on a risk basis
by O.K.H. Steffen*
The Journal of The South African Institute of Mining and Metallurgy MARCH/APRIL 1997 47
Planning of open pit mines on a risk basis
These classifications are in effect statements of confidence that of the mineral resource estimation between different
or ‘risk’ and need to be clearly defined and included in the categories i.e. CAT 1, CAT 2 and CAT 3 respectively. It is
tonnage grade curve, as shown in Figure 1. An understanding therefore proposed that for open pit designs, the confidence
of the grade distribution and tonnage distribution of the total for slope designs should be categorised using the same
resource is fundamental in the first step of composing a fundamental approach as that adopted for resource/reserve
proper mine plan. Since the planning process is concerned definitions. This can be illustrated in Figure 2.
about the physical exposure of ore in given time increments Definitions for the classification are suggested as follows:
and at specific grades and tonnages, a full understanding of A proven slope angle (CAT 1) requires that the continuity
the risks associated with the specific locations of ore tonnages of the stratigraphic and lithological units within the affected
and grades is necessary. No planning should commence prior rock mass is confirmed in space from adequate intersections.
to a full appreciation and assessment of the tonnage grade Detailed structural mapping of the rock fabric is implied
curves as shown in Figure 1. which can be extrapolated with a high confidence for the
affected rock mass and that strength characteristics of the
Slope stability structural features and the in-situ rock has been determined
by the appropriate testing procedures to allow reliable
As in the case of mineral resource estimation, the determina- statistical interpretations to be made. Groundwater pressure
tion of slope angles is dependent on the understanding of
distributions within the affected rock mass should have been
geological and geotechnical information and the confidence
measured using piezometer installations to allow a high
of design is equally based on the degree of certainty which
confidence in the groundwater model. Data reliability should
applies to the data available. Unlike the case of mineral
be such that an analytical model can be used to carry out the
resource estimation, where the exploration is specifically
design to a confidence of 85%.
targeted to provide ore reserve information, the requirement
for slope design only becomes necessary once a prospective A probable slope angle (CAT 2) corresponds to a design
mineral resource has been discovered. Exploration core has based on information which allows a reasonable assumption
usually limited value for slope design purposes as the target to be made on the continuity of stratigraphic and lithological
areas for slope design are not necessarily the same as for the units. Some structural mapping will have been carried out
orebody. Drilling requirements for geotechnical purposes also utilising estimates of joint frequencies, lengths and conditions.
differ considerably from that for mineral exploration. Hence a All major features and joint sets should have been identified.
limited campaign for geotechnical purposes is usually under- A modicum of testing (small sample) for the physical
taken in addition to whatever value can be obtained from the properties of the in-situ rock and joint surfaces will have
original exploration campaign. been carried out. Similarly groundwater data will be based on
It is therefore not uncommon to have a slope design which water intersection in exploration holes with very few
has a much lower degree of confidence than that pertaining piezometer installations. Data will be such as to allow
to the mineral resource definition. By definition, the mineable
reserves within the resource are determined by applying a
mine design which could economically exploit the resource.
EXPLORATION
Within a life of mine plan, resources of different confidence INFORMATION
categories will be included, i.e. CAT 1, CAT 2 and CAT 3
resources. By applying the mine planning procedures, these
resources will be reclassified as proven, probable and
possible reserves respectively, or CAT 1, CAT 2 and CAT 3
reserves respectively. RESOURCES RESERVES
Maintaining a consistent assessment of confidence would
require that the confidence of the slope design should match
48 MARCH/APRIL 1997 The Journal of The South African Institute of Mining and Metallurgy
Planning of open pit mines on a risk basis
simplified design models to be developed to allow sensitivity ➤ provide information for strategic decision making.
analyses to be carried out. To achieve these objectives, certain planning criteria need
A possible slope angle (CAT 3) corresponds to application to be adopted :
of typical slope angles based on experience in similar rocks.
Quantification will be on the basis of rock mass classifi- Cut-off cost planning criteria
cations and a reasonable inference of the geological The life-of-mine open pit represents that outline of the open-
conditions within the affected rock mass. pit boundary faces beyond which no further reserves should
be recovered by open-pit methods.
Planning processes This limiting boundary can be defined by:
➤ the total ore reserve being exhausted
A systematic and disciplined planning process is advocated.
➤ the marginal increment of mining cost exceeds the
Three distinct levels of planning are recognised in developing
expected income and that the economic limit of open-
the reserves:
pit mining has been reached
➤ Life-of-mine plan (LOM). ➤ an underground operation becoming more profitable
➤ Long-term plan (LTP), which follows from the LOM. than the incremental open pits.
➤ Short-term planning (STP), which in turn follows from
But for the first one, the limit in all of these criteria is
the LTP.
defined by the increment in mining cost exceeding a specified
Each of these stages of planning represent different levels value. The increment in cost is defined purely by the mining
of risk and have different objectives. It follows therefore that cost, i.e. when the increment in mining cost only is such that
the planning criteria for each planning phase should be the total costs of product are too high. For an accurate
different. Disciplined planning means that each of these steps definition, therefore, of the open-pit boundary, a criterion
are closely interlinked; for example, that every activity in the that is sensitive to the mining cost component needs to be
short-term plan benefits the long-term objectives as defined used in defining this LOM pit limit. For this reason, a cut-off
in the life-of-mine plan. This interaction can be illustrated cost criterion is proposed which is the cost of producing the
diagrammatically as shown in Figure 3. A systematic finished product from the final increment.
planning process ensures that proper participation from all Typical financial criteria that are in common use, such as
levels of management is able to be communicated to the net present value (NPV) or internal rate of return (IRR), are
planning engineer. insensitive to the boundary limit location. These criteria are
most sensitive to the price assumed for the product, the
Life of mine plan (LOM) production schedule for mining, as well as the assumed
discount rate. Since the mining schedule, i.e. the order in
Development of the LOM plan is the first step in the planning which the ore and waste blocks are removed, is still unknown
process and has the following objectives: at this stage, these criteria cannot be used effectively for this
➤ define the inventory of ore reserve that is mineable purpose. When defining the total inventory available for
within the assumed economic parameters exploitation, it is important that every block be afforded an
➤ define the production capacity for the remaining life of equal opportunity to contribute to the profitability.
mine The cut-off cost criteria can therefore be summarised as
➤ define the infrastructure requirements follows: The LOM pit limits are such that no ore is mined
➤ determine the fixed capital costs which will result in the final product having a production
cost greater than the cut-off value. The specification of this
cut-off cost is related to an acceptable risk.
The first objective of the life-of-mine plan is to determine
the maximum inventory of open-pit mineable reserves. The
common process, assuming a block model, is to assign
revenue and cost values to each block within the model and
to use either the floating cone or Lerch-Grossman algorithm
in defining the economic boundaries to the number of ore
blocks that can be recovered from open-pit methods. The
maximum ore reserve available is therefore a function of the
value assigned to each of the blocks. Ore blocks will have
positive values when revenue exceeds costs, and waste
- Closure requirements blocks will have negative values.
Consider the marginal ore blocks. The potential of the
marginal ore blocks are threefold viz:
➤ processed as ore in the normal manner
➤ considered as stockpile for treatment by a different
process e.g. leaching, or at a later time when cash flow
or price variations allow
➤ considered as unpay and treated as waste for the
Figure 3—Planning procedure evaluation in hand.
▲
The Journal of The South African Institute of Mining and Metallurgy MARCH/APRIL 1997 49
Planning of open pit mines on a risk basis
Depending upon which of the three potentials are applied is to constantly review the operational methods adopted and
to the marginal blocks, three different values will be assigned. to adopt those methods and technology which will see a
Marginal ore blocks with the highest real value would release further reduction in the cost of production. In this manner, as
the greatest number of positive underlying ore blocks. the whole emphasis is based on cost, the efforts from the
Depending, therefore, upon whether marginal ore is mine planning staff are directed systematically and purpose-
processed or dumped as waste or stockpiled will alter the fully towards the single goal of reducing costs for the purpose
total inventory available for open-pit mining. of defining the LOM plan.
The life-of-mine plan thus provides the outline of the
ultimate pit providing the maximum mineable inventory, Defining an acceptable cut-off cost
from which the infrastructure development can be properly Deciding on an acceptable cut-off is a business decision. It
located. This prevents expensive relocation at later stages or reflects the optimism and the risk which the company is
compromises the ore development programmes, when market prepared to accept in investing in the particular ore reserve.
conditions change. Compared to the traditional cut-off-grade Some guidelines and principles underlying such a decision
approach to pit design, the essential difference lies in the can, however, be postulated as follows:
emphasis on determining the mining costs, be it either to the Firstly, the tonnage vs cost relationship (Figure 4) for the
ore process point or to a stockpile or waste location. Should ore reserve can be a first indicator. Should the relationship
there be no difference between the tramming costs to the indicate an inflection point then this could be taken as a
crusher or the dumping location, then the adoption of a decision on cost limit since the risk of increased cost is not
marginal cut-off grade for process only, will result in the matched with a corresponding increase in product. Since the
same design as the use of the cut-off cost. The procedure risk level is largely determined by the ore reserve reliability,
suggested here, however, emphasises the decision based on a this point indicates a natural cut-off point. From previous
cost of production rather than a profit which is related to an case studies, not all ore reserves display this inflection point.
assumed price. The life-of-mine plan is therefore a definition Where the inflection point is absent, the next option is to
of the inventory available which then has to be exploited and consider the cost in relation to other world producers.
managed in order to provide the maximum value to share- Reference to a world producer cost curve is therefore necessary
holders in accordance with corporate policies and philosophies. as shown in Figure 5. The relative position of the planned
Assuming different cut-off costs, the total inventory operation on the world producer cost curve is a function of
available in each incremental cost can be calculated and corporate philosophy, e.g. some companies would tolerate
presented on the curve as shown in Figure 4. The average only an operation with a limiting incremental cost which falls
cost of mining to within this cut-off cost is represented by the within the lower 50%, others within the lower two third
average cost curve. All figures are presented in present-day (66,7%) or others, again, within higher limits e.g. 85%. This
value terms and represents the marketability of the ore decision represents the corporate philosophy on investment
reserve on the world market in competition to other reserves. risk as well as market image.
Figure 4 can therefore be used in the marketing strategy of It is necessary to distinguish between the cut-off cost and
the mine which leads to strategic decision making and the average operating cost. World producer cost curves
provides the communication medium between marketing, represent the average operating costs and not the marginal
management and planners. costs of any particular operation. Since the cut-off cost is at
In this Figure it is assumed that the cost of production which it is proposed that the operation cease to produce onto
represents the minimum in terms of the present technology the market, the cut-off cost chosen must be based on
for operations. The function of the mine planning department comparisons with other operations which are likely to have a
comparable effect on the world market if they were to cease
operations. It also represents the acceptable margin of risk
compatible with the company’s stated mission and philosophy.
The margin of risk acceptable to a life-of-mine definition is
also a function of the certainty with which the information is
known, e.g. ore reserves and slope angles.
COST/FINAL PRODUCT
50 MARCH/APRIL 1997 The Journal of The South African Institute of Mining and Metallurgy
Planning of open pit mines on a risk basis
➤ develop an underground mining alternative and assign ➤ an acceptable operating cost to final product relative to
net values to each ore block; cost of capital should be world producers
included ➤ flexibility requirements within plan e.g. upside potential:
➤ assign block values equal to the differences between to increase product volume by 15% within 6 months
open pit and underground valued blocks in the sustainable for 12 months; downside potential: to
potential overlap areas reduce unit operating costs of final product by 10%
➤ using these adjusted block values, re-run the pit within 3 months sustainable for 24 months
optimisation algorithms to define the best cut-off limit ➤ maximise NPV.
between open pit and underground.
Figure 6 provides a flow diagram illustrating the input,
Based on the appropriate cut-off cost criteria, the final
design processes and the outputs of the inter-relationship
limit can therefore be established and total reserves and
between the LOM plan and the LTP.
inventory determined. This information is then utilised for
Discounted cash flows are the common basis for
the establishment of infrastructure requirements and life-of-
evaluating shareholder returns and are expressed in terms of
mine capital investment requirements. Strategic decisions can
now be made in regard to production rates. NPV or IRR or similar. Typically a NPV calculation is most
sensitive to the following parameters:
The Journal of The South African Institute of Mining and Metallurgy MARCH/APRIL 1997 51
Planning of open pit mines on a risk basis
maximising the NPV is high. Flexibility, however, has value
to the shareholder. This value should be determined using
option theory and added to the cash NPV to give a total
value, also expressed in NPV terms. The total NPV should be
maximised in the planning process.
Should the cost of production be managed differently,
e.g. the LTP allows for advanced stripping above that
required by the minimum cost curve, then the cost could
typically be as represented in the ‘managed’ cost curve
shown in Figure 7. For this case, the total benefit exceeds
that of the previous minimum cost case, i.e. a retrospective
analysis would show a higher NPV for the latter case due to
the introduction of a decision on risk. In Figure 7, the metal
price curve is unknown while the other two curves are
determinants.
Most large open pit mines in the world operate on this
basis by adopting an average stripping ratio over the life of
mine. While the waste to ore ratio does define costs of
mining to a large extent, it is more appropriate to focus on
actual cost of production rather than just one of the
parameters contributing to cost of production. Cost should
also be based on total cost of final product, not only of the
mining operation. It is therefore suggested that the cost of
operation for the mine be determined by a management
decision having regard to the minimum cost possible but
incorporating an assessment of risk while satisfying the
return necessary for the investment made. The basis for an
assessment of risk is associated with a period of time for
which additional development costs are acceptable.
52 MARCH/APRIL 1997 The Journal of The South African Institute of Mining and Metallurgy
Planning of open pit mines on a risk basis
The Journal of The South African Institute of Mining and Metallurgy MARCH/APRIL 1997 53
Planning of open pit mines on a risk basis
Scheduling comparing the net present value of the life of mine costs
only. When comparing it to other operations on the world
Accepting, therefore, that the mining will proceed along a
cost curve, it should be assumed that all operations present a
basis of a defined cost of production in terms of final product,
minimum cost of production. Since Figure 6 is a window of
many potential scheduling options now remain. A series of
present production costs on a worldwide basis, the best
sequential pushbacks can now be planned and ranked in
comparative figure to use is the present-day value of the
increasing order of cost of production. Inventory that has
average operating costs.
been defined for each of the pushbacks can now be scheduled
in terms of production cost. The only variables that can be
managed are the head grade and the stripping ratio, which Short-term planning
ultimately determine the operating costs. Scheduling the
From a defined long-term plan, short-term planning now
inventory and the logistics of the design pushbacks can now
applies to a one year period within a single business cycle.
be undertaken, based on set criteria, e.g. maximum NPV,
Short-term planning has as its major objectives:
minimum cost, specified costs etc. (for different combinations
of head grade and stripping ratios over the long-term). ➤ grade control
Comparative schedules can be produced and an optimum ➤ cost control
selected. See Figure 6. This optimum should be defined in ➤ equipment utilisation
terms of the criteria specified earlier. ➤ capital productivity
Accepting a defined cost has some interesting other ➤ labour productivity.
consequences in terms of the mine planning requirements. The short-term planning process is therefore concerned
Given that the cost will be fixed, the objective of the mine primarily with the day-to-day scheduling of feed grade to the
planning will therefore be to apply this cost in the most mill and stripping requirements for the first 12 to 18 months
beneficial manner. This translates into exposing the maximum of the LTP. Equipment utilisation includes the planning for
reserves for the given cost of operation. Minimising haul equipment replacement, repurchase and manning schedules
distances provides the maximum stripping rate for the same for determining labour productivities. Short-term planning
cost and hence the maximum amount of exposed reserves. must ensure that the long-term planning goals are achieved
The additional cost incurred over and above the minimum on a daily, weekly and monthly basis.
cost is therefore being invested into exposed reserves,
providing additional flexibility and reducing risk. Planning risks
Cost modelling Risks associated with planning are related to the confidence
which applies to the mineral resource (geology and grade
Accurate cost modelling forms an essential part of this distribution), the mining plan (geotechnical) and the business
particular process. Different cost models apply to the different assumptions (price fluctuations). These risks can be addressed
planning phases. Cost components can be isolated in the by upgrading information in the case of the first two and by
following manner: providing flexibility within the plan in the case of the latter.
➤ Fixed costs: non-discretionary/discretionary In all these cases risks can be reduced by incurring more
➤ Variable costs: non-discretionary/discretionary. expenditure but can never be eliminated. Accepted risk levels
will vary from company to company. Fault /Event tree
In the case of the LOM plan, the cost model should include
analyses provide a formalised way of adjudicating the value
total mining costs, i.e. fixed costs, variable costs and all
added by additional information. A typical example for an
mining equipment capital costs discounted into the unit
underground gold operation is presented in Figure 10.
mining operating cost. In the case of the LTP only variable
Frequently options are compared on a DCF basis only,
unit costs are included as all capital items can be accommo-
even though they represent very different risks of achiev-
dated into the cash flow analysis. At actual pit closure,
ability, or in some cases are combined with a subjective
ultimate costs will comprise only variable costs with fixed
assessment of risks applicable to each option. A formalised
and discretionary costs minimised.
risk evaluation as proposed, provides the opportunity of
Many mining simulation software packages are available
determining the relative costs to equalise the risk for each
which can produce a realistic schedule of production costs
option and therefore makes the DCF comparisons valid.
over the long term. Projections of cost in the long term rely
In the fault tree, contributing elements to the Top fault of
on a knowledge of escalation of different components of cost.
producing too few ounces, are analysed to the most funda-
It is convenient to separate out the cost components in
mental parameters. At this level, the reliability of information
the following manner:
can be reasonably estimated, as well as the cost associated
➤ energy costs with improving the reliability. In applying the branch network
➤ maintenance costs of the fault tree, the combined impact of all the elements can
➤ labour costs be summoned to result in a probability of the Top fault
➤ capital costs. happening. This procedure is therefore useful to identify the
Each of these cost components can be escalated at a critical areas requiring additional expenditure.
different rate to determine the project-sensitive parameters. Ultimately the technical planning risks can be presented
Since cost escalations are generally more reliable than the as shown in Figure 11. Categories 1, 2 and 3 reserves
prediction of future prices of any product, the risk evaluation represent the different confidences of mineable reserves, i.e.
of alternative project strategies are often determined by after the application of ore reserve and geotechnical
▲
54 MARCH/APRIL 1997 The Journal of The South African Institute of Mining and Metallurgy
Planning of open pit mines on a risk basis
The Journal of The South African Institute of Mining and Metallurgy MARCH/APRIL 1997 55
Planning of open pit mines on a risk basis
Conscious decisions need to be taken about certain SRK Internal Reports.
fundamental parameters, such as the period of risk defined LANE K.F., ‘The Economic Definition of Ore’, Mining Journal Books. 1991.
as the business risk period, as well as the pushback size. BRENNAN M.J. and SCHWARTZ E.S., ‘A New Approach to Evaluating Natural
Experience has shown that the improvement in communi- Resource Investments’, Stern J.M. and Chew D.H., (eds). The Revolution in
Corporate Finance, Basil Blackwell, 1986, pp. 78–87.
cation and understanding of decision-making between
management and planning engineer has added considerably BLACK F. and SCHOLES M. ‘The Pricing of Options and Corporate Liabilities’,
Journal of Political Economy, LXXXI (1973), pp. 637–654.
to the growth in shareholder’s value.
BRENNAN M.J. and SCHWARTZ E.S. ‘Evaluating Natural Resource Investments’,
Journal of Business 58. pp. 135–157, 1985.
Bibliography
PINDYCK R.S. ‘Irreversibility, Uncertainty and Investment’, Journal of Economic
Literature, vol. 29, no. 3. September 1991.
Australian Code for Reporting of Identified Mineral Resources and Ore
Reserves: Report of the Joint Committee of the IMM, Australia Institute of TRIGEORGIS L. and MASON S.P. ‘Valuing Managerial Flexibility’. Midland
Geoscientists and Mineral Council of Australia (JORC). July 1996. Corporate Financial Journal, vol. 5, no. 1. Spring 1987.
Ore Reserves and Resources—Colloquium SAIMM. July 1995. ANG A.H.S. and TANG W.H. ‘Probability Concepts in Engineering Planning and
JANISCH P. ‘Classification of South African Mineral Resources and Reserves Design’, Wiley J., vol. no. 1, N.Y. 1975.
within the International Framework’, note prepared for 15th CMMI Congress,
Sun City. 1994. ANG A.H.S. and TANG W.H. ‘Decision Risk and Reliability’, Wiley J., vol. no. 2,
N.Y. 1975.
MISKELLY N. ‘A Comparison of International Definitions for Reporting of Mineral
Resources’ IMM Bulletin, no 4, July 1994. LORRAIN M. and THIELE C. Anaconda, Chile. Private Correspondence. ◆
56 MARCH/APRIL 1997 The Journal of The South African Institute of Mining and Metallurgy