Vous êtes sur la page 1sur 67

Republic of the Philippines which reversed and set aside the June 24, 2009 Order2 of the

SUPREME COURT Regional Trial Court (RTC) of Makati City, Branch 148 in SP
Manila Proc. Case No. M-6046.

FIRST DIVISION In G.R. No. 199238,a petition for certiorari under Rule 65,
Banco De Oro Unibank, Inc. (BDO)assails the Resolution3
G.R. No. 196171 December 10, 2012 dated September 13, 2011 in CA-G.R. SP No. 120888 which
denied BDO’s application for the issuance of a stay order
RCBC CAPITAL CORPORATION, Petitioners, and/or temporary restraining order (TRO)/preliminary
vs. injunction against the implementation of the Writ of
BANCO DE ORO UNIBANK, INC., Respondent. Execution4 dated August 22, 2011 issued by the Makati City
RTC, Branch 148 in SP Proc. Case No. M-6046.
X- - - - - - - - - - - - - - - - - - - - - - - - - -X
Factual Antecedents
G.R. No. 199238
On May 24, 2000, RCBC entered into a Share Purchase
Agreement5 (SPA) with Equitable-PCI Bank, Inc. (EPCIB),
BANCO DE ORO UNIBANK, INC., Petitioner, George L. Go and the individual shareholders6 of Bankard, Inc.
vs. (Bankard) for the sale to RCBC of 226,460,000 shares (Subject
COURT OF APPEALS and RCBC CAPITAL CORPORATION, Shares) of Bankard, constituting 67% of the latter’s capital
Respondents. stock. After completing payment of the contract price
(₱1,786,769,400), the corresponding deeds of sale over the
DECISION subject shares were executed in January 2001.

VILLARAMA, JR., J.: The dispute between the parties arose sometime in May 2003
when RCBC informed EPCIB and the other selling
Before the Court are two consolidated petitions separately filed shareholdersof an overpayment of the subject shares, claiming
by the parties in an arbitration case administered by the there was an overstatement of valuation of accounts amounting
International Chamber of Commerce-International Court of to ₱478 million and that the sellers violated their
Arbitration (ICC-ICA) pursuant to the arbitration clause in their warrantyunder Section 5(g)of the SPA.7
contract.
As no settlement was reached, RCBC commenced arbitration
The Case proceedings with the ICC-ICA in accordance with Section 10 of
the SPA which states:
In G.R. No. 196171, a petition for review under Rule 45 of the
1997 Rules of Civil Procedure, as amended, RCBC Capital Section 10. Arbitration
Corporation (RCBC) seeks to reverse the Court of Appeals (CA)
Decision1 dated December 23, 2010 in CA-G.R. SP No. 113525
Should there be any dispute arising between the parties breach as required under Section 7 of the SPA. A counterclaim
relating to this Agreement including the interpretation or for litigation expenses and costs of arbitration in the amount of
performance hereof which cannot be resolved by agreement of US$300,000, as well as moral and exemplary damages, was
the parties within fifteen (15) days after written notice by a likewise raised by the Respondents.
party to another, such matter shall then be finally settled by
arbitration under the Rules of Conciliation and Arbitration of RCBC submitted a Reply11 to the aforesaid Answer.
the International Chamber of Commerce in force as of the time
of arbitration, by three arbitrators appointed in accordance Subsequently, the Arbitration Tribunal was constituted. Mr.
with such rules. The venue of arbitration shall be in Makati Neil Kaplan was nominated by RCBC; Justice Santiago M.
City, Philippines and the arbitration proceedings shall be Kapunan (a retired Member of this Court) was nominated by
conducted in the English language. Substantive aspects of the the Respondents; and Sir Ian Barker was appointed by the ICC-
dispute shall be settled by applying the laws of the Philippines. ICA as Chairman.
The decision of the arbitrators shall be final and binding upon
the parties hereto and the expenses of arbitration (including
On August 13, 2004, the ICC-ICA informed the parties that they
without limitation the award of attorney’s fees to the prevailing
party) shall be paid as the arbitrators shall determine.8 are required to pay US$350,000 as advance on costs pursuant
to Article 30 (3) of the ICC Rules of Arbitration (ICC Rules).
RCBC paid its share of US$107,000, the balance remaining
In its Request for Arbitration9 dated May 12, 2004, Claimant after deducting payments of US$2,500 and US$65,000 it made
RCBC charged Bankard with deviating from and contravening earlier. Respondents’ share of the advance on costs was thus
generally accepted accounting principles and practices, due to fixed at US$175,000.
which the financial statements of Bankard prior to the stock
purchase were far from fair and accurate, and resulted in the
Respondents filed an Application for Separate Advances on
overpayment of ₱556 million. For this violation of
Costs12 dated September 17, 2004 under Article 30(2) of the
sellers’representations and warranties under the SPA, RCBC
ICC Rules, praying that the ICC fix separate advances on the
sought its rescission, as well as payment of actual damages in
cost of the parties’ respective claims and counterclaims, instead
the amount of ₱573,132,110, legal interest on the purchase
price until actual restitution, moral damages and litigation and of directing them to share equally on the advance cost of
attorney’s fees, with alternative prayer for award of damages in Claimant’s (RCBC) claim. Respondents deemed this advance
cost allocation to be proper, pointing out that the total amount
the amount of at least ₱809,796,082 plus legal interest.
of RCBC’s claim is substantially higher – more than 40 times –
the total amount of their counterclaims, and that it would be
In their Answer,10 EPCIB, Go and the other selling individual unfair to require them to share in the costs of arbitrating what
shareholders (Respondents) denied RCBC’s allegations is essentially a price issue that is now time-barred under the
contending that RCBC’s claim is one for overpayment or price SPA.
reduction under Section 5(h) of the SPA which is already time-
barred, the remedy of rescission is unavailable, and even
On September 20, 2004, the ICC-ICA informed Respondents
assuming that rescission is permitted by the SPA, RCBC failed
that their application for separate advances on costs was
to file its claim within a reasonable time. They further asserted
premature pending the execution of the Terms of Reference
that RCBC is not entitled to its alternative prayer for damages,
(TOR).13 The TOR was settled by the parties and signed by the
being guilty of laches and failing to set out the details of the
Chairman and Members of the Arbitral Tribunal by October 11, that their request for postponement serves no other purpose
2004. On December 3, 2004,14 the ICC-ICA denied the but to delay the proceedings. It alleged that Respondents’
application for separate advances on costs and invited anew the unjustified refusal to pay their share in the advance on costs
Respondents to pay its share in the advance on costs. However, warrants a ruling that they have lost standing to participate in
despite reminders from the ICC-ICA, Respondents refused to the proceedings. It thus prayed that Respondents be declared
pay their share in the advance cost fixed by the ICC-ICA. On as in default, the substantive hearings be conducted as
December 16, 2004, the ICC-ICA informed the parties that if originally scheduled, and RCBC be allowed to submit rebuttal
Respondents still failed to pay its share in the advance cost, it evidence and additional witness statements.18
would apply Article 30(4) of the ICC Rules and request the
Arbitration Tribunal to suspend its work and set a new time On December 15, 2005, the ICC-ICA notified the parties of its
limit, and if such requested deposit remains unpaid at the decision to increase the advances on costs from US$350,000 to
expiry thereof, the counterclaims would be considered US$450,000 subject to later readjustments, and again invited
withdrawn.15 the Respondents to pay the US$100,000 increment within 30
days from notice. Respondents, however, refused to pay the
In a fax-letter dated January 4, 2005, the ICC-ICA invited increment, insisting that RCBC should bear the cost of
RCBC to pay the said amount in substitution of Respondents.It prosecuting its own claim and that compelling the Respondents
also granted an extension until January 17, 2005 within which to fund such prosecution is inequitable. Respondents reiterated
to pay the balance of the advance cost (US$175,000). RCBC that it was willing to pay the advance on costs for their
replied that it was not willing to shoulder the share of counterclaim.19
Respondents in the advance on costs but nevertheless
requested for a clarification as to the effect of such refusal to On December 27, 2005, the ICC-ICA advised that it was not
substitute for Respondents’share.16 possible to fix separate advances on costs as explained in its
December 3, 2004 letter, and again invited Respondents to pay
On March 10, 2005, the ICC-ICA instructed the Arbitration their share in the advance on costs. Respondents’ response
Tribunal to suspend its work and granted the parties a final contained in the letter dated January 6, 2006 was still the
time-limit of 15 days to pay the balance of the advanceon costs, same: it was willing to pay only the separate advance on costs
failing which the claims shall be considered withdrawn, without of their counterclaim.20 In view of Respondents’ continuing
prejudice to their reintroduction at a later date in another refusal to pay its equal share in the advance on costs and
proceeding. The parties were advised that if any of them objects increment, RCBC wrote the ICC-ICA stating that the latter
to the measure, it should make a request in writing within such should compel the Respondents to pay as otherwise RCBC will
period.17 For the same reason of non-receipt of the balance of be prejudiced and the inaction of the ICC-ICA and the
the advance cost, the ICC-ICA issued Procedural Order No. 3 Arbitration Tribunal will detract from the effectiveness of
for the adjournment of the substantive hearings and granting arbitration as a means of settling disputes. In accordance with
the Respondents a two-month extension within which to Article 30(4) of the ICC Rules, RCBC reiterated its request to
submit their brief of evidence and witnesses. declare the Respondents as in default without any personality
to participate in the proceedings not only with respect to their
RCBC objected to the cancellation of hearings, pointing out that counterclaims but also to the claim of RCBC.21
Respondents have been given ample time and opportunity to
submit their brief of evidence and prepare for the hearings and
Chairman Ian Barker, in a letter dated January 25, 2006, RCBC paid the additional US$100,000 under the second
stated in part: assessment to avert suspension of the Arbitration Tribunal’s
proceedings.
xxxx
Upon the commencement of the hearings, the Arbitration
2. The Tribunal has no power under the ICC Rules to Tribunal decided that hearings will be initially confined to
order the Respondents to pay the advance on costs issues of liability (liability phase) while the substantial issues
sought by the ICC or to give the Claimant any relief will be heard on a later date (quantum phase).
against the Respondents’ refusal to pay. The ICC
Rules differ from, for example, the Rules of the LCIA Meanwhile, EPCIB’s corporate name was officially changed to
(Article 24.3) which enables a party paying the share of Banco De Oro (BDO)-EPCIB after its merger with BDO was duly
costs which the other party has refused to pay, to approved by the Securities and Exchange Commission. As
recover "that amount as a debt immediately due from the such, BDO assumed all the obligations and liabilities of EPCIB
defaulting party." under the SPA.

3. The only sanction under the ICC Rules is contained On September 27, 2007, the Arbitration Tribunal rendered a
within Article 30 (4). Where a request for an advance on Partial Award23 (First Partial Award) in ICC-ICA Case No.
costs has not been complied with, after consultation 13290/MS/JB/JEM,as follows:
with the Tribunal, the Secretary-General may direct the
Tribunal to suspend its work. After expiry of a time 15 AWARD AND DIRECTIONS
limit, all claims and counterclaims are then considered
as withdrawn. This provision cannot assist a Claimant 15.1 The Tribunal makes the following declarations by
who is anxious to litigate its claim. Such a Claimant has way of Partial Award:
to pay the sums requested (including the Respondents’
share) if it wishes the arbitration to proceed.
(a) The Claimant’s claim is not time-barred
under the provisions of this SPA.
4. It may be possible for a Claimant in the course of
the arbitral hearing (or whenever costs are being
(b) The Claimant is not estopped by its conduct
considered by the Tribunal) to make submissions
based on the failure of the Respondents to pay their or the equitable doctrine of laches from pursuing
its claim.
share of the costs advance.What relief, if any, would
have to be then determined by the Tribunal after
having heard submissions from the Respondents. (c) As detailed in the Partial Award, the Claimant
has established the following breaches by the
Respondents of clause 5(g) of the SPA:
5. I should be pleased if the Claimant will advise the
Tribunal of its intention in relation to the costs advance.
If the costs are not paid, the arbitration cannot i) the assets, revenue and net worth of
proceed.22 (Italics in the original; emphasis supplied) Bankard were overstated by reason of its
policy on and recognition of Late On October 26, 2007, RCBC filed with the Makati City RTC,
Payment Fees; Branch 148 (SP Proc. Case No. M-6046)amotion to confirm the
First Partial Award, while Respondents filed a motion to vacate
ii) reported receivables were higher than the same.
their realisable values by reason of the
‘bucketing’ method, thus overstating ICC-ICA by letter25 dated October 12, 2007 increased the
Bankard’s assets; and advance on costs from US$450,000 to US$580,000. Under this
third assessment, RCBC paid US$130,000 as its share on the
iii) the relevant Bankard statements were increment. Respondents declined to pay its adjudged total
inadequate and misleading in that their share of US$290,000 on account of its filing in the RTC of a
disclosures caused readers to be motion to vacate the First Partial Award.26 The ICC-ICA then
misinformed about Bankard’s invited RCBC to substitute for Respondents in paying the
accounting policies on revenue and balance of US$130,000 by December 21, 2007.27 RCBC
receivables. complied with the request, making its total payments in the
amount of US$580,000.28
(d) Subject to proof of loss the Claimant is
entitled to damages for the foregoing breaches. While RCBC paid Respondents’ share in the increment
(US$130,000), it reiterated its plea that Respondents be
(e) The Claimant is not entitled to rescission of declared as in default and the counterclaimsdeemed as
the SPA. withdrawn.29

(f) All other issues, including any issue Chairman Barker’s letter dated December 18, 2007 states in
relating to costs, will be dealt with in a part:
further or final award.
xxxx
15.2 A further Procedural Order will be necessary
subsequent to the delivery of this Partial Award to deal 8. Contrary to the Complainant’s view, the Tribunal has
with the determination of quantum and in particular, no jurisdiction to declare that the Respondents have no
whether there should be an Expert appointed by the right to participate in the proceedings concerning the
Tribunal under Article 20(4) of the ICC Rules to assist claim. Article 30(4) of the ICC Rules applies only to any
the Tribunal in this regard. counterclaim of the Respondents.

15.3 This Award is delivered by a majority of the 9. The Tribunal interprets the Claimant’s latest
Tribunal (Sir Ian Barker and Mr. Kaplan). Justice letter as an application by the Claimant to the
Kapunan is unable to agree with the majority’s Tribunal for the issue of a partial award against the
conclusion on the claim of estoppel brought by the Respondents in respect of their failure to pay their
Respondents.24 (Emphasis supplied) share of the ICC’s requests for advance on costs.
10. I should be grateful if the Claimant would confirm in paying the advance on costs where the Arbitration Tribunal
that this is the situation. If so, the Claimant should has fixed the same.33
propose a timetable for which written submissions
should be made by both parties. This is an application Respondents, on the other hand, filed their Opposition34 to the
which can be considered by the Tribunal on written said application alleging that the Arbitration Tribunal has lost
submissions.30 (Emphasis supplied) its objectivity in an unnecessary litigation over the payment of
Respondents’ share in the advance costs. They pointed out that
RCBC, in a letter dated December 26, 2007, confirmed the RCBC’s letter merely asked that Respondents be declared as in
Arbitration Tribunal’s interpretation that it was applying for a default for their failure to pay advance costs but the Arbitration
partial award against Respondents’ failure to pay their share in Tribunal, while denying the request offered an alternative to
the advance on costs.31 RCBC: a Partial Award for Respondents’ share in the advance
costs even if it was clear from the language of RCBC’s December
Meanwhile, on January 8, 2008, the Makati City RTC, Branch 11, 2007 letter that it had no intention of litigating for the
148 issued an order in SP Proc. Case No. M-6046 confirming advance costs. Chairman Barker, after ruling earlier that it
the First Partial Award and denying Respondents’ separate cannot grant RCBC’s request to declare the Respondents as
motions to vacate and to suspend and inhibit Barker and having no right to participate in the proceedings concerning the
Kaplan. Respondents’ motion for reconsideration was likewise claim, interpreted RCBC’s letter as an application for the
denied. Respondents directly filed with this Court a petition for Arbitration Tribunal to issue a partial award in respect of such
review on certiorari under Rule 45, docketed as G.R. No. refusal of Respondents to pay their share in the advance on
182248 and entitled Equitable PCI Banking Corporation v. costs, and subsequently directed the parties to make
RCBC Capital Corporation.32 In our Decision dated December submissions on the matter.Aside from violating their right to
18, 2008, we denied the petition and affirmed the RTC’s ruling due process and to be heard by an impartial tribunal,
confirming the First Partial Award. Respondents also argued that in issuing the award for advance
cost, the ArbitrationTribunal decided an issue beyond the
On January 18, 2008, the Arbitration Tribunal set a timetable terms of the TOR.
for the filing of submission by the parties on whether it should
issue a Second Partial Award in respect of the Respondents’ Respondents also emphasized that the parties agreed on a two-
refusal to pay an advance on costs to the ICC-ICA. part arbitration: the first part of the Tribunal’s proceedings
would determine Respondents’ liability, if any, for alleged
In compliance, RCBC filed on February 7, 2008an Application violation of Section 5(g) and (h) of the SPA; and the second part
for Reimbursement of Advance on Costs Paid, praying for the of the proceedings would determine the amounts owed by one
issuance of a partial award directing the Respondents to party to another as a consequence of a finding of liability or
reimburse its payment in the amount of US$290,000 lack thereof. An award for "reimbursement of advances for
representing Respondents’ share in the Advance on Costs and costs" clearly falls outside the scope of either proceedings.
to consider Respondents’ counterclaim for actual damages in Neither can the Tribunal justify such proceedings under Article
the amount of US$300,000, and moral and exemplary damages 23 of the ICC Rules (Conservatory and Interim Measures)
as withdrawn for their failure to pay their equal share in the because that provision does not contemplate an award for the
advance on costs. RCBC invoked the plain terms of Article 30 reimbursement of advance on costs in arbitration cases.
(2) and (3) to stress the liability of Respondents to share equally Respondents further asserted that since the advances on costs
have been paid by the Claimant (RCBC), the main claim and Respondents, on the other hand, maintained that RCBC’s
counterclaim may both be heard by the Arbitration Tribunal. application for reimbursement of advance cost has no basis
under the ICC Rules. They contended that no manifest injustice
In his letter dated March 13, 2008, Chairman Barker advised can be inferred from an act of a party paying for the share of
the parties, as follows: the defaulting party as this scenario is allowed by the ICC
Rules. Neither can a partial award for advance cost be justified
1. The Tribunal acknowledges the Respondents’ under the "contractual approach" since the matter of costs for
response to the Claimant’s application for a Partial arbitration is between the ICC and the parties, not the
Award, based on the Respondents’ failure to pay their Arbitration Tribunal and the parties. An arbitration tribunal
share of the costs, as requested by the ICC. can issue decisions on costs only for those costs not fixed by
the ICC.37
2. The Tribunal notes that neither party has referred
to an article by Mat[t]hew Secomb on this very Respondents reiterated their position that Article 30(3)
subject which appears in the ICC Bulletin Vol. 14 envisions a situation whereby a party would refuse to pay its
No.1 (Spring 2003). To assist both sides and to ensure share on the advance on costs and provides a remedy therefor
that the Tribunal does not consider material on which – the other party "shall be free to pay the whole of the advance
the parties have not been given an opportunity to on costs." Such party’s reimbursement for payments of the
address, I attach a copy of this article, which also defaulting party’s share depends on the final arbitral award
contains reference to other scholarly works on the where the party liable for costs would be determined. This is
subject. the only remedy provided by the ICC Rules.38

3. The Tribunal will give each party seven days within On May 28, 2008, the Arbitration Tribunal rendered the Second
which to submit further written comments as a Partial Award,39 as follows:
consequence of being alerted to the above authorities.35
(Additional emphasis supplied) 7 AWARD

The parties complied by submitting their respective comments. 7.1 Having read and considered the submissions of both
parties, the Tribunal AWARDS, DECLARES AND ORDERS as
RCBC refuted Respondents’ allegation of partiality on the part follows:
of Chairman Barker and reiterated the prayer in its application
for reimbursement of advance on costs paid to the ICC-ICA. (a) The Respondents are forthwith to pay to the
RCBC contended that based on Mr. Secomb’s article, whether Claimant the sum of US$290,000.
the "contractual" or "provisional measures" approach is
applied, the Arbitration Tribunal is vested with jurisdiction and (b) The Respondents’ counterclaim is to be considered
authority to render an award with respect to said as withdrawn.
reimbursement of advance cost paid by the non-defaulting
party.36 (c) All other questions, including interest and costs, will
be dealt with in a subsequent award.40
The above partial award was received by RCBC and evidence, their only computation relates only to attorney’s fees
Respondents on June 12, 2008. which are simply cost of litigation properly brought at the
conclusion of the arbitration. It also pointed out that the
On July 11, 2008, EPCIB filed a Motion to Vacate Second Arbitration Tribunal was empowered by the parties’ arbitral
Partial Award41 in the Makati City RTC, Branch 148 (SP Proc. clause to determine the manner of payment of expenses of
Case No. M-6046). On July 10, 2008, RCBC filed in the same arbitration, and that the Second Partial Award was based on
court a Motion to Confirm Second Partial Award.42 authorities and treatiseson the mandatory and contractual
nature of the obligation to pay advances on costs.
EPCIB raised the following grounds for vacating the Second
Partial Award: (a) the award is void ab initio having been In its Reply,44 EPCIB contended that RCBC had the option to
rendered by the arbitrators who exceeded their power or acted agree to its proposal for separate advances on costs but decided
without it; and (b) the award was procured by undue means or against it; RCBC’s act of paying the balance of the advance cost
issued with evident partiality or attended by misbehavior on the in substitution of EPCIB was for the purpose of having EPCIB
part of the Tribunal which resulted in a material prejudice to defaulted and the latter’s counterclaim withdrawn. Having
the rights of the Respondents. EPCIB argued that there is no agreed to finance the arbitration until its completion, RCBC is
express agreement either in the SPA or the ICC Rules for such not entitled to immediate reimbursement of the amount it paid
right of reimbursement. There is likewise no implied agreement in substitution of EPCIB under an interim award, as its right to
because from the ICC Rules, the only inference is that the a partial or total reimbursement will have to be determined
parties agreed to await the dispositions on costs liability in the under the final award. EPCIB asserted that the matter of
Final Award, not before. reimbursement of advance cost paid cannot be said to have
properly arisen during arbitration. EPCIB reiterated that
On the ruling of the Arbitration Tribunal that Respondents’ Chairman Barker’s interpretation of RCBC’s December 11,
application for costs are not counterclaims, EPCIB asserted 2007 letter as an application for interim award for
that this is contrary to Philippine law as it is basic in our reimbursement is tantamount to a promise that the award will
jurisdiction that counterclaims for litigation expenses, moral be issued in due course.
and exemplary damages are proper counterclaims, which rule
should be recognized in view of Section 10 of the SPA which After a further exchange of pleadings, and other motions
provides that "substantive aspects of the dispute shall be seeking relief from the court in connection with the arbitration
settled by applying the laws of the Philippines." Finally, EPCIB proceedings (quantum phase), the Makati City RTC, Branch
takes issue with Chairman Barker’s interpretation of RCBC’s 148 issued the Order45 dated June 24, 2009 confirming the
December 11, 2007 letter as an application for a partial award Second Partial Award and denying EPCIB’s motion to vacate
for reimbursement of the substituted payments. Such conduct the same. Said court held that since the parties agreed to
of Chairman Barker is prejudicial and proves his evident submit any dispute under the SPA to arbitration and to be
partiality in favor of RCBC. bound by the ICC Rules, they are also bound to pay in equal
shares the advance on costs as provided in Article 30 (2) and
RCBC filed its Opposition,43 asserting that the Arbitration (3). It noted that RCBC was forced to pay the share of EPCIB in
Tribunal had jurisdiction to consider Respondents’ substitution of the latter to prevent a suspension of the
counterclaim as withdrawn, the same having been abandoned arbitration proceedings, while EPCIB’s non-payment seems
by not presenting any computation or substantiation by more like a scheme to delay such proceedings. On the
Arbitration Tribunal’s ruling on EPCIB’s counterclaim, no error 15 AWARD
was committed in considering it withdrawn for failure of EPCIB
to quantify and substantiate it with supporting evidence. As to 15.1 The Tribunal by a majority (Sir Ian Barker & Mr. Kaplan)
EPCIB’s claim for attorney’s fees, the RTC agreed that these awards, declares and adjudges as follows:
should be brought only at the close of arbitration.
(a) the Respondents are to pay damages to the Claimant
EPCIB moved to reconsider the June 24, 2009 Order and for for breach of the sale and purchase agreement for
the voluntary inhibition of the Presiding Judge (Judge Oscar B. Bankard shares in the sum of ₱348,736,920.29.
Pimentel) on the ground that EPCIB’s new counsel represented
another client in another case before him in which said counsel (b) The Respondents are to pay to the Claimant the sum
assailed his conduct and had likewise sought his inhibition. of US$880,000 in respect of the costs of the arbitration
Both motions were denied in the Joint Order46 dated March as fixed by the ICC Court.
23, 2010.
(c) The Respondents are to pay to the Claimant the sum
On April 14, 2010, EPCIB filed in the CA a petition for review47 of US$582,936.56 for the fees and expenses of Mr. Best.
with application for TRO and/or writ of preliminary injunction
(CA-G.R. SP No. 113525) in accordance with Rule 19, Section
4 of the Special Rules of Court on Alternative Dispute (d) The Respondents are to pay to the Claimant their
expenses of the arbitration as follows:
Resolution48 (Special ADR Rules). EPCIB assailed the Makati
City RTC, Branch 148 in denying its motion to vacate the
Second Partial Award despite (a) said award having been (i) Experts’ fees ₱7,082,788.55
rendered in excess of jurisdiction or power, and contrary to
public policy; (b) the fact that it was issued with evident (ii) Costs of without prejudice meeting
partiality and serious misconduct; (c) the award deals with a ₱22,571.45
dispute not contemplated within the terms of submission to
arbitration or beyond the scope of such submission, which (iii) Costs of arbitration hearings ₱553,420.66
therefore ought to be vacated pursuant to Article 34 of the
UNCITRAL Model Law; and (d) the Presiding Judge having (iv) Costs of transcription service ₱483,597.26
exhibited bias and prejudice against BDO and its counsel as Total ₱8,144,377.62
confirmed by his pronouncements in the Joint Order dated
March 23, 2010 in which, instead of recusing himself, he
(e) The Respondents are to pay to the Claimant the sum
imputed malice and unethical conduct in the entry of
of ₱7,000,000 for party-and-party legal costs.
appearance of Belo Gozon Elma Asuncion and Lucila Law
Offices in SP Proc. Case No. M-6046, which warrants his
voluntary inhibition. (f) The Counterclaims of the Respondents are all
dismissed.
Meanwhile, on June 16, 2010, the Arbitration Tribunal issued
the Final Award,49 as follows: (g) All claims of the Claimant are dismissed, other than
those referred to above.
15.2 Justice Kapunan does not agree with the majority of the its Opposition to the Petition to Vacate Final Award Ad
members of the Tribunal and has issued a dissenting opinion. Cautelam.
He has refused to sign this Award.50
Meanwhile, on November 10, 2010, Branch 148 (SP Proc. Case
On July 1, 2010 BDO filed in the Makati City RTC a Petition to No. M-6046) issued an Order56 confirming the Final Award
Vacate Final Award Ad Cautelam,51 docketed as SP Proc. Case "subject to the correction/interpretation thereof by the Arbitral
No. M-6995, which was raffled to Branch 65. Tribunal pursuant to the ICC Rules and the UNCITRAL Model
Law," and denying BDO’s Opposition with Motion to Dismiss.
On July 28, 2010, RCBC filed with the Makati City RTC, Branch
148 (SP Proc. Case No. M-6046) a Motion to Confirm Final On December 30, 2010, George L. Go, in his personal capacity
Award.52 BDO filed its Opposition With Motion to Dismiss53 and as attorney-in-fact of the other listed shareholders of
on grounds that a Petition to Vacate Final Award Ad Bankard, Inc. in the SPA (Individual Shareholders), filed a
Cautelamhad already been filed in SP Proc. Case No. M-6995. petition in the CA, CA-G.R. SP No. 117451, seeking to set aside
BDO also pointed out that RCBC did not file the required the above-cited November 10, 2010 Order and to enjoin Branch
petition but instead filed a mere motion which did not go 148 from further proceeding in SP Proc. Case No. M-6046. By
through the process of raffling to a proper branch of the RTC of Decision57 dated June 15, 2011, the CA dismissed the said
Makati City and the payment of the required docket/filing fees. petition. Their motion for reconsideration of the said decision
Even assuming that Branch 148 has jurisdiction over RCBC’s was likewise denied by the CA in its Resolution58 dated
motion to confirm final award, BDO asserted that RCBC had December 14, 2011.
filed before the Arbitration Tribunal an Application for
Correction and Interpretation of Award under Article 29 of the On December 23, 2010, the CA rendered its Decision in CA-
ICC Rules, which is irreconcilable with its Motion to Confirm G.R. SP No. 113525, the dispositive portion of which states:
Final Award before said court. Hence, the Motion to Confirm
Award was filed precipitately. WHEREFORE, premises considered, the following are hereby
REVERSED and SET ASIDE:
On August 18, 2010, RCBC filed an Omnibus Motion in SP
Proc. Case No. M-6995 (Branch 65) praying for the dismissal of 1. the Order dated June 24, 2009 issued in SP Proc.
BDO’s Petition to Vacate Final Award or the transfer of the Case No. M-6046 by the Regional Trial Court of Makati
same to Branch 148 for consolidation with SP Proc. Case No. City, Branch 148, insofar as it denied the Motion to
M-6046. RCBC contended that BDO’s filing of its petition with Vacate Second Partial Award dated July 8, 2008 and
another court is a blatant violation of the Special ADR Rules granted the Motion to Confirm Second Partial Award
and is merely a subterfuge to commit forum-shopping. BDO dated July 10, 2008;
filed its Opposition to the Omnibus Motion.54
2. the Joint Order dated March 23, 2010 issued in SP
On October 28, 2010, Branch 65 issued a Resolution55 Proc. Case No. M-6046 by the Regional Trial Court of
denying RCBC’s omnibus motion and directing the service of Makati City, Branch 148, insofar as it denied the Motion
the petition to RCBC for the latter’s filing of a comment thereon. For Reconsideration dated July 28, 2009 relative to the
RCBC’s motion for reconsideration was likewise denied in the
said court’s Order dated December 15, 2010. RCBC then filed
motions concerning the Second Partial Award 1. Banco De Oro’s Motion for Reconsideration, Motion
immediately mentioned above; and for Leave to File Supplement to Motion for
Reconsideration, and Motion to Inhibit are DENIED for
3. the Second Partial Award dated May 28, 2008 issued lack of merit.
in International Chamber of Commerce Court of
Arbitration Reference No. 13290/MS/JB/JEM. 2. RCBC Capital’s Motion to Expunge, Motion to
Execute against Mr. George L. Go and the Bankard
SO ORDERED.59 Shareholders, and the Motion to Execute against Banco
De Oro are hereby GRANTED.
RCBC filed a motion for reconsideration but the CA denied the
same in its Resolution60 dated March 16, 2011. On April 6, 3. The damages awarded to RCBC Capital Corporation
2011, it filed a petition for review on certiorari in this Court in the amount of Ph₱348,736,920.29 is subject to an
(G.R. No. 196171). interest of 6% per annum reckoned from the date of
RCBC Capital’s extra-judicial demand or from May 5,
On February 25, 2011, Branch 65 rendered a Decision61 in SP 2003 until the confirmation of the Final Award.
Proc. Case No. M-6995, as follows: Likewise, this compounded amount is subject to 12%
interest per annum from the date of the confirmation of
the Final Award until its satisfaction. The costs of the
WHEREFORE, premises considered, the Final Award dated arbitration amounting to US$880,000.00, the fees and
June 16, 2010 in ICC Ref. No. 13290/MS/JB/JEM is hereby expenses of Mr. Best amounting to US$582,936.56, the
VACATED with cost against the respondent. Claimant’s expenses of the arbitration amounting to
Ph₱8,144,377.62, and the party-and-party legal costs
SO ORDERED.62 amounting to Ph₱7,000,000.00 all ruled in favor of
RCBC Capital Corporation in the Final Award of the
In SP Proc. Case No. M-6046, Branch 148 issued an Order63 Arbitral Tribunal dated June 16, 2010 are subject to
dated August 8, 2011 resolving the following motions: (1) 12% legal interest per annum, also reckoned from the
Motion for Reconsideration filed by BDO, Go and Individual date of the confirmation of the Final Award until its
Shareholders of the November 10, 2010 Order confirming the satisfaction.
Final Award; (2) RCBC’s Omnibus Motion to expunge the
motion for reconsideration filed by Go and Individual 4. Pursuant to Section 40 of R.A. No. 9285, otherwise
Shareholders, and for execution of the Final Award; (3) Motion known as the Alternative Dispute Resolution Act of
for Execution filed by RCBC against BDO; (4) BDO’s Motion for 2004 in relation to Rule 39 of the Rules of Court, since
Leave to File Supplement to the Motion for Reconsideration; the Final Award have been confirmed, the same shall be
and (5) Motion for Inhibition filed by Go and Individual enforced in the same manner as final and executory
Shareholders. Said Order decreed: decisions of the Regional Trial Court, let a writ of
execution be issued commanding the Sheriff to enforce
WHEREFORE, premises considered, it is hereby ORDERED, to this instant Order confirming this Court’s Order dated
wit: November 10, 2010 that judicially confirmed the June
16, 2010 Final Award.
SO ORDERED.64 BDO further contended that the writ of execution should be
quashed for having been issued with grave abuse of discretion
Immediately thereafter, RCBC filed an Urgent Motion for amounting to lack or excess of jurisdiction as Branch 148
Issuance of a Writ of Execution.65 On August 22, 2011, after modified the Final Award at the time of execution by imposing
approving the execution bond, Branch 148 issued a Writ of the payment of interests though none was provided therein nor
Execution for the implementation of the said court’s "Order in the Order confirming the same.
dated August 8, 2011 confirming the November 10, 2010 Order
that judicially confirmed the June 16, 2010 Final Award x x During the pendency of CA-G.R. SP No. 120888, Branch 148
x."66 continued with execution proceedings and on motion by RCBC
designated/deputized additional sheriffs to replace Sheriff
BDO then filed in the CA, a "Petition for Review (With Flora who was supposedly physically indisposed.68 These
Application for a Stay Order or Temporary Restraining Order court personnel went to the offices/branches of BDO
and/or Writ of Preliminary Injunction," docketed as CA-G.R. SP attempting to serve notices of garnishment and to levy the
No. 120888. BDO sought to reverse and set aside the Orders furniture, fixtures and equipment.
dated November 10, 2010 and August 8, 2011, and any writ of
execution issued pursuant thereto, as well as the Final Award On September 12, 2011, BDO filed a Very Urgent Motion to Lift
dated June 16, 2010 issued by the Arbitration Tribunal. Levy and For Leave to Post Counter-Bond69 before Branch 148
praying for the lifting of the levy of BDO Private Bank, Inc.
In its Urgent Omnibus Motion67 to resolve the application for (BPBI) shares and the cancellation of the execution sale thereof
a stay order and/or TRO/writ of preliminary injunction, and to scheduled on September 15, 2011, which was set for hearing
quash the Writ of Execution dated August 22, 2011 and lift the on September 14, 2011. BDO claimed that the levy was invalid
Notices of Garnishment dated August 22, 2011, BDO argued because it was served by the RTC Sheriffs not to the authorized
that the assailed orders of execution (Writ of Execution and representatives of BPBI, as provided under Section 9(b), Rule
Notice of Garnishment) were issued with indecent haste and 39 in relation to Section 7, Rule 57 of the Rules of Court stating
despite the non-compliance with the procedures in Special ADR that a notice of levy on shares of stock must be served to the
Rules of the November 10, 2010 Order confirming the Final president or managing agent of the company which issued the
Award. BDO was not given sufficient time to respond to the shares. However, BDO was advised by court staff that Judge
demand for payment or to elect the method of satisfaction of Sarabia was on leave and the case could not be set for hearing.
the judgment debt or the property to be levied upon. In any
case, with the posting of a bond by BDO, Branch 148 has no In its Opposition to BDO’s application for injunctive relief,
jurisdiction to implement the appealed orders as it would pre- RCBC prayed for its outright denial as BDO’s petition raises
empt the CA from exercising its review under Rule 19 of the questions of fact and/or law which call for the CA to substitute
Special ADR Rules after BDO had perfected its appeal. BDO its judgment with that of the Arbitration Tribunal, in patent
stressed that the bond posted by RCBC was for a measly sum violation of applicable rules of procedure governing domestic
of ₱3,000,000.00 to cause execution pending appeal of a arbitration and beyond the appellate court’s jurisdiction. RCBC
monetary award that may reach ₱631,429,345.29. RCBC also asserted that BDO’s application has become moot and
failed to adduce evidence of "good cause" or "good reason" to academic as the writ of execution was already implemented
justify discretionary execution under Section 2(a), Rule 39 of and/or enforced. It also contended that BDO has no clear and
the Rules of Court. unmistakable right to warrant injunctive relief because the
issue of jurisdiction was already ruled upon in CA-G.R. SP No. THE COURT OF APPEALS ACTED CONTRARY TO LAW
117451 which dismissed the petition filed by Go and the AND PRIOR RULINGS OF THIS HONORABLE COURT
Individual Shareholders of Bankard questioning the authority AND COMMITTED REVERSIBLE ERROR IN VACATING
of Branch 148 over RCBC’s motion to confirm the Final Award THE SECOND PARTIAL AWARD ON THE BASIS OF
despite the earlier filing by BDO in another branch of the RTC CHAIRMAN BARKER’S ALLEGED PARTIALITY, WHICH
(Branch 65) of a petition to vacate the said award. IT CLAIMS IS INDICATIVE OF BIAS CONSIDERING
THAT THE ALLEGATIONS CONTAINED IN
On September 13, 2011, BDO, to avert the sale of the BPBI BDO/EPCIB’S PETITION FALL SHORT OF THE
shares scheduled on September 15, 2011 and prevent further JURISPRUDENTIAL REQUIREMENT THAT THE SAME
disruption in the operations of BDO and BPBI, paid under BE SUPPORTED BY CLEAR AND CONVINCING
protest by tendering a Manager’s Check in the amount of EVIDENCE.
₱637,941,185.55, which was accepted by RCBC as full and
complete satisfaction of the writ of execution. BDO manifested II.
before Branch 148 that such payment was made without
prejudice to its appeal before the CA.70 THE COURT OF APPEALS ACTED CONTRARY TO LAW
AND PRIOR RULINGS OF THIS HONORABLE COURT
On even date, the CA denied BDO’s application for a stay order AND COMMITTED REVERSIBLE ERROR WHEN IT
and/or TRO/preliminary injunction for non-compliance with REVERSED THE ARBITRAL TRIBUNAL’S FINDINGS OF
Rule 19.25 of the Special ADR Rules. The CA ruled that BDO FACT AND LAW IN THE SECOND PARTIAL AWARD IN
failed to show the existence of a clear right to be protected and PATENT CONTRAVENTION OF THE SPECIAL ADR
that the acts sought to be enjoined violated any right. Neither RULES WHICH EXPRESSLY PROHIBITS THE COURTS,
was BDO able to demonstrate that the injury to be suffered by IN AN APPLICATION TO VACATE AN ARBITRAL
it is irreparable or not susceptible to mathematical AWARD, FROM DISTURBING THE FINDINGS OF FACT
computation. AND/OR INTERPRE[TA]TION OF LAW OF THE
ARBITRAL TRIBUNAL.71
BDO did not file a motion for reconsideration and directly filed
with this Court a petition for certiorari with urgent application BDO raises the following arguments in G.R. No. 199238:
for writ of preliminary mandatory injunction (G.R. No.
199238). THE COURT OF APPEALS COMMITTED GRAVE ABUSE OF
DISCRETION AMOUNTING TO LACK OR EXCESS OF
The Petitions JURISDICTION IN PERFUNCTORILY DENYING PETITIONER
BDO’S APPLICATION FOR STAY ORDER, AND/OR
In G.R. No. 196171, RCBC set forth the following grounds for TEMPORARY RESTRAINING ORDER AND PRELIMINARY
the reversal of the CA Decision dated December 23, 2010: INJUNCTION DESPITE THE EXISTENCE AND CONCURRENCE
OF ALL THE ELEMENTS FOR THE ISSUANCE OF SAID
I. PROVISIONAL RELIEFS
A. PETITIONER BDO HAS CLEAR AND Procedure to be Applied
UNMISTAKABLE RIGHTS TO BE PROTECTED BY THE
ISSUANCE OF THE INJUNCTIVE RELIEF PRAYED 14 The proceedings before the Tribunal shall be governed by
FOR, WHICH, HOWEVER, WERE DISREGARDED BY the ICC Rules of Arbitration (1 January 1998) and the law
PUBLIC RESPONDENT WHEN IT DENIED PETITIONER currently applicable to arbitration in the Republic of the
BDO’S PRAYER FOR ISSUANCE OF A STAY ORDER Philippines.73
AND/OR TRO
As stated in the Partial Award dated September 27, 2007,
B. PETITIONER BDO’S RIGHT TO DUE PROCESS AND although the parties provided in Section 10 of the SPA that the
EQUAL PROTECTION OF THE LAW WAS GROSSLY arbitration shall be conducted under the ICC Rules, it was
VIOLATED BY THE RTC-MAKATI CITY BRANCH 148, nevertheless arbitration under Philippine law since the parties
THE DEPUTIZED SHERIFFS AND RESPONDENT RCBC are both residents of this country. The provisions of Republic
CAPITAL, WHICH VIOLATION WAS AIDED BY PUBLIC Act No. 87674 (RA 876),as amended by Republic Act No.
RESPONDENT’S INACTION ON AND EVENTUAL 928575 (RA 9285)principally applied in the arbitration between
DENIAL OF THE PRAYER FOR STAY ORDER AND/OR the herein parties.76
TRO
The pertinent provisions of R.A. 9285 provide:
C. DUE TO THE ACTS AND ORDERS OF RTC BRANCH
148, PETITIONER BDO SUFFERED IRREPARABLE SEC. 40. Confirmation of Award. – The confirmation of a
DAMAGE AND INJURY, AND THERE WAS DIRE AND domestic arbitral award shall be governed by Section 23 of R.A.
URGENT NECESSITY FOR THE ISSUANCE OF THE 876.
INJUNCTIVE RELIEF PRAYED FOR WHICH PUBLIC
RESPONDENT DENIED IN GRAVE ABUSE OF
A domestic arbitral award when confirmed shall be enforced in
DISCRETION72
the same manner as final and executory decisions of the
Regional Trial Court.
Essentially, the issues to be resolved are: (1) whether there is
legal ground to vacate the Second Partial Award; and (2)
The confirmation of a domestic award shall be made by the
whether BDO is entitled to injunctive relief in connection with
the execution proceedings in SP Proc. Case No. M-6046. regional trial court in accordance with the Rules of Procedure
to be promulgated by the Supreme Court.
In their TOR, the parties agreed on the governing law and rules
xxxx
as follows:

Laws to be Applied SEC. 41. Vacation Award. – A party to a domestic arbitration


may question the arbitral award with the appropriate regional
trial court in accordance with the rules of procedure to be
13 The Tribunal shall determine the issues to be resolved in promulgated by the Supreme Court only on those grounds
accordance with the laws of the Republic of the Philippines. enumerated in Section 25 of Republic Act No. 876. Any other
ground raised against a domestic arbitral award shall be b. A party to arbitration is a minor or a person judicially
disregarded by the regional trial court. declared to be incompetent.

Rule 11.4 of the Special ADR Rules sets forth the grounds for xxxx
vacating an arbitral award:
In deciding the petition to vacate the arbitral award, the court
Rule 11.4. Grounds.—(A) To vacate an arbitral award. – The shall disregard any other ground than those enumerated above.
arbitral award may be vacated on the following grounds: (Emphasis supplied)

a. The arbitral award was procured through corruption, Judicial Review


fraud or other undue means;
At the outset, it must be stated that a review brought to this
b. There was evident partiality or corruption in the Court under the Special ADR Rules is not a matter of right.
arbitral tribunal or any of its members; Rule 19.36 of said Rules specified the conditions for the
exercise of this Court’s discretionary review of the CA’s
c. The arbitral tribunal was guilty of misconduct or any decision.
form of misbehavior that has materially prejudiced the
rights of any party such as refusing to postpone a Rule 19.36.Review discretionary.—A review by the Supreme
hearing upon sufficient cause shown or to hear evidence Court is not a matter of right, but of sound judicial discretion,
pertinent and material to the controversy; which will be granted only for serious and compelling reasons
resulting in grave prejudice to the aggrieved party. The
d. One or more of the arbitrators was disqualified to act following, while neither controlling nor fully measuring the
as such under the law and willfully refrained from court’s discretion, indicate the serious and compelling, and
disclosing such disqualification; or necessarily, restrictive nature of the grounds that will warrant
the exercise of the Supreme Court’s discretionary powers, when
e. The arbitral tribunal exceeded its powers, or so the Court of Appeals:
imperfectly executed them, such that a complete, final
and definite award upon the subject matter submitted a. Failed to apply the applicable standard or test for
to them was not made. judicial review prescribed in these Special ADR
Rules in arriving at its decision resulting in substantial
The award may also be vacated on any or all of the following prejudice to the aggrieved party;
grounds:
b. Erred in upholding a final order or decision despite
a. The arbitration agreement did not exist, or is invalid the lack of jurisdiction of the court that rendered such
for any ground for the revocation of a contract or is final order or decision;
otherwise unenforceable; or
c. Failed to apply any provision, principle, policy or rule xxxx
contained in these Special ADR Rules resulting in
substantial prejudice to the aggrieved party; and The court shall not set aside or vacate the award of the arbitral
tribunal merelyon the ground that the arbitral tribunal
d. Committed an error so egregious and harmful to a committed errors of fact, or of law, or of fact and law, as the
party as to amount to an undeniable excess of court cannot substitute its judgment for that of the arbitral
jurisdiction. tribunal. (Emphasis supplied)

The mere fact that the petitioner disagrees with the Court of The above rule embodied the stricter standard in deciding
Appeals’ determination of questions of fact, of law or both appeals from arbitral awards established by jurisprudence. In
questions of fact and law, shall not warrant the exercise of the the case of Asset Privatization Trust v. Court of Appeals,77 this
Supreme Court’s discretionary power. The error imputed to Court held:
the Court of Appeals must be grounded upon any of the
above prescribed grounds for review or be closely analogous As a rule, the award of an arbitrator cannot be set aside for
thereto. mere errors of judgment either as to the law or as to the
facts.Courts are without power to amend or overrule merely
A mere general allegation that the Court of Appeals has because of disagreement with matters of law or facts
committed serious and substantial error or that it has acted determined by the arbitrators.They will not review the findings
with grave abuse of discretion resulting in substantial prejudice of law and fact contained in an award, and will not undertake
to the petitioner without indicating with specificity the nature to substitute their judgment for that of the arbitrators, since
of such error or abuse of discretion and the serious prejudice any other rule would make an award the commencement, not
suffered by the petitioner on account thereof, shall constitute the end, of litigation.Errors of law and fact, or an erroneous
sufficient ground for the Supreme Court to dismiss outright the decision of matters submitted to the judgment of the
petition. (Emphasis supplied) arbitrators, are insufficient to invalidate an award fairly and
honestly made. Judicial review of an arbitration is, thus, more
The applicable standard for judicial review of arbitral awards in limited than judicial review of a trial.78
this jurisdiction is set forth in Rule 19.10 which states:
Accordingly, we examine the merits of the petition before us
Rule 19.10. Rule on judicial review on arbitration in the solely on the statutory ground raised for vacating the Second
Philippines.--As a general rule, the court can only vacate or set Partial Award: evident partiality, pursuant to Section 24 (b) of
aside the decision of an arbitral tribunal upon a clear showing the Arbitration Law (RA 876) and Rule 11.4 (b) of the Special
that the award suffers from any of the infirmities or grounds ADR Rules.
for vacating an arbitral award under Section 24 of Republic
Act No. 876 or under Rule 34 of the Model Law in a domestic Evident Partiality
arbitration, or for setting aside an award in an international
arbitration under Article 34 of the Model Law, or for such other Evident partiality is not defined in our arbitration laws. As one
grounds provided under these Special Rules. of the grounds for vacating an arbitral award under the Federal
Arbitration Act (FAA) in the United States (US), the term
"encompasses both an arbitrator’s explicit bias toward one inconsistent judicial interpretation when an arbitrator’s failure
party and an arbitrator’s inferred bias when an arbitrator fails to disclose prior dealings is at issue."82
to disclose relevant information to the parties."79
The first case to delineate the standard of evident partiality in
From a recent decision80 of the Court of Appeals of Oregon, we arbitration proceedings was Commonwealth Coatings Corp. v.
quote a brief discussion of the common meaning of evident Continental Casualty Co., et al.83 decided by the US Supreme
partiality: Court in 1968. The Court therein addressed the issue of
whether the requirement of impartiality applies to an
To determine the meaning of "evident partiality," we begin with arbitration proceeding. The plurality opinion written by Justice
the terms themselves. The common meaning of "partiality" is Black laid down the rule that the arbitrators must disclose to
"the inclination to favor one side."Webster’s Third New Int'l the parties "any dealings that might create an impression of
Dictionary 1646 (unabridged ed 2002); see also id. (defining possible bias,"84 and that underlying such standard is "the
"partial" as "inclined to favor one party in a cause or one side premise that any tribunal permitted by law to try cases and
of a question more than the other: biased, predisposed" controversies not only must be unbiased but also must avoid
(formatting in original)). "Inclination," in turn, means "a even the appearance of bias."85 In a separate concurring
particular disposition of mind or character : propensity, bent" opinion, Justice White joined by Justice Marshall, remarked
or "a tendency to a particular aspect, state, character, or that "[t]he Court does not decide today that arbitrators are to
action."Id. at 1143 (formatting in original); see also id. (defining be held to the standards of judicial decorum of Article III judges,
"inclined" as "having inclination, disposition, or tendency"). or indeed of any judges."86 He opined that arbitrators should
not automatically be disqualified from an arbitration
The common meaning of "evident" is "capable of being perceived proceeding because of a business relationship where both
esp[ecially] by sight : distinctly visible : being in evidence : parties are aware of the relationship in advance, or where the
discernable[;] * * * clear to the understanding : obvious, parties are unaware of the circumstances but the relationship
manifest, apparent."Id. at 789 (formatting in original); see also is trivial. However, in the event that the arbitrator has a
id. (stating that synonyms of "evident" include "apparent, "substantial interest" in the transaction at hand, such
patent, manifest, plain, clear, distinct, obvious, [and] palpable" information must be disclosed.
and that, "[s]ince evident rather naturally suggests
evidence, it may imply the existence of signs and Subsequent cases decided by the US Court of Appeals Circuit
indications that must lead to an identification or inference" Courts adopted different approaches, given the imprecise
(formatting in original)). (Emphasis supplied) standard of evident partiality in Commonwealth Coatings.

Evident partiality in its common definition thus implies "the In Morelite Construction Corp. v. New York District Council
existence of signs and indications that must lead to an Carpenters Benefit Funds,87 the Second Circuit reversed the
identification or inference" of partiality.81 Despite the judgment of the district court and remanded with instructions
increasing adoption of arbitration in many jurisdictions, there to vacate the arbitrator’s award, holding that the existence of a
seems to be no established standard for determining the father-son relationship between the arbitrator and the
existence of evident partiality. In the US, evident partiality president of appellee union provided strong evidence of
"continues to be the subject of somewhat conflicting and partiality and was unfair to appellant construction contractor.
After examining prior decisions in the Circuit, the court EPCIB/BDO, in moving to vacate the Second Partial Award
concluded that – claimed that the Arbitration Tribunal exceeded its powers in
deciding the issue of advance cost not contemplated in the TOR,
x x x we cannot countenance the promulgation of a standard and that Chairman Barker acted with evident partiality in
for partiality as insurmountable as "proof of actual bias" -- as making such award. The RTC held that BDO failed to
the literal words of Section 10 might suggest. Bias is always substantiate these allegations. On appeal, the CA likewise
difficult, and indeed often impossible, to "prove." Unless an found that the Arbitration Tribunal did not go beyond the
arbitrator publicly announces his partiality, or is overheard in submission of the parties because the phrasing of the scope of
a moment of private admission, it is difficult to imagine how the agreed issues in the TOR ("[t]he issues to be determined by
"proof" would be obtained. Such a standard, we fear, the Tribunal are those issues arising from the said Request for
occasionally would require that we enforce awards in situations Arbitration, Answer and Reply and such other issues as may
that are clearly repugnant to our sense of fairness, yet do not properly arise during the arbitration")is broad enough to
yield "proof" of anything. accommodate a finding on the liability and the repercussions
of BDO’s failure to share in the advances on costs. Section 10
If the standard of "appearance of bias" is too low for the of the SPA also gave the Arbitration Tribunal authority to decide
invocation of Section 10, and "proof of actual bias" too how the costs should be apportioned between them.
high, with what are we left? Profoundly aware of the competing
forces that have already been discussed, we hold that "evident However, the CA found factual support in BDO’s charge of
partiality" within the meaning of 9 U.S.C. § 10 will be found partiality, thus:
where a reasonable person would have to conclude that an
arbitrator was partial to one party to the arbitration.x x x88 On the issue on evident partiality, the rationale in the American
(Emphasis supplied) case of Commonwealth Coatings Corp. v. Continental Cas. Co.
appears to be very prudent. In Commonwealth, the United
In Apperson v. Fleet Carrier Corporation,89 the Sixth Circuit States Supreme Court reasoned that courts "should…be even
agreed with the Morelite court’s analysis, and accordingly held more scrupulous to safeguard the impartiality of arbitrators
that to invalidate an arbitration award on the grounds of bias, than judges, since the former have completely free rein to
the challenging party must show that "a reasonable person decide the law as well as the facts, and are not subject to
would have to conclude that an arbitrator was partial" to the appellate review" in general. This taken into account, the Court
other party to the arbitration. applies the standard demanded of the conduct of
magistrates by analogy. After all, the ICC Rules require that
This "myriad of judicial interpretations and approaches to an arbitral tribunal should act fairly and impartially. Hence, an
evident partiality" resulted in a lack of a uniform standard, arbitrator’s conduct should be beyond reproach and
leaving the courts "to examine evident partiality on a case-by- suspicion. His acts should be free from the appearances of
case basis."90 The case at bar does not present a non- impropriety.
disclosure issue but conduct allegedly showing an arbitrator’s
partiality to one of the parties. An examination of the circumstances claimed to be illustrative
of Chairman Barker’s partiality is indicative of bias. Although
RCBC had repeatedly asked for reimbursement and the
withdrawal of BDO’s counterclaims prior to Chairman Barker’s
December 18, 2007 letter, it is baffling why it is only in the an arbitrator was partial to the other party to the arbitration.
said letter that RCBC’s prayer was given a complexion of Such interest or bias, moreover, "must be direct, definite and
being an application for a partial award. To the Court, the capable of demonstration rather than remote, uncertain, or
said letter signaled a preconceived course of action that speculative."92 When a claim of arbitrator’s evident partiality
the relief prayed for by RCBC will be granted. is made, "the court must ascertain from such record as is
available whether the arbitrators’ conduct was so biased and
That there was an action to be taken beforehand is confirmed prejudiced as to destroy fundamental fairness."93
by Chairman Barker’s furnishing the parties with a copy of the
Secomb article. This article ultimately favored RCBC by Applying the foregoing standard, we agree with the CA in
advancing its cause. Chairman Barker makes it appear that finding that Chairman Barker’s act of furnishing the parties
he intended good to be done in doing so but due process with copies of Matthew Secomb’s article, considering the
dictates the cold neutrality of impartiality. This means that attendant circumstances,is indicative of partiality such that a
"it is not enough…[that] cases [be decided] without bias and reasonable man would have to conclude that he was favoring
favoritism. Nor is it sufficient that…prepossessions [be rid of]. the Claimant, RCBC. Even before the issuance of the Second
[A]ctuations should moreover inspire that belief." These put Partial Award for the reimbursement of advance costs paid by
into the equation, the furnishing of the Secomb article further RCBC, Chairman Barker exhibited strong inclination to grant
marred the trust reposed in Chairman Barker. The suspicion of such relief to RCBC, notwithstanding his categorical ruling that
his partiality on the subject matter deepened. Specifically, his the Arbitration Tribunal "has no power under the ICC Rules to
act established that he had pre-formed opinions. order the Respondents to pay the advance on costs sought by
the ICC or to give the Claimantany relief against the
Chairman Barker’s providing of copies of the said text is easily Respondents’ refusal to pay."94 That Chairman Barker was
interpretable that he had prejudged the matter before him. In predisposed to grant relief to RCBC was shown by his act of
any case, the Secomb article tackled bases upon which the interpreting RCBC’s letter, which merely reiterated its plea to
Second Partial Award was founded. The subject article declare the Respondents in default and consider all
reflected in advance the disposition of the ICC arbitral counterclaims withdrawn – as what the ICC Rules provide – as
tribunal. The award can definitely be viewed as an affirmation an application to the Arbitration Tribunal to issue a partial
that the bases in the Secomb article were adopted earlier on. award in respect of BDO’s failure to share in the advance costs.
To the Court, actuations of arbitrators, like the language of It must be noted that RCBC in said letter did not contemplate
judges, "must be guarded and measured lest the best of the issuance of a partial order, despite Chairman Barker’s
intentions be misconstrued." previous letter which mentioned the possibility of granting relief
upon the parties making submissions to the Arbitration
x x x x91 (Emphasis supplied) Tribunal. Expectedly, in compliance with Chairman Barker’s
December 18, 2007 letter, RCBC formally applied for the
issuance of a partial award ordering BDO to pay its share in
We affirm the foregoing findings and conclusion of the appellate the advance costs.
court save for its reference to the obiter in Commonwealth
Coatings that arbitrators are held to the same standard of
conduct imposed on judges. Instead, the Court adopts the Mr. Secomb’s article, "Awards and Orders Dealing With the
reasonable impression of partiality standard, which requires a Advance on Costs in ICC Arbitration: Theoretical Questions and
showing that a reasonable person would have to conclude that Practical Problems"95 specifically dealt with the situation when
one of the parties to international commercial arbitration Indeed, fairness dictates that Chairman Barker refrainfrom
refuses to pay its share on the advance on costs. After a brief suggesting to or directing RCBC towards a course of action to
discussion of the provisions of ICC Rules dealing with advance advance the latter’s cause, by providing it with legal arguments
on costs, which did not provide for issuance of a partial award contained in an article written by a lawyer who serves at the
to compel payment by the defaulting party, the author stated: ICC Secretariat and was involved or had participation -- insofar
as the actions or recommendations of the ICC – in the case.
4. As we can see, the Rules have certain mechanisms to deal Though done purportedly to assist both parties, Chairman
with defaulting parties. Occasionally, however, parties have Barker’s act clearly violated Article 15 of the ICC Rules
sought to use other methods to tackle the problem of a party declaring that "[i]n all cases, the Arbitral Tribunal shall act
refusing to pay its part of the advance on costs. These have fairly and impartially and ensure that each party has a
included seeking an order or award from the arbitral tribunal reasonable opportunity to present its case." Having pre-judged
condemning the defaulting party to pay its share of the advance the matter in dispute, Chairman Barker had lost his objectivity
on costs.1âwphi1 Such applications are the subject of this in the issuance of the Second Partial Award.
article.96
In fine, we hold that the CA did not err in concluding that the
By furnishing the parties with a copy of this article, Chairman article ultimately favored RCBC as it reflected in advance the
Barker practically armed RCBC with supporting legal disposition of the Arbitral Tribunal, as well as "signalled a
arguments under the "contractual approach" discussed by preconceived course of action that the relief prayed for by RCBC
Secomb. True enough, RCBC in its Application for will be granted." This conclusion is further confirmed by the
Reimbursement of Advance Costs Paid utilized said approach Arbitral Tribunal’s pronouncements in its Second Partial Award
as it singularly focused on Article 30(3)97 of the ICC Rules and which not only adopted the "contractual approach" but even
fiercely argued that BDO was contractually bound to share in cited Secomb’s article along with other references, thus:
the advance costs fixed by the ICC.98 But whether under the
"contractual approach" or "provisional approach" (an 6.1 It appears to the Tribunal that the issue posed by this
application must be treated as an interim measure of protection application is essentially a contractual one. x x x
under Article 23 [1] rather than enforcement of a contractual
obligation), both treated in the Secomb article, RCBC xxxx
succeeded in availing of a remedy which was not expressly
allowed by the Rules but in practice has been resorted to by 6.5 Matthew Secomb, considered these points in the article in
parties in international commercial arbitration proceedings. It 14 ICC Bulletin No. 1 (2003) which was sent to the parties. At
may also be mentioned that the author, Matthew Secomb, is a Para. 19, the learned author quoted from an ICC Tribunal (Case
member of the ICC Secretariat and the "Counsel in charge of No. 11330) as follows:
the file", as in fact he signed some early communications on
behalf of the ICC Secretariat pertaining to the advance costs
"The Arbitral Tribunal concludes that the partiesin arbitrations
fixed by the ICC.99 This bolstered the impression that
conducted under the ICC Rules have a mutually binding
Chairman Barker was predisposed to grant relief to RCBC by
obligation to pay the advance on costs as determined by the ICC
issuing a partial award.
Court, based on Article 30-3 ICC Rules which – by reference –
forms part of the parties’ agreement to arbitration under such be protected, which is directly threatened by the act sought to
Rules."100 be enjoined. Further, there must be a showing that the invasion
of the right is material and substantial and that there is an
The Court, however, must clarify that the merits of the parties’ urgent and paramount necessity for the writ to prevent a
arguments as to the propriety of the issuance of the Second serious damage.105
Partial Award are not in issue here. Courts are generally
without power to amend or overrule merely because of Rule 19.22 of the Special ADR Rules states:
disagreement with matters of law or facts determined by the
arbitrators. They will not review the findings of law and fact Rule 19.22. Effect of appeal.—The appeal shall not stay the
contained in an award, and will not undertake to substitute award, judgment, final order or resolution sought to be
their judgment for that of the arbitrators. A contrary rule would reviewed unless the Court of Appeals directs otherwise upon
make an arbitration award the commencement, not the end, of such terms as it may deem just.
litigation.101 It is the finding of evident partiality which
constitutes legal ground for vacating the Second Partial Award We find no reversible error or grave abuse of discretion in the
and not the Arbitration Tribunal’s application of the ICC Rules CA’s denial of the application for stay order or TRO upon its
adopting the "contractual approach" tackled in Secomb’s finding that BDO failed to establish the existence of a clear legal
article. right to enjoin execution of the Final Award confirmed by the
Makati City RTC, Branch 148, pending resolution of its
Alternative dispute resolution methods or ADRs – like appeal.It would be premature to address on the merits the
arbitration, mediation, negotiation and conciliation – are issues raised by BDO in the present petition considering that
encouraged by this Court. By enabling parties to resolve their the CA still has to decide on the validity of said court's orders
disputes amicably, they provide solutions that are less time- confirming the Final Award. But more important, since BOO
consuming, less tedious, less confrontational, and more had already paid ₱637,941,185.55 m manager's check, albeit
productive of goodwill and lasting relationship.102 under protest, and which payment was accepted by RCBC as
Institutionalization of ADR was envisioned as "an important full and complete satisfaction of the writ of execution, there is
means to achieve speedy and impartial justice and declog court no more act to be enjoined.
dockets."103 The most important feature of arbitration, and
indeed, the key to its success, is the public’s confidence and Settled is the rule that injunctive reliefs are preservative
trust in the integrity of the process.104 For this reason, the law remedies for the protection of substantive rights and interests.
authorizes vacating an arbitral award when there is evident Injunction is not a cause of action in itself, but merely a
partiality in the arbitrators. provisional remedy, an adjunct to a main suit. When the act
sought to be enjoined has become fait accompli, the prayer for
Injunction Against Execution Of Arbitral Award provisional remedy should be denied. 106

Before an injunctive writ can be issued, it is essential that the Thus, the Court ruled in Gov. Looyuko107 that when the events
following requisites are present: (1) there must be a right inesse sought to be prevented by injunction or prohibition have
or the existence of a right to be protected; and (2) the act against already happened, nothing more could be enjoined or
which injunction to be directed is a violation of such right. The prohibited. Indeed, it is a universal principle of law that an
onus probandi is on movant to show that there exists a right to
injunction will not issue to restrain the performance of an act
already done. This is so for the simple reason that nothing more
can be done in reference thereto. A writ of injunction becomes
moot and academic after the act sought to be enjoined has
already been consummated.

WHEREFORE, premises considered, the petition m G.R. No.


199238 is DENIED. The Resolution dated September 13,2011
ofthe Court of Appeals in CA-G.R. SP No. 120888 is
AFFIRMED.

The petition in G.R. No. 196171 is DENIED. The Decision dated


December 23, 2010 of the Court of Appeals in CA-G.R. SP No.
113525 is hereby AFFIRMED.

SO ORDERED.

MARTIN S. VILLARAMA, JR.


Associate Justice
Republic of the Philippines However, petitioner was able to pay only 47% of the total
SUPREME COURT contract price in the amount of ₱2,038,456.30.7
Manila
On October 25, 1994, the Commission on Audit (COA) released
FIRST DIVISION the Technical Services Office Report8 (TSO) finding the contract
price of the Agreement to be 84.14% excessive.9 This
G.R. No. 212081 February 23, 2015 notwithstanding, petitioner, in a letter dated December 10,
1998, acknowledged its liability to respondent in the amount of
DEPARTMENT OF ENVIRONMENT AND NATURAL ₱2,239,479.60 and assured payment at the soonest possible
RESOURCES (DENR), Petitioner, time.10
vs.
UNITED PLANNERS CONSULTANTS , INC. (UPCI), For failure to pay its obligation under the Consultancy
Respondent. Agreement despite repeated demands, respondent instituted a
Complaint11 against petitioner before the Regional Trial Court
DECISION of Quezon City, Branch 222 (RTC), docketed as Case No. Q-07-
60321.12
PERLAS-BERNABE, J.:
Upon motion of respondent, the case was subsequently referred
to arbitration pursuant to the arbitration clause of the
Assailed in this petition for review on certiorari1 is the Consultancy Agreement,13 which petitioner did not oppose.14
Decision2 dated March 26, 2014 of the Court of Appeals (CA) As a result, Atty. Alfredo F. Tadiar, Architect Armando N. Alli,
in CA-G.R. SP No. 126458 which dismissed the petition for and Construction Industry Arbitration Commission (CIAC)
certiorari filed by petitioner the Department of Environment Accredited Arbitrator Engr. Ricardo B. San Juan were
and Natural Resources (petitioner). appointed as members of the Arbitral Tribunal. The court-
referred arbitration was then docketed as Arbitration Case No.
The Facts A-001.15

On July 26, 1993, petitioner, through the Land Management During the preliminary conference, the parties agreed to adopt
Bureau (LMB), entered into an Agreement for Consultancy the CIAC Revised Rules Governing Construction Arbitration16
Services3 (Consultancy Agreement) with respondent United (CIAC Rules) to govern the arbitration proceedings.17 They
Planners Consultants, Inc. (respondent) in connection with the further agreed to submit their respective draft decisions in lieu
LMB' s Land Resource Management Master Plan Project of memoranda of arguments on or before April 21, 2010, among
(LRMMP).4 Under the Consultancy Agreement, petitioner others.18
committed to pay a total contract price of ₱4,337,141.00, based
on a predetermined percentage corresponding to the particular On the due date for submission of the draft decisions, however,
stage of work accomplished.5 only respondent complied with the given deadline,19 while
petitioner moved for the deferment of the deadline which it
In December 1994, respondent completed the work required,
which petitioner formally accepted on December 27, 1994.6
followed with another motion for extension of time, asking that in accordance with the Special Rules of Court on Alternative
it be given until May 11, 2010 to submit its draft decision.20 Dispute Resolution (Special ADR Rules).34

In an Order21 dated April 30, 2010, the Arbitral Tribunal In an Order35 dated March 30, 2011, the RTC merely noted
denied petitioner’s motions and deemed its non-submission as petitioner’s aforesaid motions, finding that copies of the
a waiver, but declared that it would still consider petitioner’s Arbitral Award appear to have been sent to the parties by the
draft decision if submitted before May 7, 2010, or the expected Arbitral Tribunal, including the OSG, contrary to petitioner’s
date of the final award’s promulgation.22 Petitioner filed its claim. Onthe other hand, the RTC confirmed the Arbitral Award
draft decision23 only on May 7, 2010. pursuant to Rule 11.2 (A)36 of the Special ADR Rules and
ordered petitioner to pay respondent the costs of confirming the
The Arbitral Tribunal rendered its Award24 dated May 7, 2010 award, as prayed for, in the total amount of ₱50,000.00. From
(Arbitral Award) in favor of respondent, directing petitioner to this order, petitioner did not file a motion for reconsideration.
pay the latter the amount of (a) ₱2,285,089.89 representing the
unpaid progress billings, with interest at the rate of 12% per Thus, on June 15, 2011, respondent moved for the issuance of
annum from the date of finality of the Arbitral Award upon a writ of execution, to which no comment/opposition was filed
confirmation by the RTC until fully paid; (b) ₱2,033,034.59 as by petitioner despite the RTC’s directive therefor. In an Order37
accrued interest thereon; (c) ₱500,000.00 as exemplary dated September 12, 2011, the RTC granted respondent’s
damages; and (d) ₱150,000.00 as attorney’s fees.25 It also motion.38
ordered petitioner to reimburse respondent its proportionate
share in the arbitration costs as agreed upon in the amount of Petitioner moved to quash39 the writ of execution, positing that
₱182,119.44.26 respondent was not entitled to its monetary claims. It also
claimed that the issuance of said writ was premature since the
Unconvinced, petitioner filed a motion for reconsideration,27 RTC should have first resolved its May 19, 2010 Motion for
which the Arbitral Tribunal merely noted without any action, Reconsideration and June 1, 2010 Manifestation and Motion,
claiming that it had already lost jurisdiction over the case after and not merely noted them, thereby violating its right to due
it had submitted to the RTC its Report together with a copy of process.40
the Arbitral Award.28
The RTC Ruling
Consequently, petitioner filed before the RTC a Motion for
Reconsideration29 dated May 19, 2010 (May 19, 2010 Motion In an Order41 dated July 9, 2012, the RTC denied petitioner’s
for Reconsideration)and a Manifestation and Motion30 dated motion to quash.
June 1, 2010 (June 1, 2010 Manifestation and Motion),
asserting that it was denied the opportunity to be heard when It found no merit in petitioner’s contention that it was denied
the Arbitral Tribunal failed to consider its draft decision and due process, ruling that its May 19, 2010 Motion for
merely noted its motion for reconsideration.31 It also denied Reconsideration was a prohibited pleading under Section
receiving a copy of the Arbitral Award by either electronic or 17.2,42 Rule 17 of the CIAC Rules. It explained that the
registered mail.32 For its part, respondent filed an opposition available remedy to assail an arbitral award was to file a motion
thereto and moved for the confirmation33 of the Arbitral Award for correction of final award pursuant to Section 17.143 of the
CIAC Rules, and not a motion for reconsideration of the said resulting in the dismissal of petitioner’s special civil action for
award itself.44 On the other hand, the RTC found petitioner’s certiorari.
June 1, 2010 Manifestation and Motion seeking the resolution
of its May 19, 2010 Motion for Reconsideration to be defective The Court’s Ruling
for petitioner’s failure to observe the three day notice rule.45
Having then failed to avail of the remedies attendant to an order The petition lacks merit.
of confirmation, the Arbitral Award had become final and
executory.46
I.
On July 12, 2012, petitioner received the RTC’s Order dated
Republic Act No. (RA) 9285,54 otherwise known as the
July 9, 2012 denying its motion to quash.47
Alternative Dispute Resolution Act of 2004," institutionalized
the use of an Alternative Dispute Resolution System (ADR
Dissatisfied, it filed on September 10, 2012a petition for System)55 in the Philippines. The Act, however, was without
certiorari48 before the CA, docketed as CA-G.R. SP No. 126458, prejudice to the adoption by the Supreme Court of any ADR
averring in the main that the RTC acted with grave abuse of system as a means of achieving speedy and efficient means of
discretion in confirming and ordering the execution of the resolving cases pending before all courts in the Philippines.56
Arbitral Award.
Accordingly, A.M. No. 07-11-08-SC was created setting forth
The CA Ruling the Special Rules of Court on Alternative Dispute Resolution
(referred herein as Special ADR Rules) that shall govern the
In a Decision49 dated March 26, 2014, the CA dismissed the procedure to be followed by the courts whenever judicial
certiorari petition on two (2) grounds, namely: (a) the petition intervention is sought in ADR proceedings in the specific cases
essentially assailed the merits of the Arbitral Award which is where it is allowed.57
prohibited under Rule 19.750 of the Special ADR Rules;51 and
(b) the petition was filed out of time, having been filed way Rule 1.1 of the Special ADR Rules lists down the instances
beyond 15 days from notice of the RTC’s July 9, 2012 Order, in when the said rules shall apply, namely: "(a) Relief on the issue
violation of Rule 19.2852 in relation to Rule 19.853 of said of Existence, Validity, or Enforceability of the Arbitration
Rules which provide that a special civil action for certiorari Agreement; (b) Referral to Alternative Dispute Resolution
must be filed before the CA within 15 days from notice of the ("ADR"); (c) Interim Measures of Protection; (d) Appointment of
judgment, order, or resolution sought to be annulled or set Arbitrator; (e) Challenge to Appointment of Arbitrator; (f)
aside (or until July 27, 2012). Aggrieved, petitioner filed the Termination of Mandate of Arbitrator; (g) Assistance in Taking
instant petition. Evidence; (h) Confirmation, Correction or Vacation of Award in
Domestic Arbitration; (i) Recognition and Enforcement or
The Issue Before the Court Setting Aside of an Award in International Commercial
Arbitration; (j) Recognition and Enforcement of a Foreign
The core issue for the Court’s resolution is whether or not the Arbitral Award; (k) Confidentiality/Protective Orders; and (l)
CA erred in applying the provisions of the Special ADR Rules, Deposit and Enforcement of Mediated Settlement
Agreements."58
Notably, the Special ADR Rules do not automatically govern the d. where the arbitrators have failed or omitted to resolve
arbitration proceedings itself. A pivotal feature of arbitration as certain issue/s formulated by the parties in the Terms
an alternative mode of dispute resolution is that it is a product of Reference (TOR) and submitted to them for
of party autonomy or the freedom of the parties to make their resolution, and
own arrangements to resolve their own disputes.59 Thus, Rule
2.3 of the Special ADR Rules explicitly provides that "parties e. where the award is imperfect in a matter of form not
are free to agree on the procedure to be followed in the conduct affecting the merits of the controversy.
of arbitral proceedings. Failing such agreement, the arbitral
tribunal may conduct arbitration in the manner it considers The motion shall be acted upon by the Arbitral Tribunal or the
appropriate."60 surviving/remaining members.66

In the case at bar, the Consultancy Agreement contained an Moreover, the parties may appeal the final award to the CA
arbitration clause.61 Hence, respondent, after it filed its through a petition for review under Rule43 of the Rules of
complaint, moved for its referral to arbitration62 which was not Court.67
objected to by petitioner.63 By its referral to arbitration, the
case fell within the coverage of the Special ADR Rules. However,
with respect to the arbitration proceedings itself, the parties Records do not show that any of the foregoing remedies were
availed of by petitioner. Instead, it filed the May 19, 2010
had agreed to adopt the CIAC Rules before the Arbitral Tribunal
Motion for Reconsideration of the Arbitral Award, which was a
in accordance with Rule 2.3 of the Special ADR Rules.
prohibited pleading under the Section 17.2,68 Rule 17 of the
CIAC Rules, thus rendering the same final and executory.
On May 7, 2010, the Arbitral Tribunal rendered the Arbitral
Award in favor of respondent. Under Section 17.2, Rule 17 of
Accordingly, the case was remanded to the RTC for
the CIAC Rules, no motion for reconsideration or new trial may
confirmation proceedings pursuant to Rule 11 of the Special
be sought, but any of the parties may file a motion for
ADR Rules which requires confirmation by the court of the final
correction64 of the final award, which shall interrupt the
running of the period for appeal,65 based on any of the arbitral award. This is consistent with Section 40, Chapter 7
(A) of RA 9285 which similarly requires a judicial confirmation
following grounds, to wit: a. an evident miscalculation of
figures, a typographical or arithmetical error; of a domestic award to make the same enforceable:

b. an evident mistake in the description of any party, SEC. 40. Confirmation of Award.– The confirmation of a
domestic arbitral award shall be governed by Section 2369 of
person, date, amount, thing or property referred to in
the award; R.A. 876.70

A domestic arbitral award when confirmed shall be enforced in


c. where the arbitrators have awarded upon a matter
the same manner as final and executory decisions of the
not submitted to them, not affecting the merits of the
decision upon the matter submitted; regional trial court.
The confirmation of a domestic award shall be made by the b. Reversing the arbitral tribunal’s preliminary
regional trial court in accordance with the Rules of Procedure determination upholding its jurisdiction;
to be promulgated by the Supreme Court.
c. Denying the request to refer the dispute to
A CIAC arbitral award need not be confirmed by the regional arbitration;
trial court to be executory as provided under E.O. No. 1008.
(Emphases supplied) d. Granting or refusing an interim relief;

During the confirmation proceedings, petitioners did not e. Denying a petition for the appointment of an
oppose the RTC’s confirmation by filing a petition to vacate the arbitrator;
Arbitral Award under Rule 11.2 (D)71 of the Special ADR Rules.
Neither did it seek reconsideration of the confirmation order in f. Confirming, vacating or correcting a domestic arbitral
accordance with Rule 19.1 (h) thereof. Instead, petitioner filed award;
only on September 10, 2012 a special civil action for certiorari
before the CA questioning the propriety of (a) the RTC Order
g. Suspending the proceedings to set aside an
dated September 12, 2011 granting respondent’s motion for
international commercial arbitral award and referring
issuance of a writ of execution, and (b) Order dated July 9,2012
denying its motion to quash. Under Rule 19.26 of the Special the case back to the arbitral tribunal;
ADR Rules, "[w]hen the Regional Trial Court, in making a ruling
under the Special ADR Rules, has acted without or in excess of h. Allowing a party to enforce an international
its jurisdiction, or with grave abuse of discretion amounting to commercial arbitral award pending appeal;
lack or excess of jurisdiction, and there is no appeal or any
plain, speedy, and adequate remedy in the ordinary course of i. Adjourning or deferring a ruling on whether to set
law, a party may file a special civil action for certiorari to annul aside, recognize and or enforce an international
or set aside a ruling of the Regional Trial Court." Thus, for commercial arbitral award;
failing to avail of the foregoing remedies before resorting to
certiorari, the CA correctly dismissed its petition. j. Allowing a party to enforce a foreign arbitral award
pending appeal; and
II.
k. Denying a petition for assistance in taking evidence.
Note that the special civil action for certiorari described in Rule (Emphasis supplied)
19.26 above may be filed to annul or set aside the following
orders of the Regional Trial Court. Further, Rule 19.772 of the Special ADR Rules precludes a
party to an arbitration from filing a petition for certiorari
a. Holding that the arbitration agreement is in existent, questioning the merits of an arbitral award.
invalid or unenforceable;
If so falling under the above-stated enumeration, Rule 19.28 of
the Special ADR Rules provide that said certiorari petition
should be filed "with the [CA] within fifteen (15) days from to effectuate its object and purpose, or to make effective rights,
notice of the judgment, order or resolution sought to be powers, privileges or jurisdiction which it grants, including all
annulled or set aside. No extension of time to file the petition such collateral and subsidiary consequences as may be fairly
shall be allowed." and logically inferred from its terms. Ex necessitate legis. And
every statutory grant of power, right or privilege is deemed to
In this case, petitioner asserts that its petition is not covered include all incidental power, right or privilege. This is so
by the Special ADR Rules (particularly, Rule 19.28 on the 15- because the greater includes the lesser, expressed in the
day reglementary period to file a petition for certiorari) but by maxim, in eo plus sit, simper inest et minus.75 (Emphases
Rule 65 of the Rules of Court (particularly, Section 4 thereof on supplied)
the 60-day reglementary period to file a petition for certiorari),
which it claimed to have suppletory application in arbitration As the Court sees it, execution is but a necessary incident to
proceedings since the Special ADR Rules do not explicitly the Court’s confirmation of an arbitral award. To construe it
provide for a procedure on execution. The position is untenable. otherwise would result in an absurd situation whereby the
confirming court previously applying the Special ADR Rules in
Execution is fittingly called the fruit and end of suit and the life its confirmation of the arbitral award would later shift to the
of the law. A judgment, if left unexecuted, would be nothing but regular Rules of Procedure come execution. Irrefragably, a
an empty victory for the prevailing party.73 court’s power to confirm a judgment award under the Special
ADR Rules should be deemed to include the power to order its
While it appears that the Special ADR Rules remain silent on execution for such is but a collateral and subsidiary
the procedure for the execution of a confirmed arbitral award, consequence that may be fairly and logically inferred from the
it is the Court’s considered view that the Rules’ procedural statutory grant to regional trial courts of the power to confirm
mechanisms cover not only aspects of confirmation but domestic arbitral awards.
necessarily extend to a confirmed award’s execution in light of
the doctrine of necessary implication which states that every All the more is such interpretation warranted under the
statutory grant of power, right or privilege is deemed to include principle of ratio legis est anima which provides that a statute
all incidental power, right or privilege. In Atienza v. Villarosa,74 must be read according to its spirit or intent,76 for what is
the doctrine was explained, thus: within the spirit is within the statute although it is not within
its letter, and that which is within the letter but not within the
No statute can be enacted that can provide all the details spirit is not within the statute.77 Accordingly, since the Special
involved in its application.1âwphi1 There is always an omission ADR Rules are intended to achieve speedy and efficient
that may not meet a particular situation. What is thought, at resolution of disputes and curb a litigious culture,78 every
the time of enactment, to be an all embracing legislation may interpretation thereof should be made consistent with these
be inadequate to provide for the unfolding of events of the objectives.
future. So-called gaps in the law develop as the law is enforced.
One of the rules of statutory construction used to fill in the gap Thus, with these principles in mind, the Court so concludes
is the doctrine of necessary implication. The doctrine states that the Special ADR Rules, as far as practicable, should be
that what is implied in a statute is as much a part thereof as made to apply not only to the proceedings on confirmation but
that which is expressed. Every statute is understood, by also to the confirmed award’s execution.
implication, to contain all such provisions as may be necessary
Further, let it be clarified that – contrary to petitioner’s stance On this score, the petition for certiorari in CA-G.R. SP No.
– resort to the Rules of Court even in a suppletory capacity is 126458 was likewise properly dismissed.
not allowed. Rule 22.1 of the Special ADR Rules explicitly
provides that "[t]he provisions of the Rules of Court that are IV.
applicable to the proceedings enumerated in Rule 1.1 of these
Special ADR Rules have either been included and incorporated Nevertheless, while the Court sanctions the dismissal by the
in these Special ADR Rules or specifically referred to herein."79 CA of the petition for certiorari due to procedural infirmities,
Besides, Rule 1.13 thereof provides that "[i]n situations where there is a need to explicate the matter of execution of the
no specific rule is provided under the Special ADR Rules, the confirmed Arbitral Award against the petitioner, a government
court shall resolve such matter summarily and be guided by agency, in the light of Presidential Decree No. (PD) 144584
the spirit and intent of the Special ADR Rules and the ADR otherwise known as the "Government Auditing Code of the
Laws." Philippines." Section 26 of PD 1445 expressly provides that
execution of money judgment against the Government or any
As above-mentioned, the petition for certiorari permitted under of its subdivisions, agencies and instrumentalities is within the
the Special ADR Rules must be filed within a period of fifteen primary jurisdiction of the COA, to wit:
(15) days from notice of the judgment, order or resolution
sought to be annulled or set aside.80 Hence, since petitioner’s SEC. 26. General jurisdiction. The authority and powers of the
filing of its certiorari petition in CA-G.R. SP No. 126458 was Commission shall extend to and comprehend all matters
made nearly two months after its receipt of the RTC’s Order relating to auditing procedures, systems and controls, the
dated July 9, 2012,or on September 10, 2012,81 said petition keeping of the general accounts of the Government, the
was clearly dismissible.82 preservation of vouchers pertaining thereto for a period of ten
years, the examination and inspection of the books, records,
III. and papers relating to those accounts; and the audit and
settlement of the accounts of all persons respecting funds or
Discounting the above-discussed procedural considerations, property received or held by them in an accountable capacity,
the Court still finds that the certiorari petition had no merit. as well as the examination, audit, and settlement of all debts
and claims of any sort due from or owing to the Government or
Indeed, petitioner cannot be said to have been denied due any of its subdivisions, agencies and instrumentalities. The
process as the records undeniably show that it was accorded said jurisdiction extends to all government-owned or controlled
ample opportunity to ventilate its position. There was clearly corporations, including their subsidiaries, and other self-
nothing out of line when the Arbitral Tribunal denied governing boards, commissions, or agencies of the
petitioner’s motions for extension to file its submissions having Government, and as herein prescribed, including non-
failed to show a valid reason to justify the same or in rendering governmental entities subsidized by the government, those
the Arbitral Award sans petitioner’s draft decision which was funded by donation through the government, those required to
filed only on the day of the scheduled promulgation of final pay levies or government share, and those for which the
award on May 7, 2010.83 The touchstone of due process is government has put up a counterpart fund or those partly
basically the opportunity to be heard. Having been given such funded by the government. (Emphases supplied)
opportunity, petitioner should only blame itself for its own
procedural blunder.
From the foregoing, the settlement of respondent’s money claim
is still subject to the primary jurisdiction of the COA despite
finality of the confirmed arbitral award by the RTC pursuant to
the Special ADR Rules.85 Hence, the respondent has to first
seek the approval of the COA of their monetary claim. This
appears to have been complied with by the latter when it filed
a "Petition for Enforcement and Payment of Final and
Executory Arbitral Award"86 before the COA. Accordingly, it is
now the COA which has the authority to rule on this latter
petition. WHEREFORE, the petition is DENIED. The Decision
dated March 26, 2014 of the Court of Appeals in CA-G.R. SP
No. 126458 which dismissed the petition for certiorari filed by
petitioner the Department of Environment and Natural
Resources is hereby AFFIRMED.

SO ORDERED.

ESTELA M. PERLAS-BERNABE
Associate Justice
DIVISION Law,"[6] and that each of the parties shall appoint one
arbitrator, and the three arbitrators would then appoint the
[ GR No. 198226, Jul 18, 2014] fourth arbitrator who shall act as Chairman.

ABOITIZ TRANSPORT SYSTEM CORPORATION v. CARLOS Among the attachments to the Agreement was a letter[7] dated
A. GOTHONG LINES + January 8, 1996 written by respondent Chiongbian and
addressed to Gothong, stating that WLI committed to acquire
from CAGLI's inventory certain spare parts and materials not
DECISION exceeding P400 Million. In this relation, a valuation of CAGLI's
inventory was conducted wherein it was shown that the same
PERLAS-BERNABE, J.: amounted to P514 Million.[8] Thereafter, WLI received inventory
valued at P558.89 Million, but only paid CAGLI the amount of
Assailed in these petitions for review on certiorari[1] are the P400 Million as agreed upon in the Agreement.[9] Dissatisfied,
Orders dated August 13, 2010,[2] April 15, 2011,[3] and July 6, CAGLI sent to WLI various letters in 2001, demanding that the
2011[4] of the Regional Trial Court of Cebu City, Branch 20 latter pay or return the inventory that it received in excess of
(RTC) in Civil Case No. CEB-34951, which confirmed the notice P400 Million.[10]
of dismissal filed by respondent Carlos A. Gothong Lines, Inc.
(CAGLI) and, consequently, dismissed the case without Sometime in 2002, the Chiongbian and Gothong families
prejudice, denied petitioners Aboitiz Transport System decided to sell their respective interests in WLI/WG&A to the
Corporation (ATSC) and Aboitiz Shipping Corporation's (ASC) Aboitiz family. This resulted in the execution of a Share
motion for reconsideration, and deemed ATSC's motion to Purchase Agreement[11] whereby Aboitiz Equity Ventures (AEV)
exclude respondent Victor S. Chiongbian (respondent agreed to purchase and acquire the WLI/WG&A shares of the
Chiongbian) from arbitration moot and academic, respectively. Chiongbian and Gothong families. Thereafter, the corporate
name of WLI/WG&A was changed to ATSC.[12]
The Facts
Six (6) years later, or in 2008, CAGLI sent a letter[13] dated
ASC, CAGLI, and William Lines, Inc. (WLI), principally owned February 14, 2008 to ATSC demanding that the latter pay the
by the Aboitiz, Gothong, and Chiongbian families, respectively, excess inventory it delivered to WLI amounting to
entered into an Agreement[5] dated January 8, 1996, which was P158,399,700.00. CAGLI likewise demanded AEV and
signed by Jon Ramon Aboitiz for ASC, Benjamin D. Gothong respondent Chiongbian that they refer their dispute to
(Gothong) for CAGLI, and respondent Chiongbian for WLI. In arbitration.[14] In response, AEV countered that the excess
the said Agreement, ASC and CAGLI agreed to transfer their inventory had already been returned to CAGLI and that it
shipping assets to WLI in exchange for the latter's shares of should not be included in the dispute, considering that it is an
capital stock. The parties likewise agreed that WLI would run entity separate and distinct from ATSC.[15] Thus, CAGLI was
the merged shipping business and be renamed "WG&A, Inc." constrained to file a complaint[16] before the RTC against
Pertinently, Section 11.06 of the Agreement provides that all Chiongbian, ATSC, ASC, and AEV to compel them to submit to
disputes arising out of or in connection with the Agreement arbitration.
shall be finally settled by arbitration in accordance with
Republic Act No. (RA) 876, otherwise known as "The Arbitration For their part, ATSC and AEV moved for the dismissal of the
case, contending that CAGLI did not have a cause of action for stage of the proceedings.[27]
arbitration since its claim had already been paid or otherwise,
extinguished, and, in any event, said action had already Separately, the RTC issued an Order[28] dated July 6, 2011,
prescribed.[17] denying ATSC's Motion for Reconsideration/To Exclude,
holding that the issue raised in the said motion has been
The RTC Proceedings rendered moot and academic in view of the confirmation of
CAGLI's notice of dismissal.
In an Order[18] dated December 4, 2009, the RTC dismissed the
complaint only with respect to AEV for lack of cause of Hence, the instant petitions.
action,[19] but not as to the other defendants. Thereafter, the
RTC issued an Order[20] dated February 26, 2010, directing The Issues Before the Court
CAGLI, respondent Chiongbian, ATSC, and ASC to proceed to
arbitration, and accordingly, the parties appointed their The issues for the Court's resolution are as follows: (a) whether
respective arbitrators, with ATSC and ASC doing so only on an or not the RTC was correct in confirming CAGLI's notice of
ad cautelam basis.[21] dismissal and, consequently, dismissing the case without
prejudice; and (b) whether or not respondent Chiongbian
Meanwhile, ATSC filed a Motion for Reconsideration/To should be excluded from the arbitration proceedings.
Exclude[22] dated March 25, 2010 praying that respondent
Chiongbian be excluded from the arbitration proceedings since The Court's Ruling
the latter was not a party to the Agreement. Pending resolution
of the said motion, CAGLI filed a Notice of Dismissal[23] dated The petition is meritorious.
July 8, 2010, averring that it has decided to withdraw its
complaint in view of the fact that the opposing parties had not A. Propriety of CAGLI's Notice of Dismissal.
filed their respective responsive pleadings.
At the outset, the Court notes that the nature of the complaint
In an Order[24] dated August 13, 2010, the RTC found CAGLI's filed by CAGLI before the RTC is for the enforcement of an
Notice of Dismissal meritorious, and, thus, confirmed the same arbitration agreement, governed by Section 6 of RA 876, viz.:
and ordered the case dismissed without prejudice.
Section 6. Hearing by court. A party aggrieved by the failure,
Dissatisfied, ATSC and ASC moved for reconsideration[25] which neglect or refusal of another to perform under an agreement in
was, however, denied in an Order[26] dated April 15, 2011. In writing providing for arbitration may petition the court for an
said Order, the RTC cited Section 1 of Rule 17 of the Rules of order directing that such arbitration proceed in the manner
Court which allows the plaintiff to file a notice of dismissal of provided for in such agreement. Five days notice in writing of
the complaint as a matter of right "before service of the answer the hearing of such application shall be served either personally
or a motion for summary judgment." It further ruled that, save or by registered mail upon the party in default. The court shall
for the condition that no answer or motion for summary hear the parties, and upon being satisfied that the making of
judgment had been priorly filed, nothing in the rules or law the agreement or such failure to comply therewith is not in
expressly prohibits or restricts the right of the plaintiff to issue, shall make an order directing the parties to proceed to
withdraw the complaint by mere notice of dismissal at any arbitration in accordance with the terms of the agreement. If
the making of the agreement or default be in issue the court answer or of a motion for summary judgment," mentioned in
shall proceed to summarily hear such issue. If the finding be Section 1[37] of Rule 17 of the Rules of Court when a notice of
that no agreement in writing providing for arbitration was dismissal may be filed by the plaintiff, no longer applies. As a
made, or that there is no default in the proceeding consequence, a notice of dismissal filed by the plaintiff at such
thereunder, the proceeding shall be dismissed. If the judgment stage should no longer be entertained or confirmed.
finding be that a written provision for arbitration was made
and there is a default in proceeding thereunder, an order In view of the foregoing, it was an error on the part of the RTC
shall be made summarily directing the parties to proceed to have confirmed the notice of dismissal and to have dismissed
with the arbitration in accordance with the terms thereof. the complaint without prejudice.

x x x x (Emphasis supplied) B. Parties covered by Arbitration Proceedings.

Section 2 of RA 876 specifies who may be subjected to


In the case of Gonzales v. Climax Mining, Ltd. (Gonzales),[29] the
arbitration, to wit:
Court had instructed that the special proceeding under the
above-quoted provision is the procedural mechanism for the
enforcement of the contract to arbitrate.[30] RA 876 explicitly Sec. 2. Persons and matters subject to arbitration. Two or more
confines the court's authority only to pass upon the issue of persons or parties may submit to the arbitration of one or more
whether there is or there is no agreement in writing providing arbitrators any controversy existing between them at the time
for arbitration. If there is such agreement, the court shall issue of the submission and which may be the subject of an action,
an order summarily directing the parties to proceed with the or the parties to any contract may in such contract agree to
arbitration in accordance with the terms thereof; otherwise, the settle by arbitration a controversy thereafter arising between
proceeding shall be dismissed.[31] To stress, such proceeding is them. Such submission or contract shall be valid, enforceable
merely a summary remedy to enforce the agreement to arbitrate and irrevocable, save upon such grounds as exist at law for the
and the duty of the court is not to resolve the merits of the revocation of any contract.
parties' claims but only to determine if they should proceed to
arbitration or not.[32] xxxx

In the present case, the records show that the primary relief In Gonzales, the Court explained that "[d]isputes do not go to
sought for in CAGLI's complaint, i.e., to compel the parties to arbitration unless and until the parties have agreed to abide by
submit to arbitration,[33] had already been granted by the RTC the arbitrator's decision. Necessarily, a contract is required for
through its Order[34] dated February 26, 2010. Undeniably, arbitration to take place and to be binding."[38] Furthermore, in
such Order partakes of a judgment on the merits of the Del Monte Corporation USA v. Court of Appeals,[39] the Court
complaint for the enforcement of the arbitration agreement. stated that "[t]he provision to submit to arbitration any dispute
arising therefrom and the relationship of the parties is part of
At this point, although no responsive pleading had been filed that contract. As a rule, contracts are respected as the law
by ATSC,[35] it is the rules on appeal, or other proceedings after between the contracting parties and produce effect as between
rendition of a judgment or final order no longer those on notice them, their assigns and heirs."[40] Succinctly put, only those
of dismissal that come into play. Verily, upon the rendition of a parties who have agreed to submit a controversy to arbitration
judgment or final order,[36] the period "before service of the who, as against each other, may be compelled to submit to
arbitration. SO ORDERED.

In the present case, Section 11.06 of the Agreement, which Carpio, (Chairperson), Brion, Del Castillo, and Perlas-Bernabe,
embodies the Arbitration Agreement among the parties, JJ., concur.
provides:

All disputes arising out of or in connection with this Agreement


including any issue as to this Agreement's validity or
enforceability, which cannot be settled amicably among the
parties, shall be finally settled by arbitration in accordance with
the Arbitration Law (Republic Act No. 876) by an arbitration
tribunal composed of four (4) arbitrators. Each of the parties
shall appoint one (1) arbitrator, the three (3) to appoint the
fourth arbitrator who shall act as Chairman. Any award by the
arbitration tribunal shall be final and binding upon the parties
and shall be enforced by judgment of the Courts of Cebu or
Metro Manila. [41]

The three parties to the Agreement and necessarily to the


arbitration agreement embodied therein are: (a) ASC, (b) CAGLI,
and (c) WLI/WG&A/ATSC. Contracts, like the subject
arbitration agreement, take effect only between the parties,
their assigns and heirs.[42] Respondent Chiongbian, having
merely physically signed the Agreement as a representative of
WLI, is not a party thereto and to the arbitration agreement
contained therein. Neither is he an assignee or an heir of any
of the parties to the arbitration agreement. Hence, respondent
Chiongbian cannot be included in the arbitration proceedings.

WHEREFORE, the petitions are GRANTED. The Orders dated


August 13, 2010, April 15, 2011, and July 6, 2011 of the
Regional Trial Court of Cebu City, Branch 20 (RTC) in Civil Case
No. CEB-34951 are hereby REVERSED and SET ASIDE. The
Order dated February 26, 2010 of the RTC is REINSTATED
with MODIFICATION excluding Victor S. Chiongbian from the
arbitration proceedings.
Republic of the Philippines II, Bonito-III, and Bonito-IV, with a total area of 288.8656
SUPREME COURT hectares, situated in Barangay Luklukam, Sitio Bagong Bayan,
Manila Municipality of Jose Panganiban, Camarines Norte. The parties
also executed a Supplemental Agreement5 dated June 1, 1987.
SECOND DIVISION The mining claims were covered by MPSA Application No.
APSA-V-0009 jointly filed by J.G. Realty as claimowner and
G.R. No. 163101 February 13, 2008 Benguet as operator.

BENGUET CORPORATION, petitioner, In the RAWOP, Benguet obligated itself to perfect the rights to
vs. the mining claims and/or otherwise acquire the mining rights
DEPARTMENT OF ENVIRONMENT AND NATURAL to the mineral claims. Within 24 months from the execution of
RESOURCES -MINES ADJUDICATION BOARD and J.G. the RAWOP, Benguet should also cause the examination of the
REALTY AND MINING CORPORATION, respondents. mining claims for the purpose of determining whether or not
they are worth developing with reasonable probability of
profitable production. Benguet undertook also to furnish J.G.
DECISION Realty with a report on the examination, within a reasonable
time after the completion of the examination. Moreover, also
VELASCO, JR., J.: within the examination period, Benguet shall conduct all
necessary exploration in accordance with a prepared
The instant petition under Rule 65 of the Rules of Court seeks exploration program. If it chooses to do so and before the
the annulment of the December 2, 2002 Decision1 and March expiration of the examination period, Benguet may undertake
17, 2004 Resolution2 of the Department of Environment and to develop the mining claims upon written notice to J.G. Realty.
Natural Resources-Mining Adjudication Board (DENR-MAB) in Benguet must then place the mining claims into commercial
MAB Case No. 0124-01 (Mines Administrative Case No. R-M- productive stage within 24 months from the written notice.6 It
2000-01) entitled Benguet Corporation (Benguet) v. J.G. Realty is also provided in the RAWOP that if the mining claims were
and Mining Corporation (J.G. Realty). The December 2, 2002 placed in commercial production by Benguet, J.G. Realty
Decision upheld the March 19, 2001 Decision3 of the MAB should be entitled to a royalty of five percent (5%) of net
Panel of Arbitrators (POA) which canceled the Royalty realizable value, and to royalty for any production done by
Agreement with Option to Purchase (RAWOP) dated June 1, Benguet whether during the examination or development
19874 between Benguet and J.G. Realty, and excluded Benguet periods.
from the joint Mineral Production Sharing Agreement (MPSA)
application over four mining claims. The March 17, 2004 Thus, on August 9, 1989, the Executive Vice-President of
Resolution denied Benguet’s Motion for Reconsideration. Benguet, Antonio N. Tachuling, issued a letter informing J.G.
Realty of its intention to develop the mining claims. However,
The Facts on February 9, 1999, J.G. Realty, through its President,
Johnny L. Tan, then sent a letter to the President of Benguet
On June 1, 1987, Benguet and J.G. Realty entered into a informing the latter that it was terminating the RAWOP on the
RAWOP, wherein J.G. Realty was acknowledged as the owner following grounds:
of four mining claims respectively named as Bonito-I, Bonito-
a. The fact that your company has failed to perform the On June 7, 2000, J.G. Realty filed a Petition for Declaration of
obligations set forth in the RAWOP, i.e., to undertake Nullity/Cancellation of the RAWOP9 with the Legaspi City POA,
development works within 2 years from the execution of Region V, docketed as DENR Case No. 2000-01 and entitled
the Agreement; J.G. Realty v. Benguet.

b. Violation of the Contract by allowing high graders to On March 19, 2001, the POA issued a Decision,10 dwelling upon
operate on our claim. the issues of (1) whether the arbitrators had jurisdiction over
the case; and (2) whether Benguet violated the RAWOP
c. No stipulation was provided with respect to the term justifying the unilateral cancellation of the RAWOP by J.G.
limit of the RAWOP. Realty. The dispositive portion stated:

d. Non-payment of the royalties thereon as provided in WHEREFORE, premises considered, the June 01, 1987
the RAWOP.7 [RAWOP] and its Supplemental Agreement is hereby
declared cancelled and without effect. BENGUET is
In response, Benguet’s Manager for Legal Services, Reynaldo P. hereby excluded from the joint MPSA Application over
Mendoza, wrote J.G. Realty a letter dated March 8, 1999, 8 the mineral claims denominated as "BONITO-I",
therein alleging that Benguet complied with its obligations "BONITO-II", "BONITO-III" and "BONITO-IV".
under the RAWOP by investing PhP 42.4 million to rehabilitate
the mines, and that the commercial operation was hampered SO ORDERED.
by the non-issuance of a Mines Temporary Permit by the Mines
and Geosciences Bureau (MGB) which must be considered as Therefrom, Benguet filed a Notice of Appeal11 with the MAB on
force majeure, entitling Benguet to an extension of time to April 23, 2001, docketed as Mines Administrative Case No. R-
prosecute such permit. Benguet further claimed that the high M-2000-01. Thereafter, the MAB issued the assailed December
graders mentioned by J.G. Realty were already operating prior 2, 2002 Decision. Benguet then filed a Motion for
to Benguet’s taking over of the premises, and that J.G. Realty Reconsideration of the assailed Decision which was denied in
had the obligation of ejecting such small scale miners. Benguet the March 17, 2004 Resolution of the MAB. Hence, Benguet
also alleged that the nature of the mining business made it filed the instant petition.
difficult to specify a time limit for the RAWOP. Benguet then
argued that the royalties due to J.G. Realty were in fact in its The Issues
office and ready to be picked up at any time. It appeared that,
previously, the practice by J.G. Realty was to pick-up checks 1. There was serious and palpable error when the
from Benguet representing such royalties. However, starting Honorable Board failed to rule that the contractual
August 1994, J.G. Realty allegedly refused to collect such obligation of the parties to arbitrate under the Royalty
checks from Benguet. Thus, Benguet posited that there was no Agreement is mandatory.
valid ground for the termination of the RAWOP. It also
reminded J.G. Realty that it should submit the disagreement to
2. The Honorable Board exceeded its jurisdiction when
arbitration rather than unilaterally terminating the RAWOP.
it sustained the cancellation of the Royalty Agreement
for alleged breach of contract despite the absence of Supreme Court as provided in this Constitution without
evidence. its advice and consent." On the other hand, Section 79
of RA No. 7942 provides that decisions of the MAB may
3. The Questioned Decision of the Honorable Board in be reviewed by this Court on a "petition for review by
cancelling the RAWOP prejudice[d] the substantial certiorari." This provision is obviously an expansion of
rights of Benguet under the contract to the unjust the Court’s appellate jurisdiction, an expansion to
enrichment of JG Realty.12 which this Court has not consented. Indiscriminate
enactment of legislation enlarging the appellate
Restated, the issues are: (1) Should the controversy have first jurisdiction of this Court would unnecessarily burden
been submitted to arbitration before the POA took cognizance it.
of the case?; (2) Was the cancellation of the RAWOP supported
by evidence?; and (3) Did the cancellation of the RAWOP Second, when the Supreme Court, in the exercise of its
amount to unjust enrichment of J.G. Realty at the expense of rule-making power, transfers to the CA pending cases
Benguet? involving a review of a quasi-judicial body’s decisions,
such transfer relates only to procedure; hence, it does
The Court’s Ruling not impair the substantive and vested rights of the
parties. The aggrieved party’s right to appeal is
preserved; what is changed is only the procedure by
Before we dwell on the substantive issues, we find that the which the appeal is to be made or decided. The parties
instant petition can be denied outright as Benguet resorted to still have a remedy and a competent tribunal to grant
an improper remedy. this remedy.

The last paragraph of Section 79 of Republic Act No. (RA) 7942 Third, the Revised Rules of Civil Procedure included
or the "Philippine Mining Act of 1995" states, "A petition for Rule 43 to provide a uniform rule on appeals from
review by certiorari and question of law may be filed by the
quasi-judicial agencies. Under the rule, appeals from
aggrieved party with the Supreme Court within thirty (30) days their judgments and final orders are now required to be
from receipt of the order or decision of the [MAB]." brought to the CA on a verified petition for review. A
quasi-judicial agency or body has been defined as an
However, this Court has already invalidated such provision in organ of government, other than a court or legislature,
Carpio v. Sulu Resources Development Corp.,13 ruling that a which affects the rights of private parties through either
decision of the MAB must first be appealed to the Court of adjudication or rule-making. MAB falls under this
Appeals (CA) under Rule 43 of the Rules of Court, before definition; hence, it is no different from the other quasi-
recourse to this Court may be had. We held, thus: judicial bodies enumerated under Rule 43. Besides, the
introductory words in Section 1 of Circular No. 1-91––
To summarize, there are sufficient legal footings "among these agencies are"––indicate that the
authorizing a review of the MAB Decision under Rule 43 enumeration is not exclusive or conclusive and
of the Rules of Court. First, Section 30 of Article VI of acknowledge the existence of other quasi-judicial
the 1987 Constitution, mandates that "[n]o law shall be agencies which, though not expressly listed, should be
passed increasing the appellate jurisdiction of the deemed included therein.
Fourth, the Court realizes that under Batas Pambansa Even if we entertain the petition although Benguet skirted the
(BP) Blg. 129 as amended by RA No. 7902, factual appeal to the CA via Rule 43, still, the December 2, 2002
controversies are usually involved in decisions of quasi- Decision and March 17, 2004 Resolution of the DENR-MAB in
judicial bodies; and the CA, which is likewise tasked to MAB Case No. 0124-01 should be maintained.
resolve questions of fact, has more elbow room to
resolve them. By including questions of fact among the First Issue: The case should have first been brought
issues that may be raised in an appeal from quasi- to
judicial agencies to the CA, Section 3 of Revised voluntary arbitration before the POA
Administrative Circular No. 1-95 and Section 3 of Rule
43 explicitly expanded the list of such issues. Secs. 11.01 and 11.02 of the RAWOP pertinently
provide:
According to Section 3 of Rule 43, "[a]n appeal under
this Rule may be taken to the Court of Appeals within 11.01 Arbitration
the period and in the manner herein provided whether
the appeal involves questions of fact, of law, or mixed
Any disputes, differences or disagreements between
questions of fact and law." Hence, appeals from quasi-
judicial agencies even only on questions of law may be BENGUET and the OWNER with reference to anything
whatsoever pertaining to this Agreement that cannot be
brought to the CA.
amicably settled by them shall not be cause of any
action of any kind whatsoever in any court or
Fifth, the judicial policy of observing the hierarchy of administrative agency but shall, upon notice of one
courts dictates that direct resort from administrative party to the other, be referred to a Board of Arbitrators
agencies to this Court will not be entertained, unless consisting of three (3) members, one to be selected by
the redress desired cannot be obtained from the BENGUET, another to be selected by the OWNER and
appropriate lower tribunals, or unless exceptional and the third to be selected by the aforementioned two
compelling circumstances justify availment of a remedy arbitrators so appointed.
falling within and calling for the exercise of our primary
jurisdiction.14
xxxx
The above principle was reiterated in Asaphil Construction and
Development Corporation v. Tuason, Jr. (Asaphil).15 However, 11.02 Court Action
the Carpio ruling was not applied to Asaphil as the petition in
the latter case was filed in 1999 or three years before the No action shall be instituted in court as to any matter
promulgation of Carpio in 2002. Here, the petition was filed on in dispute as hereinabove stated, except to enforce the
April 28, 2004 when the Carpio decision was already applicable, decision of the majority of the Arbitrators.16
thus Benguet should have filed the appeal with the CA.
Thus, Benguet argues that the POA should have first referred
Petitioner having failed to properly appeal to the CA under Rule the case to voluntary arbitration before taking cognizance of the
43, the decision of the MAB has become final and executory. case, citing Sec. 2 of RA 876 on persons and matters subject to
On this ground alone, the instant petition must be denied. arbitration.
On the other hand, in denying such argument, the POA ruled general law, such as RA 876. It also argued that the POA cannot
that: be considered as a "court" under the contemplation of RA 876
and that jurisprudence saying that there must be prior resort
While the parties may establish such stipulations clauses, to arbitration before filing a case with the courts is inapplicable
terms and conditions as they may deem convenient, the same to the instant case as the POA is itself already engaged in
must not be contrary to law and public policy. At a glance, there arbitration.
is nothing wrong with the terms and conditions of the
agreement. But to state that an aggrieved party cannot initiate On this issue, we rule for Benguet.
an action without going to arbitration would be tying one’s
hand even if there is a law which allows him to do so.17 Sec. 2 of RA 876 elucidates the scope of arbitration:

The MAB, meanwhile, denied Benguet’s contention on the Section 2. Persons and matters subject to arbitration.––
ground of estoppel, stating: Two or more persons or parties may submit to the
arbitration of one or more arbitrators any
Besides, by its own act, Benguet is already estopped in controversy existing between them at the time of
questioning the jurisdiction of the Panel of Arbitrators the submission and which may be the subject of an
to hear and decide the case. As pointed out in the action, or the parties to any contract may in such
appealed Decision, Benguet initiated and filed an contract agree to settle by arbitration a controversy
Adverse Claim docketed as MAC-R-M-2000-02 over the thereafter arising between them. Such submission
same mining claims without undergoing contractual or contract shall be valid, enforceable and
arbitration. In this particular case (MAC-R-M-2000-02) irrevocable, save upon such grounds as exist at law
now subject of the appeal, Benguet is likewise in for the revocation of any contract.
estoppel from questioning the competence of the Panel
of Arbitrators to hear and decide in the summary Such submission or contract may include question[s]
proceedings J.G. Realty’s petition, when Benguet itself arising out of valuations, appraisals or other
did not merely move for the dismissal of the case but controversies which may be collateral, incidental,
also filed an Answer with counterclaim seeking precedent or subsequent to any issue between the
affirmative reliefs from the Panel of Arbitrators.18 parties. (Emphasis supplied.)

Moreover, the MAB ruled that the contractual provision on In RA 9285 or the "Alternative Dispute Resolution Act of 2004,"
arbitration merely provides for an additional forum or venue the Congress reiterated the efficacy of arbitration as an
and does not divest the POA of the jurisdiction to hear the alternative mode of dispute resolution by stating in Sec. 32
case.19 thereof that domestic arbitration shall still be governed by RA
876. Clearly, a contractual stipulation that requires prior resort
In its July 20, 2004 Comment,20 J.G. Realty reiterated the to voluntary arbitration before the parties can go directly to
above rulings of the POA and MAB. It argued that RA 7942 or court is not illegal and is in fact promoted by the State. Thus,
the "Philippine Mining Act of 1995" is a special law which petitioner correctly cites several cases whereby arbitration
should prevail over the stipulations of the parties and over a clauses have been upheld by this Court.21
Moreover, the contention that RA 7942 prevails over RA 876 referable to arbitration, shall stay the action or
presupposes a conflict between the two laws. Such is not the proceeding until an arbitration has been had in
case here. To reiterate, availment of voluntary arbitration accordance with the terms of the agreement: Provided,
before resort is made to the courts or quasi-judicial agencies of That the applicant, for the stay is not in default in
the government is a valid contractual stipulation that must be proceeding with such arbitration. (Emphasis supplied.)
adhered to by the parties. As stated in Secs. 6 and 7 of RA 876:
In other words, in the event a case that should properly be the
Section 6. Hearing by court.––A party aggrieved by the subject of voluntary arbitration is erroneously filed with the
failure, neglect or refusal of another to perform courts or quasi-judicial agencies, on motion of the defendant,
under an agreement in writing providing for the court or quasi-judicial agency shall determine whether
arbitration may petition the court for an order such contractual provision for arbitration is sufficient and
directing that such arbitration proceed in the effective. If in affirmative, the court or quasi-judicial agency
manner provided for in such agreement. Five days shall then order the enforcement of said provision. Besides, in
notice in writing of the hearing of such application shall BF Corporation v. Court of Appeals, we already ruled:
be served either personally or by registered mail upon
the party in default. The court shall hear the parties, In this connection, it bears stressing that the lower
and upon being satisfied that the making of the court has not lost its jurisdiction over the case. Section
agreement or such failure to comply therewith is not 7 of Republic Act No. 876 provides that proceedings
in issue, shall make an order directing the parties to therein have only been stayed. After the special
proceed to arbitration in accordance with the terms proceeding of arbitration has been pursued and
of the agreement. If the making of the agreement or completed, then the lower court may confirm the award
default be in issue the court shall proceed to made by the arbitrator.22
summarily hear such issue. If the finding be that no
agreement in writing providing for arbitration was J.G. Realty’s contention, that prior resort to arbitration is
made, or that there is no default in the proceeding unavailing in the instant case because the POA’s mandate is to
thereunder, the proceeding shall be dismissed. If the arbitrate disputes involving mineral agreements, is misplaced.
finding be that a written provision for arbitration A distinction must be made between voluntary and compulsory
was made and there is a default in proceeding arbitration. In Ludo and Luym Corporation v. Saordino, the
thereunder, an order shall be made summarily Court had the occasion to distinguish between the two types of
directing the parties to proceed with the arbitration arbitrations:
in accordance with the terms thereof.
Comparatively, in Reformist Union of R.B. Liner, Inc. vs.
xxxx NLRC, compulsory arbitration has been defined both as
"the process of settlement of labor disputes by a
Section 7. Stay of civil action.––If any suit or proceeding government agency which has the authority to
be brought upon an issue arising out of an agreement investigate and to make an award which is binding on
providing for the arbitration thereof, the court in which all the parties, and as a mode of arbitration where the
such suit or proceeding is pending, upon being satisfied parties are compelled to accept the resolution of their
that the issue involved in such suit or proceeding is dispute through arbitration by a third party." While a
voluntary arbitrator is not part of the governmental However, we find that Benguet is already estopped from
unit or labor department’s personnel, said arbitrator questioning the POA’s jurisdiction. As it were, when J.G. Realty
renders arbitration services provided for under labor filed DENR Case No. 2000-01, Benguet filed its answer and
laws.23 (Emphasis supplied.) participated in the proceedings before the POA, Region V.
Secondly, when the adverse March 19, 2001 POA Decision was
There is a clear distinction between compulsory and voluntary rendered, it filed an appeal with the MAB in Mines
arbitration. The arbitration provided by the POA is compulsory, Administrative Case No. R-M-2000-01 and again participated
while the nature of the arbitration provision in the RAWOP is in the MAB proceedings. When the adverse December 2, 2002
voluntary, not involving any government agency. Thus, J.G. MAB Decision was promulgated, it filed a motion for
Realty’s argument on this matter must fail. reconsideration with the MAB. When the adverse March 17,
2004 MAB Resolution was issued, Benguet filed a petition with
As to J.G. Realty’s contention that the provisions of RA 876 this Court pursuant to Sec. 79 of RA 7942 impliedly recognizing
cannot apply to the instant case which involves an MAB’s jurisdiction. In this factual milieu, the Court rules that
administrative agency, it must be pointed out that Section the jurisdiction of POA and that of MAB can no longer be
11.01 of the RAWOP states that: questioned by Benguet at this late hour. What Benguet should
have done was to immediately challenge the POA’s jurisdiction
by a special civil action for certiorari when POA ruled that it
[Any controversy with regard to the contract] shall not
has jurisdiction over the dispute. To redo the proceedings fully
be cause of any action of any kind whatsoever in any participated in by the parties after the lapse of seven years from
court or administrative agency but shall, upon notice date of institution of the original action with the POA would be
of one party to the other, be referred to a Board of anathema to the speedy and efficient administration of justice.
Arbitrators consisting of three (3) members, one to be
selected by BENGUET, another to be selected by the
OWNER and the third to be selected by the Second Issue: The cancellation of the RAWOP
aforementioned two arbiters so appointed.24 (Emphasis was supported by evidence
supplied.)
The cancellation of the RAWOP by the POA was based on two
There can be no quibbling that POA is a quasi-judicial body grounds: (1) Benguet’s failure to pay J.G. Realty’s royalties for
which forms part of the DENR, an administrative agency. the mining claims; and (2) Benguet’s failure to seriously pursue
Hence, the provision on mandatory resort to arbitration, freely MPSA Application No. APSA-V-0009 over the mining claims.
entered into by the parties, must be held binding against
them.25 As to the royalties, Benguet claims that the checks representing
payments for the royalties of J.G. Realty were available for pick-
In sum, on the issue of whether POA should have referred the up in its office and it is the latter which refused to claim them.
case to voluntary arbitration, we find that, indeed, POA has no Benguet then thus concludes that it did not violate the RAWOP
jurisdiction over the dispute which is governed by RA 876, the for nonpayment of royalties. Further, Benguet reasons that
arbitration law. J.G. Realty has the burden of proving that the former did not
pay such royalties following the principle that the complainants
must prove their affirmative allegations.
With regard to the failure to pursue the MPSA application, Notably, Benguet’s claim that J.G. Realty must prove
Benguet claims that the lengthy time of approval of the nonpayment of its royalties is both illogical and unsupported
application is due to the failure of the MGB to approve it. In by law and jurisprudence.
other words, Benguet argues that the approval of the
application is solely in the hands of the MGB. The allegation of nonpayment is not a positive allegation as
claimed by Benguet. Rather, such is a negative allegation that
Benguet’s arguments are bereft of merit. does not require proof and in fact transfers the burden of proof
to Benguet. Thus, this Court ruled in Jimenez v. National Labor
Sec. 14.05 of the RAWOP provides: Relations Commission:

14.05 Bank Account As a general rule, one who pleads payment has the
burden of proving it. Even where the plaintiff must
OWNER shall maintain a bank account at ___________ allege non-payment, the general rule is that the burden
or any other bank from time to time selected by OWNER rests on the defendant to prove payment, rather than
with notice in writing to BENGUET where BENGUET on the plaintiff to prove non-payment. The debtor has
shall deposit to the OWNER’s credit any and all the burden of showing with legal certainty that the
advances and payments which may become due the obligation has been discharged by payment.27
OWNER under this Agreement as well as the purchase (Emphasis supplied.)
price herein agreed upon in the event that BENGUET
shall exercise the option to purchase provided for in the In the instant case, the obligation of Benguet to pay royalties to
Agreement. Any and all deposits so made by J.G. Realty has been admitted and supported by the provisions
BENGUET shall be a full and complete acquittance of the RAWOP. Thus, the burden to prove such obligation rests
and release to [sic] BENGUET from any further on Benguet.
liability to the OWNER of the amounts represented
by such deposits. (Emphasis supplied.) It should also be borne in mind that MPSA Application No.
APSA-V-0009 has been pending with the MGB for a
Evidently, the RAWOP itself provides for the mode of royalty considerable length of time. Benguet, in the RAWOP, obligated
payment by Benguet. The fact that there was the previous itself to perfect the rights to the mining claims and/or otherwise
practice whereby J.G. Realty picked-up the checks from acquire the mining rights to the mineral claims but failed to
Benguet is unavailing. The mode of payment is embodied in a present any evidence showing that it exerted efforts to speed up
contract between the parties. As such, the contract must be and have the application approved. In fact, Benguet never even
considered as the law between the parties and binding on alleged that it continuously followed-up the application with
both.26 Thus, after J.G. Realty informed Benguet of the bank the MGB and that it was in constant communication with the
account where deposits of its royalties may be made, Benguet government agency for the expeditious resolution of the
had the obligation to deposit the checks. J.G. Realty had no application. Such allegations would show that, indeed, Benguet
obligation to furnish Benguet with a Board Resolution was remiss in prosecuting the MPSA application and clearly
considering that the RAWOP itself provided for such payment failed to comply with its obligation in the RAWOP.
scheme.
Third Issue: There is no unjust enrichment in the instant WHEREFORE, we DISMISS the petition, and AFFIRM the
case December 2, 2002 Decision and March 17, 2004 Resolution of
the DENR-MAB in MAB Case No. 0124-01 upholding the
Based on the foregoing discussion, the cancellation of the cancellation of the June 1, 1987 RAWOP. No costs.
RAWOP was based on valid grounds and is, therefore, justified.
The necessary implication of the cancellation is the cessation SO ORDERED.
of Benguet’s right to prosecute MPSA Application No. APSA-V-
0009 and to further develop such mining claims. PRESBITERO J. VELASCO, JR.
Associate Justice
In Car Cool Philippines, Inc. v. Ushio Realty and Development
Corporation, we defined unjust enrichment, as follows:

We have held that "[t]here is unjust enrichment when a


person unjustly retains a benefit to the loss of another,
or when a person retains money or property of another
against the fundamental principles of justice, equity
and good conscience." Article 22 of the Civil Code
provides that "[e]very person who through an act of
performance by another, or any other means, acquires
or comes into possession of something at the expense of
the latter without just or legal ground, shall return the
same to him." The principle of unjust enrichment under
Article 22 requires two conditions: (1) that a person is
benefited without a valid basis or justification, and (2)
that such benefit is derived at another’s expense or
damage.

There is no unjust enrichment when the person who


will benefit has a valid claim to such benefit.28
(Emphasis supplied.)

Clearly, there is no unjust enrichment in the instant case as


the cancellation of the RAWOP, which left Benguet without any
legal right to participate in further developing the mining
claims, was brought about by its violation of the RAWOP.
Hence, Benguet has no one to blame but itself for its
predicament.
claims billed by Titan after completion of three projects covered
by agreements they entered into with each other. Upon
Uniwide's motion to dismiss/suspend proceedings and Titan's
open court manifestation agreeing to the suspension, Civil Case
No. 98-0814 was suspended for it to undergo arbitration.4
Titan's complaint was thus re-filed with the CIAC.5 Before the
CIAC, Uniwide filed an answer which was later amended and
re-amended, denying the material allegations of the complaint,
with counterclaims for refund of overpayments, actual and
THIRD DIVISION exemplary damages, and attorney's fees. The agreements
between Titan and Uniwide are briefly described below.
G.R. No. 126619 December 20, 2006
PROJECT 1.6
UNIWIDE SALES REALTY AND RESOURCES
CORPORATION, petitioner, The first agreement (Project 1) was a written "Construction
vs. Contract" entered into by Titan and Uniwide sometime in May
TITAN-IKEDA CONSTRUCTION AND DEVELOPMENT 1991 whereby Titan undertook to construct Uniwide's
CORPORATION, respondent. Warehouse Club and Administration Building in Libis, Quezon
City for a fee of P120,936,591.50, payable in monthly progress
billings to be certified to by Uniwide's representative.7 The
parties stipulated that the building shall be completed not later
than 30 November 1991. As found by the CIAC, the building
DECISION
was eventually finished on 15 February 19928 and turned over
to Uniwide.

PROJECT 2.
TINGA, J.:
Sometime in July 1992, Titan and Uniwide entered into the
This Petition for Review on Certiorari under Rule 45 seeks the second agreement (Project 2) whereby the former agreed to
partial reversal of the 21 February 1996 Decision1 of the Court construct an additional floor and to renovate the latter's
of Appeals Fifteenth Division in CA-G.R. SP No. 37957 which warehouse located at the EDSA Central Market Area in
modified the 17 April 1995 Decision2 of the Construction Mandaluyong City. There was no written contract executed
Industry Arbitration Commission (CIAC). between the parties for this project. Construction was allegedly
to be on the basis of drawings and specifications provided by
The case originated from an action for a sum of money filed by Uniwide's structural engineers. The parties proceeded on the
Titan-Ikeda Construction and Development Corporation (Titan) basis of a cost estimate of P21,301,075.77 inclusive of Titan's
against Uniwide Sales Realty and Resources Corporation 20% mark-up. Titan conceded in its complaint to having
(Uniwide) with the Regional Trial Court (RTC), Branch 119, 3 received P15,000,000.00 of this amount. This project was
Pasay City arising from Uniwide's non-payment of certain
completed in the latter part of October 1992 and turned over to [Uniwide] is absolved of any liability for the claims made
Uniwide. by [Titan] on this Project.

PROJECT 3.9 Project 2 – Edsa Central:

The parties executed the third agreement (Project 3) in May [Uniwide] is absolved of any liability for VAT payment on
1992. In a written "Construction Contract," Titan undertook to this project, the same being for the account of the
construct the Uniwide Sales Department Store Building in [Titan]. On the other hand, [Titan] is absolved of any
Kalookan City for the price of P118,000,000.00 payable in liability on the counterclaim for defective construction
progress billings to be certified to by Uniwide's representative.10 of this project.
It was stipulated that the project shall be completed not later
than 28 February 1993. The project was completed and turned [Uniwide] is held liable for the unpaid balance in the
over to Uniwide in June 1993. amount of P6,301,075.77 which is ordered to be paid to
the [Titan] with 12% interest per annum commencing
Uniwide asserted in its petition that: (a) it overpaid Titan for from 19 December 1992 until the date of payment.
unauthorized additional works in Project 1 and Project 3; (b) it
is not liable to pay the Value-Added Tax (VAT) for Project 1; (c) On Project 3 – Kalookan:
it is entitled to liquidated damages for the delay incurred in
constructing Project 1 and Project 3; and (d) it should not have [Uniwide] is held liable for the unpaid balance in the
been found liable for deficiencies in the defectively constructed amount of P5,158,364.63 which is ordered to be paid to
Project 2. the [Titan] with 12% interest per annum commencing
from 08 September 1993 until the date of payment.
An Arbitral Tribunal consisting of a chairman and two members
was created in accordance with the CIAC Rules of Procedure [Uniwide] is held liable to pay in full the VAT on this
Governing Construction Arbitration. It conducted a preliminary project, in such amount as may be computed by the
conference with the parties and thereafter issued a Terms of Bureau of Internal Revenue to be paid directly thereto.
Reference (TOR) which was signed by the parties. The tribunal The BIR is hereby notified that [Uniwide] Sales Realty
also conducted an ocular inspection, hearings, and received the and Resources Corporation has assumed responsibility
evidence of the parties consisting of affidavits which were and is held liable for VAT payment on this project. This
subject to cross-examination. On 17 April 1995, after the accordingly exempts Claimant Titan-Ikeda
parties submitted their respective memoranda, the Arbitral Construction and Development Corporation from this
Tribunal promulgated a Decision,11 the decretal portion of obligation.
which is as follows:
Let a copy of this Decision be furnished the Honorable
"WHEREFORE, judgment is hereby rendered as follows: Aurora P. Navarette Recina, Presiding Judge, Branch
119, Pasay City, in Civil Case No. 94-0814 entitled
On Project 1 – Libis: Titan-Ikeda Construction Development Corporation,
Plaintiff – versus – Uniwide Sales Realty and Resources
Corporation, Defendant, pending before said court for the arbitrators were guilty of misconduct in refusing to hear
information and proper action. evidence pertinent and material to the controversy; (4) one or
more of the arbitrators were disqualified to act as such under
SO ORDERED."12 Section nine of Republic Act No. 876 and willfully refrained
from disclosing such disqualifications or of any other
Uniwide filed a motion for reconsideration of the 17 April 1995 misbehavior by which the rights of any party have been
decision which was denied by the CIAC in its Resolution dated materially prejudiced; or (5) the arbitrators exceeded their
6 July 1995. Uniwide accordingly filed a petition for review with powers, or so imperfectly executed them, that a mutual, final
the Court of Appeals,13 which rendered the assailed decision on and definite award upon the subject matter submitted to them
21 February 1996. Uniwide's motion for reconsideration was was not made.19
likewise denied by the Court of Appeals in its assailed
Resolution14 dated 30 September 1996. Other recognized exceptions are as follows: (1) when there is a
very clear showing of grave abuse of discretion20 resulting in
Hence, Uniwide comes to this Court via a petition for review lack or loss of jurisdiction as when a party was deprived of a
under Rule 45. The issues submitted for resolution of this fair opportunity to present its position before the Arbitral
Court are as follows:15 (1) Whether Uniwide is entitled to a Tribunal or when an award is obtained through fraud or the
return of the amount it allegedly paid by mistake to Titan for corruption of arbitrators,21 (2) when the findings of the Court of
additional works done on Project 1; (2) Whether Uniwide is Appeals are contrary to those of the CIAC,22 and (3) when a
liable for the payment of the Value-Added Tax (VAT) on Project party is deprived of administrative due process.23
1; (3) Whether Uniwide is entitled to liquidated damages for
Projects 1 and 3; and (4) Whether Uniwide is liable for Thus, in Hi-Precision Steel Center, Inc. v. Lim Kim Builders,
deficiencies in Project 2. Inc.,24 we refused to review the findings of fact of the CIAC for
the reason that petitioner was requiring the Court to go over
As a rule, findings of fact of administrative agencies and quasi- each individual claim and counterclaim submitted by the
judicial bodies, which have acquired expertise because their parties in the CIAC. A review of the CIAC's findings of fact would
jurisdiction is confined to specific matters, are generally have had the effect of "setting at naught the basic objective of a
accorded not only respect, but also finality, especially when voluntary arbitration and would reduce arbitration to a largely
affirmed by the Court of Appeals.16 In particular, factual inutile institution." Further, petitioner therein failed to show
findings of construction arbitrators are final and conclusive any serious error of law amounting to grave abuse of discretion
and not reviewable by this Court on appeal.17 This rule, resulting in lack of jurisdiction on the part of the Arbitral
however admits of certain exceptions. Tribunal, in either the methods employed or the results reached
by the Arbitral Tribunal, in disposing of the detailed claims of
the respective parties. In Metro Construction, Inc. v. Chatham
In David v. Construction Industry and Arbitration Commission,18 Properties, Inc.,25 we reviewed the findings of fact of the Court
we ruled that, as exceptions, factual findings of construction of Appeals because its findings on the issue of whether
arbitrators may be reviewed by this Court when the petitioner petitioner therein was in delay were contrary to the findings of
proves affirmatively that: (1) the award was procured by the CIAC. Finally, in Megaworld Globus Asia, Inc. v. DSM
corruption, fraud or other undue means; (2) there was evident Construction and Development Corporation,26 we declined to
partiality or corruption of the arbitrators or of any of them; (3) depart from the findings of the Arbitral Tribunal considering
that the computations, as well as the propriety of the awards, (1) Such change has been authorized by the proprietor
are unquestionably factual issues that have been discussed by in writing; and
the Arbitral Tribunal and affirmed by the Court of Appeals.
(2) The additional price to be paid to the contractor has
In the present case, only the first issue presented for resolution been determined in writing by both parties.
of this Court is a question of law while the rest are factual in
nature. However, we do not hesitate to inquire into these The Court of Appeals did take note of this provision, but
factual issues for the reason that the CIAC and the Court of deemed it inapplicable to the case at bar because Uniwide had
Appeals, in some matters, differed in their findings. already paid, albeit with unwritten reservations, for the
"additional works." The provision would have been operative
We now proceed to discuss the issues in seriatim. had Uniwide refused to pay for the costs of the "additional
works." Instead, the Court of Appeals applied Art. 142327 of the
Payment by Mistake for Project 1 New Civil Code and characterized Uniwide's payment of the said
amount as a voluntary fulfillment of a natural obligation. The
The first issue refers to the P5,823,481.75 paid by Uniwide for situation was characterized as being akin to Uniwide being a
additional works done on Project 1. Uniwide asserts that Titan debtor who paid a debt even while it knew that it was not legally
was not entitled to be paid this amount because the additional compelled to do so. As such debtor, Uniwide could no longer
works were without any written authorization. demand the refund of the amount already paid.

It should be noted that the contracts do not contain Uniwide counters that Art. 1724 makes no distinction as to
stipulations on "additional works," Uniwide's liability for whether payment for the "additional works" had already been
"additional works," and prior approval as a requirement before made. It claims that it had made the payments, subject to
Titan could perform "additional works." reservations, upon the false representation of Titan-Ikeda that
the "additional works" were authorized in writing. Uniwide
characterizes the payment as a "mistake," and not a "voluntary"
Nonetheless, Uniwide cites Article (Art. ) 1724 of the New Civil fulfillment under Art. 1423 of the Civil Code. Hence, it urges
Code as basis for its claim that it is not liable to pay for
the application, instead, of the principle of solutio indebiti under
"additional works" it did not authorize or agree upon in writing. Arts. 215428 and 215629 of the Civil Code.
The provision states:
To be certain, this Court has not been wont to give an expansive
Art. 1724. The contractor who undertakes to build a
construction of Art. 1724, denying, for example, claims that it
structure or any other work for a stipulated price, in applies to constructions made of ship vessels,30 or that it can
conformity with plans and specifications agreed upon validly deny the claim for payment of professional fees to the
with the landowner, can neither withdraw from the architect.31 The present situation though presents a thornier
contract nor demand an increase in the price on problem. Clearly, Art. 1724 denies, as a matter of right,
account of the higher cost of labor or materials, save payment to the contractor for additional works which were not
when there has been a change in the plans and
authorized in writing by the proprietor, and the additional price
specifications, provided:
of which was not determined in writing by the parties.
Yet the distinction pointed out by the Court of Appeals is The CIAC refused to acknowledge that the additional works on
material. The issue is no longer centered on the right of the Project 1 were indeed unauthorized by Uniwide. Neither did the
contractor to demand payment for additional works Court of Appeals arrive at a contrary determination. There
undertaken because payment, whether mistaken or not, was would thus be some difficulty for this Court to agree with this
already made by Uniwide. Thus, it would not anymore be most basic premise submitted by Uniwide that it did not
incumbent on Titan to establish that it had the right to demand authorize the additional works on Project 1 undertaken by
or receive such payment. Titan. Still, Uniwide does cite testimonial evidence from the
record alluding to a concession by employees of Titan that these
But, even if the Court accepts Art. 1724 as applicable in this additional works on Project 1 were either authorized or
case, such recognition does not ipso facto accord Uniwide the documented.33
right to be reimbursed for payments already made, since Art.
1724 does not effect such right of reimbursement. It has to be Yet even conceding that the additional works on Project 1 were
understood that Art. 1724 does not preclude the payment to not authorized or committed into writing, the undisputed fact
the contractor who performs additional works without any prior remains that Uniwide paid for these additional works. Thus, to
written authorization or agreement as to the price for such claim a refund of payments made under the principle of solutio
works if the owner decides anyway to make such payment. indebiti, Uniwide must be able to establish that these payments
What the provision does preclude is the right of the contractor were made through mistake. Again, this is a factual matter that
to insist upon payment for unauthorized additional works. would have acquired a mantle of invulnerability had it been
determined by both the CIAC and the Court of Appeals.
Accordingly, Uniwide, as the owner who did pay the contractor However, both bodies failed to arrive at such a conclusion.
for such additional works even if they had not been authorized Moreover, Uniwide is unable to direct our attention to any
in writing, has to establish its own right to reimbursement not pertinent part of the record that would indeed establish that
under Art. 1724, but under a different provision of law. the payments were made by reason of mistake.
Uniwide's burden of establishing its legal right to
reimbursement becomes even more crucial in the light of the We note that Uniwide alleged in its petition that the CIAC award
general presumption contained in Section 3(f), Rule 131 of the in favor of Titan in the amount P5,158,364.63 as the unpaid
Rules of Court that "money paid by one to another was due to balance in Project 3 included claims for additional works of
the latter." P1,087,214.18 for which no written authorization was
presented. Unfortunately, this issue was not included in its
Uniwide undertakes such a task before this Court, citing the memorandum as one of the issues submitted for the resolution
provisions on solutio indebiti under Arts. 2154 and 2156 of the of the Court.
Civil Code. However, it is not enough to prove that the
payments made by Uniwide to Titan were "not due" because Liability for the Value-Added Tax (VAT)
there was no prior authorization or agreement with respect to
additional works. There is a further requirement that the The second issue takes us into an inquiry on who, under the
payment by the debtor was made either through mistake or law, is liable for the payment of the VAT, in the absence of a
under a cloud of doubt. In short, for the provisions on solutio written stipulation on the matter. Uniwide claims that the VAT
indebiti to apply, there has to be evidence establishing the was already included in the contract price for Project 1. Citing
frame of mind of the payor at the time the payment was made.32 Secs. 99 and 102 of the National Internal Revenue Code,
Uniwide asserts that VAT, being an indirect tax, may be shifted costs is [sic] proportionately placed at 60%-40% of
to the buyer by including it in the cash or selling price and it is the contract price, simplified accounting computes
entirely up to the buyer to agree or not to agree to absorb the VAT at 4% of the contract price. Whatever is the
VAT.34 Thus, Uniwide concludes, if there is no provision in the balance for VAT that remains to be paid on Project 1 –
contract as to who should pay the VAT, it is presumed that it Libis shall remain the obligation of [Titan]. (Emphasis
would be the seller.35 supplied.)38

The contract for Project 1 is silent on which party should Liquidated Damages
shoulder the VAT while the contract for Project 3 contained a
provision to the effect that Uniwide is the party responsible for On the third issue of liquidated damages, the CIAC rejected
the payment of the VAT.36 Thus, when Uniwide paid the amount such claim while the Court of Appeals held that the matter
of P2,400,000.00 as billed by Titan for VAT, it assumed that it should be left for determination in future proceedings where
was the VAT for Project 3. However, the CIAC and the Court of the issue has been made clear.
Appeals found that the same was for Project 1.
In rejecting Uniwide's claim for liquidated damages, the CIAC
We agree with the conclusions of both the CIAC and the Court held that there is no legal basis for passing upon and resolving
of Appeals that the amount of P2,400,000.00 was paid by Uniwide's claim for the following reasons: (1) no claim for
Uniwide as VAT for Project 1. This conclusion was drawn from liquidated damages arising from the alleged delay was ever
an Order of Payment37 dated 7 October 1992 wherein Titan made by Uniwide at any time before the commencement of
billed Uniwide the amount of P2,400,000.00 as "Value Added Titan's complaint; (2) the claim for liquidated damages was not
Tax based on P60,000,000.00 Contract," computed on the included in the counterclaims stated in Uniwide's answer to
basis of 4% of P60,000,000.00. Said document which was Titan's complaint; (3) the claim was not formulated as an issue
approved by the President of Uniwide expressly indicated that to be resolved by the CIAC in the TOR;39 and (4) no attempt was
the project involved was the "UNIWIDE SALES WAREHOUSE made to modify the TOR to accommodate the same as an issue
CLUB & ADMIN BLDG." located at "90 E. RODRIGUEZ JR. to be resolved.
AVE., LIBIS, Q.C." The reduced base for the computation of the
tax, according to the Court of Appeals, was an indication that Uniwide insists that the CIAC should have applied Section 5,
the parties agreed to pass the VAT for Project 1 to Uniwide but Rule 10 of the Rules of Court.40 On this matter, the Court of
based on a lower contract price. Indeed, the CIAC found as Appeals held that the CIAC is an arbitration body, which is not
follows: necessarily bound by the Rules of Court. Also, the Court of
Appeals found that the issue has never been made concrete
Without any documentary evidence than Exhibit "H" to enough to make Titan and the CIAC aware that it will be an
show the extent of tax liability assumed by [Uniwide], issue. In fact, Uniwide only introduced and quantified its claim
the Tribunal holds that the parties is [sic] obliged to pay for liquidated damages in its Memorandum submitted to the
only a share of the VAT payment up to P60,000,000.00 CIAC at the end of the arbitration proceeding. The Court of
out of the total contract price of P120,936,591.50. As Appeals also noted that the only evidence on record to prove
explained by Jimmy Gow, VAT is paid on labor only delay in the construction of Project 1 is the testimony of Titan's
for construction contracts since VAT had already engineer regarding the date of completion of the project while
been paid on the materials purchased. Since labor
the only evidence of delay in the construction of Project 3 is the the Terms of Reference were expressly showed [sic] to
affidavit of Uniwide's President. be amended, issues outside thereof may not be resolved.
As already noted in the Decision, "no attempt was ever
According to Uniwide, the ruling of the Court of Appeals on the made by the [Uniwide] to modify the TOR in order to
issue of liquidated damages goes against the established accommodate the issues related to its belated
judicial policy that a court should always strive to settle in one counterclaim" on this issue. (Emphasis supplied.)
proceeding the entire controversy leaving no root or branch to
bear the seeds of future litigations.41 Uniwide claims that the Arbitration has been defined as "an arrangement for taking and
required evidence for an affirmative ruling on its claim is abiding by the judgment of selected persons in some disputed
already on the record. It cites the pertinent provisions of the matter, instead of carrying it to established tribunals of justice,
written contracts which contained deadlines for liquidated and is intended to avoid the formalities, the delay, the expense
damages. Uniwide also noted that the evidence show that and vexation of ordinary litigation."43 Voluntary arbitration, on
Project 1 was completed either on 15 February 1992, as found the other hand, involves the reference of a dispute to an
by the CIAC, or 12 March 1992, as shown by Titan's own impartial body, the members of which are chosen by the parties
evidence, while Project 3, according to Uniwide's President, was themselves, which parties freely consent in advance to abide by
completed in June 1993. Furthermore, Uniwide asserts, the the arbitral award issued after proceedings where both parties
CIAC should have applied procedural rules such as Section 5, had the opportunity to be heard. The basic objective is to
Rule 10 with more liberality because it was an administrative provide a speedy and inexpensive method of settling disputes
tribunal free from the rigid technicalities of regular courts.42 by allowing the parties to avoid the formalities, delay, expense
and aggravation which commonly accompany ordinary
On this point, the CIAC held: litigation, especially litigation which goes through the entire
hierarchy of courts.44 As an arbitration body, the CIAC can only
The Rule of Procedure Governing Construction resolve issues brought before it by the parties through the TOR
Arbitration promulgated by the CIAC contains no which functions similarly as a pre-trial brief. Thus, if Uniwide's
provision on the application of the Rules of Court to claim for liquidated damages was not raised as an issue in the
arbitration proceedings, even in a suppletory capacity. TOR or in any modified or amended version of it, the CIAC
Hypothetically admitting that there is such a provision, cannot make a ruling on it. The Rules of Court cannot be used
suppletory application is made only if it would not to contravene the spirit of the CIAC rules, whose policy and
contravene a specific provision in the arbitration rules objective is to "provide a fair and expeditious settlement of
and the spirit thereof. The Tribunal holds that such construction disputes through a non-judicial process which
importation of the Rules of Court provision on ensures harmonious and friendly relations between or among
amendment to conform to evidence would the parties."45
contravene the spirit, if not the letter of the CIAC
rules. This is for the reason that the formulation of the Further, a party may not be deprived of due process of law by
Terms of Reference is done with the active participation an amendment of the complaint as provided in Section 5, Rule
of the parties and their counsel themselves. The TOR is 10 of the Rules of Court. In this case, as noted by the Court of
further required to be signed by all the parties, their Appeals, Uniwide only introduced and quantified its claim for
respective counsel and all the members of the Arbitral liquidated damages in its memorandum submitted to the CIAC
Tribunal. Unless the issues thus carefully formulated in at the end of the arbitration proceeding. Verily, Titan was not
given a chance to present evidence to counter Uniwide's claim failed to submit any "as-built" plans for Project 2, such plans
for liquidated damages. allegedly serving as a condition precedent for payment. Uniwide
further claims that Titan had substantially overcharged
Uniwide alludes to an alleged judicial admission made by Engr. Uniwide for Project 2, there being uncontradicted expert
Luzon Tablante wherein he stated that Project 1 was completed testimony that the total cost of Project 2 did not exceed
on 10 March 1992. It now claims that by virtue of Engr. P7,812,123.60. Furthermore, Uniwide alleged that the works
Tablante's statement, Titan had admitted that it was in delay. performed were structurally defective, as evidenced by the
We disagree. The testimony of Engr. Tablante was offered only structural damage on four columns as observed on ocular
to prove that Project 1 was indeed completed. It was not offered inspection by the CIAC and confirmed by Titan's project
to prove the fact of delay. It must be remembered that the manager.
purpose for which evidence is offered must be specified because
such evidence may be admissible for several purposes under On the necessity of submitting "as-built" plans, this Court rules
the doctrine of multiple admissibility, or may be admissible for that the submission of such plans is not a pre-requisite for
one purpose and not for another, otherwise the adverse party Titan to be paid by Uniwide. The argument that said plans are
cannot interpose the proper objection. Evidence submitted for required by Section 308 of Presidential Decree No. 1098
one purpose may not be considered for any other purpose.46 (National Building Code) and by Section 2.11 of its
Furthermore, even assuming, for the sake of argument, that Implementing Rules before payment can be made is untenable.
said testimony on the date of completion of Project 1 is The purpose of the law is "to safeguard life, health, property,
admitted, the establishment of the mere fact of delay is not and public welfare, consistent with the principles of sound
sufficient for the imposition of liquidated damages. It must environmental management and control." The submission of
further be shown that delay was attributable to the contractor these plans is necessary only in furtherance of the law's
if not otherwise justifiable. Contrarily, Uniwide's belated claim purpose by setting minimum standards and requirements to
constitutes an admission that the delay was justified and control the "location, site, design, quality of materials,
implies a waiver of its right to such damages. construction, use, occupancy, and maintenance" of buildings
constructed and not as a requirement for payment to the
Project 2: "as-built" plans, overpricing, defective construction contractor.47 The testimony of Engr. Tablante to the effect that
the "as-built" plans are required before payment can be claimed
To determine whether or not Uniwide is liable for the unpaid by Titan is a mere legal conclusion which is not binding on this
balance of P6,301,075.77 for Project 2, we need to resolve four Court.
sub-issues, namely: (1) whether or not it was necessary for
Titan to submit "as-built" plans before it can be paid by Uniwide claims that, according to one of its consultants, the
Uniwide; (2) whether or not there was overpricing of the project; true price for Project 2 is only P7,812,123.60. The CIAC and
(3) whether or not the P15,000,000.00 paid by Uniwide to Titan the Court of Appeals, however, found the testimony of this
for Project 2 constitutes full payment; and (4) whether or not consultant suspect and ruled that the total contract price for
Titan can be held liable for defective construction of Project 2. Project 2 is P21,301,075.77. The CIAC held:

The CIAC, as affirmed by the Court of Appeals, held Uniwide The Cost Estimate for Architectural and Site
liable for deficiency relating to Project 2 in the amount of Development Works for the EDSA Central, Dau Branch
P6,301,075.77. It is nonetheless alleged by Uniwide that Titan Project (Exhibit "2-A" for [Uniwide] and made as a
common exhibit by [Titan] who had it marked at [sic] its endorsing for payment by Uniwide to Titan the amount of
own Exhibit "U"), which was admittedly prepared by P6,301,075.77.50
Fermindoza and Associates, [Uniwide]'s own architects,
shows that the amount of P17,750,896.48 was arrived Uniwide asserts that Titan should not have been allowed to
at. Together with the agreed upon mark-up of 20% on recover on Project 2 because the said project was defective and
said amount, the total project cost was P21,301,075.77. would require repairs in the amount of P800,000.00. It claims
that the CIAC and the Court of Appeals should have applied
The Tribunal holds that the foregoing document is Nakpil and Sons v. Court of Appeals51 and Art. 1723 of the New
binding upon the [Uniwide], it being the mode agreed Civil Code holding a contractor responsible for damages if the
upon by which its liability for the project cost was to be edifice constructed falls within fifteen years from completion on
determined.48 (Emphasis supplied.) account of defects in the construction or the use of materials of
inferior quality furnished by him or due to any violation of the
Indeed, Uniwide is bound by the amount indicated in the above terms of the contract.
document. Claims of connivance or fraudulent conspiracy
between Titan and Uniwide's representatives which, it is On this matter, the CIAC conducted an ocular inspection of the
alleged, grossly exaggerated the price may properly be premises on 30 January 1995. What transpired in the said
dismissed. As held by the CIAC: ocular inspection is described thus:

The Tribunal holds that [Uniwide] has not introduced On 30 January 1995, an ocular inspection was
any evidence to sustain its charge of fraudulent conducted by the Arbitral Tribunal as requested by
conspiracy. As a matter of fact, [Uniwide]'s own [Uniwide]. Photographs were taken of the alleged
principal witness, Jimmy Gow, admitted on cross- construction defects, an actual ripping off of the plaster
examination that he does not have any direct evidence of a certain column to expose the alleged structural
to prove his charge of connivance or complicity between defect that is claimed to have resulted in its being
the [Titan] and his own representatives. He only made "heavily damaged" was done, clarificatory questions
that conclusion by the process of his own "logical were asked and manifestations on observations were
reasoning" arising from his consultation with other made by the parties and their respective counsels. The
contractors who gave him a much lower estimate for the entire proceedings were recorded on tape and
construction of the Dau Project. There is thus no reason subsequently transcribed. The photographs and
to invalidate the binding character of Exhibit "2-A" transcript of the ocular inspection form part of the
which, it is significant to point out, is [Uniwide]'s own records and considered as evidence.52
evidence.49 (Emphasis supplied.)
And, according to these evidence, the CIAC concluded as
Accordingly, deducting the P15,000,000.00 already paid by follows:
Uniwide from the total contract price of P21,301,075.77, the
unpaid balance due for Project 2 is P6,301,075.77. This is the It is likewise the holding of this Tribunal that [Uniwide]'s
same amount reflected in the Order of Payment prepared by counterclaim of defective construction has not been
Uniwide's representative, Le Consultech, Inc. and signed by no sufficiently proven. The credibility of Engr. Cruz,
less than four top officers and architects of Le Consultech, Inc.
[Uniwide]'s principal witness on this issue, has been necessary and important for the realization of
severely impaired. During the ocular inspection of the national development goals.
premises, he gave such assurance of the soundness of
his opinion as an expert that a certain column was Aware of the objective of voluntary arbitration in the
heavily damaged judging from the external cracks that labor field, in the construction industry, and in any
was readily apparent x x x other area for that matter, the Court will not assist one
or the other or even both parties in any effort to subvert
xxxx or defeat that objective for their private purposes. The
Court will not review the factual findings of an arbitral
On insistence of the Tribunal, the plaster was chipped tribunal upon the artful allegation that such body had
off and revealed a structurally sound column x x x "misapprehended facts" and will not pass upon issues
which are, at bottom, issues of fact, no matter how
Further, it turns out that what was being passed off as cleverly disguised they might be as "legal questions."
a defective construction by [Titan], was in fact an old The parties here had recourse to arbitration and chose
column, as admitted by Mr. Gow himself x x x x53 the arbitrators themselves; they must have had
(Emphasis supplied.) confidence in such arbitrators. The Court will not,
therefore, permit the parties to relitigate before it the
issues of facts previously presented and argued before
Uniwide had the burden of proving that there was defective the Arbitral Tribunal, save only where a clear showing
construction in Project 2 but it failed to discharge this burden. is made that, in reaching its factual conclusions, the
Even the credibility of its own witness was severely impaired. Arbitral Tribunal committed an error so egregious and
Further, it was found that the concrete slab placed by Titan hurtful to one party as to constitute a grave abuse of
was not attached to the old columns where cracks were discretion resulting in lack or loss of jurisdiction.
discovered. The CIAC held that the post-tensioning of the new Prototypical examples would be factual conclusions of
concrete slab could not have caused any of the defects
the Tribunal which resulted in deprivation of one or the
manifested by the old columns. We are bound by this finding of other party of a fair opportunity to present its position
fact by the CIAC. before the Arbitral Tribunal, and an award obtained
through fraud or the corruption of arbitrators. Any
It is worthy to stress our ruling in Hi-Precision Steel Center, Inc. other, more relaxed rule would result in setting at
v. Lim Kim Steel Builders, Inc.54 which was reiterated in David naught the basic objective of a voluntary arbitration and
v. Construction Industry and Arbitration Commission,55 that: would reduce arbitration to a largely inutile institution.
(Emphasis supplied.)
x x x Executive Order No. 1008 created an arbitration
facility to which the construction industry in the WHEREFORE, premises considered, the petition is DENIED
Philippines can have recourse. The Executive Order and the Decision of the Court of Appeals dated 21 February
was enacted to encourage the early and expeditious 1996 in CA-G.R. SP No. 37957 is hereby AFFIRMED.
settlement of disputes in the construction industry,
a public policy the implementation of which is
SO ORDERED.
Quisumbing, J., Chairperson, Carpio, Carpio Morales, And
Velasco, Jr., JJ., concur.
Republic of the Philippines G.R. SP No. 112127 which dismissed its appeal from the
SUPREME COURT Arbitral Tribunal’s Partial Award4 dated December 15, 2009
Manila (Partial Award) on the ground of forum shopping; while the
petition in G.R. No. 1967285 filed by Sumitomo Corporation
SECOND DIVISION (Sumitomo) seeks to annul and set aside the CA’s Decision6
dated January 26, 2011 and Resolution7 dated April 29, 2011
G.R. No. 196723 August 28, 2013 in CA-G.R. SP No. 113828 which modified the Arbitral
Tribunal’s Final Award8 dated March 17, 2010 (Final Award) by
way of deleting the award of attorney’s fees in Sumitomo’s favor.
ASIAN CONSTRUCTION AND DEVELOPMENT
CORPORATION, Petitioner,
vs. The Facts
SUMITOMO CORPORATION, Respondent.
On March 15, 1996, Asian Construction entered into a Civil
x-----------------------x Work Agreement9 (Agreement) with Sumitomo for the
construction of a portion of the Light Rail Transit System along
the Epifanio Delos Santos Avenue, specifically, from Shaw
G.R. No. 196728 Boulevard, Mandaluyong City to Taft Avenue, Pasay City for a
total cost of US$19,982,000.00 (Project).10 The said Agreement
SUMITOMO CORPORATION, Petitioner, provides that the "validity, interpretation, enforceability, and
vs. performance of the same shall be governed by and construed in
ASIAN CONSTRUCTION AND DEVELOPMENT accordance with the law of the State of New York, U.S.A. (New
CORPORATION, Respondent. York State Law), without regard to, or legal effect of, the
conflicts of law provisions thereof"11 and that any dispute,
DECISION controversy or claim arising therefrom "shall be solely and
finally settled by arbitration."12
PERLAS-BERNABE, J.:
In May 1996, Sumitomo paid Asian Construction the amount
Before the Court are consolidated petitions for review on of US$2,997,300.00 as advance payment to be recovered in
certiorari which assail separate issuances of the Court of accordance with the terms of the Agreement. Later, an
Appeals (C A) in relation to the partial and final awards additional advance payment of US$1,998,200.00 was made in
rendered by the Construction Industry Arbitration October 1997.13 In all, Asian Construction received from
Commission's (CIAC) Arbitral Tribunal (Arbitral Tribunal) in Sumitomo the amount of US$9,731,606.62, inclusive of the
CIAC Case No. 28-2008. advance payments (before withholding tax of US$97,308.44).14

In particular, the petition in G.R. No. 1967231 filed by Asian On September 1, 1998, Sumitomo informed Asian Construction
Construction and Development Corporation (Asian that it was terminating the Agreement effective September 5,
Construction) seeks to annul and set aside the CA’s 1998 due to the following reasons: (a) Asian Construction’s
Resolutions dated July 23, 20102 and April 18, 20113 in CA- failure "to perform and complete the civil work for Notice to
Proceed issued construction areas within the duration of the
Time Schedule in the ‘Contract Specification of Civil and to itemize and justify its claims, the same could have been
Architectural Works (Station No. 8 to Station No. 13) x x x’"; (b) amicably settled years ago. In this respect, it made a
Asian Construction’s failure to "provide adequate traffic counterclaim for the unutilized portion of the advance
management as required in the Scope of Works pursuant to payments, attorney’s fees and costs of litigation in the amount
subparagraph 5.2.4 of the Contract Specification of Civil and of at least ₱10,000,000.00.29
Architectural Work"; and (c) Asian Construction’s failure to
"pay the suppliers of certain materials and equipment used in Subsequently, the parties signed a TOR,30 stipulating the
the construction of the Project in violation of paragraph 3.1.3, admitted facts and defining the issues to be determined in the
Article 3 of the Agreement."15 In view of the foregoing, arbitration proceedings.
Sumitomo requested Asian Construction to "make the
necessary arrangements for the proper turnover of the Project On December 15, 2009, the Arbitral Tribunal rendered the
x x x."16 Asian Construction, however, claimed that the Partial Award31 which affirmed its jurisdiction over the dispute
accomplishments under Progress Billing No. (PB) 01817 dated but held that the parties were bound by their Agreement that
June 10, 1998 and PB 01918 dated July 6, 1998, as well as the substantive New York State Law shall apply in the
other various claims, were still left unpaid.19 Hence, on resolution of the issues.32 It proceeded to dismiss both the
December 22, 1998, it sent Sumitomo a letter,20 demanding claims and counterclaims of the parties on the ground that
payment of the total amount of US$6,371,530.89. This was these had already prescribed under New York State Law’s six-
followed by several correspondences between the parties year statute of limitations33 and ruled that, in any case, were it
through 1999 to 2007 but no settlement was achieved.21 to resolve the same on the merits, "it would not produce an
affirmative recovery for the claimant."34
The Proceedings Before the Arbitral Tribunal
Aggrieved, Asian Construction filed before the CA, on January
On September 2, 2008, Asian Construction filed a complaint22 5, 2010, a Rule 43 Petition for Review,35 docketed as CA-G.R.
with the CIAC, docketed as CIAC Case No. 28-2008, seeking SP No. 112127 (First CA Petition), seeking the reversal of the
payment for its alleged losses and reimbursements amounting Partial Award.
to US$9,501,413.13, plus attorney’s fees in the amount of
₱2,000,000.00.23 As a matter of course, an Arbitral Tribunal Meanwhile, notwithstanding its dismissal of the claims and
was constituted, with Alfredo F. Tadiar being designated as counterclaims, the Arbitral Tribunal further directed the
Chairman, and Salvador P. Castro and Jesse B. Grove as parties to itemize their respective claims for costs and
Members.24 attorney’s fees and to submit factual proof and legal bases for
their entitlement thereto.36 Pursuant to this directive,
For its part, Sumitomo filed a Motion to Dismiss,25 questioning Sumitomo submitted evidence to prove the costs it had
the CIAC’s jurisdiction over the dispute on the ground that the incurred and paid as a result of the arbitration proceedings.37
arbitration should proceed in accordance with the Commercial Asian Construction, on the other hand, did not present any
Arbitration Rules of Japan.26 However, the aforesaid motion statement or document to substantiate its claims but, instead,
was denied.27 As such, Sumitomo filed an Answer,28 reiterating submitted an Opposition38 dated March 8, 2010 (opposition) to
the CIAC’s alleged lack of jurisdiction and further asserting that Sumitomo’s claim for costs. The Arbitral Tribunal did not act
the claim was already time-barred. It added that had Asian upon the opposition because it was treated, in effect, as a
Construction discharged its obligations under the Agreement motion for reconsideration which was prohibited under the
CIAC Revised Rules of Procedure Governing Construction The CA Ruling
Arbitration (CIAC Revised Rules).39
On July 23, 2010, the CA rendered a Resolution47 (July 23,
On March 17, 2010, the Arbitral Tribunal rendered the Final 2010 Resolution), dismissing Asian Construction’s First CA
Award40 which granted Sumitomo’s claim for attorney’s fees in Petition against the Partial Award on the ground of forum-
the amount of US$200,000.00. It held that while the filing of shopping, after it was shown that: (a) the aforesaid petition was
the arbitration suit cannot be regarded as "clearly unfounded" filed while the arbitration case was still pending final resolution
because of the two progress billings that were left unpaid, Asian before the Arbitral Tribunal; and (b) Asian Construction’s
Construction’s disregard of the Agreement to have the dispute opposition to Sumitomo’s claim for costs filed before the
resolved in accordance with New York State Law had forced Arbitral Tribunal had, in fact, effectively sought for the same
Sumitomo to incur attorney’s fees in order to defend its relief and stated the same allegations as those in its First CA
interest.41 It further noted that if Asian Construction had Petition. The CA also noted Asian Construction’s premature
accepted the settlement offered by Sumitomo, then, the resort to a petition for review because what was sought to be
arbitration proceedings would have even been aborted.42 On the nullified was not a final award, but only a partial one. The CA
other hand, a similar claim for attorney’s fees made by Asian eventually denied Asian Construction’s motion for
Construction was denied by reason of the latter’s failure to reconsideration in a Resolution48 dated April 18, 2011. Hence,
submit, as directed, proof of its entitlement thereto.43 As to the Asian Construction’s petition before the Court, docketed as
matter of costs, the Arbitral Tribunal declared Sumitomo G.R. No. 196723.
relieved from sharing pro-rata in the arbitration costs and,
consequently, directed Asian Construction to shoulder the Meanwhile, the CA gave due course to Asian Construction’s
same costs in full and reimburse Sumitomo the amount of Second CA Petition assailing the Final Award and rendered a
₱849,532.45. However, it ordered Sumitomo to bear all the Decision49 on January 26, 2011, upholding the Arbitral
expenses related to the appointment of the foreign arbitrator Tribunal’s ruling except the award of attorney’s fees in favor of
considering that such service was secured upon its own Sumitomo. The CA held that the fact that Asian Construction
initiative and without the participation and consent of Asian initiated an action or refused to compromise its claims cannot
Construction.44 be considered unjustified or made in bad faith as to entitle
Sumitomo to the aforesaid award. Consequently, Sumitomo
Dissatisfied with the Arbitral Tribunal’s ruling, Asian moved for reconsideration,50 asserting that Asian
Construction filed another Rule 43 Petition for Review45 before Construction’s Second CA Petition should have instead been
the CA, on May 3, 2010, docketed as CA-G.R. SP No. 113828 dismissed in its entirety considering their Agreement that the
(Second CA Petition), this time, to set aside the Final Award. In Arbitral Tribunal’s decisions and awards would be final and
this light, it claimed gross negligence and partiality on the part non-appealable. However, in a Resolution51 dated April 29,
of the Arbitral Tribunal and asserted, inter alia, that, apart from 2011, the CA denied the motion for reconsideration. Thus,
being a non-arbitrable issue, an award of attorney’s fees would Sumitomo’s petition before the Court, docketed as G.R. No.
be premature since the prevailing party can only be determined 196728.
when the case is decided with finality. Moreover, it maintained
that both claims of Asian Construction and the counterclaims The Issues Before the Court
of Sumitomo had already been dismissed for being time-
barred.46
The essential issues for the Court’s resolution are as follows: seeks to prevent the vexation brought upon the courts and the
(a) in G.R. No. 196723, whether or not the CA erred in litigants by a party who asks different courts to rule on the
dismissing Asian Construction’s First CA Petition on the same or related causes and grant the same or substantially the
ground of forum shopping; and (b) in G.R. No. 196728, whether same reliefs and in the process creates the possibility of
or not the CA erred in reviewing and modifying the Final Award conflicting decisions being rendered by the different fora upon
which Sumitomo insists to be final and unappealable. the same issues.54

The Court’s Ruling In this case, the Court finds that the CA committed no
reversible error in dismissing Asian Construction’s First CA
The petitions should be denied. Petition on the ground of forum shopping since the relief sought
(i.e., the reconsideration of the Partial Award) and the
A. Dismissal of Asian allegations stated therein are identical to its opposition to
Sumitomo’s claim for costs filed before the Arbitral Tribunal
while CIAC Case No. 28-2008 was still pending. These
Construction’s First CA circumstances clearly square with the first kind of forum
shopping which thereby impels the dismissal of the First CA
Petition; forum shopping. Petition on the ground of litis pendentia.

Forum shopping is the act of a litigant who repetitively availed On this score, it is apt to point out that Asian Construction’s
of several judicial remedies in different courts, simultaneously argument that it merely complied with the directive of the
or successively, all substantially founded on the same Arbitral Tribunal cannot be given any credence since it (as well
transactions and the same essential facts and circumstances, as Sumitomo) was only directed to submit evidence to prove the
and all raising substantially the same issues, either pending in costs it had incurred and paid as a result of the arbitration
or already resolved adversely by some other court, to increase proceedings. However, at variance with the tribunal’s directive,
his chances of obtaining a favorable decision if not in one court, Asian Construction, in its opposition to Sumitomo’s claim for
then in another. More particularly, forum shopping can be costs, proceeded to seek the reversal of the Partial Award in the
committed in three ways, namely: (a) by filing multiple cases same manner as its First CA Petition. It cannot, therefore, be
based on the same cause of action and with the same prayer, doubted that it treaded the course of forum shopping,
the previous case not having been resolved yet (where the warranting the dismissal of the aforesaid petition.
ground for dismissal is litis pendentia); (b) by filing multiple
cases based on the same cause of action and with the same
In any case, the Court observes that the First CA Petition
prayer, the previous case having been finally resolved (where remains dismissible since the CIAC Revised Rules provides for
the ground for dismissal is res judicata); and (c) by filing the resort to the remedy of a petition for review only against a
multiple cases based on the same cause of action but with final arbitral award,55 and not a partial award, as in this case.
different prayers (splitting of causes of action, where the ground
for dismissal is also either litis pendentia or res judicata). 52
Forum shopping is treated as an act of malpractice and, in this In fine, the Court upholds the CA’s dismissal of Asian
accord, constitutes a ground for the summary dismissal of the Construction’s petition in CA-G.R. SP No. 112127 (First CA
actions involved.53 To be sure, the rule against forum shopping Petition) and based on this, denies its petition in G.R. No.
196723.
B. Review and modification of the Final Award. decisions of certain administrative agencies ‘final,’ the Court
still takes cognizance of petitions showing want of jurisdiction,
Sumitomo Corporation faults the CA for reviewing and grave abuse of discretion, violation of due process, denial of
modifying a final and non-appealable arbitral award and insists substantial justice or erroneous interpretation of the law" and
that the Asian Construction’s Second CA Petition should have that, in particular, "voluntary arbitrators, by the nature of their
been, instead, dismissed outright. It mainly argues that by functions, act in a quasi-judicial capacity, such that their
entering into stipulations in the arbitration clause – which decisions are within the scope of judicial review."62
provides that "the order or award of the arbitrators will be the
sole and exclusive remedy between the parties regarding any In this case, the Court finds that the CA correctly reviewed and
and all claims and counterclaims with respect to the matter of modified the Arbitral Tribunal’s Final Award insofar as the
the arbitrated dispute"56 and that "the order or award rendered award of attorney’s fees in favor of Sumitomo is concerned since
in connection with an arbitration shall be final and binding the same arose from an erroneous interpretation of the
upon the parties,"57 Asian Construction effectively waived any law.1âwphi1
and all appeals from the Arbitral Tribunal’s decision or award.
To elucidate, jurisprudence dictates that in the absence of a
Sumitomo’s argument is untenable. governing stipulation, attorney’s fees may be awarded only in
case the plaintiff's action or defendant's stand is so untenable
A brief exegesis on the development of the procedural rules as to amount to gross and evident bad faith.63 This is embodied
governing CIAC cases clearly shows that a final award rendered in Article 2208 of the Civil Code which states:
by the Arbitral Tribunal is not absolutely insulated from
judicial review. Article 2208. In the absence of stipulation, attorney's fees and
expenses of litigation, other than judicial costs, cannot be
To begin, Executive Order No. (EO) 1008,58 which vests upon recovered, except:
the CIAC original and exclusive jurisdiction over disputes
arising from, or connected with, contracts entered into by xxxx
parties involved in construction in the Philippines, plainly
states that the arbitral award "shall be final and inappealable (5) Where the defendant acted in gross and evident bad faith in
except on questions of law which shall be appealable to the refusing to satisfy the plaintiff's64 plainly valid, just and
Court."59 Later, however, the Court, in Revised Administrative demandable claim;
Circular (RAC) No. 1-95,60 modified this rule, directing that the
appeals from the arbitral award of the CIAC be first brought to xxxx
the CA on "questions of fact, law or mixed questions of fact and
law." This amendment was eventually transposed into the
In this case, the parties agreed that reasonable attorney’s fees
present CIAC Revised Rules which direct that "a petition for
shall be paid by the defaulting party if it fails to perform any of
review from a final award may be taken by any of the parties
within fifteen (15) days from receipt thereof in accordance with its obligations under the Agreement or by the party not
prevailing, if any dispute concerning the meaning and
the provisions of Rule 43 of the Rules of Court."61 Notably, the
interpretation thereto arises.65 However, since the parties’
current provision is in harmony with the Court’s
respective claims under the Agreement had already prescribed
pronouncement that "despite statutory provisions making the
pursuant to New York State Law, considering as well that the
dispute was not regarding the meaning or construction of any
provision under the Agreement,66 their stipulation on attorney’s
fees should remain inoperative. Therefore, discounting the
application of the foregoing stipulation, the Court proceeds to
examine the matter under the lens of bad faith pursuant to the
above-discussed rules on attorney’s fees.

After a careful scrutiny of the records, the Court observes that


there was no gross and evident bad faith on the part of Asian
Construction in filing its complaint against Sumitomo since it
was merely seeking payment of its unpaid works done pursuant
to the Agreement. Neither can its subsequent refusal to accept
Sumitomo’s offered compromise be classified as a badge of bad
faith since it was within its right to either accept or reject the
same owing to its contractual nature.67 Verily, absent any other
just or equitable reason to rule otherwise,68 these incidents are
clearly off-tangent with a finding of gross and evident bad faith
which altogether negates Sumitomo’s entitlement to attorney’s
fees.

Hence, finding the CA’s review of the Final Award and its
consequent deletion of the award of attorney’s fees to be proper,
the Court similarly denies Sumitomo’s petition in G.R. No.
196728.

WHEREFORE, the petitions are DENIED. The Resolutions


dated July 23, 2010 and April 18, 2011 of the Court of Appeals
in CA-G.R. SP No. 112127, as well as its Decision dated
January 26, 2011 and Resolution dated April 29, 2011 in CA-
G.R. SP No. 113828 are hereby AFFIRMED.

SO ORDERED.

ESTELA M. PERLAS-BERNABE
Associate Justice
Republic of the Philippines Petitioner claimed that these were "unauthorized insertions"
SUPREME COURT constituting a material breach of their agreement.
Manila Consequently, on May 9, 2002,4 petitioner notified respondent
of its intention to terminate the agreement effective June 10,
FIRST DIVISION 2002.

G.R. No. 169332 February 11, 2008 Thereafter, respondent filed an arbitration suit pursuant to the
arbitration clause of its agreement with petitioner. It contended
ABS-CBN BROADCASTING CORPORATION, petitioner, that the airing of WINS WEEKLY was made with petitioner's
vs. prior approval. It also alleged that petitioner only threatened to
WORLD INTERACTIVE NETWORK SYSTEMS (WINS) JAPAN terminate their agreement because it wanted to renegotiate the
CO., LTD., respondent. terms thereof to allow it to demand higher fees. Respondent
also prayed for damages for petitioner's alleged grant of an
exclusive distribution license to another entity, NHK (Japan
DECISION Broadcasting Corporation).5

CORONA, J.: The parties appointed Professor Alfredo F. Tadiar to act as sole
arbitrator. They stipulated on the following issues in their
This petition for review on certiorari under Rule 45 of the Rules terms of reference (TOR)6:
of Court seeks to set aside the February 16, 2005 decision1 and
August 16, 2005 resolution2 of the Court of Appeals (CA) in CA- 1. Was the broadcast of WINS WEEKLY by the claimant
G.R. SP No. 81940. duly authorized by the respondent [herein petitioner]?

On September 27, 1999, petitioner ABS-CBN Broadcasting


2. Did such broadcast constitute a material breach of
Corporation entered into a licensing agreement with the agreement that is a ground for termination of the
respondent World Interactive Network Systems (WINS) Japan agreement in accordance with Section 13 (a) thereof?
Co., Ltd., a foreign corporation licensed under the laws of
Japan. Under the agreement, respondent was granted the
exclusive license to distribute and sublicense the distribution 3. If so, was the breach seasonably cured under the
of the television service known as "The Filipino Channel" (TFC) same contractual provision of Section 13 (a)?
in Japan. By virtue thereof, petitioner undertook to transmit
the TFC programming signals to respondent which the latter 4. Which party is entitled to the payment of damages
received through its decoders and distributed to its they claim and to the other reliefs prayed for?
subscribers.
xxx xxx xxx
A dispute arose between the parties when petitioner accused
respondent of inserting nine episodes of WINS WEEKLY, a The arbitrator found in favor of respondent.7 He held that
weekly 35-minute community news program for Filipinos in petitioner gave its approval to respondent for the airing of WINS
Japan, into the TFC programming from March to May 2002. 3 WEEKLY as shown by a series of written exchanges between
the parties. He also ruled that, had there really been a material shall be final and unappealable and that no motion for
breach of the agreement, petitioner should have terminated the reconsideration shall be filed, then the petition for review must
same instead of sending a mere notice to terminate said fail. It ruled that it is the RTC which has jurisdiction over
agreement. The arbitrator found that petitioner threatened to questions relating to arbitration. It held that the only instance
terminate the agreement due to its desire to compel respondent it can exercise jurisdiction over an arbitral award is an appeal
to re-negotiate the terms thereof for higher fees. He further from the trial court's decision confirming, vacating or modifying
stated that even if respondent committed a breach of the the arbitral award. It further stated that a petition for certiorari
agreement, the same was seasonably cured. He then allowed under Rule 65 of the Rules of Court is proper in arbitration
respondent to recover temperate damages, attorney's fees and cases only if the courts refuse or neglect to inquire into the facts
one-half of the amount it paid as arbitrator's fee. of an arbitrator's award. The dispositive portion of the CA
decision read:
Petitioner filed in the CA a petition for review under Rule 43 of
the Rules of Court or, in the alternative, a petition for certiorari WHEREFORE, the instant petition is hereby
under Rule 65 of the same Rules, with application for DISMISSED for lack of jurisdiction. The application for
temporary restraining order and writ of preliminary injunction. a writ of injunction and temporary restraining order is
It was docketed as CA-G.R. SP No. 81940. It alleged serious likewise DENIED. The Regional Trial Court of Quezon
errors of fact and law and/or grave abuse of discretion City Branch 93 is directed to proceed with the trial for
amounting to lack or excess of jurisdiction on the part of the the Petition for Confirmation of Arbitral Award.
arbitrator.
SO ORDERED.
Respondent, on the other hand, filed a petition for confirmation
of arbitral award before the Regional Trial Court (RTC) of Petitioner moved for reconsideration. The same was denied.
Quezon City, Branch 93, docketed as Civil Case No. Q-04- Hence, this petition.
51822.
Petitioner contends that the CA, in effect, ruled that: (a) it
Consequently, petitioner filed a supplemental petition in the CA should have first filed a petition to vacate the award in the RTC
seeking to enjoin the RTC of Quezon City from further and only in case of denial could it elevate the matter to the CA
proceeding with the hearing of respondent's petition for via a petition for review under Rule 43 and (b) the assailed
confirmation of arbitral award. After the petition was admitted decision implied that an aggrieved party to an arbitral award
by the appellate court, the RTC of Quezon City issued an order does not have the option of directly filing a petition for review
holding in abeyance any further action on respondent's petition under Rule 43 or a petition for certiorari under Rule 65 with
as the assailed decision of the arbitrator had already become the CA even if the issues raised pertain to errors of fact and law
the subject of an appeal in the CA. Respondent filed a motion or grave abuse of discretion, as the case may be, and not
for reconsideration but no resolution has been issued by the dependent upon such grounds as enumerated under Section
lower court to date.8 24 (petition to vacate an arbitral award) of RA 876 (the
Arbitration Law). Petitioner alleged serious error on the part of
On February 16, 2005, the CA rendered the assailed decision the CA.
dismissing ABS-CBN’s petition for lack of jurisdiction. It stated
that as the TOR itself provided that the arbitrator's decision
The issue before us is whether or not an aggrieved party in a (d) That the arbitrators exceeded their powers, or so
voluntary arbitration dispute may avail of, directly in the CA, a imperfectly executed them, that a mutual, final and
petition for review under Rule 43 or a petition for certiorari definite award upon the subject matter submitted to
under Rule 65 of the Rules of Court, instead of filing a petition them was not made.
to vacate the award in the RTC when the grounds invoked to
overturn the arbitrator’s decision are other than those for a Based on the foregoing provisions, the law itself clearly provides
petition to vacate an arbitral award enumerated under RA 876. that the RTC must issue an order vacating an arbitral award
only "in any one of the . . . cases" enumerated therein. Under
RA 876 itself mandates that it is the Court of First Instance, the legal maxim in statutory construction expressio unius est
now the RTC, which has jurisdiction over questions relating to exclusio alterius, the explicit mention of one thing in a statute
arbitration,9 such as a petition to vacate an arbitral award. means the elimination of others not specifically mentioned. As
RA 876 did not expressly provide for errors of fact and/or law
Section 24 of RA 876 provides for the specific grounds for a and grave abuse of discretion (proper grounds for a petition for
petition to vacate an award made by an arbitrator: review under Rule 43 and a petition for certiorari under Rule
65, respectively) as grounds for maintaining a petition to vacate
Sec. 24. Grounds for vacating award. - In any one of an arbitral award in the RTC, it necessarily follows that a party
the following cases, the court must make an order may not avail of the latter remedy on the grounds of errors of
vacating the award upon the petition of any party to fact and/or law or grave abuse of discretion to overturn an
the controversy when such party proves affirmatively arbitral award.
that in the arbitration proceedings:
Adamson v. Court of Appeals10 gave ample warning that a
(a) The award was procured by corruption, fraud, or petition to vacate filed in the RTC which is not based on the
other undue means; or grounds enumerated in Section 24 of RA 876 should be
dismissed. In that case, the trial court vacated the arbitral
award seemingly based on grounds included in Section 24 of
(b) That there was evident partiality or corruption in the RA 876 but a closer reading thereof revealed otherwise. On
arbitrators or any of them; or appeal, the CA reversed the decision of the trial court and
affirmed the arbitral award. In affirming the CA, we held:
(c) That the arbitrators were guilty of misconduct in
refusing to postpone the hearing upon sufficient cause The Court of Appeals, in reversing the trial court's
shown, or in refusing to hear evidence pertinent and
decision held that the nullification of the decision of the
material to the controversy; that one or more of the Arbitration Committee was not based on the grounds
arbitrators was disqualified to act as such under section provided by the Arbitration Law and that xxx private
nine hereof, and willfully refrained from disclosing such respondents (petitioners herein) have failed to
disqualifications or of any other misbehavior by which substantiate with any evidence their claim of partiality.
the rights of any party have been materially prejudiced; Significantly, even as respondent judge ruled against
or the arbitrator's award, he could not find fault with their
impartiality and integrity. Evidently, the nullification
of the award rendered at the case at bar was not
made on the basis of any of the grounds provided by (3) Exclusive appellate jurisdiction over all final
law. judgments, decisions, resolutions, orders or awards of
Regional Trial Courts and quasi-judicial agencies,
xxx xxx xxx instrumentalities, boards or commissions, including
the Securities and Exchange Commission, the
It is clear, therefore, that the award was vacated not Employees’ Compensation Commission and the Civil
because of evident partiality of the arbitrators but Service Commission, except those falling within the
because the latter interpreted the contract in a way appellate jurisdiction of the Supreme Court in
which was not favorable to herein petitioners and accordance with the Constitution, the Labor Code of the
because it considered that herein private respondents, Philippines under Presidential Decree No. 442, as
by submitting the controversy to arbitration, was amended, the provisions of this Act and of
seeking to renege on its obligations under the contract. subparagraph (1) of the third paragraph and
subparagraph (4) of the fourth paragraph of Section 17
of the Judiciary Act of 1948. (Emphasis supplied)
xxx xxx xxx
As such, decisions handed down by voluntary arbitrators fall
It is clear then that the Court of Appeals reversed the within the exclusive appellate jurisdiction of the CA. This
trial court not because the latter reviewed the
decision was taken into consideration in approving Section 1 of
arbitration award involved herein, but because the Rule 43 of the Rules of Court.12 Thus:
respondent appellate court found that the trial court
had no legal basis for vacating the award. (Emphasis
supplied). SECTION 1. Scope. - This Rule shall apply to appeals
from judgments or final orders of the Court of Tax
Appeals and from awards, judgments, final orders or
In cases not falling under any of the aforementioned grounds resolutions of or authorized by any quasi-judicial
to vacate an award, the Court has already made several
agency in the exercise of its quasi-judicial functions.
pronouncements that a petition for review under Rule 43 or a Among these agencies are the Civil Service Commission,
petition for certiorari under Rule 65 may be availed of in the Central Board of Assessment Appeals, Securities and
CA. Which one would depend on the grounds relied upon by Exchange Commission, Office of the President, Land
petitioner.
Registration Authority, Social Security Commission,
Civil Aeronautics Board, Bureau of Patents,
In Luzon Development Bank v. Association of Luzon Trademarks and Technology Transfer, National
Development Bank Employees,11 the Court held that a Electrification Administration, Energy Regulatory
voluntary arbitrator is properly classified as a "quasi-judicial Board, National Telecommunications Commission,
instrumentality" and is, thus, within the ambit of Section 9 (3) Department of Agrarian Reform under Republic Act
of the Judiciary Reorganization Act, as amended. Under this Number 6657, Government Service Insurance System,
section, the Court of Appeals shall exercise: Employees Compensation Commission, Agricultural
Inventions Board, Insurance Commission, Philippine
xxx xxx xxx Atomic Energy Commission, Board of Investments,
Construction Industry Arbitration Commission, and
voluntary arbitrators authorized by law. (Emphasis party disagrees with the whole or any part of the arbitrator's
supplied) award may be availed of" cannot be held to preclude in proper
cases the power of judicial review which is inherent in courts.16
This rule was cited in Sevilla Trading Company v. Semana,13 We will not hesitate to review a voluntary arbitrator's award
Manila Midtown Hotel v. Borromeo,14 and Nippon Paint where there is a showing of grave abuse of authority or
Employees Union-Olalia v. Court of Appeals.15 These cases held discretion and such is properly raised in a petition for
that the proper remedy from the adverse decision of a voluntary certiorari17 and there is no appeal, nor any plain, speedy
arbitrator, if errors of fact and/or law are raised, is a petition remedy in the course of law.18
for review under Rule 43 of the Rules of Court. Thus,
petitioner's contention that it may avail of a petition for review Significantly, Insular Savings Bank v. Far East Bank and Trust
under Rule 43 under the circumstances of this case is correct. Company19 definitively outlined several judicial remedies an
aggrieved party to an arbitral award may undertake:
As to petitioner's arguments that a petition for certiorari under
Rule 65 may also be resorted to, we hold the same to be in (1) a petition in the proper RTC to issue an order to
accordance with the Constitution and jurisprudence. vacate the award on the grounds provided for in Section
24 of RA 876;
Section 1 of Article VIII of the 1987 Constitution provides that:
(2) a petition for review in the CA under Rule 43 of the
SECTION 1. The judicial power shall be vested in one Rules of Court on questions of fact, of law, or mixed
Supreme Court and in such lower courts as may be questions of fact and law; and
established by law.
(3) a petition for certiorari under Rule 65 of the Rules of
Judicial power includes the duty of the courts of Court should the arbitrator have acted without or in
justice to settle actual controversies involving rights excess of his jurisdiction or with grave abuse of
which are legally demandable and enforceable, and to discretion amounting to lack or excess of jurisdiction.
determine whether or not there has been a grave
abuse of discretion amounting to lack or excess of Nevertheless, although petitioner’s position on the judicial
jurisdiction on the part of any branch or remedies available to it was correct, we sustain the dismissal of
instrumentality of the Government. (Emphasis its petition by the CA. The remedy petitioner availed of, entitled
supplied) "alternative petition for review under Rule 43 or petition for
certiorari under Rule 65," was wrong.
As may be gleaned from the above stated provision, it is well
within the power and jurisdiction of the Court to inquire Time and again, we have ruled that the remedies of appeal and
whether any instrumentality of the Government, such as a certiorari are mutually exclusive and not alternative or
voluntary arbitrator, has gravely abused its discretion in the successive.20
exercise of its functions and prerogatives. Any agreement
stipulating that "the decision of the arbitrator shall be final and Proper issues that may be raised in a petition for review under
unappealable" and "that no further judicial recourse if either Rule 43 pertain to errors of fact, law or mixed questions of fact
and law.21 While a petition for certiorari under Rule 65 should F. THE ERROR COMMITTED BY THE SOLE
only limit itself to errors of jurisdiction, that is, grave abuse of ARBITRATOR IS NOT A SIMPLE ERROR OF
discretion amounting to a lack or excess of jurisdiction.22 JUDGMENT OR ABUSE OF DISCRETION. IT IS GRAVE
Moreover, it cannot be availed of where appeal is the proper ABUSE OF DISCRETION TANTAMOUNT TO LACK OR
remedy or as a substitute for a lapsed appeal.23 EXCESS OF JURISDICTION.

In the case at bar, the questions raised by petitioner in its A careful reading of the assigned errors reveals that the real
alternative petition before the CA were the following: issues calling for the CA's resolution were less the alleged grave
abuse of discretion exercised by the arbitrator and more about
A. THE SOLE ARBITRATOR COMMITTED SERIOUS the arbitrator’s appreciation of the issues and evidence
ERROR AND/OR GRAVELY ABUSED HIS DISCRETION presented by the parties. Therefore, the issues clearly fall under
IN RULING THAT THE BROADCAST OF "WINS the classification of errors of fact and law — questions which
WEEKLY" WAS DULY AUTHORIZED BY ABS-CBN. may be passed upon by the CA via a petition for review under
Rule 43. Petitioner cleverly crafted its assignment of errors in
B. THE SOLE ARBITRATOR COMMITTED SERIOUS such a way as to straddle both judicial remedies, that is, by
ERROR AND/OR GRAVELY ABUSED HIS DISCRETION alleging serious errors of fact and law (in which case a petition
IN RULING THAT THE UNAUTHORIZED BROADCAST for review under Rule 43 would be proper) and grave abuse of
DID NOT CONSTITUTE MATERIAL BREACH OF THE discretion (because of which a petition for certiorari under Rule
AGREEMENT. 65 would be permissible).

C. THE SOLE ARBITRATOR COMMITTED SERIOUS It must be emphasized that every lawyer should be familiar with
ERROR AND/OR GRAVELY ABUSED HIS DISCRETION the distinctions between the two remedies for it is not the duty
IN RULING THAT WINS SEASONABLY CURED THE of the courts to determine under which rule the petition should
BREACH. fall.24 Petitioner's ploy was fatal to its cause. An appeal taken
either to this Court or the CA by the wrong or inappropriate
mode shall be dismissed.25 Thus, the alternative petition filed
D. THE SOLE ARBITRATOR COMMITTED SERIOUS in the CA, being an inappropriate mode of appeal, should have
ERROR AND/OR GRAVELY ABUSED HIS DISCRETION been dismissed outright by the CA.
IN RULING THAT TEMPERATE DAMAGES IN THE
AMOUNT OF P1,166,955.00 MAY BE AWARDED TO
WINS. WHEREFORE, the petition is hereby DENIED. The February
16, 2005 decision and August 16, 2005 resolution of the Court
of Appeals in CA-G.R. SP No. 81940 directing the Regional Trial
E. THE SOLE ARBITRATOR COMMITTED SERIOUS Court of Quezon City, Branch 93 to proceed with the trial of the
ERROR AND/OR GRAVELY ABUSED HIS DISCRETION petition for confirmation of arbitral award is AFFIRMED.
IN AWARDING ATTORNEY'S FEES IN THE
UNREASONABLE AMOUNT AND UNCONSCIONABLE
AMOUNT OF P850,000.00. Costs against petitioner.

SO ORDERED.
RENATO C. CORONA
Associate Justice

Vous aimerez peut-être aussi