Vous êtes sur la page 1sur 42

BEIJING DATONGLONGYUAN ENERGY TECHNOLOGY Co.

,LTD

PT DATONG JAYA INDONESIA


www.datonglongyuan.com
Mr.Andy Wan
0086 - 13910117983
0062- 81297753376
Circulating Fluidizing Bed Boiler ( CFB) is a proven clean energy
harness technology , it suits a variety of fossil coal , well running
characteristics , environmental friendly . It has been developing
rapidly domestic and abroad . With application of CFB BOILER de-
sulfurization can be obtained inside furnace . Nox emission
reduced to 1/3 – 1/4 of PC Boiler . Comparing with PC boiler , CFB
boiler develops fast , naturally, some issues come up need to be
justified and address , some issues existing observed after boiler
put into run , some run are not so well , give CFB boiler technology
bad reputation . On top of that , comparing with PC boiler,
uninterrupted run of a CFB boiler is critical indicator . How to avoid unscheduled
outage is everybody’s concern.

As matter of fact , there are lots of factors impact CFB boiler’s reliability .
As per our long time research and modification experience, we found out , 3 key
aspects are affecting CFB boiler uninterrupted run .

1. Reliable performance of coal handling system ensure undisruptive coal


feeding .

2. Anti-abrasion measures taken on key eroded areas reliable, reduce risk of tube
rupture .

3. Slag cooler stable and reliable performance ensure smooth slag discharge .
CFB Boiler Uninterrupted Run Indicators Analysis

Unscheduled Outage
2014 National Benchmark for CFB
Boiler Plants 300MW Capacity , mean
unscheduled outage 0.33/unit.year
Some units 300MW Capacity obtained
record high uninterrupted run days .
• Availability Hours
Unit #5 , Baolihua Plant : 434 days .
200MW Capacity , Shenhua Yili Plant
Unit #1 : 341 days .
135MW Capacity , Pansan Plant Unit
#1 : 311days .
Coal Feeding System Clogging Caused Coal Supply Interruption

1. Raw coal bunker clogging impacts unit output load .


In case clogging emerges , coal feeder normal runs interrupted ,coal
supply decreased , likely the unit is forced to ramp down .

2. Pose threat to Unit safety run .


In case clogging occurs, coal feeder normal affected , triggers boiler
unstable combustion . In case multiple coal feeder coal supply
interrupted ,Boiler steam generation drops in large scale , combustion
gets worse , likely fire out causing unscheduled shutdown . On top of
that ,sometimes , in case coal feeder encounters coal interruption,
likely flue gas goes reverse into CF ,cause unimagined incident .
3. Raw coal bunker clogging impacts economical run
In case coal bunker clogging emerged , plus interrupted coal
feeder work , in light of stabilizing combustion , alternatively ,
fuel oil is applied , thus, operational cost increased .

Therefore , clogging affects unit normal run , clogging prevention


shall have to be put on emphasis in normal operation, ensuring safety ,
economical and civilized production .
Anti - Abrasion Measures
for Key Easy Abrasion Areas
In the course of CFB Boiler application , acknowledge abrasion principle on
metal surface and fair assessment of abrasion rate , will play significant role
in aspects of Boiler design and routine O & M .
In a certain extent, the economy and availability for A CFB Boiler subjects to
its anti-abrasion design and abrasion-proof performance.

 Double abrasion

 Triple abrasion
Abrasion Rate
CFB Boiler Key Eroded Area
Water wall surrounding tubes
Dense area refractory
Overlapping between dense area
and water wall
Furnace four corners
Furnace flue gas exit access
Furnace middle portion
Platen through water wall
 Furnace Platen lower part
Distribution plate and air nozzle
 Furnace ceiling area
 Separator incoming and discharge
 duct
 Loop seal vertical chute and inside
Heat reheat area
Abrasion at Refractory Overlapping Area
Abrasion at Refractory Overlapping Area

Side water wall

Refractory Material
Abrasion observed At Dense Area

Coal feeding Port


Water wall At Furnace Corner
Abrasion Observed at Water wall At Furnace Four Corners

abrasion caused by Inappropriate


refractory workmanship
Abrasion Observed at Water wall At Furnace Four Corner

Flue gas flush shall have to be


considered during installtion.
Abrasion Observed at Water Wall Dilute Area

Tube Burst due to


Water Wall Partial Water Wall Finned Plate
Inappropriate Structure abrasion
Water Wall abrasion at Dilute Area
Weld seam not properly polished
cause abrasion

Finned plate deformed cause


abrasion
Water Wall abrasion at Cyclone Separator
Water Wall abrasion at Cyclone Separator

abrasion caused by Flue Gas entry Cyclone Separator


Abrasion on Platen Heat Exchanger

Eroded on Extended Platen Eroded on Double Water Wall


Collector Through Water wall
Abrasion Caused by Platen Deformation

Platen Re heater Platen Re heater Tube


Deformed ( 150MW) Eroded and Burst(135MW)
Abrasion at Platen Area

Refractory Material Detached due to


Platen Re-heater deformed
Abrasion due to Platen Refractory Material Detached
Platen Heating Surface Layout and Anti-abrasion Design
Height maintains 15m above
Air Distribution Plate.
 Span between two platens
greater than 700mm, thus,
remain ample spacing for
maintenance purposes .
 Anchor pin :1000Pieces/m2 is
recommended .
 Good quality cast able plastic
refractory applies.
Sealing and Expansion Design

Expansion differential shall have to consider between Platen and water wall seal .
Expansion bellow required , both expansion and seal to be considered .
Metal expansion bellow shall be suppressed prior installation .
External Bed

Low fluidizing velocity selection during design . ( 0.5m/s , theoretically


abrasion far and away less.
• Imported 300MW CFB Boiler ,tube burst occurs due to tube bundle clipping
zone impacting .
• Detailed design shall consider – resolving expansion and vibration issues .
Air Nozzle abrasion

 Internal leaks.
 Air resistance poor Match
up.
 Short lifespan, easy eroded .
Air Nozzle abrasion Issues
Special Spay Lining Technology

 Special Spray Alloy material enhanced water wall anti-abrasion


capability , prolong lifespan.
 In particular , for those Boiler burning good quality coal , evidently
prolongs lifespan after Special Spray done .
Precautions for Special Spay Modification
Those Boiler burned inferior coal , ( LHV and High ash content ) special
spray protection cycle short , under different cases , approximate 3 – 12
months .
• Special Spay service providers varies a lot , as implementation
requirements is strict , sometimes , wrinkles or uneven emerged , de-scale
or detached readily , becomes new vulnerable position for burst .
• Welding seam ruined , spray material penetrates into base material ,
resulting water wall tube rupture . Secondary handling takes time ,
involving more workload . As you know , shut Boiler down , necessary
polish and rinse , buildup and double spray taken .
Special Lining Applications

Lining Overlapping Lining De-scale


Issues Observed after Special Lining
Positive Multiple Elevations Anti-abrasion Beam Technology
 Anti-abrasion convex formed by refractory material , along water wall
height , lay out at set interval or incline multiple elevations .
 Anti-abrasion convex evidently slowdown ash dripping velocity and
density ( velocity drops from 8m/s to 2m/s .)
 Guarantee water wall lifespan prolongs from approximate 3 months to
over 1 year .

Technical Hallmarks
1. Positive Approach, ease ash dripping velocity and density .
2. Easy installation, large modification inside furnace not necessary .
3. Reliable performance, maintenance free.
Positive Multiple Elevations Anti-abrasion Beam Technology
Positive Multiple Stage Anti-abrasion Beam Technology

Prior After
Modification Modification
Snapshot of Applications
Statistics Analysis after Modification

feeding
Statistics Analysis After Modification
Application List
 Ruiping Power Plant , Henan (2×135MW CFB Boiler )
 Chentang Power Plant TianJin (1×135MW CFB Boiler)
 Zhongfu Power Plang , Henan (1×135MW CFB Boiler )
 Hua dian Uda Power Plant (2×150MW CFB Boiler )
 QinHuangdao Power Plant (2×300MW CFB Boiler )
 Guodian Xiaolongtan Power Plant (2×300MW CFB Boiler )
 ShenHua Xilaifeng Power Plant (2×200MW CFB Boiler )
 Linhuan Zhongli Power Plant, Anhui (2×300MW CFB Boiler)
 Baolihua Power Generation Company , Canton (1×300MW CFB Boiler)
 Xuzhou Mining Power Generation Company (2×300MW CFB Boiler)
 Pingshi Power Generation Company Shaoguan (2×300MW CFB Boiler)
 Datang Honghe Power Plant (2×300MW CFB Boiler )
Summary

Main factors of resulting furnace water wall abrasion : ash dripping along
tube bundle.
 From aspects of design and Boiler selection , consideration of applicable
cross section flue gas velocity regards key of alleviating furnace abrasion .
 From aspect of engineering methodology , improve erection workmanship
is insurance of lessening abrasion on Water wall .
 Application of Anti – abrasion Beam , Give-in Tube and Special Spray can
reduce water wall abrasion .
 Application of Anti-abrasion Beam obtained significant outcome in aspect
of Boiler abrasion prevention .
BEIJING DATONGLONGYUAN ENERGY TECHNOLOGY Co.,LTD
PT DATONG JAYA INDONESIA

Vous aimerez peut-être aussi