SAUDI ARAMCO INSPECTION CHECKLIST
Passively Cooled Shelter Installation Inspection SAIC-K-4035 30-Apr-13 HVAC
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

Each equipment unit shall be installed at the location indicated on the


drawings and in accordance with details of mounting, with vibration SAES-K-001
A1
isolation as required by the Design Specifications and in accordance Para 5.1.7
to equipment Manufacturer’s recommendations.

For Communications Facilities direct expansion (DX) type HVAC


systems shall be used. (9COM: 6000013333 per SAES-K-101)
Exception:
1) Chilled water system or Other type of air conditioning units may be SAES-K-003
A2
used only with the prior approval of Communications Engineering & Para. 6.5
Technical Support Department / Facilities Engineering Group.
2) For Communication Facilities and Data Centers, Computer Room
Precision Type air conditioning units shall be used.

All HVAC systems covered by this Standard shall be provided with


standby capacity as follows:
1) If the system is served by two or more normally operating units,
the capacity of the standby unit(s) shall be at least 50% of the SAES-K-003
A3
system's maximum design capacity. Para 6.6
2) If the system is served by one normally operating unit only, the
capacity of the standby unit shall be equal to the capacity of the
normally operating unit.

Fresh Air Intake shall:


1) be located at a minimum of 2.4 meters above grade. SAES-K-003
A4
2) have a Sand trap louver,Filter,Bird screen,Differential pressure Para 6.7
gauge,Volume damper.

HVAC control systems shall be capable of providing the following


functions:
1. Automatic change over between the operating and standby units
weekly, and/or in the event of operating unit failure.
SAES-K-003
A5 2. Remote alarms to NOCC (Network Operations Control Center) in
Para. 6.10
case of any HVAC equipment failure and/or any other alarms in the
HVAC equipment
3. Capable to be connected to Building Management System (BMS).
The Control shall be BACNET compatible.

The internal air temperature of Hybrid Cooled Communications


SAES-K-003
A6 Shelters shall be recorded in accordance with the requirements of
Para.7.3
paragraph 6.9.

Page 1 of 3
SAUDI ARAMCO ID/PID - 18-May-05 -REV 0 (Standards Cutoff -March 2013) Rev 7 31-Mar-13
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Passively Cooled Shelter Installation Inspection SAIC-K-4035 30-Apr-13 HVAC
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

The Battery Room of the Hybrid Cooled Communications Shelters


shall be provided with a separate cooling system to maintain a 33°C
maximum indoor air temperature when the Summer Night Dry Bulb
Temperature (SNDBT) is equal or less than 31°C. Exception: SAES-K-003
A7
Communication Engineering & Technical Support Department / Para.7.4.1
Facilities Engineering Group shall be consulted to obtain the required
design temperature of the Battery Room for communications shelter
located in areas with SNDBT higher than 32°C.

The Battery Room shall not have any ventilation opening or fan that SAES-K-003
A8
would compromise the effectiveness of the hybrid cooling system. Para. 7.4.2

The recorder shall have the capability of continuously recording for a


SAES-K-003
A9 minimum duration of six months and shall have the capability of
Para. 6.9.2
being accessed remotely through Saudi Aramco IT network.

The temperature measurements shall be performed 1.5 m above the


floor and 0.4 m in front of the equipment. The temperature and SAES-K-003
A10
humidity measurements shall be performed at 1.5 m (±0.3 m) above Para 5.8 6.9.3
the floor and 0.1 m (±0.3 m) away from the equipment.

Factory-built Passively Cooled Shelters with their cooling systems


shall be subjected to a Thermal Performance Test at the factory
SAES-K-003
A11 under simulated indoor thermal load and ambient air temperature
Para 6.4.1 7.6.1
conditions to ensure that the indoor air temperature limit requirement
will not be exceeded.

Cooling systems of Shelters built on site shall also be subjected to a


factory Thermal Performance Test, and it shall be guaranteed by the
manufacturer of the cooling system that the indoor air temperature of
the site-built Shelter will not exceed the temperature limit required.
SAES-K-003
A12 Cooling systems of Shelters built on site shall also be subjected to a
Para 6.4.2 7.6.2
factory Thermal Performance Test, and it shall be guaranteed by the
manufacturer of the cooling system that the indoor air temperature of
the site-built Shelters shall not exceed the temperature limit stated in
paragraphs 7.2 and 7.4.1.

Insulation of refrigerant pipes exposed to outdoors shall be provided


SAES-K-003
A13 with galvanized steel or aluminum sheet metal cladding, fastened
Para 5.10 6.11
with corrosion resistant metal straps or screws.

REMARKS:

REFERENCE DOCUMENTS:

1-SAES-K-003 -- Air Conditioning Systems For Communications Buildings, 31 May, 2004 Facilities & Data Centers 19 December 2010

2-SAES-K-001 -- Heating, Ventilating and Air Conditioning (HVAC), 05 July 2009 Design and Installation of Heating,
Ventilating and Air Conditioning Systems 5 December 2012

Contractor / Third-Party Saudi Aramco

Page 2 of 3
Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED