Vous êtes sur la page 1sur 2

Applications Requirements – Liquid Cooled Generator Sets

Generator set installation checklist Cooling System


Set mounted radiator
Enclosed or containerized generator
This checklist should be used to validate the completion of
Radiator air outlet clean, free from obstruction …
a generator set installation, prior to commissioning. A Coolant overflow clear and routed to avoid pollution …
check-list should be completed for each generator of a Check for possibility of hot air recirculation …
multiple installation.
Remote / roof mounted radiator systems
Project Details Header tank is of adequate size …
Project Name ...………………………………………………… Overflow is clear and routed to avoid spillage …
………………………………………...…….…………………… Static/friction head is within engine/system capability …
Customer (End User).…………………………………..……... Engine vent pipes inclined toward radiator / header …
…………………..……………………………………………….. Fuel cooler installed if required …
Address of Site …………………...……………………………. Pipework avoids air locks – air bleed valves provided …
…………………………………………………………………… Pipework isolated from generator set vibration …
…………………..………………………………………………. Pipework complete, cleaned, tested & painted …
Tel. No ………………………..………………………………… Enclosure penetrations properly sealed …
Auxiliary supply to fans correctly installed …
Email…………………………………………………………….
Electrical bonding completed …
Heat exchanger & cooling tower systems
Generator set details
Generator set model.…………………………………………..
Header tank is of adequate size …
Overflow is clear and routed to avoid spillage …
Generator set serial number………………….Set no……….
Static/friction head is within engine/system capability …
Control type……………………………………………………...
Engine vent pipes inclined toward radiator / header …
Control serial number…………………………………………..
Fuel cooler installed if required …
System control type (if applicable)……………………………
Pipework avoids air locks – air bleed valves provided …
Pipework isolated from generator set vibration …
Generator site and services Pipework complete, cleaned, tested & painted …
Installation work complete … Enclosure penetrations properly sealed …
Site clean & clear from obstruction & secure … Secondary cooling system is complete …
Site services complete & commissioned … Cooling tower make-up supply is complete …
(lightning, electrical auxiliary supplies, water, etc.)
Auxiliary supply to fans correctly installed …
Observations…………………………………………………....
Electrical bonding completed …
……………………………………………………………………

Fuel System
Site general
Bulk storage facility
Enclosure sited in open air on level, firm ground …
No loose materials near to generator set … Bulk storage tank installation complete …
Air intake / exit paths clear and clean … Bulk tank incorporates water trap …
Access & egress routes unobstructed … Spillage containment complete …
Soil / sand covered to prevent dust (gravel, etc) … Isolating valves correctly positioned …
Site drainage adequate … Tank contents gauge installed …
Pipework and cables are secure with no trip hazards … Content alarm contacts fitted & wired …
Electrical bonding complete … Transfer pump installed and connected …
All key components are labelled … Solenoid & pre-filter between bulk & service tank …
Pipework and services colour coded & labelled … Pipework correct material, cleaned, tested & painted …
External spillage control adequate for fluid capacity … Vent installed, piped to safe area and open …
Electrical bonding completed …
Insulation & pipeline heating installed …
Fill point installed & alarm fitted …
Document Number: PGK FCD 04-0182 1 Installation checklist – enclosed sets V1.0
© 2004 Cummins Power Generation Ltd
Applications Requirements – Liquid Cooled Generator Sets

Storage facility secure … Joints welded or flanges secure with correct gaskets …
Installation with day tank (within / near enclosure) Muffler correctly supported …
Positive head at engine for critical applications … Stack/tail pipe prevents rain/snow ingress …
Connection to fill, overflow & vent lines completed … Condensate drain provided …
Overflow head of fuel within tank pressure limits … Exit directed away from buildings / personnel …
Enclosure penetrations properly sealed … System is lagged & clad as required …
Fire valves & contacts installed & wired … Enclosure weathering complete & sealed …
Installations without day tank Flammable materials properly protected …
Positive head at engine for critical applications …
Fuel inlet head/restriction within engine limits … Ventilation & attenuation
Fuel return head/restriction within engine limits … Installation design prevents hot air recirculation …
Isolating and solenoid valves fitted … Installation design accounts for prevailing wind …
Check for no valves in spill return … Air exit directed away from buildings / personnel …
Flexible connections to engine … Forced ventilation systems wired …
Electrical bonding complete … Louver mechanisms complete & wired as required …
Enclosure penetrations properly sealed … Bird guard is fitted to intake & outlet …
Spillage containment complete & alarms wired …
Fire valves & contacts installed & wired …
Electrical system
Control system
Gaseous fuel system
Field wiring to set mounted control complete …
Pipework complete, material and construction correct …
Customer wiring to set mounted control complete …
Regulator and shut-off valves in correct locations …
Interconnection to remote control complete …
Enclosure penetrations properly sealed …
Remote emergency stop controls wired …
Leak test and certification complete …
Generator / Switchgear / Changeover / Transfer
Means of disconnection / isolation provided …
Fire alarm / suppression system Switchgear installation & pre-testing completed …
System installation + remote alarms complete … Cables installed correctly, marked, allow movement …
Sensors protected from radiant heat … Enclosure penetrations properly sealed …
Labelling and lock off system complete … Power connections complete & torque-marked …
Cable tests complete & certificates available …
Starting system Enclosure
Battery starting All electrical boxes clean & covers replaced …
Starting batteries correct & installed on tray or stand … Auxiliary electrical supply complete …
Battery cables to engine routed correctly … Grounding system complete & tested …
Battery charger installed & wired … Electrical bonding of services / assemblies complete …
Compressed air / hydraulic starting Utility supply available as required …
Compressor set installed and wired … Small power & lighting circuits tested & certificated …
Compressed air pipework correctly rated & installed …
Isolating valves correctly positioned & labelled …
Pipework tested, painted & labelled …
Correct pressure regulator & LP safety valve …
Flexible connection to engine fitted … Checklist completed by ……………………………………….
Date……………………………………………………………...
Exhaust system Print Name………………………………………………………
Installation design prevents exhaust recirculation … Company………………………………………………………..
Installation allows for pipework expansion … Note: Completion of this checklist does not relieve the installer of contractual
obligations.

Document Number: PGK FCD 04-0182 2 Installation checklist – enclosed sets V1.0
© 2004 Cummins Power Generation Ltd

Vous aimerez peut-être aussi