1(a) Drilling of 165mm dia borewell in all soils including all 3 x 75.0 M 140.00 Rmt 31500.00
charges etc complete ,
(b) Inserting of 180mm dia 6kg/cm2 pvc casing pipe 3 x 20.0 M 330.00 Rmt 19800.00
including all charges etc complete
(c) Geological survey charges for borewell 3 x 1.0 Nos 500.00 Each 1500.00
TOTAL 340000.00
For pannel Board consisting of above components for 3- phase motor 3 x 1.0 No 4900.00 each 14700.00
suitable up to 7.5 HP with DOL starter and suitable range of capacitor
and switch fuse units as above
3 Supply of Galvanised mild steel pipes (Medium class) of 50 mm dia 3 x 45.0 M 208.00 Rmt 28080.00
Nominal bore confirming to IS 1239/part - 1 1990 constinuosley welded
ERW/HFTW type and screwel at both ends as per IS 554 and end fitted
with socket (Heavy class) as per IS 1239/part - II / 1992 and the end
fitted with plastic ring exact length of 3.00 Mt + 5% etc., complete.
4 Supply and delivery of PVC insulated and PVC shealthed flexible - 3 3 x 60.0 M 38.00 Rmt 6840.00
Core Flat type submersible cable suitable for submersible pump set
conductors composed of ennealed high conductivity copper wire,
confirming to IS 694 with its revisions and Ammendments from time to
time, etc., complete 3 Core 2.5 Sqmm
5 Supply and delivery of 50 mm dia GI Non Return vlave confirming ISI 3 x 1.0 No 480.00 each 1440.00
specification
6 Supply and delivery of 7/20 Serivce wire of Reputed make etc., 3 x 90.0 M 11.00 Rmt 2970.00
complete.
7 Supply and delivery of G.I Bend heavy duty 'C' class threaded at both 3 x 1.0 No 60.00 each 180.00
ends of 50x90mm with arm length of 20 cm
8 Supply and delivery of 50 mm dia MS clamp set 450 mm length, 12 mm 3 x 2.0 Sets 145.00 each 870.00
thick plate, 75 mm vide with 6 Nos of 16 mm bolts & nuts
9 Supply and delivery of mild steel threaded flanges 50 mm dia MS flange 3 x 1.0 Set 99.00 each 297.00
set (2nos) of 150 mm dia 12 mm thick of (flange) with 4 nos 15 mm dia
bolts & nuts
10 Supply and fixing of MS bore well cover to suit 165 mm dia bore well 3 x 1.0 No 100.00 each 300.00
including all charges complete.
11 Installation Errection Earthing testing and Commissioning of 3 x 1.0 Job 1500.00 each 4500.00
Submersible pump set including conveyance of all materials to work site
including fixing of G.I pipes valves, specials and all other related items
but excluding cost of GI pipes, valves, and specials etc., with a trial run
of one week.
TOTAL 114954.00
B)
It is to be exprassively understood that the measured work is to be taken not (with standing any custom practise to the contractor) according to the actual quantities when
in place and finished work according to the drawing or as may be ordered as per from the time to time by the Divisional Engineer, P.R from time to time and the cost
calculated by measurements or weight at their respective prices without any additional charges for any necessary or contingent work connected therewith. The rates as
per the work in with and compeleted in every respect.
Name of the VDC/HWC : Sri.R.Shankar Goud R/o Battapur Amount of Contract : 188133.00
Sl.No Qty Description of item APDSS No Rate Per Amount
1 2 3 4 5 6 7
Providing pipeline for water supply with HDPE pipes as per IS 4984/1995. With its
ammendments and revisions there on including supply of pipes, specials, as per
requirements, trench exvacation for pipeplines in all soils except Rock lowering, laying and
jointing of pipelines true to aligment and gradient, and refilling trenches with excavated earth
and filling pipeline with water and testing etc., complete. The rates are inclusive of cost,
conveyance of all materials and labour charges needed for finished pipeline
work.includingVAT, C.E.D & APGST Charges charges.
TOTAL 188133.00
1) INTRODUCTION:- The Habitation is located in Armor mandal and is _____ km from the mandal head
quarters. The population of the village as per 2001 cencus is __________
a) Drilling of 165mm dia borewell with 180mm dia 6Kg/cm2 PVC casing pipe
b) Submersible pumpset 5HP/10 Stages with all accessories
c)Providing Pumping main with 75 mm dia 6 kg/cm2 HDPE Pipe line
d)LS provision for GI & HDPE Connections& Valve chambers
6) CONCLUSION:-With the above Items of work, the estimate is preapared with common SSR 2005-06
worked out to Rs 3.40 Lakhs.
pipes and trench excavation for earth work excavation in all types of soils except hard rock which required partial blasting and
depositing on bank with initial lead of 10 mts and lift of 2mts laying of pipes carefully into trench and laying in alingment and gradient
jointing the pipeline with materials including refilling the trench with excavated soils removal of surplus earth from the soil testing the
pipeline to hydraulic field test pressure including 16.32% CED& 4% VATcharges etc complete for finished item of work. (Trench size
is 0.50x0.75 for 63 to 75mm dia pipe, 0.70x1.00 for 90 to 140mm dia and 0.80x110 for 160mm to 200mm dia).
( HDPE - PE 80 grade)
E/W/E Rate - (9b+12b+13b)/3 = (28.50+30.50+31.50) / 3 =30.17/1 cum
63 mm dia 75mm dia 90 mm dia 110 mm dia 125 mm dia 140 mm dia 160 mm dia
Description of Item 4Kg/ 6Kg/ 4Kg/ 6Kg/ 4Kg/ 6Kg/ 4Kg/ 6Kg/ 4Kg/ 6Kg/ 4Kg/ 6Kg/ 4Kg/ CM2 6Kg/ CM2
CM2 CM2 CM2 CM2 CM2 CM2 CM2 CM2 CM2 CM2 CM2 CM2
Cost of Materials
A Cost of pipes including 16.32% CED & 4 % VAT 48.53 67.50 66.33 95.83 95.97 136.15 143.51 204.17 184.17 261.39 228.02 327.43 298.75 427.09
C 120% - 75% extra for narrow foundation 13.58 13.58 13.58 13.58 15.84 15.84 15.84 15.84 15.84 15.84 15.84 15.84 19.91 19.91
D Lowering laying and jointing of pipes 4.54 4.54 5.40 5.40 7.38 7.38 9.02 9.02 10.25 10.25 11.48 11.48 13.12 13.12
E Refilling charges at 7.10/Cum 2.66 2.66 2.66 2.66 4.97 4.97 4.97 4.97 4.97 4.97 4.97 4.97 6.25 6.25
F Testing charges 1.89 1.89 2.25 2.25 3.60 3.60 4.40 4.40 5.00 5.00 5.60 5.60 6.40 6.40
33.98 33.98 35.20 35.20 52.91 52.91 55.35 55.35 57.18 57.18 59.01 59.01 72.23 72.23
Total 82.51 101.48 101.53 131.03 148.88 189.06 198.86 259.52 241.35 318.57 287.03 386.44 370.98 499.32
Add VAT @ 4% on civil work 1.36 1.36 1.41 1.41 2.12 2.12 2.21 2.21 2.29 2.29 2.36 2.36 2.89 2.89
Finished Item of Rate 83.87 102.84 102.94 132.44 150.99 191.17 201.07 261.73 243.64 320.86 289.39 388.80 373.87 502.21
75 mm dia 6 kg/cm2 PE-80 Grade HDPE Pipe line 1200.00 M 132.44 Rmt 158928.00