Académique Documents
Professionnel Documents
Culture Documents
Fuel System
Site general
Bulk storage facility
Enclosure sited in open air on level, firm ground
No loose materials near to generator set
Bulk storage tank installation complete
Air intake / exit paths clear and clean
Bulk tank incorporates water trap
Access & egress routes unobstructed
Spillage containment complete
Soil / sand covered to prevent dust (gravel, etc)
Isolating valves correctly positioned
Site drainage adequate
Tank contents gauge installed
Pipework and cables are secure with no trip hazards
Content alarm contacts fitted & wired
Electrical bonding complete
Transfer pump installed and connected
All key components are labelled
Solenoid & pre-filter between bulk & service tank
Pipework and services colour coded & labelled
Pipework correct material, cleaned, tested & painted
External spillage control adequate for fluid capacity
Vent installed, piped to safe area and open
Electrical bonding completed
Insulation & pipeline heating installed
Fill point installed & alarm fitted
Document Number: PGK FCD 04-0182 1 Installation checklist – enclosed sets V1.0
© 2004 Cummins Power Generation Ltd
Applications Requirements – Liquid Cooled Generator Sets
Storage facility secure
Joints welded or flanges secure with correct gaskets
Installation with day tank (within / near enclosure) Muffler correctly supported
Positive head at engine for critical applications
Stack/tail pipe prevents rain/snow ingress
Connection to fill, overflow & vent lines completed
Condensate drain provided
Overflow head of fuel within tank pressure limits
Exit directed away from buildings / personnel
Enclosure penetrations properly sealed
System is lagged & clad as required
Fire valves & contacts installed & wired
Enclosure weathering complete & sealed
Installations without day tank Flammable materials properly protected
Positive head at engine for critical applications
Fuel inlet head/restriction within engine limits
Ventilation & attenuation
Fuel return head/restriction within engine limits
Installation design prevents hot air recirculation
Isolating and solenoid valves fitted
Installation design accounts for prevailing wind
Check for no valves in spill return
Air exit directed away from buildings / personnel
Flexible connections to engine
Forced ventilation systems wired
Electrical bonding complete
Louver mechanisms complete & wired as required
Enclosure penetrations properly sealed
Bird guard is fitted to intake & outlet
Spillage containment complete & alarms wired
Fire valves & contacts installed & wired
Electrical system
Control system
Gaseous fuel system
Field wiring to set mounted control complete
Pipework complete, material and construction correct
Customer wiring to set mounted control complete
Regulator and shut-off valves in correct locations
Interconnection to remote control complete
Enclosure penetrations properly sealed
Remote emergency stop controls wired
Leak test and certification complete
Generator / Switchgear / Changeover / Transfer
Means of disconnection / isolation provided
Fire alarm / suppression system Switchgear installation & pre-testing completed
System installation + remote alarms complete
Cables installed correctly, marked, allow movement
Sensors protected from radiant heat
Enclosure penetrations properly sealed
Labelling and lock off system complete
Power connections complete & torque-marked
Cable tests complete & certificates available
Starting system Enclosure
Battery starting All electrical boxes clean & covers replaced
Starting batteries correct & installed on tray or stand
Auxiliary electrical supply complete
Battery cables to engine routed correctly
Grounding system complete & tested
Battery charger installed & wired
Electrical bonding of services / assemblies complete
Compressed air / hydraulic starting Utility supply available as required
Compressor set installed and wired
Small power & lighting circuits tested & certificated
Compressed air pipework correctly rated & installed
Isolating valves correctly positioned & labelled
Pipework tested, painted & labelled
Correct pressure regulator & LP safety valve
Flexible connection to engine fitted
Checklist completed by ……………………………………….
Date……………………………………………………………...
Exhaust system Print Name………………………………………………………
Installation design prevents exhaust recirculation
Company………………………………………………………..
Installation allows for pipework expansion
Note: Completion of this checklist does not relieve the installer of contractual
obligations.
Document Number: PGK FCD 04-0182 2 Installation checklist – enclosed sets V1.0
© 2004 Cummins Power Generation Ltd