Casting Plan AI-CB2-C-CT-0003
For
Cooling Tower 4nd Segmen
Rev. 0 Page 1 / 13
TABLE OF CONTENTS
2. GENERAL DESCRIPTION
3. WORK METHOD
6. QUALITY PLAN
CRAFT OF NIGHT
No. DAY SHIFT Remarks
EMPLOYER SHIFT
1 Super visor 1 1
Dewa+Vibrator+Lighting
2 Electrician 2 2
CRAFT OF NIGHT
No. DAY SHIFT Remarks
EMPLOYER SHIFT
6 Rebar worker 3 3
7 HSE staff 2 2
8 QC 1 1
9 Traffic control 3 3
10 Road cleaning 3 3
11 Dewatering team 1 1
Total 50 50
1.2 Equipment
2. GENERAL
A. TOTAL VOLUME
1) V= 1107 ㎥
2) V/ 3 Pump cars ≒ 1170 ㎥ / 7 ㎥ ≒ 159 Mixer Trucks / Pump Car
ELECTRICAL PLAN
Doc No. :
Casting Plan AI-CB2-C-CT-0003
For
Cooling Tower 4nd Segmen
Rev. 0 Page 7 / 13
MPa % kg/㎥
35 37 40.1 160 432 302 130 670 1000 5.62
3.3.1 Planning
A pre-concreting meeting will be held internally and with concrete supplier to
finalize all of the proposed concreting procedure in advance.
3.3.4 Casting
The Concrete will be placed in a predetermined layering sequence;
approximately 50 cm, to avoid any possibility of cold joint we must pouring 1
segmen on 1 times. It is approximately the time spent in each poured layer will
be not exceeded 60 minutes.
In case of sudden rain, plastic sheeting or canvas will be used to cover the concrete
top surface. The plastic sheets will be provided sufficiently both for emergency case
of sudden rain and for fully cover the whole concrete surface immediately.
Pre-pour inspection of the rebar, form panels, embedded items and construction
joints will be carried out before concrete pouring.
Three (3) concrete pumps and One (1) back-up pump car will be engaged for
concrete pouring e.g. 3 pumps is organized for concrete pouring; 1 pump will be at
the workface for standby and will be on duty when the pouring pump is trouble or
breakdown. The concrete pump arrangement will be prior arrangement for their
highest efficiency when the concrete placement is to be carried.
Electric-type concrete vibrators will be used for concrete compaction during
concrete placing to ensure adequate vibration keeping each 50 cm distance during
the entire pouring stage with sufficient quantity (Refer to clause 4.2 Equipment) and
continue finish with trowel so concrete can levelling, for safety worker required for
use rubber shoes. Provide water tank for do curing and finish concrete trowel
machine.
Mechanical disturbance of concrete during the specified curing period and damaged
to finished concrete shall be prevented. After completing placing and finishing
operations, efforts must continue to protect the concrete from high temperature,
Doc No. :
Casting Plan AI-CB2-C-CT-0003
For
Cooling Tower 4nd Segmen
Rev. 0 Page 11 / 13
direct sunlight, low humidity and drying winds. If possible, the work should be kept in
a uniformly moderate temperature condition to allow the concrete to develop its full-
strength potential.
The concrete should also be protected against thermal-shrinkage cracking from
rapid temperature drops, particularly during the first 24 hours.
0.5 m
The combined protection material as below will be used for curing purposes. This
will be done immediately once the concrete is reached its stiffening time by fully
cover the whole concrete surface onto the whole to prevent concrete temperature
loss too quick and result high temperature differential between the surface and at
the middle. Care must be taken during the entire curing (for 7 days) to ensure.
addition, form tie holes can be filled and any necessary repairs made by uncovering
a small portion of the concrete at a time to carry on this work with approved
materials. These repairs should be completed in the first few days after stripping so
the repairs and tie-hole fillings can cure with the surrounding concrete.