Doosan Heavy Industries

Vietnam
Dung Quat Economic Zone,
Binh Thuan, Binh Son, Quang Ngai,
Vietnam
T +84 55 5618 900
F +84 553 618 950

A 21-May-12 Danny J.Y.Jeong K.J.Lim For Information

Rev. Date Drawn Checked Approved Details of Revision

Owner :

AES-VCM MONG DUONG


POWER COMPANY LIMITED

Owner's Engineer :

Contractor :

Project : PC : T10206

MONG DUONG II 2 X 560MW (NET) COAL FIRED POWER PROJECT UAS : QE01

Unit : PO

KKS : ZEN
Title : T10206-QE01-POZEN__-040203 INSPECTION
AND TEST PLAN FOR Reg. No. 040203
CABLE TRAYS INSTALLATION Revision : A

Drawing No. : Page-No :


T10206-QE01-P0ZEN-040203 1 of 4

Page 1
Doc. No. T10206-QE01-POZEN-040203 Rev. A

ITP for Cable Tray Installation AES-VCM


Contractor DOOSAN 2 of 4

This note is only applicable for AES-VCM Mong Duong

Detailed Legend

S : Surveillance Point / DOOSAN / Subcontractor does not send a notification to AES-VCM Mong Duong
except for the first or last operation on the basis of each process. AES-VCM Mong Duong
could check the operation, if he is present at the site during the inspection by Doosan.

R : Report Review Point / DOOSAN / Subcontractor is required to prepare a certificate or document


attesting to the satisfactory performance of the related test or inspection for review by
AES-VCM Mong Duong.
Duong

W : Witness Point / DOOSAN / Subcontractor shall submit request for inspection to AES-VCM to
decide whether they will attend such inspection or not.

H : Hold Point / Downstream construction and other activities shall not proceed
without attendance or any written approval of AES-VCM Mong Duong.

NOTE : The Site ITP and all of the abovementioned reports will be kept available by
DOOSAN at anytime for control and or review by AES-VCM Mong Duong.

Page 2
Doc. No. T10206-QE01-POZEN-040203 Rev. A
Inspection & Test Plan for Cable Tray
Installation
AES-VCM
Contractor DOOSAN Page 3 of 4

Inspection & Test Activities


Specific Applicable drawing
Remarks
Item Name Oper. No. Inspection Process number, Standard Code number, Subcontractor DOOSAN AES-VCM Verification Document
(Allowable tolerance)
Specification
A Sign A Sign A Sign

Check the condition of cable Supports, Racks, Trays


A1 Packing List R R R Packing List N/A
and Trunking while receiving.
A.Material
Receipt Technical Specification,
Check size and type of the Supports, Racks, Trays Material Technical
A2 R R R T10206-YR02-POZEN- N/A
and Trunking with respect to the requisitions. Specification
14403

Check the installation is according to the designed Approved Construction


B1 H W W Refer to attached Checklist N/A
layout drawing & specification. Drawing T10206-YD04---

Check the levelling and alignment of tray and rack and Approved Construction
B2 H W W Refer to attached Checklist N/A
expansion joints if any are specified are in place. Drawing T10206-YD04---

No sharp edges cut to be permitted. Cutting edges of Approved Construction


B3 H W W Refer to attached Checklist N/A
trays/trunkings are touch-up painted. Drawing T10206-YD04---

B. Cable Ensure the gap between parallel runs is quite enough Approved Construction
Tray B4 H W W Refer to attached Checklist N/A
to accommodate the layer of cables. Drawing T10206-YD04---
Installation
Ensure there are no sharp 90 degrees bends are Approved Construction
B5 H W W Refer to attached Checklist N/A
made. Drawing T10206-YD04---

Ensure the cable trays numbered according to cable


Approved Construction
B6 trays route layout on which KKS nos. are indicated and H W W Refer to attached Checklist N/A
Drawing T10206-YD04---
explained.

Ensure the cable trays numbered according to


Approved Construction
B7 cable trays route layout on which KKS nos. are H W W Refer to attached Checklist N/A
Drawing T10206-YD04---
indicated and explained.

Abbreviation : S: Surveillance R: Report Review W: Witness Inspection H: Hold Inspection

Note : All inspection shall be performed in accordance with the approved Site Inspection and Test Plans/Project Specifications
Inspection Check List
Project : Cable Tray Installation Works Ref. No.
Drawing No. : Date :
Specific Location :

CHECK ITEM

Verification & Approval Observed


No Inspection elements Result
Yes No N/A / Remarks

Check the condition of cable Supports, Racks, Trays and Trunking while
1
receiving.

Check size and type of the Supports, Racks, Trays and Trunking with
2
respect to the requisitions.

Check the installation is according to the designed layout drawing &


3
specification.

Check the leveling & alignment of tray & rack and expansion joints if
4
any are specified are in place.

No sharp edges cut to be permitted. Cutting edges of trays/trunkings are


5
touch-up painted.

Ensure the gap between parallel runs is quite enough to accommodate the
6
layer of cables.

7 Ensure there are no sharp 90 degrees bends are made.

Ensure the cable trays numbered according to cable trays route


8
layout on which KKS nos. are indicated and explained.

Check whether the exclusive earth continuity between the trays /


9
trunking / racks where the joints are made.

Earth jumper cable with crimp type terminals to be fitted to all cable
10
tray joints.

Checked by : (Subcontractor DOOSAN Electrical Dept. DOOSAN QA/QC Dept. AES-VCM


Name & Signature Name & Signature Name & Signature Name & Signature
Position Position Position Position
Date Date Date Date

page 4