CONSTRUCCION DE INFRAESTRUCTURA VIAL EN LA AV. ANDRES AVELINO CÁCERES (TRAMO JR. PACHACUTEC - AV. LOS GERANIOS) DE LA CIUDAD
PROYECTO:
DE JULIACA, PROVINCIA DE SAN ROMAN - PUNO (SEGUNDA ETAPA)
01.02.01.01 SEGURIDAD DURANTE LA CONSTRUCCION Und 1 --- --- --- 1.00 1.00
Cinta de seguridad color amarillo 2 --- --- --- 2.00
Malla de seguridad color naranja 2 --- --- --- 2.00
Tanquera de madera 7 --- --- --- 7.00
01.02.03 DEMOLICIONES
01.02.03.01 DEMOLICION DE BUZONES M3 2.86
Buzon (1) - Av. Andres Avelino Caceres 1 Area= 0.64 0.07 0.04
Buzon (4) - Av. Andres Avelino Caceres 1 Area= 0.64 0.41 0.26
Buzon (5) - Av. Andres Avelino Caceres 1 Area= 0.64 0.41 0.26
Buzon (6) - Av. Andres Avelino Caceres 1 Area= 0.64 0.34 0.22
PLANILLA DE METRADOS
CONSTRUCCION DE INFRAESTRUCTURA VIAL EN LA AV. ANDRES AVELINO CÁCERES (TRAMO JR. PACHACUTEC - AV. LOS GERANIOS) DE LA CIUDAD
PROYECTO:
DE JULIACA, PROVINCIA DE SAN ROMAN - PUNO (SEGUNDA ETAPA)
Buzon (7) - Av. Andres Avelino Caceres 1 Area= 0.64 0.08 0.05
Buzon (11) - Av. Andres Avelino Caceres 1 Area= 0.64 0.58 0.37
Buzon (12) - Av. Andres Avelino Caceres 1 Area= 0.64 0.79 0.50
Buzon (13) - Av. Andres Avelino Caceres 1 Area= 0.64 0.56 0.36
Buzon (14) - Av. Andres Avelino Caceres 1 Area= 0.64 0.55 0.35
Buzon (15) - Av. Andres Avelino Caceres 1 Area= 0.64 0.32 0.21
Buzon (16) - Av. Andres Avelino Caceres 1 Area= 0.64 0.38 0.24
01.03.02 EXCAVACIONES
01.03.02.01 EXCAVACION EN FORMA MANUAL M3 463.61
Av. Andres Avelino Caceres (Jr. Machupicchu - Av. Tupac Yupanqui) 1 986.06 10.10 0.02 199.18
Av. Andres Avelino Caceres (Jr. Machupicchu - Av. Tupac Yupanqui) 1 1,011.02 10.10 0.02 204.23
Av. Andres Avelino Caceres (Centro 1) 1 4.00 16.00 0.02 1.28
Av. Andres Avelino Caceres (Centro 2) 1 20.00 16.00 0.02 6.40
Av. Andres Avelino Caceres (Centro 3) 1 23.00 16.00 0.02 7.36
Av. Andres Avelino Caceres (Centro 4) 1 27.52 16.00 0.02 8.80
Av. Andres Avelino Caceres (Centro 5) 1 36.70 14.74 0.02 10.82
Av. Andres Avelino Caceres (Centro 6) 1 29.31 10.40 0.02 6.10
Av. Andres Avelino Caceres (Centro 7) 1 34.73 10.40 0.02 7.22
Jr. Marcapata 1 61.82 9.88 0.02 12.21
CONSTRUCCION DE INFRAESTRUCTURA VIAL EN LA AV. ANDRES AVELINO CÁCERES (TRAMO JR. PACHACUTEC - AV. LOS GERANIOS) DE LA CIUDAD
PROYECTO:
DE JULIACA, PROVINCIA DE SAN ROMAN - PUNO (SEGUNDA ETAPA)
01.04. PAVIMENTO
01.04.01 SUB RASANTE
01.04.01.01 MATERIAL DE SUB RASANTE: CANTERA M3 7,653.28
Av. Andres Avelino Caceres (Jr. Machupicchu - Av. Tupac Yupanqui) 1 986.06 10.10 0.44 4,347.18
Av. Andres Avelino Caceres (Jr. Machupicchu - Av. Tupac Yupanqui) 1 1,011.02 10.10 0.44 4,457.23
Av. Andres Avelino Caceres (Centro 1) 1 4.00 16.00 0.44 27.94
PLANILLA DE METRADOS
CONSTRUCCION DE INFRAESTRUCTURA VIAL EN LA AV. ANDRES AVELINO CÁCERES (TRAMO JR. PACHACUTEC - AV. LOS GERANIOS) DE LA CIUDAD
PROYECTO:
DE JULIACA, PROVINCIA DE SAN ROMAN - PUNO (SEGUNDA ETAPA)
CONSTRUCCION DE INFRAESTRUCTURA VIAL EN LA AV. ANDRES AVELINO CÁCERES (TRAMO JR. PACHACUTEC - AV. LOS GERANIOS) DE LA CIUDAD
PROYECTO:
DE JULIACA, PROVINCIA DE SAN ROMAN - PUNO (SEGUNDA ETAPA)
01.04.03 BASE
01.04.03.01 MATERIAL SELECCIONADO M3 2,410.76
Av. Andres Avelino Caceres (Jr. Machupicchu - Av. Tupac Yupanqui) 1 986.06 10.10 0.08 796.73
Av. Andres Avelino Caceres (Jr. Machupicchu - Av. Tupac Yupanqui) 1 1,011.02 10.10 0.08 816.90
Av. Andres Avelino Caceres (Centro 1) 1 4.00 16.00 0.08 5.12
Av. Andres Avelino Caceres (Centro 2) 1 20.00 16.00 0.08 25.60
Av. Andres Avelino Caceres (Centro 3) 1 23.00 16.00 0.08 29.44
Av. Andres Avelino Caceres (Centro 4) 1 27.52 16.00 0.08 35.22
Av. Andres Avelino Caceres (Centro 5) 1 36.70 14.74 0.08 43.27
Av. Andres Avelino Caceres (Centro 6) 1 29.31 10.40 0.08 24.39
Av. Andres Avelino Caceres (Centro 7) 1 34.73 10.40 0.08 28.90
Jr. Marcapata 1 61.82 9.88 0.08 48.84
CONSTRUCCION DE INFRAESTRUCTURA VIAL EN LA AV. ANDRES AVELINO CÁCERES (TRAMO JR. PACHACUTEC - AV. LOS GERANIOS) DE LA CIUDAD
PROYECTO:
DE JULIACA, PROVINCIA DE SAN ROMAN - PUNO (SEGUNDA ETAPA)
CONSTRUCCION DE INFRAESTRUCTURA VIAL EN LA AV. ANDRES AVELINO CÁCERES (TRAMO JR. PACHACUTEC - AV. LOS GERANIOS) DE LA CIUDAD
PROYECTO:
DE JULIACA, PROVINCIA DE SAN ROMAN - PUNO (SEGUNDA ETAPA)
CONSTRUCCION DE INFRAESTRUCTURA VIAL EN LA AV. ANDRES AVELINO CÁCERES (TRAMO JR. PACHACUTEC - AV. LOS GERANIOS) DE LA CIUDAD
PROYECTO:
DE JULIACA, PROVINCIA DE SAN ROMAN - PUNO (SEGUNDA ETAPA)
Buzon (3) - Av. Andres Avelino Caceres 1 Perím= 4.71 --- 4.71
Buzon (4) - Av. Andres Avelino Caceres 1 Perím= 4.71 --- 4.71
Buzon (5) - Av. Andres Avelino Caceres 1 Perím= 4.71 --- 4.71
Buzon (6) - Av. Andres Avelino Caceres 1 Perím= 4.71 --- 4.71
Buzon (7) - Av. Andres Avelino Caceres 1 Perím= 4.71 --- 4.71
Buzon (8) - Av. Andres Avelino Caceres 1 Perím= 4.71 --- 4.71
Buzon (9) - Av. Andres Avelino Caceres 1 Perím= 4.71 --- 4.71
Buzon (10) - Av. Andres Avelino Caceres 1 Perím= 4.71 --- 4.71
Buzon (11) - Av. Andres Avelino Caceres 1 Perím= 4.71 --- 4.71
Buzon (12) - Av. Andres Avelino Caceres 1 Perím= 4.71 --- 4.71
Buzon (13) - Av. Andres Avelino Caceres 1 Perím= 4.71 --- 4.71
Buzon (14) - Av. Andres Avelino Caceres 1 Perím= 4.71 --- 4.71
Buzon (15) - Av. Andres Avelino Caceres 1 Perím= 4.71 --- 4.71
Buzon (16) - Av. Andres Avelino Caceres 1 Perím= 4.71 --- 4.71
CONSTRUCCION DE INFRAESTRUCTURA VIAL EN LA AV. ANDRES AVELINO CÁCERES (TRAMO JR. PACHACUTEC - AV. LOS GERANIOS) DE LA CIUDAD
PROYECTO:
DE JULIACA, PROVINCIA DE SAN ROMAN - PUNO (SEGUNDA ETAPA)
Entre: Av. Hipolito Unanue - Av. Los Geranios 5 --- --- --- 5.00
Entre: Av. Los Geranios - Av. Tupac Yupanqui 2 --- --- --- 2.00
CONSTRUCCION DE INFRAESTRUCTURA VIAL EN LA AV. ANDRES AVELINO CÁCERES (TRAMO JR. PACHACUTEC - AV. LOS GERANIOS) DE LA CIUDAD
PROYECTO:
DE JULIACA, PROVINCIA DE SAN ROMAN - PUNO (SEGUNDA ETAPA)
CONSTRUCCION DE INFRAESTRUCTURA VIAL EN LA AV. ANDRES AVELINO CÁCERES (TRAMO JR. PACHACUTEC - AV. LOS GERANIOS) DE LA CIUDAD
PROYECTO
DE JULIACA, PROVINCIA DE SAN ROMAN - PUNO (SEGUNDA ETAPA)
02 CONSTRUCCION DE VEREDAS
02.01. OBRAS PRELIMINARES
02.01.01 TRAZO, NIVELACIÓN Y REPLANTEO
02.01.01.01 TRAZO Y REPLANTEO DURANTE LA CONSTRUCCIÓN M2 8,397.82
En veredas acabado coloreado - frotachado incluye rampas 1 Area= 8,397.82 --- 8,397.82
CONSTRUCCION DE INFRAESTRUCTURA VIAL EN LA AV. ANDRES AVELINO CÁCERES (TRAMO JR. PACHACUTEC - AV. LOS GERANIOS) DE LA CIUDAD
PROYECTO
DE JULIACA, PROVINCIA DE SAN ROMAN - PUNO (SEGUNDA ETAPA)
CONSTRUCCION DE INFRAESTRUCTURA VIAL EN LA AV. ANDRES AVELINO CÁCERES (TRAMO JR. PACHACUTEC - AV. LOS GERANIOS) DE LA CIUDAD
PROYECTO
DE JULIACA, PROVINCIA DE SAN ROMAN - PUNO (SEGUNDA ETAPA)
02.03.02 VEREDAS
02.03.02.01 VEREDAS: CONCRETO F'C=175 KG/CM2, E=10 CM. ACA M2 7,952.86
Manzana (M-01) 1 Area= 587.797 --- 587.80
Manzana (M-02) 1 Area= 436.568 --- 436.57
Manzana (M-03) 1 Area= 310.921 --- 310.92
Manzana (M-04) 1 Area= 1,077.759 --- 1,077.76
Manzana (M-05) 1 Area= 250.304 --- 250.30
Manzana (M-06) 1 Area= 303.628 --- 303.63
Manzana (M-07) 1 Area= 1,814.696 --- 1,814.70
Manzana (M-08) 1 Area= 472.317 --- 472.32
Manzana (M-09) 1 Area= 466.308 --- 466.31
Manzana (M-10) 1 Area= 397.060 --- 397.06
Manzana (M-11) 1 Area= 309.788 --- 309.79
Manzana (M-12) 1 Area= 975.761 --- 975.76
Manzana (M-13) 1 Area= 445.096 --- 445.10
Area Verde 07 1 Area= 155.259 --- 155.26
CONSTRUCCION DE INFRAESTRUCTURA VIAL EN LA AV. ANDRES AVELINO CÁCERES (TRAMO JR. PACHACUTEC - AV. LOS GERANIOS) DE LA CIUDAD
PROYECTO
DE JULIACA, PROVINCIA DE SAN ROMAN - PUNO (SEGUNDA ETAPA)
02.03.03 RAMPAS
02.03.03.01 RAMPAS: CONCRETO F'C=175 KG/CM2, E=10 CM. BRUÑAD M2 50.40
RAMPA TIPO II
Manzana (M-01) 1 3.00 1.20 --- 3.60
Manzana (M-02) 1 3.00 1.20 --- 3.60
Manzana (M-03) 1 3.00 1.20 --- 3.60
Manzana (M-04) 1 3.00 1.20 --- 3.60
Manzana (M-05) 1 3.00 1.20 --- 3.60
Manzana (M-06) 0 3.00 1.20 --- 0.00
Manzana (M-07) 2 3.00 1.20 --- 7.20
Manzana (M-08) 1 3.00 1.20 --- 3.60
Manzana (M-09) 1 3.00 1.20 --- 3.60
Manzana (M-10) 1 3.00 1.20 --- 3.60
Manzana (M-11) 1 3.00 1.20 --- 3.60
PLANILLA DE METRADOS
CONSTRUCCION DE INFRAESTRUCTURA VIAL EN LA AV. ANDRES AVELINO CÁCERES (TRAMO JR. PACHACUTEC - AV. LOS GERANIOS) DE LA CIUDAD
PROYECTO
DE JULIACA, PROVINCIA DE SAN ROMAN - PUNO (SEGUNDA ETAPA)
CONSTRUCCION DE INFRAESTRUCTURA VIAL EN LA AV. ANDRES AVELINO CÁCERES (TRAMO JR. PACHACUTEC - AV. LOS GERANIOS) DE LA CIUDAD
PROYECTO
DE JULIACA, PROVINCIA DE SAN ROMAN - PUNO (SEGUNDA ETAPA)
CONSTRUCCION DE INFRAESTRUCTURA VIAL EN LA AV. ANDRES AVELINO CÁCERES (TRAMO JR. PACHACUTEC - AV. LOS GERANIOS) DE LA CIUDAD
PROYECTO
DE JULIACA, PROVINCIA DE SAN ROMAN - PUNO (SEGUNDA ETAPA)
03 CONSTRUCCION DE CUNETAS
03.01. OBRAS PRELIMINARES
03.01.01 TRAZO, NIVELACIÓN Y REPLANTEO
03.01.01.01 TRAZO Y REPLANTEO DURANTE LA CONSTRUCCIÓN M2 1,288.82
En cuneta tipo I 1 1,692.45 0.50 --- 846.22
En cuneta tipo II 1 227.19 1.00 --- 227.19
En cuneta tipo III 2 81.78 0.20 --- 32.71
Canal 1 158.04 1.00 --- 158.04
Sumidero 1 20.55 1.20 --- 24.66
CONSTRUCCION DE INFRAESTRUCTURA VIAL EN LA AV. ANDRES AVELINO CÁCERES (TRAMO JR. PACHACUTEC - AV. LOS GERANIOS) DE LA CIUDAD
PROYECTO
DE JULIACA, PROVINCIA DE SAN ROMAN - PUNO (SEGUNDA ETAPA)
CONSTRUCCION DE INFRAESTRUCTURA VIAL EN LA AV. ANDRES AVELINO CÁCERES (TRAMO JR. PACHACUTEC - AV. LOS GERANIOS) DE LA CIUDAD
PROYECTO
DE JULIACA, PROVINCIA DE SAN ROMAN - PUNO (SEGUNDA ETAPA)
CONSTRUCCION DE INFRAESTRUCTURA VIAL EN LA AV. ANDRES AVELINO CÁCERES (TRAMO JR. PACHACUTEC - AV. LOS GERANIOS) DE LA CIUDAD
PROYECTO
DE JULIACA, PROVINCIA DE SAN ROMAN - PUNO (SEGUNDA ETAPA)
Intersección: Av. Andres Avelino Caceres - Jr. Marcapata 1 34.906 Area= 0.20 6.98
7 1.00 Area= 0.20 1.40
Entre AV-01 y AV-02 1 25.884 Area= 0.20 5.18
9 1.00 Area= 0.20 1.80
Entre AV-02 y AV-03 1 28.644 Area= 0.20 5.73
10 1.00 Area= 0.20 2.00
Entre AV-03 y AV-04 1 33.156 Area= 0.20 6.63
12 1.00 Area= 0.20 2.40
03.04.02 CANAL
03.04.02.01 CANAL: CONCRETO F'C=210 KG/CM2 M3 101.12
Muro 2 157.9978 0.20 0.80 50.56
Fondo 1 157.9978 0.60 0.20 18.96
Tapa 1 157.9978 1.00 0.20 31.60
PLANILLA DE METRADOS
CONSTRUCCION DE INFRAESTRUCTURA VIAL EN LA AV. ANDRES AVELINO CÁCERES (TRAMO JR. PACHACUTEC - AV. LOS GERANIOS) DE LA CIUDAD
PROYECTO
DE JULIACA, PROVINCIA DE SAN ROMAN - PUNO (SEGUNDA ETAPA)
03.04.03 SUMIDEROS
03.04.03.01 SUMIDERO: CONCRETO F'C=210 KG/CM2 M3 11.72
Sumidero pequeño 1 Area= 2.168 1.20 2.60
2 Area= 5.695 0.20 2.28
2 8.30 0.120 0.17 0.34
-2 0.60 0.600 0.20 -0.14
CONSTRUCCION DE INFRAESTRUCTURA VIAL EN LA AV. ANDRES AVELINO CÁCERES (TRAMO JR. PACHACUTEC - AV. LOS GERANIOS) DE LA CIUDAD
PROYECTO
DE JULIACA, PROVINCIA DE SAN ROMAN - PUNO (SEGUNDA ETAPA)
CONSTRUCCION DE INFRAESTRUCTURA VIAL EN LA AV. ANDRES AVELINO CÁCERES (TRAMO JR. PACHACUTEC - AV. LOS GERANIOS) DE LA CIUDAD
PROYECTO
DE JULIACA, PROVINCIA DE SAN ROMAN - PUNO (SEGUNDA ETAPA)
04 SEÑALIZACION VIAL
04.01. OBRAS PRELIMINARES
04.01.01 TRAZO, NIVELACIÓN Y REPLANTEO
04.01.01.01 TRAZO Y REPLANTEO DURANTE LA CONSTRUCCIÓN M2 619.68
En señalizacion de via 1 Area = 619.68 --- 619.68
linea de parada
Av. Andres Avelino Caceres (Jr. Machupicchu - Av. Tupac Yupanqui), 7 9.50 0.50 --- 33.25
Av. Andres Avelino Caceres (Jr. Machupicchu - Av. Tupac Yupanqui), 7 9.50 0.50 --- 33.25
Jr. Marcapata (Jr. Hallasi - Av. Los Geranios) 0 9.50 0.50 --- 0.00
linea discontinua
Av. Andres Avelino Caceres (Jr. Machupicchu - Av. Tupac Yupanqui), 110 3.00 0.10 --- 33.00
Av. Andres Avelino Caceres (Jr. Machupicchu - Av. Tupac Yupanqui), 107 3.00 0.10 --- 32.10
Jr. Marcapata (Jr. Hallasi - Av. Los Geranios) 3 3.00 0.10 --- 0.90
PLANILLA DE METRADOS
CONSTRUCCION DE INFRAESTRUCTURA VIAL EN LA AV. ANDRES AVELINO CÁCERES (TRAMO JR. PACHACUTEC - AV. LOS GERANIOS) DE LA CIUDAD
PROYECTO
DE JULIACA, PROVINCIA DE SAN ROMAN - PUNO (SEGUNDA ETAPA)
Estacionamiento
Entre: Jr. Machupicchu - Jr. San Ambrosio 1 130.79 0.10 --- 13.08
Entre: Jr. San Ambrosio - Jr. Maria Parado de Bellido 1 89.06 0.10 --- 8.91
Entre: Jr. Maria Parado de Bellido - Jr. Collasuyo 1 42.83 0.10 --- 4.28
Entre: Jr. Collasuyo - Av. Hipolito Unanue 1 181.31 0.10 --- 18.13
Entre: Av. Hipolito Unanue - Jr. Caylloma 1 58.66 0.10 --- 5.87
Entre: Jr. Caylloma - Jr. Aricoma 1 89.00 0.10 --- 8.90
Entre: Jr. Aricoma - Av. Tupac Yupanqui 1 199.52 0.10 --- 19.95
Entre: Jr. Machupicchu - Jr. Vallecito 1 108.00 0.10 --- 10.80
Entre: Jr. Vallecito - Jr. Ocho de Enero 1 99.39 0.10 --- 9.94
Entre: Jr. Ocho de Enero - Jr. Jesus Caceres Velasquez 1 135.51 0.10 --- 13.55
Entre: Jr. Jesus Caceres Velasquez - Av. Hipolito Unanue 1 88.25 0.10 --- 8.82
Entre: Av. Hipolito Unanue - Av. Los Geranios 1 211.56 0.10 --- 21.16
Entre: Av. Los Geranios - Av. Tupac Yupanqui 1 189.89 0.10 --- 18.99
DE LA DESCRIPCION DE PARTIDA # Eletm # de Pz Longt 0.25 0.56 0.99 1.55 2.2 3.97
ø
PARTIDA Iguales x Elemt x Piez 1/4 3/8 1/2 5/8 3/4 1
0.94 - - - - - -
0.66 - - - - - -
ACERO LONGITUDINAL
0.10 20 ø 1/2 0.10 1/2 1 20 158.20 - - 3,164.00 - - -
158 - - - - - -
TAPA DE CANAL
ACERO TRANSVERSAL
0.94
0.14 632 ø 1/2 0.14 1/2 1 632 2.16 - - 1,365.12 - - -
0.94 - - - - - -
ACERO LONGITUDINAL
0.10 10 ø 1/2 0.10 1/2 1 10 158.20 - - 1,582.00 - - -
158 - - - - - -
DE LA DESCRIPCION DE PARTIDA # Eletm # de Pz Longt 0.25 0.56 0.99 1.55 2.2 3.97
ø
PARTIDA Iguales x Elemt x Piez 1/4 3/8 1/2 5/8 3/4 1
ACERO TRANSVERSAL
0.10 6 ø 1/2 0.10 1/2 1 6 1.14 - - 6.84 - - -
0.94 - - - - - -
ACERO LONGITUDINAL
TOTAL EN KG 7,677.43
TOTAL EN KG 7,677.43
PLANILLA DE METRADOS DE SUMIDERO
SUMIDERO GRANDE
ACERO TRANSVERSAL EXTERIOR
0.10 0.10
0.91 72 ø 3/8 0.91 3/8 1 72 3.16 - 227.52 - - - -
PLANILLA DE METRADOS DE SUMIDERO
1.14 - - - - - -