% Wastage 275.00
Total 5775.00
LABOUR
Labour for laying ,dressing ,watering
ramming complete. 80 Sft 15.00 1200.00
Total 6975.00
Add 25 % (C.P +O.H .C) 1743.75
Net Total 8718.75
Rate Per Sft = 8718 /100 = 87.18
Complete Rate 87 Per Sft.

Rate /Sft. Rs. = 87

Sports Complex Phase-VI, DHA, Lahore Cantt.


GROUNDS & INTERNAL WORKS
PLUMBING - Rate Analysis

Plumbing Works
1-SANITARY FIXTURES AND FITTING
BOQ REF Providing & Fixing water closet Prime quality ICL-IFO in plain colored glazed eartheware with 3
# 1.1(a) galleons lowdown flushing cistern including C.p Flush pipe, PVC flexible inlets, T-Stopcock,
Sonex/Master, brass nuts and washers and fixed neatly to floor and walls with brass screws i/c
backlite seat and lid of matching shade. Complete as per drawings, specification and as directed by
the Engineer Incharge.

European W.C
Unit /Nos
S.# Description Qty Unit Rate Amount
MATERIAL
1 W.C European Type i/c low level
flushing cistern 1 Each 5600 5600.00
2 Tee stop cock 1 Each 797 797.00
3 Rubber connection & Hockey Pipe 1 Each 250 250.00
4 Seat Cover 1 Each 375 375.00
5 uPVC Bend 1 Each 346 346.00
Total 7368.00
LABOUR
1 Labour Charges 1 Each 500 500.00

Total 500.00

Material 7368.00
Labour 500.00
Sub Total (a) 7868.00

Add 25% Overhead charges 25 1967.00

Sub Total (b) 1967.00

Grand Total 9835.00

Say Rate / Unit /Nos 9835

Plumbing Works
1-SANITARY FIXTURES AND FITTING
BOQ REF Providing and fixing prime quality wash basin under counter type as manufactured by ICL/IFO in
# 1.2 approved color with best quality water mixer (Master/Sonex?Fasail) with color head, two tee stop
cock with C.P brass flexible connections, wall flanges, wall brackets chrome plated waste 1 1/4"
dia chrome plated bottle trap, complete as per drawings, specification and as directed by the
Engineer Incharge.

Wash hand Basin with Padestal


Unit /Nos
S.# Description Qty Unit Rate Amount
MATERIAL
1 Wash hand Basin with Padestal 1 Each 5500 5500.00
2 Tee stop cock 2 Each 797 1594.00
3 Bottle trap 1 Each 1250 1250.00
4 Mixer Master (019 CP) 1 Each 2840 2840.00

Total 11184.00
LABOUR
1 Labour Charges 1 Each 500 500.00

Total 500.00

Material 11184.00
Labour 500.00
Sub Total (a) 11684.00

Add 25% Overhead charges 25 2921.00

Sub Total (b) 2921.00

Grand Total 14605.00

Rate / Unit /Nos 14605


Plumbing Works
1-SANITARY FIXTURES AND FITTING
BOQ REF Providing and fixing prime quality wash basin under counter type as manufactured by ICL/IFO in
# 1.3 approved color with best quality water mixer (Master/Sonex?Fasail) with color head, two tee stop
cock with C.P brass flexible connections, wall flanges, wall brackets chrome plated waste 1 1/4"
dia chrome plated bottle trap, complete as per drawings, specification and as directed by the
Engineer Incharge.

Wash hand BasinVanity Type


Unit /Nos
S.# Description Qty Unit Rate Amount
MATERIAL
1 Wash hand Basin 1 Each 4000 4000.00
2 Tee stop cock 2 Each 797 1594.00
3 Bottle trap 1 Each 1250 1250.00
4 Mixer Master (019 CP) 1 Each 2840 2840.00

Total 9684.00
LABOUR
1 Labour Charges 1 Each 700 700.00

Total 700.00

Material 9684.00
Labour 700.00
Sub Total (a) 10384.00

Add 25% Overhead charges 25 2596.00

Sub Total (b) 2596.00

Grand Total 12980.00

Rate / Unit /Nos 12980

Plumbing Works
1-SANITARY FIXTURES AND FITTING
BOQ REF Providing & fixing Shower mixer of Sonex/Master/Faisal including head & 3 Nos. of tee stop
# 1.4 cocks, C.P brass pipe, complete as per drawings, specification and as directed by the Engineer
Incharge.

Shower Mixer
Unit /Nos
S.# Description Qty Unit Rate Amount
MATERIAL
1 Shower Set Master 1 Each 15000 15000.00
2 Shower Mixer Master (0.39 B) 1 Each 5500 5500.00
3 Tee stop cock 2 Each 797 1594.00

Total 7094.00
LABOUR
1 Labour Charges 1 Each 500 500.00
Total 500.00

Material 7094.00
Labour 500.00
Sub Total (a) 7594.00

Add 25% Overhead charges 25 1898.50

Sub Total (b) 1898.50

Grand Total 9492.50

Rate / Unit /Nos 9493

Plumbing Works
1-SANITARY FIXTURES AND FITTING
BOQ REF Providing and fixing Muslim Shower C.P. Double bibcock of make Master, Faisal, Super Asia or
# 1.5 approved equivalent with C.P pipe 15 mm dia. complete in all respects including pipe connections,
all fittings, testing etc.

Muslim Shower C.P. Double bibcock


Unit /Nos
S.# Description Qty Unit Rate Amount
MATERIAL
Muslim Shower C.P. Double bibcock
Master (070 CP) 1 Each 2950 2950.00

Total 2950.00
LABOUR
1 Labour Charges 1 Each 500 500.00

Total 500.00

Material 2950.00
Labour 500.00
Sub Total (a) 3450.00

Add 25% Overhead charges 25 862.50

Sub Total (b) 862.50

Grand Total 4312.50

Say. Rate / Unit /Nos 4313

Plumbing Works
1-SANITARY FIXTURES AND FITTING
BOQ REF Providing and fixing chromium plated soap dish of Master/ Sonex.
# 1.7
Chrome Plated Soap dish
Unit /Nos
S.# Description Qty Unit Rate Amount
MATERIAL
Chrome Plated Soap dish 1 Each 755 755.00
Total 755.00
LABOUR
1 Labour Charges 1 Each 200 200.00

Total 200.00

Material 755.00
Labour 200.00
Sub Total (a) 955.00

Add 25% Overhead charges 25 238.75

Sub Total (b) 238.75

Grand Total 1193.75

Say. Rate / Unit /Nos 1194

Plumbing Works
1-SANITARY FIXTURES AND FITTING
BOQ REF Providing and fixing chromium plated toilet paper holder.
# 1.8
Toilet paper holder
Unit /Nos
S.# Description Qty Unit Rate Amount
MATERIAL
1 C.P Toilet Paper Holder 1 Each 777 777.00

Total 777.00
LABOUR
1 Labour Charges 1 Each 200 200.00

Total 200.00

Material 777.00
Labour 200.00
Sub Total (a) 977.00

Add 25% Overhead charges 25 244.25

Sub Total (b) 244.25

Grand Total 1221.25

Say. Rate / Unit /Nos 1221

Plumbing Works
1-SANITARY FIXTURES AND FITTING
BOQ REF Providing and fixing chromium plated towel rail 24" long and 3/4" dia.
# 1.9
Chrome Plated Towel rail
Unit /Nos
S.# Description Qty Unit Rate Amount
MATERIAL
1 C.P Towel Rail 1 Each 1095 1095.00

Total 1095.00
LABOUR
1 Labour Charges 1 Each 200 200.00

Total 200.00

Material 1095.00
Labour 200.00
Sub Total (a) 1295.00

Add 25% Overhead charges 25 323.75

Sub Total (b) 323.75

Grand Total 1618.75

Say. Rate / Unit /Nos 1619

Plumbing Works
1-SANITARY FIXTURES AND FITTING
BOQ REF Providing and fixing looking glass (Imported Belgium) 5mm thick, first quality complete with
# 1.10 frame and fixing clamps.
Mirror of Belgium
Unit /Nos
S.# Description Qty Unit Rate Amount
MATERIAL
1 Mirror of Belgium 1 Each 1120 1120.00

Total 1120.00
LABOUR
1 Labour Charges 1 Each 200 200.00

Total 200.00

Material 1120.00
Labour 200.00
Sub Total (a) 1320.00

Add 25% Overhead charges 25 330.00

Sub Total (b) 330.00

Grand Total 1650.00

Say. Rate / Unit Sft. 1650

Plumbing Works
1-SANITARY FIXTURES AND FITTING
BOQ REF Providing and fixing chromium plated Coat Hooks
# 1.11
CP Coat Hooks
Unit /Nos
S.# Description Qty Unit Rate Amount
MATERIAL
1 CP Coat Hooks 1 Sft. 250 250.00

Total 250.00
LABOUR
1 Labour Charges 1 Each 150 150.00

Total 150.00

Material 250.00
Labour 150.00
Sub Total (a) 400.00

Add 25% Overhead charges 25 100.00

Sub Total (b) 100.00

Grand Total 500.00

Say. Rate / Unit Sft. 500

Plumbing Works
2-WATER SUPPLY PIPES AND FITTING
BOQ REF Providing, fixing, jointing and testing Polypropylene Random (PPR) pipes Dadex make "Polydex"
# 2.1 (a) or approved equivalent pressure pipe for cold water as per DIN 8077-8078 for pipes and DIN
16962, PN25 for fittings (polyfusion welded joints) inside building including fittings and specials
(sockets, tees, elbows, bends, crosses, reducers, adaptor, plugs and union etc.) supported on walls
or suspended from roof slab or run in chases including pipe hangers, supports, cutting and making
good the chases and holes, complete in all respects.

PPR pipes make Dedex 40 mm Dia


Unit %Rft.
S.# Description Qty Unit Rate Amount
MATERIAL & LABOUR
1 40mm dia 100 Rft. 121.95 12195.12
2 Fittings (60% of pipe cost) 7317.07
3 Jointing Solution 100 Rft. 0.10 10.00
4 Labour for Laying 100 Rft. 40.00 4000.00

Total 23522.20
Add 5% Wastage 1176.11
Sub Total (a) 24698.30

Add 25% Overhead charges 25 6174.58

Sub Total (b) 6174.58

Grand Total 30872.88

Say. Rate / Unit Rft. 309

Plumbing Works
2-WATER SUPPLY PIPES AND FITTING
BOQ REF Providing, fixing, jointing and testing Polypropylene Random (PPR) pipes Dadex make "Polydex"
# 2.1 (b) or approved equivalent pressure pipe for cold water as per DIN 8077-8078 for pipes and DIN
16962, PN25 for fittings (polyfusion welded joints) inside building including fittings and specials
(sockets, tees, elbows, bends, crosses, reducers, adaptor, plugs and union etc.) supported on walls
or suspended from roof slab or run in chases including pipe hangers, supports, cutting and making
good the chases and holes, complete in all respects.

PPR pipes make Dedex 32mm Dia


Unit %Rft.
S.# Description Qty Unit Rate Amount
MATERIAL & LABOUR
1- 32mm dia 100 Rft. 78.00 7800.00
2- Fittings (60% of pipe cost) 4680.00
Jointing Solution 100 Rft. 0.10 10.00
Labour for Laying 100 Rft. 35.00 3500.00

Total 15990.00
Add 5% Wastage 799.50
Sub Total (a) 16789.50

Add 25% Overhead charges 25 4197.38

Sub Total (b) 4197.38

Grand Total 20986.88

Say. Rate / Unit Rft. 210

Plumbing Works
2-WATER SUPPLY PIPES AND FITTING
BOQ REF Providing, fixing, jointing and testing Polypropylene Random (PPR) pipes Dadex make "Polydex"
# 2.1 (c) or approved equivalent pressure pipe for cold water as per DIN 8077-8078 for pipes and DIN
16962, PN25 for fittings (polyfusion welded joints) inside building including fittings and specials
(sockets, tees, elbows, bends, crosses, reducers, adaptor, plugs and union etc.) supported on walls
or suspended from roof slab or run in chases including pipe hangers, supports, cutting and making
good the chases and holes, complete in all respects.

PPR pipes make Dedex 25mm Dia


Unit %Rft.
S.# Description Qty Unit Rate Amount
MATERIAL & LABOUR
1- 25mm dia 100 Rft. 48.00 4800.00
2- Fittings (60% of pipe cost) 2880.00
3- Jointing Solution 100 Rft. 0.10 10.00
4- Labour for Laying 100 Rft. 35.00 3500.00

Total 11190.00
Add 5% Wastage 559.50
Sub Total (a) 11749.50

Add 25% Overhead charges 25 2937.38

Sub Total (b) 2937.38

Grand Total 14686.88

Say. Rate / Unit Rft. 147


Plumbing Works
2-WATER SUPPLY PIPES AND FITTING
BOQ REF Providing and installing ball valves of following nominal dia, kitz make, including jointing, fitting,
# 2.2 (a) painting, testing, complete in all respects to match with following pipe diameters.

Ball Valve 25 mm dia


Unit Each
S.# Description Qty Unit Rate Amount
MATERIAL
1- 25mm dia 1 Rft. 938.00 938.00
2- Jointing Solution L.S 15.00
3- Labour for Fixing L.S 500.00

Total 1453.00
Sub Total (a) 1453.00

Add 25% Overhead charges 25 363.25

Sub Total (b) 363.25

Grand Total 1816.25

Say. Rate / Unit 18.16

Sub Total (b) 18.16

Grand Total 1834.41

Say. Rate / Unit Each 1834


Plumbing Works
2-WATER SUPPLY PIPES AND FITTING
BOQ REF Providing and installing ball valves of following nominal dia, kitz make, including jointing, fitting,
# 2.2 (b) painting, testing, complete in all respects to match with following pipe diameters.
Ball Valve 32mm dia
Unit Each
S.# Description Qty Unit Rate Amount
MATERIAL
1- 32mm dia 1 Rft. 1533.00 1533.00
Jointing Solution L.S 15.00
Labour for Fixing L.S 500.00

Total 2048.00
Sub Total (a) 2048.00

Add 25% Overhead charges 25 512.00

Sub Total (b) 512.00

Grand Total 2560.00

Say. Rate / Unit Rft. 25.60

Sub Total (b) 25.60

Grand Total 2585.60


Say. Rate / Unit Each 2586

Plumbing Works
2-WATER SUPPLY PIPES AND FITTING
BOQ REF Providing, fixing, jointing and testing G.I Pipes (Medium Quality) including fittings and specials
# 2.3 (a) (sockets, tees, elbows, bends, crosses, reducers, adaptor, plugs and union etc.) supported on walls
or suspended from roof slab or run in chases including pipe hangers, supports, cutting and making
good the chases and holes, complete in all respects.

G.I Pipe 3/4" dia


Unit %Rft.
S.# Description Qty Unit Rate Amount
MATERIAL
1- G.I Pipe 3/4" dia 100 Rft. 95 9500.00
2- Fitting bend, socket 60% 100 Rft. 57 5700.00

Total 15200.00
LABOUR
1 Labour Charges 100 Rft. 40 4000.00

Total 4000.00

Material 15200.00
Labour 4000.00
Sub Total (a) 19200.00

Add 25% Overhead charges 25 4800.00

Sub Total (b) 4800.00

Grand Total 24000.00

Say. Rate / Unit Rft. 240.00

Plumbing Works
2-WATER SUPPLY PIPES AND FITTING
BOQ REF Providing, fixing, jointing and testing G.I Pipes (Medium Quality) including fittings and specials
# 2.3 (b) (sockets, tees, elbows, bends, crosses, reducers, adaptor, plugs and union etc.) supported on walls
or suspended from roof slab or run in chases including pipe hangers, supports, cutting and making
good the chases and holes, complete in all respects.

G.I Pipe 1/2" dia


Unit %Rft.
S.# Description Qty Unit Rate Amount
MATERIAL
1- G.I Pipe 1/2" dia 100 Rft. 70 7000.00
2- Fitting bend, socket (60% of Pipe) 4200.00

Total 11200.00
LABOUR
1 Labour Charges 100 Rft. 40 4000.00

Total 4000.00

Material 11200.00
Labour 4000.00
Sub Total (a) 15200.00

Add 25% Overhead charges 25 3800.00

Sub Total (b) 3800.00

Grand Total 19000.00

Say. Rate / Unit Rft. 190.00

Plumbing Works
3-SOIL , WASTE, VANTILATING PIPES
BOQ REF Providing, fixing, cutting, jointing and testing uPVC piping conforming to ISO 3633:1991
# 3.1 (a) ( wall thickness=3.2 mm) including uPVC fittings with solvent cement jointing Dadex make
"Class B" or approved equal , rates include cost of clamping to walls and ceiling , hangers,
supports, cutting through walls and providing sleeves through concrete slabs for pipelines and
pipe fittings of the following diameter:

u PVC pipe 4" dia


Unit %Rft.
S.# Description Qty Unit Rate Amount
MATERIAL
1 4" Dia Pipe 100 Rft. 180 18000.00
2 Fitting bend, socket (60% of Pipe
cost) 10800.00

Total 28800.00
LABOUR
1 Labour Charges 100 Rft. 40 4000.00

Total 4000.00

Material 28800.00
Labour 4000.00
Sub Total (a) 32800.00

Add 25% Overhead charges 25 8200.00

Sub Total (b) 8200.00

Grand Total 41000.00

Say. Rate / Unit Rft. 410.00

Plumbing Works
3-SOIL , WASTE, VANTILATING PIPES

BOQ REF Providing, fixing, cutting, jointing and testing uPVC piping conforming to ISO 3633:1991
# 3.1 (b) ( wall thickness=3.2 mm) including uPVC fittings with solvent cement jointing Dadex make
"Class B" or approved equal , rates include cost of clamping to walls and ceiling , hangers,
supports, cutting through walls and providing sleeves through concrete slabs for pipelines and
pipe fittings of the following diameter:

u PVC pipe 3" dia


Unit %Rft.
S.# Description Qty Unit Rate Amount
MATERIAL
1- 3" Dia Pipe 100 Rft. 119 11900.00
2- Fitting bend, socket (60% of Pipe 7140.00
cost)

Total 19040.00
LABOUR
1 Labour Charges 100 Rft. 40 4000.00

Total 4000.00

Material 19040.00
Labour 4000.00
Sub Total (a) 23040.00

Add 25% Overhead charges 25 5760.00

Sub Total (b) 5760.00

Grand Total 28800.00

Say. Rate / Unit Rft. 288.00

Plumbing Works
3-SOIL , WASTE, VANTILATING PIPES
BOQ REF Providing, fixing, cutting, jointing and testing uPVC piping conforming to ISO 3633:1991
# 3.1 (c) ( wall thickness=3.2 mm) including uPVC fittings with solvent cement jointing Dadex make
"Class B" or approved equal , rates include cost of clamping to walls and ceiling , hangers,
supports, cutting through walls and providing sleeves through concrete slabs for pipelines and
pipe fittings of the following diameter:

u PVC pipe 2" dia


Unit %Rft.
S.# Description Qty Unit Rate Amount
MATERIAL
1- 2" Dia Pipe 100 Rft. 84 8400.00
2-
5040.00
Fitting bend, socket (60% of pipe cost)

Total 13440.00
LABOUR
1 Labour Charges 100 Rft. 30 3000.00

Total 3000.00

Material 13440.00
Labour 3000.00
Sub Total (a) 16440.00

Add 25% Overhead charges 25 4110.00

Sub Total (b) 4110.00

Grand Total 20550.00


Say. Rate / Unit Rft. 206

Plumbing Works
3-SOIL , WASTE, VANTILATING PIPES
BOQ REF Providing, Laying RCC Pipe of WASA Standard Quality Class-II i/c Laying at site complete as per
# 3.2 (a) drawing, design and as instructed by the Engineer.

RCC pipe 9" dia


Unit %Rft
S.# Description Qty unit Rate Amount
MATERIAL
1- 9" Dia RCC Pipe 100 Rft 162 16200.00
2- Rubber Ring 9" dia 8 each 15 120.00

Total 16320.00
LABOUR
1 Labour for Laying 100 Rft 50 5000.00

Total 5000.00

Material 16320.00
Labour 5000.00
Sub Total (a) 21320.00

Add 25% Overhead charges 25 5330.00

Sub Total (b) 5330.00

Grand Total 26650.00

Say. Rate / unit Rft 266.50

Plumbing Works
3-SOIL , WASTE, VANTILATING PIPES

BOQ REF Providing and fixing 100 mm dia uPVC floor trap including Stainless Steel grating ,and cover.
# 3.3

Floor Trap
Unit /Nos
S.# Description Qty Unit Rate Amount
MATERIAL
1 Floor Trap 1 Each 344 344.00

Total 344.00
LABOUR
1 Labour Charges 1 Each 500 500.00

Total 500.00

Material 344.00
Labour 500.00
Sub Total (a) 844.00

Add 25% Overhead charges 25 211.00


Sub Total (b) 211.00

Grand Total 1055.00

Say. Rate / Unit /Nos 1055.00

Plumbing Works
3-SOIL , WASTE, VANTILATING PIPES
BOQ REF Providing and constructing gully trap of size 6" x 6" at locations shown on drawings with cover,
# 3.4 complete in all respects.

Gully trap 6" x 6"


Unit /Nos
S.# Description Qty Unit Rate Amount
MATERIAL
1- RCC Gulley Trap 6"x6" 1 Each 336 336.00
2- C.I Cover 8" dia 1 Each 290 290.00

Total 626.00
LABOUR
1 Labour Charges 1 Each 500 500.00

Total 500.00

Material 626.00
Labour 500.00
Sub Total (a) 1126.00

Add 25% Overhead charges 25 281.50

Sub Total (b) 281.50

Grand Total 1407.50

Say. Rate / Unit /Nos 1407.50

Plumbing Works
4- MISELLANEOUS
BOQ REF Provide, install, test and commission Gas geysers - Ambassador/Canon - of capacity 35 gallons
# 4.4 each complete with inlet, outlet, safety valves complete in all repects.

Gas Geysers of 35 Liter


Unit /Nos
S.# Description Qty Unit Rate Amount
MATERIAL

1 Gas Geyser - 35 ltrs 1 Each 13300 13300.00

Total 13300.00
LABOUR
1 Labour Charges 1 Each 1000 1000.00

Total 1000.00
Material 13300.00
Labour 1000.00
Sub Total (a) 14300.00

Add 25% Overhead charges 25 3575.00

Sub Total (b) 3575.00

Grand Total 17875.00

Say. Rate / Unit 17875.00


Sports Complex Phase-VI, DHA, Lahore Cantt.
GROUNDS & INTERNAL WORKS
CIVIL WORKS - Measurment Sheet
Measurements (ft)
Item No. Description No. L B H Quantities
IPC#4
1 EARTH WORKS
Excavation for foundations for walls and
columns in all kind of soil and back filling the
excavated material including breaking clods,
watering, compaction in layers not exceeding
12" in depth to full compaction, dressing and
1.1 disposal of surplus excavated stuff complete as
per drawings, specification and as directed by
the Engineer Incharge.

Grid, 2-15 /B-R


Wall-1 2 x 1 58.25 2.75 2.50 800.94 Cft
Wall-2 (Grid, R/2 - 15) 2 x 1 30.50 2.75 2.50 419.38 Cft
Wall-3 4 x 1 22.50 2.75 2.50 618.75 Cft
Wall-4 2 x 1 45.75 2.75 2.50 629.06 Cft
Columns Footing FA-FA 12 x 1 4.00 3.00 2.50 360.00 Cft
IPC#5
inside walls 4-1/2" thick
Wall-1 2 x 1 7.00 1.50 1.00 21.00 Cft
Wall-2 2 x 1 6.00 1.50 1.00 18.00 Cft
Wall-3 8 x 1 5.00 1.50 1.00 60.00 Cft
Wall-4 8 x 1 2.88 1.50 1.00 34.56 Cft
Wall-5 2 x 1 5.42 1.50 1.00 16.26 Cft
Wall-6 2 x 1 6.50 1.50 1.00 19.50 Cft
Wall-7 2 x 1 5.38 1.50 1.00 16.14 Cft
Wall-8 2 x 1 1.75 1.50 1.00 5.25 Cft
Total Qty up to IPC-12 3018.84
Previouse Paid -3018.84 Cft
Net Qty This IPC-12 0.00 Cft
Supply Ghasso from approved sources
including digging, loading and unloading and
filling including dressing, watering and
consolidation by ramming in layers not
1.4 exceeding 6" in depth to full compaction upto
99% complete as per drawings, specification
and as directed by the Engineer Incharge.

IPC-9
Ghasso Filling 1 x 1 56.00 32.08 3.00 5389.44 Cft
Less Walls
Less Long Wall 8 2 x 1 21.13 0.75 3.00 -95.06 Cft
Less Short Wall 9 4 x 1 19.75 0.75 3.00 -177.70 Cft
Less wall-1 2 x 1 7.00 0.375 3.00 -15.75 Cft
Less wall-2 2 x 1 8.75 0.375 3.00 -19.68 Cft
Less wall-3 2 x 1 8.75 0.375 3.00 -19.68 Cft
Less wall-4 2 x 1 6.92 0.375 3.00 -15.57 Cft
Less wall-5 8 x 1 5.00 0.375 3.00 -45.00 Cft
Less wall-7 2 x 1 6.00 0.375 3.00 -13.50 Cft
2 x 1 5.44 0.375 3.00 -12.24 Cft
Total Qty up to IPC-12 4975.26 Cft
Previouse Paid 3731.00 Cft
Held Qty Now Claim in IPC-12 1244.26 Cft

Sheet-38
Sports Complex Phase-VI, DHA, Lahore Cantt.
GROUNDS & INTERNAL WORKS
CIVIL WORKS - Measurment Sheet
Measurements (ft)
Item No. Description No. L B H Quantities

Providing mixing and spraying anti termite


solution Fiprokil, Fipronil or approved
equivalent mixed with water, as per
2.1 manufacturer's specification etc complete as
per drawings, specification and as directed by
the Engineer Incharge.

IPC-4
Grid, 2-15 /B-R
Wall-1 2 x 1 58.25 2.75 320.39 Sft
Wall-2 (Grid, R/2 - 15) 2 x 1 30.50 2.75 167.75 Sft
Wall-4 2 x 1 45.75 2.75 251.63 Sft
Columns Footing FA-FA 12 x 1 4.00 3.00 144.00 Sft
IPC-5
Inside Walls 4-1/2" Thik
Wall-1 2 x 1 7.00 1.50 21.00 Sft
Wall-2 2 x 1 6.00 1.50 18.00 Sft
Wall-3 8 x 1 5.00 1.50 60.00 Sft
Wall-4 8 x 1 2.88 1.50 34.56 Sft
Wall-5 2 x 1 5.42 1.50 16.26 Sft
Wall-6 2 x 1 6.50 1.50 19.50 Sft
Wall-7 2 x 1 5.38 1.50 16.14 Sft

Wall-8 2 x 1 1.75 1.50 5.25 Sft


balance qty ipc-4 247.49
IPC-9
Termite under P.C.C 1 x 1 56.00 32.08 - 1796.48 Sft
Less Walls
Long Wall 8 -2 x 1 21.13 0.75 - -31.69 Cft
Short Wall 9 -4 x 1 19.75 0.75 - -59.25 Cft
wall-1 -2 x 1 7.00 0.375 - -5.25 Sft
wall-2 -2 x 1 8.75 0.375 - -6.56 Sft
wall-3 -2 x 1 8.75 0.375 - -6.56 Sft
wall-4 -2 x 1 6.92 0.375 - -5.15 Sft
wall-5 -8 x 1 5.00 0.375 - -15.00 Sft
wall-6 -2 x 1 2.00 0.375 - -1.50 Sft
wall-7 -2 x 1 6.00 0.375 - -4.50 Sft
-2 x 1 5.44 0.375 - -4.08 Sft
Total Qty up to IPC-12 2978.90 Sft
Previouse paid -2978.90 Sft
Net Qty This IPC-12 0.00 Sft

Providing and laying 1:4:8 cement concrete mix


using Chenab sand and graded stone ballast 2"
and down gauge in foundations/under floor
3.1 including leveling, compacting and curing etc
complete as per drawings, specification and as
directed by the Engineer Incharge.

IPC#4

Sheet-39
Sports Complex Phase-VI, DHA, Lahore Cantt.
GROUNDS & INTERNAL WORKS
CIVIL WORKS - Measurment Sheet
Measurements (ft)
Item No. Description No. L B H Quantities
Grid, 2-15 /B-R

Wall-1 2 x 1 58.25 2.75 0.33 105.72 Cft


Wall-2 (Grid, R/2 - 15) 2 x 1 30.50 2.75 0.33 55.36 Cft

Wall-3 4 x 1 22.50 2.75 0.33 81.68 Cft


Wall-4 2 x 1 45.75 2.75 0.33 83.04 Cft
Columns Footing FA-FA 12 x 1 4.00 3.00 0.33 47.53 Cft
IPC#5
Inside Walls 4-1/2" Thik
Wall-1 2 x 1 7.00 1.50 0.33 6.93 Cft
Wall-2 2 x 1 6.00 1.50 0.33 5.94 Cft
Wall-3 8 x 1 5.00 1.50 0.33 19.80 Cft
Wall-4 8 x 1 2.88 1.50 0.33 11.40 Cft
Wall-5 2 x 1 5.42 1.50 0.33 5.37 Cft
Wall-6 2 x 1 6.50 1.50 0.33 6.44 Cft
Wall-7 2 x 1 5.38 1.50 0.33 5.33 Cft
Wall-8 2 x 1 1.75 1.50 0.33 1.73 Cft
This IPC-9
P.C.C (1:4:8) 1 x 1 56.00 32.08 0.33 598.23 Cft
Less Walls
Less Long Wall 8 -2 x 1 21.13 0.75 0.33 -10.56 Cft
Less Short Wall 9 -4 x 1 19.75 0.75 0.33 -19.73 Cft
Less wall-1 -2 x 1 7.00 0.375 0.33 -1.75 Cft
Less wall-2 -2 x 1 8.75 0.375 0.33 -2.19 Cft
Less wall-3 -2 x 1 8.75 0.375 0.33 -2.19 Cft
Less wall-4 -2 x 1 6.92 0.375 0.33 -1.73 Cft
Less wall-5 -8 x 1 5.00 0.375 0.33 -5.00 Cft
Less wall-6 -2 x 1 2.00 0.375 0.33 -0.50 Cft
Less wall-7 -2 x 1 6.00 0.375 0.33 -1.50 Cft
Less -2 x 1 5.44 0.375 0.33 -1.36 Cft
Total Qty up to IPC-12 987.99 Cft
Previouse paid -987.99 Cft
Net Qty This IPC-12 0.00 Cft
Providing and laying reinforced cement
concrete using graded stone crush 3/4" and
down gauge having a minimum works cylinder
crushing strength of 3000 psi at 28 days with a
mix not leaner than 1:2:4 in Foundations,
Plinth/footing beams of required section
including form work and its removal,
3.2 compacting and curing etc complete as per
drawings, specification and as directed by the
Engineer Incharge but excluding the cost of
reinforcement. (30% chenab sand + 70%
Lawarancpur sand and Margla crush).

IPC-4
FA-FA 12 x 1 4.00 3.00 0.75 108.00 Cft
IPC-9
Filling Concrete 1 x 1 4.00 4.00 4.500 72.00 Cft
Sheet-40
Sports Complex Phase-VI, DHA, Lahore Cantt.
GROUNDS & INTERNAL WORKS
CIVIL WORKS - Measurment Sheet
Measurements (ft)
Item No. Description No. L B H Quantities
Total Qty up to IPC-12 180.00 Cft
Previouse Paid -180.00 Cft
Net balance Qty This IPC-12 Nil Cft

Providing and laying reinforced cement


concrete using graded stone crush 1/2" and
down gauge having a minimum works cylinder
crushing strength of 4000 psi at 28 days with a
mix not leaner than 1:1-1/2:3 in Columns and
pillars of required section including form work
and its removal, compacting and curing etc
3.3 complete as per drawings, specification and as
directed by the Engineer Incharge but
excluding the cost of reinforcement. (30%
chenab sand + 70% Lawarancpur sand and
Margla crush). (Mixed by Weight Batching
Plant)

IPC-5
C-1 24 x 1 1.00 0.67 7.42 119.31 Cft
RCC Wall 12 x 1 1.67 0.33 7.42 49.07 Cft
IPC#7
C-1 24 x 1 1.00 0.67 10.00 160.80 Cft.
Columns mid slab Qty 12 x 1 1.67 1.00 0.25 5.01 Cft.
cap of column mid 12 x 1 1.67 1.00 1.25 25.05 Cft.
Total Qty up to IPC-12 359.24 Cft.
Previouse Paid -359.24 Cft.
Net Qty This IPC-12 0.00 Cft.
Providing and laying reinforced cement
concrete using graded stone crush 3/4" and
down gauge having a minimum works cylinder
crushing strength of 3000 psi at 28 days with a
mix not leaner than 1:2:4 in Slab, Beams,
pavilion slab, steps, lintels, shelves & Parapet
of required section including form work and its
3.5 removal, compacting and curing etc complete
as per drawings, specification and as directed
by the Engineer Incharge but excluding the
cost of reinforcement. (30% chenab sand +
70% Lawarancpur sand and Margla crush).

IPC#6
Lintels
L-2 2 x 1 4.75 0.75 0.75 5.34 Cft
IPC#7
Beams , Lintel & Slab
Lintels of Vantilators 8 x 1 3.50 0.75 0.50 10.50 Cft
Lintels of Doors 2 x 1 4.75 0.75 0.50 3.56 Cft
B-1 4 x 1 20.50 1.00 0.75 61.50 Cft
B-1 4 x 1 22.00 1.00 0.75 66.00 Cft
B-2 2 x 1 58.00 0.75 2.00 174.00 Cft
Deduction -2 x 1 58.00 0.75 0.50 -43.50 Cft
B-3 2 x 1 32.25 1.00 2.00 129.00 Cft
Sheet-41
Sports Complex Phase-VI, DHA, Lahore Cantt.
GROUNDS & INTERNAL WORKS
CIVIL WORKS - Measurment Sheet
Measurements (ft)
Item No. Description No. L B H Quantities
Deduction -2 x 1 32.25 0.75 0.50 -24.19 Cft

Roof Slab Concrete 1 x 1 58.00 34.25 0.42 834.33 Cft


IPC-8
Lintels on 4.5" thick wall
D-1 1 x 1 4.75 0.375 0.50 0.89 Cft
D-2 2 x 1 4.50 0.375 0.50 1.69 Cft

D3 8 x 1 4.00 0.375 0.50 6.00 Cft


V1 2 x 1 5.75 0.375 0.50 2.16 Cft
V4 1 x 1 3.50 0.375 0.50 0.66 Cft
Total Qty up to IPC-12 1227.94 Cft
Previouse Paid -1227.94 Cft
Net Qty This IPC-12 0.00 Cft
Providing and laying 1-1/2" thick damp proof
course with cement concrete 1:2:4 cast insitu
using graded screened crush of 1/2" and down
gauge i/c compacting, curing, form work and its
removal etc. complete with applying a coat of
hot bitumen using 35 lbs. per hundred square
5.1 feet (1.71 kg/sqm) on damp proof course after
complete drying and cleaning the surface etc.
complete as per drawings, specification and as
directed by the Engineer Incharge.

IPC-6
Section A-A
Long Wall Out Side 4 x 1 58.25 1.13 263.29 Sft
Short Wall Out Side 4 x 1 34.08 1.13 154.01 Sft
Long Wall Inside 2 x 1 45.50 1.13 102.38 Sft
Short Wall Inside 4 x 1 22.50 1.13 101.25 Sft
Inside Section B-B
Wall-1 2 x 1 7.00 0.75 10.50 Sft
Wall-2 2 x 1 6.00 0.75 9.00 Sft
Wall-3 8 x 1 5.00 0.75 30.00 Sft
Wall-4 8 x 1 2.88 0.75 17.28 Sft
Wall-5 2 x 1 5.42 0.75 8.13 Sft
Wall-6 2 x 1 6.50 0.75 9.75 Sft
Wall-7 2 x 1 5.38 0.75 8.07 Sft
Wall-8 2 x 1 1.75 0.75 2.63 Sft
Total Qty up to IPC-12 716.28 Sft.
Previouse Paid -716.28 Sft
Net Qty This IPC-12 0.00 Sft
Providing and laying first class burnt brick
masonry set in cement mortar 1:5 (OPC +
Chenab sand) in straight or curved wall
including scaffolding, raking out joints and
6.1 curing etc in foundation etc. complete as per
drawings, specification and as directed by the
Engineer Incharge. (Compressive strength =
1800psi)

IPC-4
Wall-1 Long Side 2 x 1 59.50 2.25 0.50 133.88 Cft
Step-2 2 x 1 59.08 1.82 0.50 107.53 Cft
Step-3 2 x 1 58.66 1.50 0.50 87.99 Cft
Sheet-42
Sports Complex Phase-VI, DHA, Lahore Cantt.
GROUNDS & INTERNAL WORKS
CIVIL WORKS - Measurment Sheet
Measurements (ft)
Item No. Description No. L B H Quantities

Step-4 2 x 1 58.25 1.13 6.00 789.87 Cft


Wall-2 Short Wall
Step-1 2 x 1 33.00 2.25 0.50 74.25 Cft
Step-2 2 x 1 33.14 1.82 0.50 60.32 Cft
Step-3 2 x 1 33.84 1.50 0.50 50.76 Cft
Step-4 2 x 1 34.26 1.13 6.00 464.57 Cft
Inside Section A-A
Wall-1

Step-1 4 x 1 23.76 2.25 0.50 106.92 Cft


Step-2 4 x 1 23.34 1.82 0.50 84.96 Cft
Step-3 4 x 1 22.92 1.50 0.50 68.76 Cft
Step-4 4 x 1 22.50 1.13 6.00 610.20 Cft
Wall-2
Step-1 2 x 1 55.81 2.25 0.50 125.57 Cft
Step-2 2 x 1 44.33 1.82 0.50 80.68 Cft
Step-3 2 x 1 43.91 1.50 0.50 65.87 Cft
Step-4 2 x 1 43.49 1.13 6.00 472.88 Cft
IPC#5
Section B-B
Wall-1 Step-1 2 x 1 6.83 1.13 0.50 5.46 Cft
Step-2 2 x 1 7.00 0.75 6.00 63.00 Cft
Wall-2 Step-1 2 x 1 5.83 1.13 0.50 6.59 Cft
Step-2 2 x 1 6.00 0.75 6.00 54.00 Cft
Wall-3 Step-1 8 x 1 4.83 1.13 0.50 21.83 Cft
Step-2 8 x 1 5.00 0.75 6.00 180.00 Cft
Wall-4 Step-1 8 x 1 4.33 1.13 0.50 19.57 Cft
Step-2 8 x 1 4.50 0.75 6.00 162.00 Cft
Wall-5 Step-1 2 x 1 5.78 1.13 0.50 6.53 Cft
Step-2 2 x 1 5.95 0.75 6.00 53.55 Cft
Wall-6 Step-1 2 x 1 6.33 1.13 0.50 7.15 Cft
Step-2 2 x 1 6.50 0.75 6.00 58.50 Cft
Wall-7 Step-1 2 x 1 5.17 1.13 0.50 5.84 Cft
Step-2 2 x 1 5.38 0.75 6.00 48.42 Cft
Wall-8 Step-1 2 x 1 1.82 1.13 0.50 2.06 Cft
Step-2 2 x 1 2.00 0.75 6.00 18.00 Cft
IPC-10
Brick work tube well foundation 1 x 2 5.50 0.75 4.50 18.56 Cft
1 x 2 4.00 0.75 4.50 13.50 Cft
Total Qty up to IPC-12 4129.56 Cft
Previouse Paid -4129.56 Cft
Net Qty This IPC-12 Nil Cft
Providing and laying first class burnt brick
masonry in 9" thick wall set in cement mortar
(OPC + Chenab sand) 1:5 in straight or curved
wall including scaffolding, raking out joints and
curing etc in super structure at any height
6.2 complete as per drawings, specification and as
directed by the Engineer Incharge.
(Compressive strength = 1800psi)

Sheet-43
Sports Complex Phase-VI, DHA, Lahore Cantt.
GROUNDS & INTERNAL WORKS
CIVIL WORKS - Measurment Sheet
Measurements (ft)
Item No. Description No. L B H Quantities
IPC#6
Inside Wall Section B-B
Long Wall 4 x 1 21.13 0.75 10.00 698.03 Cft
Short Wall 4 x 1 135.00 0.75 10.00 4051.23 Cft
Brick Columns 13-1/2
Columns 8 x 1 0.75 0.75 10.00 45.00 Cft
Deduction Doors
D-1 -2 x 1 3.25 0.75 7.00 -34.13 Cft
V-2 -6 x 1 2.00 0.75 1.00 -9.00 Cft
V-3 -4 x 1 1.00 0.75 1.00 -3.00 Cft
Total Qty up to IPC-12 4748.13 Cft
Previouse Paid -4748.13 Cft
Net Qty This IPC-12 0.00 Cft

Providing and laying first class burnt brick


masonry in 4 1/2" thick wall set in cement
mortar (OPC + Chenab sand) 1:3 in straight or
curved wall including scaffolding, raking out
6.3 joints and curing etc in super structure at any
height complete as per drawings, specification
and as directed by the Engineer Incharge.
(Compressive strength = 1800psi)

IPC-8
wall-1 2 x 1 7.00 - 9.00 126.00 Sft
wall-2 2 x 1 8.75 - 9.00 157.50 Sft
wall-3 2 x 1 8.75 - 9.00 157.50 Sft
wall-4 2 x 1 6.92 - 9.00 124.56 Sft
wall-5 8 x 1 5.00 - 9.00 360.00 Sft
wall-6 2 x 1 2.00 - 9.00 36.00 Sft
wall-7 2 x 1 6.00 - 9.00 108.00 Sft
2 x 1 5.44 - 9.00 97.92 Sft
Deductions Door
D-1 -1 x 1 3.25 - 7.00 -22.75 Sft
D-2 -2 x 1 3.00 - 7.00 -42.00 Sft
D3 -8 x 1 2.50 - 7.00 -140.00 Sft
Deductions Vantilators
V1 -2 x 1 4.25 - 1.67 -14.17 Sft
V4 -1 x 1 2.00 - 1.67 -3.33 Sft
Deductions Lintels
D-1 -1 x 1 4.75 - 0.50 -2.38 Sft
D-2 -2 x 1 4.50 - 0.50 -4.50 Sft
D3 -8 x 1 4.00 - 0.50 -16.00 Sft
V1 -2 x 1 5.75 - 0.50 -5.75 Sft
V4 -1 x 1 3.50 - 0.50 -1.75 Sft
Total Qty up to IPC-12 914.89 Sft
previouse Paid -914.89 Sft
Net Qty This IPC-12 0.00 Sft

Sheet-44
Sports Complex Phase-VI, DHA, Lahore Cantt.
GROUNDS & INTERNAL WORKS
CIVIL WORKS - Measurment Sheet
Measurements (ft)
Item No. Description No. L B H Quantities
1/2" thick Cement plaster 1:4 on walls and
columns etc including making edges, smooth
with steel trowel, corners, and curing etc. on
Internal surfaces with ordinary portland cement
7.2 and chenab sand at any height complete as
per drawings, specification and as directed by
the Engineer Incharge.

IPC-8
Wall-8 outer side 4 x 1 19.708 - 9.00 709.49 Sft
Wall-9 outer side 4 x 1 19.83 - 9.00 713.99 Sft
Piller 8 x 1 3.00 - 9.00 216.00 Sft
wall-7 2 x 1 5.92 - 9.00 106.51 Sft
Add Patti
D-1 3 x 1 17.25 0.75 - 38.81 Sft
V-3 4 x 1 5.33 0.75 - 15.99 Sft
V-2 6 x 1 7.00 0.75 - 31.50 Sft
V-4 1 x 1 7.00 0.75 - 5.25 Sft
Add Shade of Roof Slab Under soffit
1 x 1 58.25 8.00 - 466.00 Sft
1 x 1 58.25 5.00 - 291.25 Sft
1 x 2 21.24 5.00 - 212.40 Sft
Sides B3 &B2
1 x 1 58.25 - 2.00 116.50 Sft
2 x 1 34.25 - 2.00 137.00 Sft
Deductions
D-1 -3 x -1 3.25 - 7.00 68.25 Sft
V-3 -4 x -1 1.00 - 1.50 6.00 Sft
V-2 -6 x -1 2.00 - 1.50 17.94 Sft
V-4 -1 x -1 2.00 - 1.50 3.00 Sft
IPC-9
wall-1 2 x 2 7.00 - 9.00 252.00 Sft
wall-2 2 x 4 4.00 - 9.00 288.00 Sft
wall-3 2 x 4 4.00 - 9.00 288.00 Sft
wall-4 2 x 2 6.98 - 9.00 251.37 Sft
wall-5 2 x 8 5.00 - 9.00 720.00 Sft
wall-6 2 x 2 2.00 - 9.00 72.00 Sft
wall-7 1 x 4 6.00 - 9.00 216.00 Sft
wall-8 2 x 2 19.625 - 9.00 706.50 Sft
wall-9 2 x 2 19.75 - 9.00 711.00 Sft
Roof under soffit 2 x 1 19.63 19.75 - 775.19 Sft
Outer Long side wall 13-1/2" plaster 2 x 1 58.25 - 3.00 349.50 Sft
Outer short side wall 13-1/2" plaster 2 x 1 34.25 - 3.00 205.50 Sft
Patti of door
D3 2 x 4 16.50 0.50 - 66.00 Sft
D-2 2 x 1 17.00 0.50 - 17.00 Sft
D1 2 x 1 17.25 0.75 - 25.88 Sft
V1 2 x 1 11.84 0.50 - 11.84 Sft
V2 2 x 3 7.34 0.75 - 33.03 Sft
V-3 2 x 2 5.34 0.75 - 16.02 Sft

Box 2 x 4 3.33 0.75 - 19.99 Sft


Add Columns

Sheet-45
Sports Complex Phase-VI, DHA, Lahore Cantt.
GROUNDS & INTERNAL WORKS
CIVIL WORKS - Measurment Sheet
Measurements (ft)
Item No. Description No. L B H Quantities
C-1 24 x 1 3.67 - 7.75 682.62 Sft
C-1 Cap sides 12 x 1 8.42 - 1.25 126.30 Sft
C-1 Cap bottom 12 x 1 1.67 1.00 - 20.04 Sft
Slab mid Between Columns Top &
Bottom Face 12 x 2 1.66 - 1.00 39.94 Sft
Sides of Slab 12 x 2 1.66 - 0.33 13.27 Sft
Side of B-3 1 x 1 58.25 - 2.00 116.50 Sft
Add mid portion of Roof under soffit 1 x 1 21.25 6.00 - 127.50 Sft

Less Door vantilators


D3 -2 x 8 2.50 - 7.00 -280.00 Sft
D-2 -2 x 2 3.00 - 7.00 -84.00 Sft
D1 -2 x 1 3.25 - 7.00 -45.51 Sft
V1 -2 x 1 4.25 - 1.66 -14.11 Sft
V2 -2 x 3 2.00 - 1.66 -19.92 Sft
V-3 -2 x 2 1.00 - 1.66 -6.64 Sft
Box -2 x 4 0.83 - 0.83 -5.55 Sft
Total Qty up to IPC-12 8851.12 Sft
Previouse Paid -8851.12 Sft
Net Qty pay This IPC-12 Nil Sft

13 MISCELLANEOUS
Providing and fixing uPVC pipes rainwater
down pipe of required dia. including all
necessary accessories with bolts and nuts fixed
in cement concrete 1:2:4 complete as per
13.1 drawings, specification and as directed by the
Engineer Incharge. 4" dia

IPC-10

(i) UPVC PiPe on Each Column 1 x 4 - - 15.50 62.00 Rft


Total Qty up to IPC-12 62.00 Rft
Previouse Paid 62.00 Rft
Net Qty This IPC-12 0.00 Rft

20.1 . Area
IPC-2
Area A 1 x 1 121898.00 1.97 240139.06 Cft
Area B 1 x 1 74390.59 1.24 92244.33 Cft
Area C 1 x 1 27135.69 1.35 36633.18 Cft
Area D 1 x 1 75106.00 0.54 40557.24 Cft
Total 409,573.81 Cft
Gym Area 1 x 1 174,314.14 Cft
Total Qty up to IPC-12 583,887.95 Cft
Previouse Paid 583,887.95 Cft
Net Qty This IPC-12 Nil Cft
B Plumbing work

Sheet-46
Sports Complex Phase-VI, DHA, Lahore Cantt.
GROUNDS & INTERNAL WORKS
CIVIL WORKS - Measurment Sheet
Measurements (ft)
Item No. Description No. L B H Quantities
Part-2: WATER SUPPLY
Providing, fixing, jointing and testing
Polypropylene Random (PPR) pipes Dadex
make "Polydex" or approved equivalent
pressure pipe for cold water as per DIN 8077-
8078 for pipes and DIN 16962, PN25 for fittings
(polyfusion welded joints) inside building
including fittings and specials (sockets, tees,
elbows, bends, crosses, reducers, adaptor,
2.1 plugs and union etc.) supported on walls or
suspended from roof slab or run in chases
including pipe hangers, supports, cutting and
making good the chases and holes, complete
in all respects.

IPC-9
b 32mm dia PIPE
From wash basin To Bath
Line-1,3,5,7,10 2 x 2 62.25 - - 249 Rft
Geyser Line
line -12, 15 1 x 1 9.50 - - 9.5 Rft

Main Line approch 1 x 1 22.00 - - 22 Rft


Total Qty up IPC-12 280.5 Rft
Previouse paid -280.5 Rft
Net Qty This IPC-12 0 Rft

c 25mm dia PIPE


up point-4 wash basin
Line-2,6 2 x 1 - - 17.00 34 Rft

up point-4 for shower&cock in bath line 4,8 2 x 1 - - 44.00 88 Rft

Line-13,14 up point for wash basin &cock 1 x 1 - - 16.00 16 Rft


Total Qty up IPC-12 138 Rft
Previouse -138 Rft
Net Qty This IPC-12 0 Rft
Part-3 Sewrage Line
Providing, fixing, cutting, jointing and testing
uPVC piping conforming to ISO 3633:1991
(wall thickness=3.2 mm) including uPVC fittings
with solvent cement jointing Dadex make
"Class B" or approved equal, rates include cost
3.1 of clamping to walls and ceiling , hangers,
supports, cutting through walls and providing
sleeves through concrete slabs for pipelines
and pipe fittings of the following diameter:

IPC-9
(i) upvc PiPe 4" dia
Line-1 1 x 1 1.50 - - 1.5 Rft
Line-2 1 x 1 4.33 - - 4.33 Rft
Line-3 1 x 1 2.58 - - 2.583 Rft
Line-4 1 x 1 4.00 - - 4 Rft

Line-5 1 x 1 6.00 - - 6 Rft


Sheet-47
Sports Complex Phase-VI, DHA, Lahore Cantt.
GROUNDS & INTERNAL WORKS
CIVIL WORKS - Measurment Sheet
Measurements (ft)
Item No. Description No. L B H Quantities
Line-6 1 x 1 3.67 - - 3.67 Rft
Line-7 1 x 1 25.25 - - 25.25 Rft
Line-8 1 x 1 25.25 - - 25.25 Rft
Line-9 1 x 1 24.00 - - 24 Rft
Line-10 1 x 1 23.75 - - 23.75 Rft
Line-11 1 x 1 7.67 - - 7.67 Rft
Line-12 1 x 1 10.92 - - 10.92 Rft
Line-13 1 x 1 5.83 - - 5.833 Rft
Line-14 1 x 1 6.50 - - 6.5 Rft
Line-15 1 x 1 7.50 - - 7.5 Rft
Line-16 1 x 1 10.75 - - 10.75 Rft
Line-17 1 x 1 5.83 - - 5.833 Rft
Line-18 1 x 1 6.33 - - 6.333 Rft
Total Qty up IPC-12 181.672 Rft
Previouse -181.672 Rft
Net Qty This IPC-12 0.00 Rft

Irrigation Part
u pvc Class D irrigation standard BS 3505
PiPe Line with all matching molded fittings
9 of dia

This IPC-12

1.5 inch dia 1 x 1 1946.16 - - 1946.16 ft


2 inch dia 1 x 1 1792.50 - - 1792.50 ft
3 inch dia 1 x 1 1000.50 - - 1000.50 ft
4 inch dia 1 x 1 526.00 526.00 ft

Non BOQ Item


Supply Earth filling material on site loading
,unloading and including filling in ground Area
with leveling ,dressing and watering complete
as per drawings, specification and as directed
by the Engineer Incharge.

IPC-10
Total Area 1 x 1 600.875 533.125 1.75 560597.60

Add Area Solid wall Column No(226-236) 1 x 1 40.675 19.625 1.75 1396.93

Less End Triangle -1 x 0.50 7.46 19 1.75 -124.02


-1 x 0.50 6.5 6.5 1.75 -36.97
Less Gym Area
Grid( H-N1)/4-10 -1 x 1 163.783 119.5 1.75 -34251.12
Grid( H-P)/(2-4) -1 x 1 178.783 41.25 1.75 -12905.90
Grid(M-P)/(1-2) -1 x 1 43.92 14.5 1.75 -1114.47
Grid(H-J)/(1-2) -1 x 1 44.5 14.5 1.75 -1129.19
Grid(J-M)/1-2 -1 x 1 37.25 12 1.75 -782.25
-2 x 1 21.25 6 1.75 -446.25
Sheet-48
Sports Complex Phase-VI, DHA, Lahore Cantt.
GROUNDS & INTERNAL WORKS
CIVIL WORKS - Measurment Sheet
Measurements (ft)
Item No. Description No. L B H Quantities
Less Tennis Grid(A-H)/4-10 -1 x 1 142.075 120.75 1.75 -30022.22
Tiolet Block -1 x 1 58.25 34.25 1.75 -3491.36
Pavilion -1 x 1 141.91 33.123 1.75 -8225.85
-1 x 1 18.333 52.67 1.75 -1668.66
-1 x 1 25.42 1.75 1.75 -77.85
-1 x 1 15.42 7 1.75 -188.90
Less Guard Room -1 x 1 11.04 8.5 1.75 -164.22
-1 x 1 13.25 7 1.75 -162.31
This IPC-12
Total Area 1 x 1 600.875 533.125 0.50 160170.74
Add Area Solid wall Column No(226-236) 1 x 1 40.675 19.625 0.50 399.12
Less End Triangle -1 x 0.50 7.46 19 0.50 -35.44
-1 x 0.50 6.5 6.5 0.50 -10.56
Less Gym Area
Grid( H-N1)/4-10 -1 x 1 163.783 119.5 0.50 -9786.03
Grid( H-P)/(2-4) -1 x 1 178.783 41.25 0.50 -3687.40
Grid(M-P)/(1-2) -1 x 1 43.92 14.5 0.50 -318.42
Grid(H-J)/(1-2) -1 x 1 44.5 14.5 0.50 -322.63
Grid(J-M)/1-2 -1 x 1 37.25 12 0.50 -223.50
-2 x 1 21.25 6 0.50 -127.50
Less Tennis Grid(A-H)/4-10 -1 x 1 142.075 120.75 0.50 -8577.78
Tiolet Block -1 x 1 58.25 34.25 0.50 -997.53
Pavilion -1 x 1 141.91 33.123 0.50 -2350.24
-1 x 1 18.333 52.67 0.50 -461.66
-1 x 1 25.42 1.75 0.50 -22.24
-1 x 1 15.42 7 0.50 -53.97
Less Guard Room -1 x 1 11.04 8.5 0.50 -46.92
-1 x 1 13.25 7 0.50 -46.38
Total Qty up to IPC-12 600704.67
Previouse Bill -467203.00
Net Qty This IPC-12 133501.67

Sheet-49
Sports Complex Phase-VI, DHA, Lahore Cantt.
GROUNDS & INTERNAL WORKS
CIVIL WORKS - Measurment Sheet
Measurements (ft)
Item No. Description No. L B H Quantities

Sheet-50
Sports Complex Phase-VI, DHA, Lahore Cantt.
GROUNDS & INTERNAL WORKS
CIVIL WORKS - Measurment Sheet
Measurements (ft)
Item No. Description No. L B H Quantities

Sheet-51
Sports Complex Phase-VI, DHA, Lahore Cantt.
GROUNDS & INTERNAL WORKS
CIVIL WORKS - Bills of Quantities
B.O.Q Previouse Certified This Certified Upto Date
S NO. DESCRIPTION UNIT RATE
Quantity Amount Quantity Amount Quantity Amount Quantity Amount

1 EARTH WORKS

1.1 Excavation for foundations for walls and columns in all


kind of soil and back filling the excavated material
including breaking clods, watering, compaction in
layers not exceeding 12" in depth to full compaction,
dressing and disposal of surplus excavated stuff
complete as per drawings, specification and as
directed by the Engineer Incharge.

Cft 7 16,529.0 115,703 3,018.86 21,132.00 - 3,018.86 21,132.00


All Excavated Material laying the Ground in 6" layers
full compaction and remaing Rate=(11-7)=4 Cft 4 16,529.0 66,116 3,018.82 12,075.28 - 3,018.8200 12,075.28
1.2 Back filling with excavated Material including breaking
clods,watering,compaction in layers not exceding 6" in
depth to full compaction ,dressing and as directed by
the Engineer Incharge.
4 6,000.0 24,000 - - -
1.3 Disposal of surplus excavated Material within DHA
Limits, and as directed by the Engineer Incharge.
6 3,234.9 19,409
1.4 Supply Ghasso from approved sources including
digging, loading and unloading and filling including
dressing, watering and consolidation by ramming in
layers not exceeding 6" in depth to full compaction
upto 99% complete as per drawings, specification and
as directed by the Engineer Incharge.

Cft 25 410,103.0 10,252,575 3,731.00 93,275.00 1,244.26 31,106.44 4,975.26 124,381.44


Non BOQ Item
Supply Earth filling material on site loading ,unloading
and including filling in ground Area with leveling
,dressing and watering complete as per drawings,
specification and as directed by the Engineer Incharge.

Cft 9.25 799,284.00 7,393,377 467,203.00 4,321,627.75 133,501.67 1,234,890.45 600,704.67 5,556,518.20

Total
4,448,110.0 1,265,996.89 5,714,106.9
2 TERMITE CONTROL TREATMENT
Providing mixing and spraying anti termite solution
Fiprokil, Fipronil or approved equivalent mixed with
2.1 water, as per manufacturer's specification etc complete
as per drawings, specification and as directed by the
Engineer Incharge.
Sft 10 5,889.0 58,890 2,978.90 29,789.00 - 2,978.90 29,789.00

Total
29,789.00 - 29,789.00

Sheet-52
B.O.Q Previouse Certified This Certified Upto Date
S NO. DESCRIPTION UNIT RATE
Quantity Amount Quantity Amount Quantity Amount Quantity Amount

3 PLAIN AND REINFORCED CONCRETE

Marghallah crush, Chenab 30% & LP 70% sand


3.1 Providing and laying 1:4:8 cement concrete mix using
Chenab sand and graded stone ballast 2" and down
gauge in foundations/under floor including leveling,
compacting and curing etc complete as per drawings,
specification and as directed by the Engineer Incharge.
Cft 200 14,794.0 2,958,800 987.99 197,598.00 - 987.99 197,598.00

3.2 Providing and laying reinforced cement concrete using


graded stone crush 3/4" and down gauge having a
minimum works cylinder crushing strength of 3000 psi
at 28 days with a mix not leaner than 1:2:4 in
Foundations, Plinth/footing beams of required section
including form work and its removal, compacting and
curing etc complete as per drawings, specification and
as directed by the Engineer Incharge but excluding the
cost of reinforcement. (30% chenab sand + 70%
Lawarancpur sand and Margla crush).

Cft 350 1,774.0 620,900 180.00 63,000.00 - 180.00 63,000.00


-
-
3.3 Providing and laying reinforced cement concrete using
graded stone crush 1/2" and down gauge having a
minimum works cylinder crushing strength of 4000 psi
at 28 days with a mix not leaner than 1:1-1/2:3 in
Columns and pillars of required section including form
work and its removal, compacting and curing etc
complete as per drawings, specification and as
directed by the Engineer Incharge but excluding the
cost of reinforcement. (30% chenab sand + 70%
Lawarancpur sand and Margla crush). (Mixed by
Weight Batching Plant)
Cft 400 208.0 83,200 359.24 143,697.76 359.24 143,697.76
- - - -
- - - -
3.4 Providing and laying reinforced cement concrete using
graded stone crush 1/2" and down gauge having a
minimum works cylinder crushing strength of 3000 psi
at 28 days with a mix not leaner than 1:2:4 in wall,
retaining wall, load bearing wall including form work
and its removal, compacting and curing etc complete
as per drawings, specification and as directed by the
Engineer Incharge but excluding the cost of
reinforcement. (30% chenab sand + 70% Lawarancpur
sand and Margla crush).

Cft 350 185.0 64,750 - - - -


- - - -
- - - -

Sheet-53
B.O.Q Previouse Certified This Certified Upto Date
S NO. DESCRIPTION UNIT RATE
Quantity Amount Quantity Amount Quantity Amount Quantity Amount
3.5 Providing and laying reinforced cement concrete using
graded stone crush 3/4" and down gauge having a
minimum works cylinder crushing strength of 3000 psi
at 28 days with a mix not leaner than 1:2:4 in Slab,
Beams, pavilion slab, steps, lintels, shelves & Parapet
of required section including form work and its
removal, compacting and curing etc complete as per
drawings, specification and as directed by the
Engineer Incharge but excluding the cost of
reinforcement. (30% chenab sand + 70% Lawarancpur
sand and Margla crush).

Cft 400 1,566.0 626,400 1,227.936 491,174.24 - 1,227.9356 491,174.24


- - - -
- - - -
3.6 Providing and laying 2" thick Cement concrete mix
1:2:4 using graded stone crush 1/2" and down gauge
as base layer under floor including the cost of cement
slurry etc complete as per drawings, specification and
as directed by the Engineer Incharge. (30% chenab
sand, 70 % Lawarancpur and margla crush)

Sft 57 1,831.0 104,367 - - - -

3.7 Providing and laying 2" thick Plain Cement concrete


1:2:4 top finish for plinth protection, including 1 1/2"
wide & 1/4" thick Marble divider at 2'.6" c/c complete
as per drawings, specification and as directed by the
Engineer Incharge. (30% chenab sand, 70 %
Lawarancpur and Margla crush)

Sft 65 698.0 45,370

Total 895,470.00 - 895,470


4 REINFORCEMENT

4.1 Providing and laying deformed steel reinforcement


bars with minimum yield stress of 60,000 psi including
the cost of straightening, cutting, bending, placing in
position at any level and height, binding with 18 SWG
gauge wire, wastage, removal of rust also including
chairs & spacers complete as per drawings,
specification and as directed by the Engineer Incharge.

Kg. 115 11,435.0 1,315,025 5,890.34 677,389.45 - 5,890.3430 677,389.45

Total 677,389.45 - 677,389.45

Sheet-54
B.O.Q Previouse Certified This Certified Upto Date
S NO. DESCRIPTION UNIT RATE
Quantity Amount Quantity Amount Quantity Amount Quantity Amount

5 DAMP PROOFING

5.1 Providing and laying 1-1/2" thick damp proof course


with cement concrete 1:2:4 cast insitu using graded
screened crush of 1/2" and down gauge i/c
compacting, curing, form work and its removal etc.
complete with applying a coat of hot bitumen using 35
lbs. per hundred square feet (1.71 kg/sqm) on damp
proof course after complete drying and cleaning the
surface etc. complete as per drawings, specification
and as directed by the Engineer Incharge.

Sft 48 173.0 8,304 716.28 34,381.44 716.28 34,381.44


5.2 Providing damp proof course on vertical surface with
3/4" thick cement plaster 1:4 (OPC + Chenab sand)
mixed with any approved water proofing agent i/c
curing etc complete as per drawings, specification and
as directed by the Engineer Incharge.
Sft 42 275.0 11,550

Total
34,381.44 - 34,381.44
6 BRICK MASONRY
-

6.1 Providing and laying first class burnt brick masonry set
in cement mortar 1:5 (OPC + Chenab sand) in straight
or curved wall including scaffolding, raking out joints
and curing etc in foundation etc. complete as per
drawings, specification and as directed by the
Engineer Incharge. (Compressive strength = 1800psi)

Cft 200 11,478.0 2,295,600 4,129.56 825,912.26 - 4,129.5613 825,912.26

6.2 Providing and laying first class burnt brick masonry in


9" thick wall set in cement mortar (OPC + Chenab
sand) 1:5 in straight or curved wall including
scaffolding, raking out joints and curing etc in super
structure at any height complete as per drawings,
specification and as directed by the Engineer Incharge.
(Compressive strength = 1800psi)

Cft 212 1,153.0 244,436 4,748.13 1,006,603.56 - 4,748.13 1,006,603.56


6.3 Providing and laying first class burnt brick masonry in 4
1/2" thick wall set in cement mortar (OPC + Chenab
sand) 1:3 in straight or curved wall including
scaffolding, raking out joints and curing etc in super
structure at any height complete as per drawings,
specification and as directed by the Engineer Incharge.
(Compressive strength = 1800psi)

Sft 75 311.0 23,325 914.89 68,616.74 - 914.890 68,616.74

Sheet-55
B.O.Q Previouse Certified This Certified Upto Date
S NO. DESCRIPTION UNIT RATE
Quantity Amount Quantity Amount Quantity Amount Quantity Amount

Total 1,901,132.56 - 1,901,132.56

7 CEMENT PLASTER (with Chenab Sand)

7.1 1/2" thick Cement plaster 1:3 on soffit of ceiling,


cantilever slabs, sides and soffit of beams etc including
making edges, smooth with steel trowel, corners, and
curing etc. with ordinary portland cement and chenab
sand at any height complete as per drawings,
specification and as directed by the Engineer Incharge.

Sft 23 3,704.0 85,192 - - -

7.2 1/2" thick Cement plaster 1:4 on walls and columns etc
including making edges, smooth with steel trowel,
corners, and curing etc. on Internal surfaces with
ordinary portland cement and chenab sand at any
height complete as per drawings, specification and as
directed by the Engineer Incharge.
Sft 24 2,123.0 50,952 8,851.12 212,426.88 8,851.120 212,426.88

- - -

Total
212,426.88 - 212,426.88
8 CARPENTRY AND JOINERY

8.1 Providing and fixing 1½" (40 mm) thick deodar wood
panelled or panelled and glazed, doors with M.S
Pressed frame, lacker polish, Lock, Door closer,
hinges, tower bolt etc. complete as per drawings,
specifications and as directed by the Engineer
Incharge.
(Basic cost of the lock is Rs. 1750)
Sft 800 250.0 200,000 - - -

8.2

Providing, making and fixing in position full height


cabinets 24" deep consisting of solid deodar wooden
2"x1" frame and 3/4" thick both side laminated sheet
for cabinet box, shelves, leafs etc. Lipped with deodar
wood in design pattern with approved hardware i.e.
Locks, hinges, handles, catchers, hanging rods with
brackets etc. including spirit/lacquered polish of
approved shade to all exposed wooden surfaces.
Complete as per drawings, specifications and as
directed by the Engineer Incharge. Sft 653 88.0 57,464 - - -

Total
- - -

Sheet-56
B.O.Q Previouse Certified This Certified Upto Date
S NO. DESCRIPTION UNIT RATE
Quantity Amount Quantity Amount Quantity Amount Quantity Amount

9 ALUMINIUM WORKS

9.1 Providing and fixing all types of glazed aluminium


windows, vantilator of anodized bronze colour partly
fixed and party sliding using deluxe section of Ms.
Alco/Pakistan Cables or other approved manufacturer
having Frame of size 100mm x 20mm and leaf frame
sections of 50mm x 20mm, all of 1.6mm thickness i/c
5mm thick imported tinted glass with rubber gasket
using approved standard latches, hardware etc.,
complete as per drawings, specification and as
directed by the Engineer Incharge.

Sft 650 40.0 26,000 - - -

Total
- - -
10 FLOOR AND WALL FINISHES

10.1 Providing and laying Granite Tiles (Master) Full Body


Premium Quality on Flooring 12"x12" of approved
make and shade jointing with matching color pigments
and bedding over 3/4" cement sand mortar 1:3
including Finishing and curing etc. complete as per
drawings, specifications and as directed by the
Engineer Incharge.
(Base cost of Granite Tile Box: Rs. 850/m2)
Sft 150 1,055.0 158,250

10.2 Providing & Laying 4" high Granite Tile (Master)


skirting with cement sand plaster (1:3) filling the joints
with matching color pigment, complete as per the
drawings, specifications and as directed by the
Engineer Incharge. (Base price = 130/sft)
Sft 250 261.0 65,250

10.3 Providing and laying floor of tiles (matte finish) 8" x 8"
of Master or equivalent of approved color including
jointing and washing the tiles with cement slurry with
matching color pigment and curing etc. complete as
per drawings, specification and as directed by the
Engineer Incharge.
Sft 150 645.0 96,750

Sheet-57
B.O.Q Previouse Certified This Certified Upto Date
S NO. DESCRIPTION UNIT RATE
Quantity Amount Quantity Amount Quantity Amount Quantity Amount
10.4 Providing and laying glazed tiles 12” x 8” of Master or
equivalent of approved color in dado including jointing
and washing the tiles with white cement slurry, with
matching color pigment, curing and cleaning etc
complete as per drawings, specification and as
directed by the Engineer Incharge.

Sft 150 2,779.0 416,850

10.5 Providing and fixing 3/4" thick pre-polished Boticina


marble windows sill laid with cement sand plaster
including round gola on both sides, complete as per
the drawings, specifications and as directed by the
Engineer Incharge.
Sft 417 22.0 9,174

10.6 Providing and laying Blue Pearl granite 3/4" thick as


required on floor/stair ( tread and riser ) and on
counters top as required, with gola etc. complete as
per drawings, specification and as directed by the
Engineer Incharge.
Sft 1,117 199.0 222,283

10.7 Providing & Laying 4" high Pearl Blue skirting with
cement sand plaster (1:3) filling the joints with
matching color pigment, complete as per the drawings,
specifications and as directed by the Engineer
Incharge.
Rft 519 87.0 45,153

Total
- - -
WATER PROOFING/ EXPANSION JOINT FILLING
11

11.1 Providing and laying hot bitumen on roof of 34 lbs per


100 Sft. finished with washed coarse sand, Jambolon
board 1.5" thick, single layer of polythene sheet of 500
gauge on roof for water proofing, 1st class burnt clay
tiles of 9”x4½”x1½” size grouted with 1:3 cement
mortar over 4” thick puddled earth compacted and
smooth finished to slope mixed with bhoosa @ 1seer
of bhoosa for 1Cft. of puddled earth in ground floor
including flush pointing on the tiles work with 1:3
cement mortar and curing etc. complete as per
drawings, specification and as directed by the
Engineer Incharge.
Sft 15,000 1,995.0 29,925,000

Total
- - -
12 PAINTING

Sheet-58
B.O.Q Previouse Certified This Certified Upto Date
S NO. DESCRIPTION UNIT RATE
Quantity Amount Quantity Amount Quantity Amount Quantity Amount
12.1 Providing and laying three coats of plastic emulsion
paint of ICI or Burger or Kansi or equivalent of
approved shade including surface preperation, primer
coat, filling, cutting etc. at any height Complete as per
drawings, specification and as directed by the
Engineer Incharge.
Sft 25 1,995.0 49,875

Total - - -
12.2 Providing and Applying three coats of Graffito paint on
external walls of approved shade on plastered surface
at any height. Complete as per drawings, specification
and as directed by the Engineer Incharge.
Sft 31 3,150.0 97,650

Total
- - -
13 MISCELLANEOUS

13.1 Providing and fixing uPVC pipes rainwater down pipe


of required dia. including all necessary accessories
with bolts and nuts fixed in cement concrete 1:2:4
complete as per drawings, specification and as
directed by the Engineer Incharge. 4" dia

Rft 257 52.0 13,364 62.00 15,934.00 - 62.00 15,934.00

13.2 Providing and laying 1:2:4 cement concrete khurras 2"


thick, 2' x 2' size on roof including finishing with
cement plaster 1:4 curing etc. complete in all respects
as directed by the Engineer Incharge or according to
the specification of drawing and as approved by the
consultant.
Sft 929 4.0 3,716
Total
15,934.00 - 15,934.00
14 CAR PARKING PAVEMENT

14.1 Construction of Hard Standing / PCC Car Parking


Floor consisting of well-compacted earth in 6 layers
over 6" thick Sub Base Material of Stone Product (NLC
Standared) over 4" thick PCC 1:2:4 with First Class
brick on edge pattern 4ft x 4ft complete as per
drawing, design and as instructed by the Engineer
Incharge.
Sft 339 30,622.0 10,380,858 - - -

Total
- - -
15 Jogging Track Top Finish

Sheet-59
B.O.Q Previouse Certified This Certified Upto Date
S NO. DESCRIPTION UNIT RATE
Quantity Amount Quantity Amount Quantity Amount Quantity Amount
15.1 Providing & Laying 1" Stone Dust over 3" gravel 1/2"
pure layer over 2" sand filling over compacted earth
complete as per drawing, design and as specified by
the Engineer Incharge. Sft 65 24,054.0 1,563,510

Total
- - -
16 TUFF PAVEMENT

16.1 P/F Tuff tiles 60 mm thick of any colour and design of


tuff / Izhar Pvt. Ltd./BANU MUKHTAR/Concreto Taxila
over 2" thick sand cusion i/c compaction complete as
per drawing, design and as per instructions of
Engineer Incharge.
Sft 85 3,168.0 269,280

16.2 Providing and laying sub-base course of stone product


of approved quality and grade 60% fine and 40%
course aggregate, including placing, mixing,spreading
and compaction of sub-base material (NLC Standard)
to required depth, camber, grade to achieve 100 %
maximum modified AASHO dry density, including
carriage of all material to site of work complete as per
drawing design and as per instructions of Engineer
Incharge. Cft 53 1,584.0 83,952

Total
- - -
17 Edging Stone

17.1 Providing & Fixing Edging Stone "K2" of Izhar


Industries/ Banu Mukhtar / Concreto complete as per
drawings, design and as per instructions of Engineer
Incharge. Nos. 51 16,009.0 816,459

17.2 Providing and laying 1:2:4 cement concrete mix using


Chenab sand and graded stone ballast 2" and down
gauge for benching with Edging Stone including
leveling, compacting and curing etc complete as per
drawings, design and as directed by the Engineer
Incharge.
Cft 245 667.0 163,415
Total
- - -
18 M.S Works

18.1 Providing and installing M.S. pipe 6" i/d, 3/16" (150
mm i/d 5 mm) thick including jointing/welding at site
with hoop for Basketball court including
excavation,PCC 1:4:8, RCC 1:2:4 complete as per
drawing, design and as specified by the Engineer
Incharge. Nos. 57,223 2.0 114,446

Sheet-60
B.O.Q Previouse Certified This Certified Upto Date
S NO. DESCRIPTION UNIT RATE
Quantity Amount Quantity Amount Quantity Amount Quantity Amount
18.2 Providing and installing M.S. pipe 4" i/d, 1/8" (100mm
i/d 3 mm) thick including jointing/welding at site without
Net for Volleyball court including excavation,PCC
1:4:8, RCC 1:2:4 complete with 3 coats of Enamel
Paint (ICI) and as per drawing, design and as specified
by the Engineer Incharge.
Nos. 19,415 2.0 38,830

18.3

Providing and installing of M.S. pipe 4" i/d, 1/8"


(100mm i/d 3 mm) thick including jointing/welding
frame (Ball Court) without Net for football ground
including excavation,PCC 1:4:8, RCC 1:2:4 complete
with 3 coats of Enamel Paint (ICI) and as per drawing,
design and as specified by the Engineer Incharge. Nos. 11,500 2.0 23,000

18.4
Providing and installing M.S. pipe 4" i/d, 1/8" (100mm
i/d 3 mm) thick including jointing/welding at site without
Net for Cricket Practice Pitch including
excavation,PCC 1:4:8, RCC 1:2:4 complete as per
drawing, design and as specified by the Engineer
Incharge. Nos. 18,750 28.0 525,000

Total - - -

19 RAIN WATER DISPOSAL

19.1 Excavation for 12" dia pipe Cft 11 16,980.0 186,780

19.2 Providing and laying Gravel 1.5" to 2" gauge Under


Rain water 12" dia pipe Cft 51 3,194.0 162,894

19.3 P/L UPVC Rain water 8" dia pipe Rft 997 2,156.0 2,149,532

19.4 UP/L PVC Rain water 12" dia pipe Rft 1,315 1,037.0 1,363,655

19.5 RCC Rain Water Collecting Chambers Each 9,785 95.0 929,575

Sheet-61
B.O.Q Previouse Certified This Certified Upto Date
S NO. DESCRIPTION UNIT RATE
Quantity Amount Quantity Amount Quantity Amount Quantity Amount
19.6 Providing & Construction of Rainwater collecting tank
size of 12' x 15' x 8' inside consisting of excavation,
PCC 1:4:8, RCC (1:1.5:3) Bottom Slab, Top slab, and
walls, including formwork, cement plaster (1:3) on
interior and exterior surfaces, 1/2" thick terrazzo dado
on floor and walls. Steel reinforcement, water stopper,
24" dia Manhole cover with frame, and Brickwork (1:3)
as shown in drawing. Complete as per drawings,
specification and as directed by the Engineer.
Gallon
s 79 10,000.0 790,000

Total - - -
20.1
Removel Of Debris. Cft 8 250,000.0 2,000,000 583,887.95 4,671,103.62 583,887.95 4,671,103.62

Total 4,671,103.62 - 4,671,103.62

Irrigation
u pvc Class D irrigation standard BS 3505
9 PiPe Line with all matching molded fittings
of dia

1.5 inch dia ft 250 1400.00 350,000 1,946.16 486,540.00 1,946.16 486,540.00

2 inch dia ft 350 400.00 140,000 1,792.50 627,375.00 1,792.50 627,375.00

3 inch dia ft 450 2450.00 1,102,500 1,000.50 450,225.00 1,000.50 450,225.00

4 inch dia ft 600 600.00 360,000 526.00 315,600.00 526.00 315,600.00

Total 1,952,500 1,879,740.00 1,879,740.00

Development of water well having bore depth of 185


to 200 ft, with 8 inch PVC casing pipe, 4 inch column
pipe as a delivery, pump setting depth at 150ft with
fully submersible imported italian pump with 35-HP 400
volts ,III phase electric motor having 200 gallons per
14
minute discharge, motor control unit with protection
relays , & all required fitting upto ground level

Sheet-62
B.O.Q Previouse Certified This Certified Upto Date
S NO. DESCRIPTION UNIT RATE
Quantity Amount Quantity Amount Quantity Amount Quantity Amount

Job - 1.0 269,500.00 1.00 242,550.00 1.00 242,550.00

Total 242,550.00 - 242,550.00

B Plumbing work
Part-2: WATER SUPPLY

Providing, fixing, jointing and testing Polypropylene


Random (PPR) pipes Dadex make "Polydex" or
approved equivalent pressure pipe for cold water as
per DIN 8077-8078 for pipes and DIN 16962, PN25 for
fittings (polyfusion welded joints) inside building
including fittings and specials (sockets, tees, elbows,
bends, crosses, reducers, adaptor, plugs and union
2.1 etc.) supported on walls or suspended from roof slab
or run in chases including pipe hangers, supports,
cutting and making good the chases and holes,
complete in all respects.

b 32mm dia PIPE Rft 157 230.0 36,110.00 280.50 44,038.50 280.50 44,038.50

c 25mm dia PiPE Rft 97 360.0 34,920.00 138.00 13,386.00 138.00 13,386.00
Claim Held Amount due to test
Report (6,000.17) (6,000.17)

6,000.17 6,000.17

Total 51,424.33 6,000.17 57,424.50


Part-3
Sewerage Line
Providing, fixing, cutting, jointing and testing uPVC
piping conforming to ISO 3633:1991 (wall
thickness=3.2 mm) including uPVC fittings with solvent
cement jointing Dadex make "Class B" or approved
equal, rates include cost of clamping to walls and
3.1 ceiling , hangers, supports, cutting through walls and
providing sleeves through concrete slabs for pipelines
and pipe fittings of the following diameter:

(i)UPVC pipe 4" dia Rft 391 50,310.0 19,671,210.00 181.67 71,032.97 - 181.67 71,032.97

Sheet-63
B.O.Q Previouse Certified This Certified Upto Date
S NO. DESCRIPTION UNIT RATE
Quantity Amount Quantity Amount Quantity Amount Quantity Amount

Total Qty 71,032.97 - 71,032.97

Total of Civil works 79,416,206 13,250,744 3,151,737.1 16,402,481.3

Sheet-64
Project; Sports Complex DHA Lahre Phase-6
M/Ali Associate
SUMMRY OF Ground and Interal WORKS
Sr.No Discription BOQ Amount Previous Amount This IPC Total Amount
A. CIVIL WORK

1 Sub Total Earth Work 10,411,687.10 4,448,110.03 1,265,996.89 5,714,106.92

2
Sub Total Termite Control Treament 58,890.00 29,789.00 - 29,789.00

3
Sub Total Plan And Reinforced 4,523,641.00 895,470.00 - 895,470.00

4
Sub Total Reinforcement 1,315,025.00 677,389.45 - 677,389.45

5
DAMP PROOFING 19,854.00 34,381.44 - 34,381.44

6
Sub Total Brick Masonary 2,540,036.00 1,901,132.56 - 1,901,132.56

7
Sub Total Cement Plaster 136,144.00 212,426.88 - 212,426.88

8
Sub Total Carpantry And Joinry 257,464.00 - - -

9
Sub Total Alluminium Works 26,000.00 - - -

10
Sub Total Floor And Wall Finishes 1,013,710.00 - - -
WATER PROOFING/ EXPANSION JOINT
11 FILLING
29,925,000.00 - - -

12
PAINTING 147,525.00 - - -

13
MISCELLANEOUS 17,080.00 15,934.00 - 15,934.00
Project; Sports Complex DHA Lahre Phase-6
M/Ali Associate
SUMMRY OF Ground and Interal WORKS
Sr.No Discription BOQ Amount Previous Amount This IPC Total Amount
14
Car Parking 10,380,858.00 - - -

15
Jogging Track Top Finish 1,563,510.00 - - -

16
TUFF PAVEMENT 353,232.00 - - -
17 Edging Stone 979,874.00 - - -
18
M.S Works 701,276.00 - - -
19 RAIN WATER DISPOSAL 5,582,436.00 - - -

20.1
REMOVEL OF DEBRIS 2,000,000.00 4,671,103.62 4,671,103.62
Irrigation Part
9 Upvc Irrigation Pipes under ground 1,952,500.00 1,879,740.00 1,879,740.00
Development of water well having bore depth of
185 to 200 ft, with 8 inch PVC casing pipe, 4
inch column pipe as a delivery, pump setting
depth at 150ft with fully submersible imported
italian pump with 35-HP 400 volts ,III phase
14 electric motor having 200 gallons per minute
discharge, motor control unit with protection
relays , & all required fitting upto ground level

- 242,550.00 - 242,550.00
Plumbing work
2.1 water Supply pipe 32mm & 25mm
71,030.00 51,424.33 6,000.17 57,424.50
Plumbing work
3.1 4" dia
19,671,210.00 71,032.97 - 71,032.97
Project; Sports Complex DHA Lahre Phase-6
M/Ali Associate
SUMMRY OF Ground and Interal WORKS
Sr.No Discription BOQ Amount Previous Amount This IPC Total Amount
Grand Total 73,905,742.10 13,250,744 3,151,737.1 16,402,481.3
Bar bending Schedhule Public washroom
M/S Ali Associate
Cut Total
Item Dia Spacing Total Length Length
Sr # Description Shape No
no # inches Nos In (ft) In (ft)
IPC#7 This Sheet-1

1 Toilet Block Roof


Beams & Slab
Reinforcement
Beams
B-1 Short side
Bottom Bars 21.833 #6 - 4 x 4 16 21.833 349.328

Top Bars 26.583 #6 - 4 x 2 8 26.583 212.664

Bottom bars 21.83 #6 - 4 x 4 16 21.83 349.28

Top Bars bars 34 #6 - 4 x 2 8 34 272

0.833
Rings
0.833 0.83 #3 - 8 x 36 288 3.832 1103.616
0.833

Beam on coridoor
B-1 Long side
Bottom Bars 9 #4 - 2 x 4 8 9 72

Top Bars 9 #4 - 2 x 4 8 9 72

Rings 1
0.33 0.33 #3 - 2 x 8 16 2.16 34.56
1

Sheet-2
Outer Beam
B2 Long Side
Bottom Bars 58.17 #6 - 2 x 4 8 58.17 465.36

Top Bars 58.17 #6 - 2 x 2 4 58.17 232.68


0.25
Rings 0.5
#3 2 x 72 144 5 720
1.25 1.75
Cut Total
Item Dia Spacing Total Length Length
Sr # Description Shape No
no # inches Nos In (ft) In (ft)
0.75
Outer Beam
B3 short Side
Bottom Bars 34 #6 - 2 x 4 8 34.00 272

Top Bars 34 #4 - 2 x 4 8 34 272


0.25
Rings 0.5
#3 2 x 45 90 5 450
1.25 1.75

0.75

Columns cap
Bottom Bars 2.75 #4 12 x 3 36 2.75 99

Rings 0.75
2.5 2.5 #3 12 x 3 36 7 252

0.75
Slab Reinforcement
Bottom Bars
main bars 21.833 #4 2 x 40 80 21.833 1746.64

Distribution Bars 21.833 #4 2 x 40 80 21.833 1746.64

Coridoor Main Bars 7.33 #4 1 x 40 40 7.33 293.2

Distribution bars 21.833 #4 1 x 11 11 21.83 240.163

Shad main bars on


Long Span #4 2 x 56 112 10 1120
10

sheet-3
Shad main bars on
Short Span #4 1 x 24 24 9 216
9

Shad main bars on


Short Span #4 1 x 28 28 5.67 158.76
5.67
Distribution Bars on
long span #4 2 x 8 16 58.17 930.72
58.17
Cut Total
Item Dia Spacing Total Length Length
Sr # Description Shape No
no # inches Nos In (ft) In (ft)
Shad main bars on
Short Span #4 1 x 9 9 33.83 304.47
33.83

Distribution Bars on
long span Top #4 2 x 9 18 33.83 608.94
33.83

Top Extra Bars on long


span #4 1 x 13 13 58.17 756.21
58.17

Extra Bars on Short


span
12 #4 2 X 14 28 12 336

Extra Bars on Long


span
9 #4 1 X 58 58 9 522

15 #4 1 x 49 49 15 735

Beam inner side tie bars

Both side 14.5 #4 2 X 19 38 14.5 551

Coridoor Long extra 17 #4 1 x 15 15 17 255

Coridoor Short extra 14.5 #4 1 x 16 16 14.5 232

Corner Bars 18.75 #5 4 x 4 16 18.75 300

Sr.No Dia Of Bars Total Length in (ft) Uint Weight Total Weight (Kg)

1 #3 2560.176 0.171 437.790


2 #4 11267.743 0.302 3402.858
3 #5 300.000 0.472 141.600
4 #6 2153.312 0.680 1464.252
5 #8 0.000 1.209 0.000
5446.501
Grand Total Weight in ( Kgs)
Bar bending Schedhule Of Watch Tower NDP
National Technical Services
Cut Total
Item Dia Spacing Total Length Length
Sr # Description Shape No
no # inches Nos In (ft) In (ft)
Watch Tower
1 1 Footing main Bars
T/B both Ways
D-1 4.5 4 - 1 x 4 4 4.5 18

0.205
0.33 0.33 3 - 1 x 9 9 1.570 14.13
0.205

D-2 4.25 4 - 2 x 4 8 4.25 34

0.205
0.33 0.33 3 - 2 x 8 16 1.570 25.12
0.205
D-3 3.75 4 - 8 x 4 32 3.75 120

0.205
0.33 0.33 3 - 8 x 8 64 1.570 100.48
0.205
V-1
5.5 4 - 2 x 4 8 5.5 44

0.205
0.33 0.33 3 - 2 x 10 20 1.570 31.4
0.205

v-4 3.25 4 - 1 x 4 4 3.25 13

0.205
0.33 0.33 3 - 1 x 8 8 1.570 12.56
0.205

Sr.No Dia Of Bars Total Length in (ft) Uint Weight Total Weight (Kg)
1 3 183.690 0.170 31.227
2 4 229.000 0.302 69.158
3 5 0.000 0.472 0.000
4 6 0.000 0.680 0.000
5 8 0.000 1.209 0.000
Grand Total Weight in ( Kgs) 100.378
Bar Bending Shedhule
Enternal Work B.W Sports Complex
M/S Ali Associate
Sr No Item No Discription Dia No Spacing No Of Bars Cut L Total L Shaps
4
Columns

C-1 #4 24.00 5.00 13.00 1,560.00


4.1
Bottom #3 24.00 6.00" 26.00 3.29 2,052.96

Lintals

L-2

Bottom #4 2.00 3.00 4.75 28.50

Top #4 2.00 3.00 4.75 28.50

Ring #3 2.00 6.00" 8.00 3.00 48.00

L-3 -

Bottom #6 2.00 2.00 9.00 36.00

Bottom #4 2.00 1.00 9.00 18.00

Rings #3 2.00 6.00" 18.00 3.50 126.00

Beams

1 B-1

Bottom #5 4.00 3.00 23.75 285.00

Top #4 4.00 2.00 23.75 190.00

Rings #3 4.00 9.00" 30.00 4.88 585.60

2 B-1

Bottom #5 4.00 3.00 23.50 282.00

Top #4 4.00 2.00 23.50 188.00

Rings #3 4.00 9.00" 30.00 4.88 585.60

3 B-2

Bottom #5 2.00 4.00 59.25 474.00

Top #4 2.00 3.00 59.25 355.50

Rings #3 2.00 9.00" 30.00 5.00 300.00

4 B-3
Bottom #6 2.00 4.00 39.25 314.00

Top #4 2.00 5.00 39.25 392.50

Rings #3 2.00 9.00" 30.00 5.00 300.00

CB-1

Bottom #4 2.00 2.00 10.00 40.00

Top #4 2.00 2.00 10.00 40.00

Rings #3 2.00 6.00" 20.00 3.08 123.20

Slab

Grid,(B-Q)/ 1-15

Bottom #4 2.00 6.50" 22.00 37.00 1,628.00

Bottom #4 2.00 6.50" 22.00 40.00 1,760.00

Top #4 2.00 6.50" 21.00 34.75 1,459.50

Top #4 2.00 6.50" 21.00 28.75 1,207.50

Distribution Bars #3 1.00 7.00" 14.00 35.00 490.00

Corridor Area

Side -A -1

Bottom #4 1.00 9.00" 82.00 10.50 861.00

Top #3 1.00 10.00" 10.00 62.25 622.50

Side-2 -

Bottom #4 1.00 7.50" 95.00 14.00 1,330.00

Top #3 1.00 10.00" 7.00 62.25 435.75

Side-B-1 & 2

Bottom #4 2.00 7.50" 35.00 14.00 980.00

Top #3 2.00 10.00" 7.00 38.25 535.50

Cornor Bars #4 4.00 4.00 15.00 240.00

Sr.No Dia Total Length Weight Unit

1 #3 6205.11 1058.59 Kg

2 #4 12307.00 3730.07 Kg
3 #5 1041.00 492.63 Kg

4 #6 350.00 238.20 Kg

5 #8 Kg

Total 5519.49 Kg

Vous aimerez peut-être aussi