Académique Documents
Professionnel Documents
Culture Documents
FEASIBILITY STUDY ON
IED
Innovation Energie Développement
2 chemin de la Chauderaie
Francheville 69340, France
Tel. +33 (0)4 72 59 13 20
Fax. +33 (0)4 72 59 13 39
E-mail: ied@ied-sa.fr
Version 1 Version 2
Date 7 March 2008 28 March 2008
Written by TDV / PSAV/ GDC TDV / PSAV/ GDC
Reviewed by DRM DRM
Approved by DRM DRM
Distribution level EATTA EATTA
TABLE OF CONTENT
ACRONYMS
PHYSICAL UNITS
1. General Introduction
LIST OF TABLES
LIST OF FIGURES
LIST OF MAPS
Map 1.1: Tea Growing Districts of Kenya and project zone
LIST OF FIGURES
Figure 2.1: Voltage drop profile and power transit in Othaya feeder
Figure 2.2: Electrical diagram of grid connection (A1)
Figure 2.3: Voltage drop profile and power transit in 11kV Othaya feeder
Figure 2.4: Electrical diagram of grid connection (A2)
Figure 2.5: Electrical diagram of grid connection (A3)
Figure 2.6: Voltage drop profile and power transit in 11kV Othaya feeder
LIST OF MAPS
Map 2.1: GURA area, Tea Factories and existing MV system
Map 2.2: Gura SHP grid connection scenarios
Map 2.3: Dedicated 11 kV connection
LIST OF FIGURES
Figure 3.1: Energy cost and energy content in one ton of made tea
Figure 3.2: Annual thermal fuel consumption vs. made tea production
Figure 3.3: Annual electricity consumption from the 4 tea factories
Figure 3.4: Annual peak load curve (kW) for the 4 tea factories
Figure 3.5: Daily load curve for the 4 tea factories
Figure 3.6: Expected daily load curves for the 4 Tea Factories
Figure 3.7: Load Duration Curve models (%)
Figure 3.8: Actual Load Duration Curve (kW) for each tea factory
Figure 3.9: Actual Load Duration Curve (kW) for each tea factory
Figure 3.10: Load forecast indicators
LIST OF MAPS
LIST OF FIGURES
Figure 4.1: Monthly rainfall and runoffs (Gura)
Figure 4.2: Empirical Frequency Curve (EFC) for Gura – Median year
Figure 4.3: Empirical Frequency Curve (EFC) for Gura – Dry year
Figure 4.4: Empirical Frequency Curve (EFC) for Gura – Rainy year
Figure 4.5: Demand and Load Duration Curve
Figure 4.6: Simulation of the placement of energy – SHP supply to 4 tea factories
Figure 4.7: Main characteristics of the Pelton turbine
Figure 4.8: Power & Flow Duration Curves – Median year
Figure 4.9: Power & Flow Duration Curves – Dry year T10
Figure 4.10: Power & Flow Duration Curves – Rainy year T10
Figure 4.11: Single-line electrical diagram of the SHP powerhouse
Figure 4.12: Suggested detailed work programme
LIST OF MAPS
Map 4.1: Location of Gura SHP site (GUR-N°1)
Map 4.2: General development plan (GUR-N°2)
LIST OF FIGURES
Figure 5.1: One-line electrical diagram for Gura SHP project
LIST OF MAPS
LIST OF FIGURES
LIST OF MAPS
7. Financial analysis
LIST OF TABLES
Table 7.1: Synthetic investment costs for Gura
LIST OF FIGURES
Figure 7.1: Structure of Financial Model
Figure 7.2: Cash Flow over 14 years
Figure 7.3: Sensitivity curve
LIST OF MAPS
EXECUTIVE SUMMARY
The project “Greening the Tea Industry in East Africa” is co-implemented by UNEP &
the African Development Bank (AfDB) and executed by the East African Tea Trade
Association (EATTA).
The objective of the initiative is to encourage the tea sector in East African region to
develop Small Hydropower Projects (SHP) with the aim of reducing operating costs,
increasing power supply reliability and reducing greenhouse gas emissions during tea
processing.
The present feasibility study has been prepared based on field survey conducted on
Gura river in Kenya between mid October and mid of December 2007 with 4 surveyor
teams: hydrological team, topographical team, rural electrification expert and
institutional expert. The study is part of a 4 year initiative endorsed by 8 EATTA
member countries in the region.
Four nearby tea factories (Gathuthi, Gitugi, Iria Ini, Chinga) belonging to KTDA have
strongly expressed their interest to be supplied by an independent hydropower source.
Each one is actually supplied by the national grid through 11kV from Othaya substation
operated by KPLC. However the frequent power outages, voltage drops and load
shedding significantly affect the tea production quality and costs. The SHP project is
most welcome to end with the reliance on backup diesel.
The Gura Small Hydro Power site is located along Gura River in the Aberdare
mountains and situated at 6 km from the closest tea factory (Gathuthi) and 24 km from
the furthest one (Chinga) in Nyeri District.
Given the favourable and well-established legal and regulatory framework for IPP
(Independent Power Producers) in Kenya, it has been proposed to interconnect the Gura
SHP scheme with a dedicated 11kV line with the 4 tea factories. An injection point to
the near MV grid will allow the sales of power to the KPLC Utility through a Power
Purchase Agreement (PPA).
Thanks to strong government support, the power distribution network has been
intensively extended during the last 2 years, in particular in the project area where all
villages, trading centres and tea buying centres are now electrified or at less than 3km
from the grid. Therefore no external power demand is considered in the study and the
total requirement (based on grid + genset consumption) for the 4 factories is about 8.6
GWh in year 1 and an expected peak load of 2.2 MW in December-January (peak
season). The annual load factor varies from 35% to 50% from one factory to another,
with an average of 44%.
The load forecast over a 20 year period has been constructed on the basis of today’s
energy consumption patterns from the 4 factories and on a range of assumptions. The
results show that the energy and peak demands will reach respectively 11.6 GWh and
2.7 MW after 20 years, and the load factor will be 50%.
In the case of Gura SHP, there is no constraint on the energy that can be absorbed by the
4 tea factories load, while the excess power will be sold to the KPLC grid. Therefore,
the share of energy placed on the tea factories local network and the share of excess
energy sold to KPLC have been assessed, and the SHP scheme size has been optimised
by maximising the total energy sold to the Tea factories and to KPLC over the SHP
lifetime, without over investing.
The Gura SHP site is a run-of-river scheme with a high head (149m). Based on rainfall
data and nearby flow measurements (Gura gauging station), a design flow of 2.5 m3/s
has been selected for Gura SHP after optimisation, leading to an installed capacity of
2.8 MW and a mean annual production of 17.9 GWh; both being above previous
demand forecast. Energy generation has been simulated for median, dry and rainy years
considering the use of a Pelton turbine.
Then a scheme of power development has been prepared to maximise the river
potential. The exact location and routing of the structures such as the weir, the intake,
the settling basin, the waterway, the forebay, penstock and powerhouse have been
established accurately on detailed maps and drawings. The canal is about 6.6 km long
and 2.5 m broad and the steel penstock is 392 m long. Then 4.4 km of existing road
have to be rehabilitated to access the SHP site and 6.6 km of service road along the
canal. Detailed views of hydraulic structures have also been prepared. The dedicated
MV line will include 3 feeders of 11kV to reach the 4 tea factories with a total length of
about 35 km.
Salient features of the feasibility study (site location, hydrology, head, power, energy,
equipment, costing, financing) are given below.
It is assumed that the development of Gura would be undertaken via a Build-Own-
Operated company (BOO) only or in partnership with the tea factory (BOO + TF)
which will bring the equity required for the development of the 2.8 MW Gura Small
Hydro Power project. The set up of this company has still to be fixed.
In order to appraise Gura SHP project and to assess the profitability for the Project
Developer (through the criterion Return on Equity - ROE), IED has run an in-house
developed financial model covering all financial and fiscal aspects of hydropower plant
development, in a real life simulation of taxes and loan values. The model computes
project costs and revenue forecasts, including investment costs, contingencies, project
development costs, O&M costs, PPA conditions (feed-in tariff), equity/loan/grant
characteristics, macroeconomic parameters (exchange rate, depreciation, taxes, inflation
...) and Carbon revenue.
Simulations have been conducted for a baseline scenario as well as for other scenarios
with more pessimistic or more optimistic assumptions. The main results indicate that:
- In the baseline scenario the project cost has been estimated at 8.75 M$ for 2.8
MW SHP plant from which 57% is for civil works, 23% for electromechanical
equipments and 5% for the electrical network (MV lines).
- The investment cost of 2,966 US$/kW (96% or project cost) is relatively high
for this type of SHP plant and could be decreased with (partial) transfer of civil
work responsibilities to the tea factories. Loans are required to compensate the
initial negative cash flow.
- Each tea factory has limited assets but together (14M$), the consortium should
be able to provide the expected equity (35% of investment cost) by setting up a
BOO company. The pay-back period in the baseline scenario is about 12 years.
- The financial return measured by ROE is rather good and the Gura project
financially viable in both cases: 13.3% with BOO Company alone or 14.6% with
BOO Company together with the 4 tea factories, in the baseline scenario. The
small difference results from the limited savings on diesel fuel costs actually
supported by the tea factory. The financial risks are perceived to be minimal.
- A sensitivity study on the PPA tariff has demonstrated the importance to
negotiate with national regulator feed-in tariff higher than the published one to
make the project more attractive.
- The ROE factor is also improved by getting better CO2 market price, better
financing conditions, etc.
Other benefits as improved quality of electricity service leading to better quality and
quantity in tea processing have not been considered in the simulation.
To comply with national regulation, an ESIA study has been conducted along the
project layout to assess the environmental and social impacts of the SHP construction.
The main negative impacts pointed out are (i) the degradation of the vegetation cover
(removal, clearance), (ii) safety concerns over having an open waterway canal and (iii)
some minor risks of pollution during construction. As required in the national guideline,
mitigation measures and an ESIA plan are prepared before submission to National
Environmental Management Authority.
Length : 392 m
Thickness : 10 mm
Powerhouse
Type : Surface powerhouse, stone masonry
structure
Floor size : Length 18.30 m Width 10.50 m and
height 5.50 m
Power and energy
Installed capacity : 2,840 kW
Median year annual energy : 17.87 GWh
Dry year T10 annual energy : 17.50 GWh
Rainy year T10 annual energy : 19.00 GWh
Turbine
Type : Pelton
Number of unit :2
Rated capacity : 1,420 kW each
Generator
Type : Synchronous
Number of unit :2
Rated capacity : 1,500 kVA each
Power transformer
Type : Outdoor, oil cooled
Number of unit :2
Rated capacity : 2,000 kVA, MV/11 kV
MV line
Type : Overhead on tubular pole
Length : 35 km following the existing track roads
Rated capacity : 11 kV - 3 phases
Supported by : 11 m poles spaced out by 130 m
Access road (Earthen, gravelled or concrete lined pavement)
Service road along the canal : 6,665 m
Rehabilitated existing road : 4,400 m (Kigumo road to access the weir)
New access : 300 m (to access to the powerhouse)
Financial parameters (Baseline scenario)
Total Project Cost : 8,752 k$
Investment cost : 2,966 US$/kW
Equity : 3,063 k$
Annual Energy produced : 17,866 MWh (average year)
Return on Equity for BOO Co : 13.3%
Return on Equity for BOO Co + 4TFs : 14.6%
1 GENERAL INTRODUCTION
1.1 Background & Objectives
Greening the Tea Industry in East Africa, a small hydropower initiative, has recently
been approved by the Global Environmental Facility (GEF) Council. The project will be
co-implemented by UNEP & the African Development Bank (AfDB) and executed by
the East African Tea Trade Association (EATTA).
The objective of the proposed Small Hydropower (0.2MW - 5MW) Project (SHP) is to
reduce electrical energy use in tea processing industries in member countries of the East
African Tea Trade Association (EATTA) while increasing power supply reliability and
reducing Greenhouse Gas emissions through the removal of barriers. Specifically, the
project aims to establish 6 small hydro power demonstration projects in at least 4 of the
EATTA member countries, preferably with an attached rural electrification component
as well as prepare additional pre-feasibility studies. Both studies and planned
installations shall serve as training grounds for the entire tea sector in the region. A
special financing window shall be designed that will provide incentives for individual
tea processing plants to move into “green power generation”.
The project is a 4 year initiative endorsed by National Governments of eight EATTA
member countries in the region, namely: Kenya, Uganda, Malawi, Zambia, Burundi,
Mozambique, Rwanda and Tanzania.
The initiative is coordinated by a Project Management Office (PMO) hosted by EATTA
and led by a PMO Director. The PMO is responsible for the operations of the project
leading to successful achievement of the project outputs and outcomes within the four-
year project period.
the yearly rainfall average on the last 10 years was 1 357 mm per year with a maximum
of 1 970 mm in 1998 and a minimum of 763 mm in 2000 (cf. Chapter 4).
The population in tea growing areas of Kenya is usually of a dispersed yet relative
dense nature. People will tend to live in small plots of lands out of the estate scenario.
Most tea estates will also have labourer compounds wherein pluckers and estate
workers reside. In most cases drinking water is supplied to the compounds and
community halls, dispensaries and schools are also supplied with electricity. The
majority of households do not have access to electricity, although a number do use car
batteries.
Some households, although a small percentage, will also reside in the few villages
surrounding tea estates, these in most cases will be made up of a few shops, a posho
mill and a school. The Tea factories are usually located close to a town which will be
electrified and that provides a range of services.
Tea production is labor intensive and accounts for 80 000 people working on the estate
and about 3 million people earning their livelihood from the sector in direct and indirect
employment. KTDA factories alone are operated/ owned by 380 000 growers.
Tea growing and manufacturing are carried out in the rural areas thereby Tea Estates
contribute significantly to rural industrialization and to the range of services available
like schools and dispensaries and the standard of living, solid households and potable
drinking water and community halls.
1
Market Report, Sale 44 – 7th and 8th November 2005
Most Kenyan teas are manufactured using the Cut Tear and Curl (CTC) method of
manufacture, although some factories also produce orthodox tea for export in middles
eastern countries.
Investments in the sector are today focused on trying to significantly reduce production
costs. Investments in hydro power wherein production costs are significantly lower than
those by KPLC tariffs or diesel generator costs and a fast payback period are seen
optimistically by the sector. Today for example some of the tea companies are
investing into more energy efficient wood energy boilers.
In Kenya there are a total of 15 tea companies and 91 tea factories who are members of
EATTA. The companies can be classed into three types of players : (i) small holder tea
cooperatives, Kenya Tea Development Agency (KTDA); (ii) large multinational
companies; Unilever, EPK and James Finlay and (iii) private small estate holdings like
and Williamson, Nandi Hill, Sotik Highlands, Maramba etc.
In 2000, the public agency in charge of the organization of tea production was
privatized and took the name of the Kenya Tea Development Agency Limited – KTDA
Ltd. Today, KTDA accounts for the biggest tea producer in the country (61%)
managing 54 tea factories. It should be noted that Tea Factories subscribing to KTDA
services are independent and autonomous bodies.
KTDA acts as the direct beneficiary of this study and any future development will
depend on the interest and intent of KTDA and the individual Tea Factories at stake.
KTDA alone has 54 tea factories spread in 24 districts. The factories are owned by
380 000 growers. KTDA was responsible for 60 % of the tea production in 2002.
The following map illustrates the tea growing districts and in particular the project zone.
This cluster of Tea Factories is home to a total of 50 500 tea growers and a total of
63 500 households. Tea growers make up about 80% of the total households in the area.
The eight factories in the study area are in operation throughout the year each
processing an average annual 13 400 tons of green leaf tea per year amounting to about
3 200 tons of made tea. The ratio between green leaf tea to made tea amounts to an
average of 4.12 kg of green tea to 1 kg of made tea – this figure however varies from
factory to factory illustrating the varying efficiencies in processing – from plucking to
packing.
9. Entrance of IPPs;
10. Elimination of government subsidies to the sector with possibly the exception of
those to rural electrification;
11. Amendment of the Electricity Act which ascended in 1998 to legislate private
sector participation and the establishment of an independent regulator.
Cost of electric power in Kenya is however high compared to regional competing
nations in the COMESA region.
power, water and environmental specific aspects and to the non specific aspects of
establishing a business in Kenya as described in Annex.
An important question is to decide whether the planned installed power in Gura will be
more than 3 MW or less. In the first case a full fledged license will be necessary, which
involves a more complex and probably longer procedure. The procedure will also
include a competitive stage and more exposure to the environmental concerns that may
delay the project.
On the other hand, the choice for a less than 3 MW project will only require an
authorisation but may be questioned by the regulator if it is not getting the best of the
site from the public interest point of view.
If at a later stage of the study the financial analysis shows little difference between
sizing above/below 3 MW, the Consultant will recommend adopting a sizing below 3
MW.
Another point to consider with special care is the location of the water intake and
channel inside the Aberdare national park, which requires the intervention of the
Tourism Ministry.
Continuity of supply is resulting from the combined impacts of (i) generation and
demand balance, (ii) transmission and sub-transmission grid capacity and integrity, (iii)
distribution grid capacity and integrity. Unbalance between demand and generation can
cause general black-out or preventive load shedding, both generating long lasting
outages. Poor capacity of the transmission, sub-transmission and distribution grids can
result in regional or local load shedding or long lasting brown-outs. Transmission and
sub-transmission faults will cause either short brown outs, or voltage dips or medium to
long outages. Distribution faults will translate into either voltage dips or medium to
long lasting outages.
Sub-transmission and distribution MV feeders fault rates are heavily depending upon
their overall extension in km, insulation status and the number of the connected
substations.
The present situation is not good in terms of voltage level. At peak time, voltage
approximate calculations (based on feeder lengths, cable cross-section, transit power
…) show that the 11 kV voltage drop exceeds the recommended 7% level in Gathuti
and Gitugi. Real voltage drops can be much worse when the 33 kV voltage cannot be
maintained in OTHAYA due to upstream low voltage regimes in HV and 33 kV. Losses
from the substation are in the order of 250 kW.
Figure 2.1: Voltage drop profile and power transit in Othaya feeder
Othaya Iria Ini Gitugi Gathuti
0.4%
4715.9 1.4%
706.7 7.0%
3391.9 8.7%
voltage drop 1194.1 8.2%
MVA transit 1216.2
The above drawing sketches the feeder supplying Gathuti, Gitugi and Iria Ini tea
factories in a simplistic ways. The power supply comes from the left at 11000 V in
Othaya. Chinga tea factory (the furthest) is supplied by another 11 kV feeder within
acceptable voltage conditions.
2.2.2.1 Balance between GURA supply and the tea factory demand
Based on the various scenarios that can be implemented to use GURA hydrological
potential, the following aspects have been taken into consideration for this preliminary
study:
• Tea factory peak power is between 5 and 600 kW per unit
• Tea factory annual power consumption ranges from 1900 to 2700 MWh per tea
factory
• GURA installed power is 2,8 MW (2x1,4)
• GURA annual generation is 9 GWh per unit
• GURA guaranteed power will not exceed 370 kW
• Water storage will not exceed 3 MWh.
Those numbers are coming from the detailed study provided in chapter 3 and 4 of this
report.
Consequently, there will be periods when GURA generation will exceed tea factory
demand, giving an opportunity to sell excess power to either KPLC or a private
consumer using KPLC grid. There will also be periods when tea factory demand will
exceed GURA generation, creating a need for back-up power.
As for quality of supply, there is no substantial change for Chinga Tea factory, which is
connected to the Chinga feeder. For the consumers supplied on the Othaya feeder, the
voltage regime has improved as shown on the figure below and the losses have been
reduced to less than 3%:
Figure 2.3: Voltage drop profile and power transit in 11kV Othaya feeder
Othaya Iria Ini Gitugi Gura Gathuti
0.1%
1333.6 1.1%
706.7 0.2%
140.0 -0.8%
1455.0 0.2%
947.0 -4.3%
3142.5 1.3%
voltage drop 1188.7
MVA transit
The above drawing shows the injection of Gura power (3000kW, 1800 kVAR) in the
Othaya feeder that causes a voltage rise above 11000 V (negative numbers) in some
locations.
There is little change in terms of quality of supply as GURA is not able to supply the
whole Othaya feeder for most of the time, especially at peak period when load
sheddings are more likely to occur. Manual restructuring of the feeder to adjust demand
to GURA potential supply is a cumbersome process that would probably not allow
supplying Iria Ini, given the present structure of the feeder.
In this scenario the tea factories would also be concerned by any 11 kV fault on their
respective feeders.
The main change in terms of continuity of supply is that GURA, due to its higher installed
power may sustain the full OTHAYA substation during load shedding most of the time on the
initial years of operation. That may simplify commuting between isolated and coupled
situations provided that adequate remote distance coupling equipment is installed in
OTHAYA substation.
Figure 2.4: Electrical diagram of grid connection (A2)
As shown on previous map 2.2, the new lines will meander within the existing KPLC 11 kV
network. It is highly recommendable that the new 11 kV lines get distinctive features when
compared with the existing KPLC overhead lines to avoid operators’ mistakes that could
threaten safety and cause faults and equipment damage. Consequently these lines should be
realized with the MV aerial bundled conductor (MV ABC) technique that will enhance public
and staff safety, improve the quality of supply and reduce maintenance requirements at a
reasonable cost.
This scenario includes two commercial options A3a and A3b that are differing under the
commercial aspects:
• According to A3-a variant, Gura SHP operator also keeps control of the new feeders
and buys whatever energy is necessary from KPLC to compensate insufficient Gura
generation to supply the tea factories that are remaining connected. On the opposite
the operator sells any energy excess to KPLC.
• According to A3-b variant, Gura operator is limited to hydropower management. In
this case KPLC takes care of the MV system and buys the whole of Gura production
under a PPA specifying high quality standard for the tea factories.
A3a scenario requires that the Gura operator also manages the MV ABC feeders on the public
domain, which is somewhat unusual and maybe risky for non-utility staff.
Remarks: The above A3 scenario is equally dealing with all four tea factories. If Chinga tea
factory was not directly supplied by dedicated line, the investment cost of connection would
be seriously reduced and the operation simplified. In that case Chinga would only benefit
from the commercial impacts and not the technical improvement brought up by Gura.
Commercial
profitability
Operation
continuity
connexion
Quality of
Quality of
efficiency
Scenario
TOTAL
easiness
supply:
supply:
Energy
feature
voltage
Invest.
Main
cost
To existing
A1 ++ ++ +++ +++ ++ 13+
11kV
To existing
A2 +++ + + + ++ 8+
33kV
To new 11
A3a +++ + +++ +++ 11+
kV
To new 11
A3b +++ + +++ +++ ++ 13+
kV
Isolated
B1 ++ ++ + 5+
(11kV)
3.2 Methodology
The demand analysis has been conducted by the RE expert in the Tea Factory and other
potential clients in the vicinity of the factory. The adopted method was:
- Debriefing with the Hydropower expert to know with more accuracy the potential for
hydropower generation and the seasonal variation in the production.
- Debriefing with the Institutional expert to get the preliminary findings on institutional
issues and possible grid connection schemes
- Meetings with local authorities and power utility to get more information on the
project area (socio-economical, demographic, rural electrification plans, …)
- Detailed survey on the energy end-uses and energy needs of the Tea Factory
(electricity and thermal needs)
- Interview of the Tea Factory manager or with the board of members to assess their
priority energy needs and their interest and willingness to provide extra power to
surrounding settlements
- Detailed investigations to identify and to select the surrounding candidates for power
supply (villages, trading centres, tea buying centres, etc.)
After having interviewed all key actors and collected the appropriate technical and socio-
economical data/information, the RE expert has prepared the following demand analysis, the
load forecast and the local grid extension plan. All tea factories have provided detailed
information on their energy consumption for at least 2 years (hard and/or soft copies), except
Gathuthi factory which has not provided data on their diesel fuel consumption.
Some information gaps have supplemented by previous surveys conducted in 2004 and 2005
in the framework of the Scoping Studies and Pre-Feasibility Studies under UNEP and EATTA
and also via continued communication with the tea companies.
The range of data collected is described in the check-list for interviews and the questionnaire
for village survey (cf. in Annex). The data from the tea factories includes:
• Yearly and monthly power consumption for the past 2 years
• Yearly and monthly diesel consumption for the past 2 years
• Yearly and monthly Peak (kVA) for the past 2 years
Energy cost
458.23
3% Energy content (USD/ton of made tea)
9.10
0%
(kWh/ton of made tea)
1139.96
7%
grid
76.60 diesel
grid 43% 88.35
oil
diesel 50%
oil wood
wood
9.074.05
15553.05 5% 2%
90%
Based on billing from energy suppliers, the following energy costs have been calculated for
the different sources:
• The kWh unit price is 5.1 KES but the average electricity tariff paid by the 4 tea
factories in 2007 was close to 10 KES per kWh or 0.14 USD/kWh, when including
fixed charges, taxes and levies. Power factor surcharge are usually avoided by
factories. 16% VAT is not refunded since 2003 (Gitugi).
• The average price for diesel fuel in 2007 was close to 70 KES/litre or 0.3 USD/kWh
equivalent.
• The firewood was sold on the local market in 2007 between 700 and 1500 KES per m3,
i.e. in average 20.5 USD per ton or 0.4 cents of USD/kWh equivalent.
• The furnace oil was sold at around 27 KES per litre or 2 cents of USD/kWh.
Table 3.1: Specific energy costs per source
2007 Average price USD / kWh
Grid 10 KES / kWh 0.14
Diesel 70 KES / L 0.29
Wood 1200 KES / m3 0.004
Oil 27 KES / L 0.02
In addition to the effective costs of purchasing or growing the varying fuels, there are great
losses which are incurred in production quality when power outages or voltage drops are
experienced.
Each tea factory has strongly expressed its interest in producing hydropower itself to:
- Improve the power quality and availability,
- Reduce the operating costs,
- Sell extra power to KPLC and make benefits
- To provide power to surrounding settlements in the tea catchment area
It has clearly indicated that any positive impact from the project shall benefit to all tea farmers
as they are all shareholders of the factories. Any improvement of power quality or any cost
reduction will increase the profit on tea sales and thus the farmers’ incomes.
Figure 3.2: Annual thermal fuel consumption vs. made tea production
Made Tea (kg) - 2007
Wood + Oil consumption (GJ eq.) - 2007
500000
18,000
450000
16,000
400000
14,000
350000
300000 Gat hut hi 12,000
Git ugi 10,000 Gitugi
250000
Iria Ini Iria Ini
200000 8,000 Chinga
Chinga
150000 6,000
100000 4,000
50000 2,000
0 0
m ar
jul
oc t
m ay
apr
nov ' 06
jan 07
jun
aug
s ep
dec
feb
m ar
ju l
oc t
m ay
apr
nov ' 06
ja n 0 7
ju n
aug
s ep
dec
fe b
In average for the 4 factories, the specific wood consumption varies over the months from 3.0
to 5.0 m3 for every ton of made tea. In addition some furnace oil is consumed when the
factories face wood shortage; the consumption is in average 50 litres/ton of made tea. In terms
of energy, the furnace oil part is not more than 10% of the total fuel consumption for thermal
needs but in term of cost, the use of expensive oil compared to wood price has high impact on
the tea production price. In Gitugi, the oil expenditure was almost 40% of the total thermal
fuel cost (wood+oil). Indeed the price for wood is in average 16 USD/ ton while the oil price
is 0.37 USD/ litre. For Iria Ini, the furnace oil costs about 18 KES per kg of made tea while
wood cost is only 5 to 8 KES.
For example in Chinga tea factory where 4,236 tons of made tea were produced over the last
12 months, the consumption of thermal fuels (wood + oil) amounts to 13,610 m3 or 10,890
tons of wood and 268,826 litres of oil, corresponding to about 63.36 GWh/year when convert
into equivalent thermal kWh (2). About 15 kWh of thermal equivalent per kg of made tea
were needed which is almost double of what has been recorded in Uganda (Igara tea factory).
When assuming that 1 ha of tree plantation produces in average 22 m3 of firewood (3), the tea
factory should have at least 682 ha of forest to be self-sufficient or should harvest at least
0.25 ha of forest for each hectare of tea plantation.
As shown by the previous graphs (Fig. 3.1), the thermal energy requirements represent about
half of the total energy costs incurred by the Tea Factories.
Yet in terms of energy content, the thermal power needs represent 89% of the total energy
requirements of the production process. The power requirements to substitute the overall
energy needs (thermal and electrical) of Chinga tea factory has amounted to 66 GWh for
2007, of which 57.5 GWh were or the thermal energy needs.
Other alternatives have been investigated in some of the tea factories as coal, saw dust,
baggast but furnace oil remains the cheaper and easiest backup option after wood. Electricity
furnaces have not been investigated as grid prices are too high.
2
by using the factors 0.8 ton/m3, 5.28 kWh/kg of firewood, 21.84 kWh/litre of oil, 3.6 MJ per kWh
3
The produced volume at the end of the 12 years has been valued in 264m3 / ha. The Annual Medium Increment
in case of the Eucalyptus sp. is 22 m3/ ha/ year.
Given the significant thermal energy requirements of the selected tea factories in Kenya and
the potential to sell excess electricity back to the grid at good price, this feasibility study will
not consider the potential for substituting the use of wood by electricity to meet the thermal
needs.
However tea factories are willing to find alternative to fuel wood as the market price has
increased from about 150 to 1250 KES in 10 years.
The factories don’t have major extension plan in terms of production capacity but they put
efforts to improve productivity and energy savings with existing equipments.
The power network in tea factories is usually designed with several separate lines:
- One or several departures (3 phases) for the factory
- One departure (single phase) for the administrative block
- One departure (single phase) for the worker settlements in the vicinity of the factory.
The same lines are supplied either by the grid or by the backup gensets. On the grid side, there
is one main power meter (3-phase electronic meter), monthly read by KPLC.
There is usually no energy meter on diesel generators, only the fuel consumption is recorded
in logbooks.
The annual consumption of energy for 2007 (with extrapolation for the last 2 months) is
summarised in the following table:
Table 3.4: Energy consumption per source
250 800
MWh/month
200 Gitugi
MWh/month
600
Chinga
150 All TF
Iria Ini 400
100 Gathuthi
200
50
0
0
1
2
3
4
5
6
7
8
9
10
11
12
1
10
11
12
Months
Months
Table 3.5: Annual electricity consumption from the 4 tea factories (2007)
Figure 3.4: Annual peak load curve (kW) for the 4 tea factories
Tea Factory - Yearly Load Curve Tea Factory - Yearly Load Curve
700 2,500
600
2,000
500
Gitugi
400 1,500
Chinga
All TF
kW
kW
6
7
10
11
12
Months Months
As the tea factories have the same process programme over the hours and days, the individual
load peaks can be added and the red curve above can be considered as first approximation
with a max peak load of 2,200 kW.
The annual load factor for each tea factory was ranging between 40% and 50% in 2007
based on the annual consumptions. This load factor is the actual amount of kilowatt-hours
consumed by the tea factory in one year as opposed to the total possible kilowatt-hours that
could be delivered to the factory during that year. A high load factor indicates high usage of
the system’s equipment and is a measure of efficiency. Lowest values are obtained in July and
August (off-peak season).
450
400
350
300 Gathuthi
250
kW
Chinga
200
150 Gitugi
100
50
0
6-7
7-8
8-9
9-10
10-11
11-12
12-13
13-14
14-15
15-16
16-17
17-18
18-19
19-20
20-21
21-22
22-23
23-24
0-1
1-2
2-3
3-4
4-5
5-6
4
Administrative boundaries in Kenya: Province > District > Division > Location > Sub-location > Village
Today the national grid (11kV) has extended far to the West, close to the Aberdare National
Park border, most of the villages are located at less than 3km and 60% of the TBC are already
electrified with new transformers (usually 50 kVA – 3 phases).
Table 3.7: Inventory of Tea Buying Centres around tea factories
Tea Buying Centres Gathuthi Gitugi Irai-Ini Chinga
Non electrified 16 12 12 17
Electrified (or ready) 28 18 27 26
Total 44 30 39 43
During the field visit in the vicinity of the 4 selected tea factories, KPLC was still working in
the field to extend their 11kV lines5 toward remote TBC as the dead line to cover 100% of the
area is December 2007. Therefore there is no RE potential for the Gura SHP project to
include a rural electrification component as explained in Chapter 5. However, despite the very
good coverage with the grid extension, small localities may also not be connected and the
actual household electrification rate is most probably below 50% (not known yet).
5
KPLC cost: 825,000 KES for 1km of 11kV line (3 phase bare ACSR – 75mm² - 11m poles) or about 12,700
USD (includes labour but not local transport)
6
KPLC cost: 205,000 KES for 50kVA-11/0,4kV transformer + 160,000 KES for structure = 365,000 KES or
about 5,600 USD (or 112$/kVA).
is expected to help them to afford the connection fees (fixed 35,000 KES) and monthly
instalments. Today about 50% of them are able to connect to the grid when available.
2500
2000
1500
Average
1000
500
0
00
00
00
00
00
0
0
:0
:0
:0
:0
:0
:0
:0
6:
8:
0:
2:
4:
10
12
14
16
18
20
22
100%
90%
80%
70%
60%
One TF
50%
40% Four TF
30%
20%
10%
0%
0%
8%
17%
25%
33%
42%
50%
58%
67%
75%
83%
92%
100%
The above load duration curve in blue colour has been simulated specifically for one tea
factory. When adding other tea factories on the local distribution network, it is necessary to
model again the load duration curve for the whole system as the curves for each tea factory
can not be simply added.
The red curve above is the model LDC curve obtained for 4 similar tea factories inter-
connected, based on additional considerations as:
6) An annual Load Factor of 45% for the whole system has been assumed.
7) The maximum peak loads from the tea factories can be added for a short period of
time
8) To optimise the use of hydropower from Gura scheme, it is highly recommended to
shift the maintenance toward different days to avoid long and low off-peak demand (1
day per week is equivalent to 15% of the time at a level of 10% of peak power for
each factory).
9) The minimum power required is dictated by the combination of 3 factories working at
their lowest level (night time) and one factory stopped for maintenance; this happens
for about 6 hours per night and 4 nights per week, i.e. 15% of the time
10) The power demand remains at a low level for another 10% of the time when the 4
factories are in production during night time.
11) The curve between the maximum and minimum demand will be little affected by
adding all tea factories, giving a final load duration curve close to the curve for one tea
factory only.
The following load duration curves (in kW) are obtained when applying the model curve (in
%) to the actual max peak power for each factory.
Figure 3.8: Actual Load Duration Curve (kW) for each tea factory
700
600
500 Chinga
400 Iria Ini
kW
300 Gathuthi
200 Gitugi
100
0
0%
%
10
21
31
42
52
63
73
83
94
The last curve below (in kW) shows frequency of the power demand for the 4 tea factories
when using the red model curve above.
Figure 3.9: Actual Load Duration Curve (kW) for each tea factory
2500
2000
1500
kW
4 Tea factories
1000
500
0
0%
%
0%
13
25
38
50
63
75
88
10
Peak Power Demand kW 2223 2334 2357 2381 2405 2429 2453 2478 2503 2528 2540 2553 2566 2578 2591 2604 2617 2630 2644 2657
Peak growth factor % 5% 1.0% 1.0% 1.0% 1.0% 1.0% 1.0% 1.0% 1.0% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5%
Gross Energy Demand MWh 8559 8987 9436 9578 9722 9867 10015 10166 10318 10473 10578 10683 10790 10898 11007 11117 11228 11341 11454 11569
Consumption growth factor % 5% 5% 1.5% 1.5% 1.5% 1.5% 1.5% 1.5% 1.5% 1.0% 1.0% 1.0% 1.0% 1.0% 1.0% 1.0% 1.0% 1.0% 1.0%
Load Factor % 44% 44% 46% 46% 46% 46% 47% 47% 47% 47% 48% 48% 48% 48% 48% 49% 49% 49% 49% 50%
LF growth factor % 0.0% 4.0% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5%
Load Forecast
14000
12000
10000
4000
2000
0
1
11
13
15
17
19
Year
Based on the information obtained from the energy invoices, metered consumption,
observations and calculations, the following will be provided by the Energy Audit:
• A table showing the consumption, the unit costs, and total costs for all purchased
energy for the previous 3 years
• A table showing the percentage changes and trends in energy costs over the previous 3
years
• A summary of energy intakes such as supply meters and tariffs
• Energy performance indicators for each facility will be calculated and compared with
benchmarks values established from similar institutions.
• The ‘maximum demand’ profile over a two or three weeks period , depending of the
kind of equipment.
• The most economical supply tariff, based on ‘maximum demand’ profile and past
invoices
• The need for power factor correction
• The suitability of putting generator(s) in standby mode, updating or replacing existing
equipments
7
The Simbara Series was first described by Shackleton in 1945.
IED – Innovation Energie Développement 56
EATTA - Feasibility Study on Gura SHP (Kenya) - Final Report
On the two sides of the river the superficial materials are made of a thick layer of laterite.
Forebay:
(1) 2 drilling bore-holes distant of 20 m on the main axis of the work - 10 m depth or
thoroughly until the bed rock, (2) Lithological cuts of the 2 bore-holes which will indicate the
water level under the natural ground, (3) Undisturbed soil sampling of each nature of soil met,
(4) Pressure measuring tests in each bore-holes at the depth of one & three meters under the
level of the forebay foundation.
Power house site:
(1) 2 drilling bore-holes distant of 15 m on the main axis of the building - 10 m depth or
thoroughly until the bed rock, (2) Lithological cuts of the 2 bore-holes which will indicate the
water level under the natural ground, (3) Undisturbed soil sampling of each nature of soil met,
(4) Pressure measuring tests in each bore-holes at the depth of one & three meters under the
level of the power house foundation.
4.2.2 Hydrology
4.2.2.1 Watershed context
The main part of the watershed of Gura river upstream Gura hydropower project is located in
the Aberdare Forest (Aberdare National Park).
The most elevated point of the watershed is about 3,900 m, while the level at the intake is
2,080 m and the level at the gauging station is 1,820 m.
The length of the river between the most elevated point and the intake is 25 km and the mean
slope 73 m/km.
The length of the river between the most elevated point and the gauging station is 40.5 km
and the mean slope 51.5 m/km.
Downstream the intake the slope of the river decreases quickly and it is only of 16.8 m/km
between the intake and the gauging station.
The catchment area at the intake is 135 km2 while it is 165 km2 at the gauging station.
Table 4.1: Physical characteristics of the catchment area
Items
Catchment area of Gura river at the intake km2 135
Extreme altitude of the area catchment in m NGF Max in m 3,900.00
Intake elevation m 2,080.00
Altitude at the gauging station m 1,820.00
Length of the river (between the most elevated point m 40,500
& the gauging station)
4.2.2.2.1 Precipitations
There is no rain gauge inside the catchment but only in east limits:
- Gathuthi tea factory
- Gitugi tea factory
- Kiangondoro
For Gathuthi TF station monthly data are available since 1993 up to 2007 with missing values
in 2004 and 2005. The daily data are so available since July 2005.
For Gitugi TF station monthly data are available since 1999 up to 2003. The daily data are not
available.
For Kiandongoro station, monthly and daily data are available since 1999 up to 2005.
4.2.2.2.2 Flows
The flows measured at Gura gauging station, 15 km downstream the intake, are available
since 1978 up to 2007 but most of the years are missing (1997, 1998, 1999, 2002).
Month 1999 2000 2001 2002 2003 2004 2005 2006 2007 Mean
1999/2003
Monthly and annual values of flows (in m3/s) and runoffs (in mm) at Gura gauging station are
indicated in the table below.
MEAN 3.189 2.357 2.683 8.053 11.565 6.740 3.410 2.861 2.784 4.572 8.731 5.231 5.189
ST.DEVIATION 1.682 1.318 1.157 3.989 5.564 7.139 1.158 0.794 1.002 2.031 3.663 1.545 1.668
This table shows that the mean annual runoff is almost 1,000 mm with small variability
(standard deviation = 319 mm and coefficient of variation = 0.320), except for the year 1979
with a very high runoff of 2 199 mm. The cumulative runoffs of May and June 1979 reached
up to 1,111 mm. As the precipitation data are missing for this period, this exceptional value of
runoff cannot be controlled. The highest runoffs are observed in April, May, June, November
and December.
Table 4.7: Monthly & annual mean runoffs (Gura)
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC YEAR
MEAN 51.80 34.60 43.60 126.50 187.70 105.90 55.30 46.40 43.70 74.20 137.20 84.90 991.80
2003 53.7 21.2 107.6 343.1 426.8 36.1 23.9 127.9 58.8 281.3 174.6 41.1 1,696.1
2004 66.4 92.7 135.2 416.2 114.0 58.7 57.1 45.6 89.4 169.1 233.8 87.5 1,565.7
2005 70.0 72.3 99.4 350.0 366.4 44.2 107.1 64.2 54.2 116.9 123.9 37.8 1,506.4
Mean 2003/2005 63.40 62.10 114.10 369.80 302.40 46.30 62.70 79.20 67.50 189.10 177.40 55.50 1,589.40
2003 40.58 9.53 43.46 113.52 271.34 172.22 59.11 51.36 56.29 98.28 154.73 97.34 1,167.81
2004 49.16 36.28 48.12 140.12 102.04 62.36 47.07 45.66 45.18 81.47 218.30 101.08 976.91
2005 65.82 43.35 63.46 83.57 167.04 115.40 79.12 81.16 85.56 69.64 80.53 58.54 993.23
Mean 2003/2005 51.90 29.70 51.70 112.40 180.10 116.70 61.80 59.40 62.30 83.10 151.20 85.70 1,046.00
The precipitations at Kiandongoro station and the runoffs at the Gura gauging station can be
only compared for the period 2003-2005 (see tables 8 and 9 above). These tables show that
the mean coefficient of runoff is almost of 2/3 (0.658) indicating a high level of surface
runoff.
450.0
400.0
350.0
300.0
Precipitation- 250.0
Runoff (mm) 200.0 Precipitation
150.0 Runoff
100.0
50.0
0.0
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35
Month
The figure above shows a delayed flow for some months, for example June and December
2003, June 2005, due to the high values of precipitation the precedent months.
It is very difficult to fit a law of probability of the maximum values of daily precipitation with
so few years of observation. The 10 more important values are upper than 50 mm and the 18
more important are upper than 40 mm and fitting a Gumbel law of probability gives the same
results if the sample of data is built up with the 7 maximum annual values or with the 7
absolute maximum values.
The Gumbel law may be expressed by:
m = 61.7
s = 9.30
yn = 0.4773
sn = 0.9449
Pt = 9.84 yt + 57.1
The slope of the law (Gradex) in a reduced Gumbel graphic is 9.84 mm
• For a return period of 10 years, y10 = 2.250 and P10 = 79.2 mm
• For a return period of 100 years, y100 = 4.600 and P100 = 102.4 mm
Like the mean monthly flows, the maximum daily flows are observed in April, May, June,
October, November and December, the most important values being observed in April and
May.
The coefficient of variation of the maximum values of the year (Cv = 27.50/9.962 = 0.362) is
higher than the same coefficient for precipitation values (Cv = 0.150).
It will be noted that, converted in runoff, the maximum value observed (45 m3/s) corresponds
to 23.5 mm per day. The mean value of the sample (27.5 m3/s) corresponds to 14.4 mm and
the standard deviation (9.96 m3/s) to 5.22 mm.
The 4 more important values are contained between 41, 6 and 45 m3/s, the 7 more important
values are higher than 35 m3/s and the 10 more important values are higher than 30 m3/s.
These near first maximum values do not denote a good exponential fitting (Gumbel law).
However, the fitting of the maximum values of runoff by a Gumbel law gives the following
results:
• m = 23.5 mm
• s = 5.22 mm
• yn = 0.5332
• sn = 1.1215
the daily outputs observed at Gura intake are directly deduced from the flows observed at the
Gura gauging station N°4AD04 (intercepted watershed: 165 km2) by the application of a
coefficient equal to 0.8182 correspondent to the catchment area ratio (=135/165)
In accordance with the hydrology study:
• the median year at Gura intake is well represented by the year 1995,
• the dry years T=5 & T=10 are represented respectively by the years 1991 & 1996,
• the rainy years T=5 & T=10 are represented respectively by the years 1982 & 1994.
The EFC curves for Gura river are given hereafter for the median year, for dry five- and ten-
years and in wet five- and ten-years.
These curves indicate a very regular hydrology having a guaranteed flow (seen all the time)
ranging between 740 l/s and 1.28 m3/s.
Figure 4.3: Empirical Frequency Curve (EFC) for Gura – Dry year
The two empirical frequency curves are crossing, so for the low values of flow, the
probability values for T=5 years will be chosen on the 10 years curve and vice versa.
The guaranteed flows are respectively equal to 1.03 m3/s and 1.28 m3/s.
The guaranteed flows are respectively equal at 950 l/s and 1.03 m3/s.
It will be noted that the values vary hardly, between dry, median or rainy years, only for high
values (low guarantee). At the contrary the low values (high guarantee) are very similar from
type of year to another.
4.2.3 Topography
Standard topographic maps scaled 1 / 50 0008 with contour lines covering the hydrographical
network, roads, built-up areas, lands & administrative boundaries, and the whole watershed
area of Gura river have been collected for the study: Nyeri 120/4-Kipipiri 120/3-Kirangop
134/1 ad Kangema 134/2.
Based on these data, a topographic survey of the Gura small hydro scheme was launched end
of November 2007 during the Consultant’s mission. The area surveyed was along the future
canal from the weir location to the power house area and close to the main structures of the
project.
This topographic survey consisted mainly in two specific components:
General topographical mapping of a 200 m width corridor of land centred along the
waterway between the weir / intake and the power house building & the outlet channel
(the requirements include 1 m equidistance between level lines; grid co-ordinates in UTM
zone 37; density of the points > than 20/ha)
Detailed mapping around the weir & the power house site (the requirements include 1 m
equidistance between level lines; grid coordinates in UTM zone 37; density of the levelled
points > than 500/ha; bathymetry under the water level of Gura river)
The following topometric bases were used for the establishment of these maps: 134 U 117
(Muyange 2)
These general and detailed maps have been used for the project design described hereunder.
8
Series Y731 Kenya Government 1975 – Printed for Directorate of Overseas Survey –
Ministry of Overseas Development
IED – Innovation Energie Développement 70
EATTA - Feasibility Study on Gura SHP (Kenya) - Final Report
The scheme of development (SOD) for small hydropower generation site on Gura river is
shown, as initially planned, in the maps 4.1 and 4.2 hereunder. All detailed maps and
drawings for Gura SHP site (GUR-N°1 to GUR-N°10) are given in annex, including sketch of
the alternative (GUR-N°3), strip topographic layout (GUR-N°4 to GUR-N°6) and detailed
views of hydraulic structures (GUR-N°7 to GUR-N°10).
The table which follows presents the location of the main works for the suggested scheme.
Table 4.13: Location of the main works (Gura)
CFn
NPV = ∑1
N
(1 + t ) n
with:
NPV = Net Present Value of the project
CF = project cash flows over the project’s lifetime
N = number of years of calculation = project’s lifetime
CFn = + RB − NB +PPA
CFn = Project cash flow in year n
RB = Reference electricity bill 9
NB = New electricity bill for Project
PPA = Revenues generated via PPA to KPLC
Note: RB, NB, PPA are all in year n
RB = Dp × Ed + Gp × (E − Ed ) NB = ( E − Ep ) × Gp
Dp = Price of Electricity generated from diesel
Ed = Energy Demand satisfied by diesel
E = Energy Demand from the tea factories
Gp = Power price from grid
Ep = Energy placed
For each SHP sizing, the tool used for the estimation of the generation potential is presented
hereafter.
9
As the tea factories will keep their grid connections, therefore the reference electricity bill
only considers the variable costs of grid power.
10
Retscreen model is available on-line at www.retscreen.net
IED – Innovation Energie Développement 75
EATTA - Feasibility Study on Gura SHP (Kenya) - Final Report
Tab 2 “hydrology and load” represents the hydrological analysis of the site in a method
of analysis defined by the user (the classified load curves are defined there - using
correlation method - by the user on the basis of series validated here of the hydrological
station N°84227 named Chambura at Kichwamba)
The type of installation suggested (here, run of the river), the residual flow and the
percentage of availability of the guaranteed flow must, in addition, be provided.
Tab n° 3 “equipment data” characterises the turbines (Type, number and operation). It
proposes a curve of output according to the considered equipment with a possible
adjustment.
Based on the Gura hydrological characteristic and the proposed equipment for the power
station, the RETScreen model estimates the annual quantity of renewable energy (in kWh)
being produced.
This value is computed, in each case, based on the flow available (from the Flow Duration
Curve), the turbine efficiency, the nominal installed capacity, the residual flow11, the head,
and the probable losses from hydraulic and electric origin.
The yearly energy generated by the SHP (yearly output) is defined by the model as the area
under the curve P of the classified power, by making a linear interpolation between the
computed values of the produced powers (12). The following assumptions of energy losses and
annual breaks/stops are taken into account in the evaluation of the energy produced:
• Maximum hydraulic losses: 5%
• Generator efficiency: 94%
• Electric losses: Transformer 1% - Parasitic electricity losses 2% → Total 3%
• Annual downtime losses: 5%
For Gura, the yearly output has been estimated for various design discharges, corresponding
to different installed capacities:
Table 4.14: Estimated yearly output vs. discharge (Gura)
Flow (m3/s) 1,5 2 2,5 3 3,5 4 4,5
Net Head (m) 148,4 148,6 148,9 149,2 149,2 149,3 148,6
Installed capacity (kW) 1 682 2 256 2 833 3 412 3 993 4 576 5 160
Energy utilisation ratio (%) 84 77 72 68 64 60 56
Yearly output (GWh/year) 12,337 15,244 17,866 20,246 22,338 24,03 25,49
11
Which is equal to 10% of the mean annual flow
12
The Flow Duration Curve represents an annual cycle. Each interval of 5% of this curve
corresponds to 5% of 8760 hours (a number of hours in one year) that is to say 438 h. The
hydrological cycle is thus well represented.
IED – Innovation Energie Développement 76
EATTA - Feasibility Study on Gura SHP (Kenya) - Final Report
• net head
• penstock
• installed equipment
The model used is an Excel spreadsheet developed by the Consultant.
II. ELECTRO MECHANICAL WORKS US$/KSH Unit Price Total Kshs Total US$ Total Kshs Total US$ Total Kshs Total US$ Total Kshs Total US$ 100 Total Kshs Total US$ 100 Total Kshs Total US$ 100 Total Kshs Total US$
1 Generating equipment LS 1 1 1 1 1 1 1
2 Electrical / Switchyard LS 1 1 1 1 1 1 1
3 Supporting equipment LS 1 1 1 1 1 1 1
4 Gates LS 1 1 1 1 1 1 1
Power kW 60 000 1 682 48 273 400 2 256 63 957 600 2 833 79 324 000 3 412 94 341 800 3 993 109 008 900 4 576 121 721 600 5 160 136 740 000
Total E.M. works 0 48 273 400 689 620 63 957 600 913 680 79 324 000 1 133 200 94 341 800 1 347 740 109 008 900 1 557 270 121 721 600 1 738 880 136 740 000 1 953 429
11 KV LINE 900 000 30 27 000 000 385 714 30 27 000 000 385 714 30 27 000 000 385 714 30,00 27 000 000 385 714 0,00 0 0 0,00 0 0 0,00
33 KV LINE km 1 500 000 0 0 0 0 0 0 0 0 0 0 0 30,00 45 000 000 642 857 30,00 45 000 000 642 857 30,00 45 000 000 642 857
III. TOTAL DIRECT COST US$ 4 745 449 5 177 907 5 595 439 6 038 239 6 719 323 7 151 188 7 640 974
Contengencies 5% 237 272 258 895 279 772 301 912 335 966 357 559 382 049
Overhead costs 15% 711 817 776 686 839 316 905 736 1 007 898 1 072 678 1 146 146
Total 5 694 539 6 213 488 6 714 526 7 245 887 8 063 187 8 581 425 9 169 168
The second input into the model is the SHP characteristics, for various installed capacity. The
installed capacity and potential energy production (corresponding to the river potential) are
computed in. The model identifies a maximum placement curve for each year of operation,
which is the minimum between the SHP installed capacity and the demand load duration
curve: at any given time, there is not necessarily enough water to produce the energy that
could be placed. The model therefore includes a mismatch factor which is a way to represent
the lack of correlation between hydrology and the power demand from the tea factories, and
the impact on energy placement. The energy placement curve is therefore corrected with the
mismatch factor in order to obtain the final energy placement value.
The graph below illustrates the energy produced by the Gura SHP, placed on the local grid of
the four (4) tea factories. On this scenario, the Gura installed capacity is 2.26 MW with an
annual output of 15.24 GWh, and the four tea factories annual demand is 8.64 GWh. From
this simulation, only 89.4% would be supplied by the Gura SHP and the four tea factories
would consume only 50.7% of the yearly output.
Figure 4.6: Simulation of the placement of energy – SHP supply to 4 tea factories
kW
Simulation of the Placement of Energy
Gura SHP supply to the 4 Tea factories
2 500
2 000
Four (4) Tea factories
Load duratrion curve
1 500
Energy placement from
the SHP
1 000
500
0
0% 21% 42% 63% 83%
We have computed the total energy placement for the various Gura SHP sizing assessed in the
previous steps. The goal of step 4 is to work out the energy placement on the 4 tea factories
local grid for each year and thus find out the excess power which will be sold to KPLC, over
the lifetime of the project.
From the above, we will select the 2.50 m3/s flow discharge, corresponding to an installed
capacity of 2,833 kW, for the full detailed feasibility study.
According to the SHP scheme sizing and the hydrology & charge data of Gura river, the
availability of power in % of the time is given by the following curves:
Figure 4.9: Power & Flow Duration Curves – Dry year T10
Ogee-type spillway weir where the entire crest length (35 m) serves as the principal
spillway in case of overflow;
Three (3) meter-high weir height from upstream apron slab to dam’s crest;
Boulder-core with concrete binder for the main Ogee core with 0.25 meter (m) concrete
wearing surface;
(1) a simple one 3.5x3.5 m in the right bank. Its function is to flush off sediments
from the upstream to the downstream locations and also to act as secondary
spillway, and
(2) a small one (dim.0.8x0.8 m) controlled by the upstream water level, to allow the
residual flow downstream (416 l/s);
Provided with upstream and downstream apron slabs with penetrating cut-off walls
beneath the river to arrest excessive seepages;
Provided with complete intake structure (towards the settling basin and the canal) with
steel trash racks to prevent large debris from entering intake, lifting mechanism for gate
control and sediment control device.
The design criteria adopted are as follows:
100 years flood frequency in the analysis of the afflux elevation (i.e. the rise in elevation
above the weir’s flood level)
Safety factor of at least 1.25 in the stability analysis of the main weir ogee core with the
maximum water pressure up to the afflux level, and seepage analysis by use of the Lane’s
weighted creep theory in the sizing of the upstream and the downstream apron slab’s
lengths.
At an elevation of 2,068 m, the intake barrier of 6.70 long and 5.00 m high, the intake is
located on the small cliff forming the north abutment, at a suitable level to allow discharge
into the settling basin and the canal.
Interdependent of the weir and the settling basin downstream, the intake is composed of two
sluices 1.50x1.50 provided with two power-controlled valves.
A trash rack and a stop log isolate the civil works downstream the settling basin.
The flow in the canal is regulated (using an “opening law” formula), at the same time, by
these first valves and an other motorised one, located at the end of the settling basin and
upstream of the canal.
The bottom of the river bed, upstream and downstream, is composed of more or less
important blocks (boulders) which were installed on the passing time and which appears
stable under the effect of the river current.
Nevertheless, on the area of the various structures composing the weir/intake, these materials
will be cleared down to the bed-rock and will be replaced by a rolled compacted fill carried
out successively starting from the two banks.
If the location of the weir is on the quick velocity area of the river, the flushing gate, the
intake and the settling basin are, on the right bank, over the (quiet) average velocity area.
In this upstream zone, these works are protected:
on the one hand by a small wall parallel to the river, occurring its with the weir and
developing upstream.
On the other hand by an arrangement of the boulders built with a coal shovel upstream
over a distance of 22 m.
These arrangements, if they do not isolate really the weir, reduce the risks of material drivings
downstream from the river bed towards the intake and the settling basin.
The map GUR-N°8 given in annex and the two tables hereafter show the outline design
details for the weir and the intake structure for Gura SHP.
Table 4.19: Weir geometrical characteristics
N° Items
1 Nominal discharge m3/s 2.5
2 Weir elevation m 2,066.00
4 Spillway lenght m 35.00
5 Spillway width m 9.81
6 Upstream apron slab elevation m 2,063.00
7 Downstream apron slab elevation m 2,062.70
8 Water levels (design flow &flood flow T=100) m 2,066.11/2,067.65
9 Associated sluice gates: m
10 to flush off the sediments downstream
11 Layout mm 1x3,500x3,500
12 Elevation m 2,066.50
13 For the residual flow (416 l/s)
14 Layout mm 1x500x500
15 Elevation m 2,065.50
16 General level of the banks m 2,690.00
• Safety because its spillway is dimensioned to protect the canal at the time of occurred
T100 flood flow (or other less important flood flows),
• Regulation because two servo-motorized sluice valves, upstream and downstream, will
allow flow regulation before its entrance in the waterway.
The settling basin, perpendicular to the weir and superficially founded at elevation 2,062.00 m
is built on reinforced concrete. It constitutes the right bank abutment of the river.
34.60 m length, its working width 4.25 m (out off 5.55 m) allows an equipped flow transit
(2.50 m3/s) under low speed (0.5 m/s)
Downstream, two manoeuvrable sluice gates at elevation 2,068.00 m regulate, on the one
hand, the transit of the nominal capacity towards the canal (1 motorized 1,200x1,200) and, on
the other hand, the periodic draining of the work (1 manual 1,500x1,500)
This last sluice gate is not designed to pass the flood through, but to be opened periodically in
the flood season for cleaning out deposits.
The normal water level is regulated by a lateral spillway at elevation 2,066.10 m. This
elevation corresponds to the structure water level when the nominal discharge goes through.
This spillway has the role to chop the flood flows (until the T100 flood flow) and to allow,
with the downstream sluice gate 1,200x1,200, the keen adjustment of the flow required by the
power station.
The water level reached in the work at the time of the happened T100 flood flow is 2,067.50
m for an drained off flow of 3.5 m3/s.
The design/dimensioning of the settling basin are given to the following chapter.
The inherent design characteristics given in the following table are adopted.
Table 4.21: Settling Basin geometrical characteristics
N° Items
1 Nominal discharge m3/s 2.50
2 Length / Width of the settling basin m 34.60x5.55
3 Height of the settling basin m Between 5.00 & 5.30
4 Storage volume m3 231
5 Length of the spillway m 11
6 Input/output raft elevation of the settling m 2,063.00 / 2,062.70
basin
7 Input elevation of the canal m 2,064.77
8 General level of exploitation m 2,068.00
9 General level of the access m 2,066.60
10 Trash rack 1
11 Water level during the design flow m 2,066.10
12 Associated sluice gates:
13 To supply the settling basin (2,50 m3/s)
14 Layout mm 2x1,500x1,500
15 Elevation m 2,063.00
16 to flush off the sediments downstream
17 Layout mm 1x1,500x1,500
18 Elevation m 2,062.70
19 to supply the canal (2,50 m3/s)
20 Layout mm 1x1,200x1,200
21 Elevation m 2,064.70
4.6.3.2.1 Dimension
The design of the settling basin uses Camp method
According Camp:
WxL / VxY = ((WxY^1/6) / VxNxG^1/2)
With:
W: Sedimentation velocity,
L: Length of the basin,
V: Flow velocity,
Y: Flow depth,
N: Manning coefficient,
G: Gravity acceleration.
When the particle diameter of sediment is 0.25 mm, according to Camp, the vertical speed W
is equal to 0.03 m/s. The diameter of 0.25 mm is typically recommended by the suppliers of
Pelton turbines.
With the assumption that flow depth Y equal with channel depth, and the basin width equal to
4.86 m, we assume that:
V = 3.00 / 1.23 x 4.86 = 0.50 m/s
((WxY^1/6) / VxNxG^1/2) = 0.03 x 1.23^0.1667 / 0.50 x 0.018 x 9.81^0.5 = 1.1016
So, for 100% sedimentation:
WxL / VxY = 1.1016
The length of the settling basin is then:
L = 1.1016 x 0.50 x 1.23 / 0.03 = 22.58 = 23 m.
So, we take L = 23 m and B = 4.90 m, with a transition length upstream (intake) equal to 7.7
m.
In the section considered and for V= 0.50 m/s, we obtain a gradient for the settling basin
equal to 0.11 mm/m.
h = 0.30 m → L = 13.73 m = 14 m
h = 0.35 m → L = 10.90 = 11 m
h = 0.40 m → L = 8.92 = 9 m
With L = 11.0 m, the water height that overflow over the spillway is 0.35 m.
According to the nature of the soils encountered, some joints could be placed in the coating.
The purpose of these joints is to locate the cracking of the concrete slabs due to the
withdrawal, the thermal expansions and the possible packing down.
The coating of the all length of the canal with a concrete lining has been proposed and has
been taken into account in the total evaluation of the works.
However this proposal to coat the waterway or to adapt its coating-type (coating by stone
pitching or masonry) could be modified according to the results of the detailed geotechnical
investigations which will be conducted on the canal later, in particular if these new provisions
result in reducing the total cost of this transfer. It will be however noted, in the chapter
dealing with the total amount of the investments, that, for the canal itself, it is primarily the
share of the earthworks which is important.
A service path protected by gravel (three meters broad) and ditches (especially for the cut
profiles and intended to drain surface waters coming from the top of the valley) will border
the canal on its all course.
A gutter of remote control, posed on sand and connecting the weir to the forebay and the
power station will be laid out close to the canal edge.
As the canal in the low earth-cut zones will cross small existing foot tracks between some
open settlements and various cultivated pieces, several new accesses for farmers and cattle
will be realised above the trapezoidal canal (concrete slab and handrails).
Lastly, to allow the natural drainage of the slope, culverts (ND 200 to ND800) will be
arranged under the raft foundation of the canal when it crosses the little marked ditches. These
ditches will become the main discharge system of (1) the small drainage sewers which could
sometimes be placed under the canal, (2) the few draining works of the canal (3) and its safety
spillways.
The design/dimensioning of the canal are given to the following chapter.
• The deepening of the waterway (depth p) is carried out without modification of the
geometry and the slope of the canal,
• Referring to the empirical frequency curve, the available minimum flow on Gura river
is permanently of 740 l/s.
• The departure of the penstock is (in the forebay) under the foundation raft of the canal.
• Volumes available: (described here below)
This evaluation is given in the table hereafter, which presents 2 variables: (1) the deepening p
and the length of the concerned reach L (the length of the reach between the canal and the
village of Munyande is approximately 1,250 m).
Table 4.25: Water reserve (m3) by deepening (d (m))
D (m) 0,10 0,25 0,50 0,75 1,00 1,25 1,50
Additional volumes mobilised compared to the
L (m)
current section of the canal
100 37 94 200 317 448 590 746
250 93 236 499 794 1 119 1 476 1 864
500 186 472 998 1 587 2 238 2 952 3 728
1 000 373 944 1 997 3 174 4 477 5 904 7 457
1 250 466 1 181 2 496 3 968 5 596 7 381 9 321
1 500 559 1 417 2 995 4 762 6 715 8 857 11 185
2 000 746 1 889 3 994 6 349 8 954 11 809 14 914
For L =1,250m and a deepening of one meter, the capacity storage is 5,600 m3.
For this volume, the power station can work with full capacity lasting T = 5,600/(2.50 – 0.74)
x 3,600 = 0.88, that is to say 1 hour approximately.
In SHP plants, the draw down/up of the water during transitory phenomena can be considered
as small. When the plant is suddenly shut down, a hydraulic bore or surge takes place while
the canal is still supplying water to the forebay. Nevertheless, this will happen during an
emergency and will be considered.
Because of it, a side spillway is provided and then the complicated procedures associated with
unsteady flows can be avoided. This side spillway is designed for maximum discharges into
the canal.
Likewise, to accommodate the deposition of silt, the entrance elevation of the forebay’s intake
is much higher than the floor base. As a result the maximum water depth picked in the
proposed forebay is approximately 4.3 m, and the mean velocity is 0.20 m/s, so that it can be
expected to settle out effectively the last harmful particles in this bottom of the reservoir.
The forebay outlet, scheduled during shut-down of the plant, will take place through a buried
pipe ND 900 towards a stable gully located in the vicinity. Plumb in the pipe outlet area, a
stone rip-rap, centred on the scouring pipe, is envisaged to prevent erosion and possible local
landslides.
Map GUR-2 (given in annex) shows the gully and the spillway alignment from the forebay.
Map GUR-10 (annex) and the two tables below show its outline design.
Table 4.26: Forebay geometrical characteristics
N° Items
1 Length / Width of the forebay m 15.50x3.75
2 L1 12.00
3 B1 3.15
4 (Maximum) Height of the forebay m2 5.5
5 Length of the spillway m2 9.5
6 Input/output raft elevation of the forebay m2 2,059.72 / 2,057.55
7 General level of exploitation m 2,062.55
8 General level of the access m 2,061.5
9 Trash rack 2.00
10 Water level during the design flow m 2,061.68/2,061.51
11 Associated scouring gates:
12 for emptying & to flush off the sediments downstream
13 Layout mm 1x1,500x1,500
14 Elevation m 2,057.55
Table 4.27: Forebay gates characteristics
4.6.5.2.1 Dimension
The width of the forebay is determined by the total width of the intake or other appurtenances,
taking into consideration the average velocity in the forebay or in front of the intake.
B is the total width of the intake, B = 0.9 + 2 x 0.60 = 2.10 m
And B1 the total width of the forebay, B1 =1.5 x B = 1.5 x 2.10 = 3.15 m
The length L of the forebay (excluding the intake length L1) is equal to 3 x B1 taking into
consideration the layout of its appurtenances, such as the side spillway and the sand sluice or
the scouring gate.
L1 = 3.50 m and L = 3 x 3.15 = 9.45 m
For hydraulic reasons partly due to the depth of the penstock ND 900, a L1 length of 12.00 m
is retained.
The length of the horizontal floor base itself is be greater than B1.
4.6.5.2.3 Spillway
The side spillway should be designed for maximum discharge into the canal (3.00 m3/s) and
the top edge of the intake should be well positioned below the lowest pool level to prevent air
entrainment during draw down.
To design the weir we use the formula: Q = m x L x h x (2gh)^0.5 with m = 0.35
L = 1.9351 / h^1.5
h = 0.30 → L = 11.70 m = 12.00 m
h = 0.35 → L = 9.35 m= 9.50 m
h = 0.40 → L = 7.65 m = 8.00 m
With L = 9.50 m, the water height that overflow over the spillway is approximately 0.35 m.
Between forebay and power house (and despite to be buried), seven anchor blocks (stable
against overturning and sliding) are placed at every sharp change along the penstock pipe.
They are designed to retain penstock pipe movement in all directions.
Two thermal joints (expansion/contraction), also playing the role of relative settlement joint
between works and penstock, are envisaged to be installed.
For manufacture and production costs reasons, but also to face the hydraulic transient states,
the penstock thickness is constant on its entire course. Later, the project building documents
will examine the possibility of reducing sequentially this thickness according to the position
of the pipe in the penstock line, and correlatively its final cost.
A fence shall enclose the entire site of the powerhouse and forbid any trespassing except by
the main gate.
The following inherence design characteristics are adopted for the powerhouse structure.
Table 4.30: Powerhouse & Tailrace geometrical characteristics
N° Items
1 Length / Width of the Power house m 18,33x10,50
2 Total surface on the ground m2 220
3 -of witch office (soundproofed) m2 7.5
4 -of witch sanitary m2 3.5
5 Elevation of the axis of the turbine m 1,903.50
6 General level of SHP exploitation m 1,903.00
Tail race water level m 1,900.80
7 Raft elevation of the tail race to Gura river m 1,899.67
8 Raft width of the tail race to Gura river m 1.2
Earthing buried network shall be done during the earthwork in order to get an earthing
resistance less than one ohm. All the metallic part and the lightning arresters on the site shall
be strongly earthed. Neutral point of transformer and generator shall be earthed through a
resistance to limit the fault-current to 30 Amp.
The site shall be protected from thunder by an active lightning rod on the PH roof and directly
earthed in specific earth rods.
The main characteristics of the mechanical and electric equipment of Gura SHP are given
hereafter:
Table 4.31: Powerhouse equipment characteristics
N° Items
1 Design flow m3/s 2.5
2 Gross head m 154.50
3 Net head m 147,54
4 SHP capacity kW 2,840.00
17 Butterfly valve
2xND 600/ NP 25 kit out
18 Diameter/Nominal water pressure
with its bypass
Servo-motorized-Closing
19 Opening/Closing
ensured by a counterweight
21 Transformers
Main transformer 3,000 kVA, MV/11 kV
Transformer of the auxiliaries 50 kVA - 11,000 V/400 V
The drawing GUR-N°11 given in annex shows the powerhouse concept plan for Gura SHP.
The generators shall be synchronous brushless ones. The supplier shall determine output
voltage by between 4 and 7.2 KV. Sets of CTs and PTs shall give the value of current and
voltage for the protective relays, the synchronizer, the voltage regulator and the metering.
Neutral point shall be formed and earthed through a resistance to limit fault current.
The main transformers shall be a D/Y type with a no-load tap changer and neutral earthed
through a resistance on the HV side. They shall be protected by thermal, buckholz and over-
current relays.
The drawable circuit-breakers shall be SF6 type. The control system and the protective relays
activates directly the tripping by voltage missing.
Auxiliary AC shall be supplied by the 100 KVA three-phase transformer and the 20 KVA
stand-by Diesel generator could supply electricity in case of a long time breakdown.
The power plant is designed for an isolated network but authorizes also operation in parallel
with other generators.
The control system has 4 modes:
1. Automatic mode, intake level monitoring: the control system starts/synchronizes/
connects and adjusts the units to the optimal power to maintain constant the intake
water level.
2. Automatic mode, network monitoring: the control system starts/synchronizes/connects
and adjusts the power to the network load but the power remains limited to the
available upstream flow.
3. Semi automatic mode: the control system starts/synchronizes/connects and maintains
the power to a set point chosen by the operator, but the power remains limited to the
available upstream flow.
4. Manual mode: the operator starts/synchronizes/connects and adjusts the power output
by push buttons on the control board.
In every mode, the protective relays, the synchro-check and the automatic emergency shut-
down remain operative.
The operator has to adjust the voltage set point and the AVR shall maintain the voltage at the
chosen value.
11 KV SWITCHGEAR
I>> I>> I>> I>>
A A A A
UNIT 2
TRIP IDENTICAL Var Var Var Var
TO
W W W W
UNIT1
V V V V
I>> kW kW kW kW
I>
Dy
11/0,4 KV
Yd 100 KVA
11/ KV R
2000 KVA
Diesel
D generator
to SYNCHRO G2 20 KVA
u> 400 V Y
u<
F V SYNCHRO
rpm 1500 KW
G1 AVR A W
brushless + or - kW
Speed & V
V
kW W Var
I> I>>
AUXILIARIES SERVICE
I>
4.6.7.4 Provisions for safety of the hydraulic works and the Gura river users
In order to protect both the SHP scheme and the passers-by, the left bank of the Gura
weir/intake and the immediate proximity of all hydraulic works, especially the
powerhouse/tailrace site, will be prohibited and will be surrounded by fencing.
Panels of information judiciously located near these works will indicate to the farmers /
villagers the nature of the equipment, the safety instruction and the ecological advantages of
such installation.
Inside these two schedules: 17 months are proposed for the realization of the canal and its
final work (forebay) and 8 months are proposed for the manufacture of the turbine generator
set.
B ENGINEERING SERVICES
I VALIDATION OF THE DETAILED ENGINEERING
8 732 125
DESIGN (DED)
II CONSTRUCTION SUPERVISION 42 632 609
COST TOTAL
N° ITEMS UNIT
KESx10^3
QTY
KESx10^3
TOTAL kUS$
8-POWER HOUSE & TAIL RACE
8.1 Normal excavation (works) m3 0.300 3 256.0 977
8.2 Rock excavation w/out blasting m3 1.500 651.2 977
8.3 Backfilling compacted m3 0.530 325.6 173
8.4 Rip-rap lining m3 0.700 300.0 210
8.5 Cleanness concrete (100 kg/m3) m3 4.900 33.2 163
8.6 Concrete lining (150 kg/m3) m3 5.250 42.1 221
8.7 Mass concrete (250 kg/m3) m3 9.000 41.3 371
8.8 Reinforced concrete (350 kg/m3) m3 11.500 165.0 1 898
8.9 Formwork for concrete m2 1.000 850.0 850
8.10 Reinforcing steel bars Kg 0.090 14 437.5 1 299
8.11 Mild steel bars Kg 0.070 1 443.8 101
8.12 Welded wire-mesh Kg 0.060 631.9 38
Production of wall/partition armed in
8.13 m2 0.850 0
breeze blocks e=22.5 coated 2 layers
Interior painting in two layers - Oil-
8.14 m2 0.380 303 115
based paint
Industrial tiling on the ground and
8.15 m2 0.750 238 179
walls inside the powerhouse
Steels for pipes, connection part and
8.16 special parts in ND 600 (inside the Kg 0.410 1 933.7 793
powerhouse)
Steels for ironwork (grating,
8.17 Kg 0.250 577.4 144
footbridge and handrail…/…)
8.18 Operating platform and access m2 7.100 1 500.0 10 650
8.19 Kerbstones m 0.430 168.0 72
8.20 Rainy network LS 275.000 1.0 275
8.21 Sewage network LS 145.000 1.0 145
8.22 Built or covered ditch 0,5x0,5h m 3.900 137.5 536
8.23 Vegetalized platform m2 2.250 750 1 688
8.24 Sowing - Plantation of trees and shrubs LS 125.000 1.0 125
21 999 314
11 kV (new line)
The next table gives more details on electrical network equipments, indicative quantities and
estimated costing for the electrification of tea factories.
• Creation of a tree nursery. Initiate a trees nursery and tree planting programme
in collaboration with the tea factories, the Kenya Forestry Service and relevant
government organs, financiers and experts,
• Undertake top-soiling and grassing programme for any access road reserve,
• Develop and document Standard Operating Procedures (SOPs), schedules and
supervision guidelines for the project for controlling the risks from oil spills, dust,
water abstraction for construction etc,
• Address safety concerns of the community for waterway canal crossings either
through covering of the canals or provision of specific crossings both for humans
and livestock,
• Regular interaction and discussions with the community. A position of
environmental manager/officer shall be created during construction to oversee to
oversee environment and social management of re-planting of trees and other
vegetation along the canal route, the recovery of any eroded areas, enhanced safety
measures and general liaison with the community during and post construction
period.
Environment Impact Statement (EIS) prepared according to the national EIA guidelines
shall be submitted to the Executive Director of NEMA.
13
Buyers may be MDG Carbon Facility, World Bank Funds, Action Carbone, Atmosfair, My Climate,
Eco-Securities, AHL Carbono ; Mitsubishi Securities…
14
The Code initially covers only Certified Emissions Reductions (CERs), that are compliant with the
Kyoto Protocol. See
http://www.defra.gov.uk/environment/climatechange/uk/carbonoffset/codeofpractice.htm
Differences between the Gold Standard for CDM projects and the Gold Standard for
voluntary offsets („Gold Standard VER“) are listed at:
http://www.cdmgoldstandard.org/uploads/file/differences_GS-CER_VER.pdf
Possibilities to engage the project on the VER market should be studied in a subsequent
study once mini hydro plant engineering details and rural electrification plan are
available.
7 FINANCIAL ANALYSIS
The aim of this section is conduct a simulation of what would be the profitability of the
project for a Project Developer, with an investment in the 2.8 MW Gura Small Hydro
Power project. The simulation therefore assesses what is the profitability for the Project
Developer (Return on Equity) on the Gura project, in a real life simulation of taxes and
loan values.
It is assumed that the development of Gura would be undertaken via a Build-Own-
Operated (BOO) company which will bring the equity required for the development of
the project. The set up of this company has still to be fixed.
The section firstly presents the model and the assumptions for running the model. The
results are then presented and indicate the project’s profitability ratios, and sensitivity
studies are carried to assess the level of risk and uncertainty.
CFn
NPV = ∑1
N
(1 + t ) n
With:
The Return on Equity (ROE) will be calculated for the BOO company alone and for the
BOO company + the tea factory: in the second case, the savings on the electricity bill
for the tea factory (which will shift from diesel electricity to hydro electricity) are
considered as a benefit and in the first they are not considered.
For the BOO Company
All the benefits of the SHP project come from the sales of power to KPLC. Thus, the
cash flows are computed as follows:
CFn =PPA+ EL
CFn =PPA+ EL + S
INTPUTS
Energy placement PPA price and Insurance rates
forecast duration
The model computes investment costs and revenue forecasts, based on the following
inputs:
Macroeconomic Parameters
The user can specify the KES/USD exchange rate during the base year, the local rate of
inflation from y+1 onward and the foreign rate of inflation from y+1 onward. We have
assumed a 2% inflation rate for both currencies. It should be pointed out that between
the start and the end of the study, the Consultant has faced significant variation of the
KES/USD exchange rate. All cost have been established on basis of January 2008
exchange rate (1 $ = 70 KES).
Time Parameters
All parameters are considered on yearly basis. It is assumed that construction works will
be carried out in year 1 and finished at the end of year 1, and that start of Commercial
Operation is assumed as right after the end of the construction period. The Length of the
study period is 20 years.
Investment Costs and Contingencies
From chapter 4.9 (Cost Estimate), the investment costs for the Gura SHP are identified.
Provisions have been made to include access roads and MV lines in the costing – as
sensitivity analyses can easily be run to modify the Investment costs. The engineering
services during construction are estimated to be at 10% of the investment costs of the
project. The investment costs presented below include contingencies, which are the
safety margin that the Bill of Quantities takes into consideration to adjust the unit prices
(in order to reflect more accurate investment costs). The E&M costs are based on
indicative prices provided by potential suppliers.
Contingencies also include insurance cost related to the construction phase which could
be taken by the BOO company:
• Construction all risk insurance: a typical cost would be 0.5% of the investment
value of civil works, electro-mechanical equipment and the MV line at the end of
construction. The insurance premium is due at the start of construction.
• Advance loss of profit. This is an insurance against delays of construction and the
subsequent later start of commercial operation. A typical cost would be 0.8% of the
sales value in the first full year of commercial operation, which would represent for
Gura less than 0.2% of the total investment cost. To be paid at the start of
construction for one year.
Table 7.1: Synthetic investment costs for Gura
ITEMS GURA SHP
KESx10^3 US $x10^3
A CONTRACTED / CONSTRUCTION WORKS 515 536 7 365
SUB-TOTAL "1" CIVIL WORKS 346 670 4 952
SUB-TOTAL "2" MAIN ELECTRO-MECHANICAL WORKS 139 901 1 999
SUB-TOTAL "3" ELECTRICAL NETWORK 28 964 414
B. ENGINEERING SERVICES 51 364 734
C. CONTINGENCIES 21 350 305
TOTAL PROJECT COST 588 250 8 404
US$ COST/kW 2 966
applied between KenGen and KPLC (2.36 KES/kWh). Usually, this tariff apply for HV
power while in our case, this is for MV power. It can be considered that it is a very
conservative value and that sensitivity studies will be carried.
Financing
Equity is assumed to cover 35% of total investment project costs. There is no Grant
component on investment costs in the base case scenario.
A loan has been assumed to finance the investment project costs that are not financed by
grant or equity. The loan is in US$. This loan finances the costs associated with the
access road, the construction costs of the plant, the MV line and all other project
development costs that are not covered by equity or grant. The conditions for the loans
are as follows:
- Loan duration and grace period: repayment over 7 years; with a grace period of 1
year (included in the 7 years).
- Commitment fees are assumed to be 0.85% of the loan amount.
- Front-end-fees cover the arranger fee, the provision, the participation commission
and the agent fee. They amount to 1% of the loan amount.
- Timing of disbursements: the disbursements are made in 12-month intervals; i.e.
during year 1.
- Repayments are made every year in equal instalments.
In case of negative cumulated cash flow, the BOO Company will be charged an 8%
interest rate on negative cash flow.
Depreciation
Investment costs are depreciated, all in straight line.
- Electromechanical equipment, engineering services, and the MV line are
depreciated over 20 years
- Civil works are depreciated over 30 years
Tax
The tax system in Kenya that is applicable to Mini Hydro Power Plants is as defined in
the Energy Act, 2006. The establishment of an appropriate financing and fiscal policy
framework for Renewable Energy Technology investments is one of the objectives of
the Government. Nevertheless, there is a not yet specific Income tax holiday for Small
hydro power projects, or no accelerated depreciation possibility.
In the model, Corporate Tax will be taken at 30%. As sensitivity study, Tax holidays on
dividend incomes for 7 years will be carried.
A provision for Licensing fees and Tax to the Local Authorities should be considered.
In the model, they will be taken at 1% of annual revenues.
Carbon revenue
The tea factories are connected to the national grid. We apply the electricity emission
factor of 0.8 tCO2/MWh as substitution of diesel and the electricity emission factor of
0.6396 tCO2/MWh as substitution of the grid electricity; and a price of 14 $ / ton of CO2
emission reduction. This price is closed to the actual CER market price, and lower than
Volontary Emissions Reduction (VER) market price. On the VER market, buyers are
willing to pay a higher price as long as the project has positive local benefits in addition
to CO2 emission reduction. This is the case for the Gura small hydropower as it will
contribute to local employment through the tea factories and also improve (in the long
term) the income of small tea growers who will be the ultimate owners of the BOO
company. Given these characteristics the BOO should seek for partnership with VER
buyers or with consultancy who, in return from the sell of VER will carry out in
partnership with the tea factories part of the remaining development activities and other
services.
Inflation
Inflation have been taken at 2%, both in US$ and in KES. As the revenues are solely in
KES, and the investment are in US$ (foreign loan in US$), there is a risk of fluctuating
inflation and therefore the PPA tariff should be indexed on the inflation rate.
Cash Flow
1 500
1 000
Cask Flow ($)
500
Cumulated Cash
Flow (k$)
0
1 2 3 4 5 6 7 8 9
‐500
‐1 000
Less attractive financing conditions (40% equity, loan interest 8%, repayment period 5
years):
Total Cost 8 752 k$
Equity 3 063 k$
Annual Energy produced 17 866 MWh (average year)
Return on Equity for BOO company 11.2%
Return on Equity for BOO company + 4TFs 12.4%
No CO2 revenues:
Total Cost 8 752 k$
Equity 3 063 k$
Annual Energy produced 17 866 MWh (average year)
Return on Equity for BOO company 10.3%
Return on Equity for BOO company + 4TFs 11.6%
More attractive financing conditions (30% equity, loan interest 6%, repayment period
10 years):
Total Cost 8 752 k$
Equity 2 626 k$
Annual Energy produced 17 866 MWh (average year)
Return on Equity for BOO company 14.5%
Return on Equity for BOO company + 4TFs 16.0%
In this scenario, the cash flow happens to be always positive until the end of the
repayment period.
600
Cumulated Cash
Flow (k$)
400
200
0
1 2 3 4 5 6 7 8 9
plants which has been adopted in Uganda, and in that case the RoE would be 21.4%
with the other hypothesis of the baseline scenario.
Figure 7.3: Return on Equity (RoE) for various PPA tariffs (feed-in tariffs)
21,0%
19,0%
17,0%
15,0%
13,0%
2,00 3,00 4,00 5,00 6,00
7.4 Conclusions
These results show that in terms of financial returns which the site could yield, we are in
an attractive situation in view of the returns which would normally be expected.
The Project is financially viable as returns on equity for BOO Company or BOO
Company together with Tea factories are 13.3% and 14.6% respectively, in the baseline
scenario. At around 15% return on equity even a private investor could be “just”
interested. Furthermore, even in the worst case scenario, the return on equity is still
positive and thus, financial risks are perceived to be minimal. The negative cash flow
during repayment period entails seeking loans from other sources or negotiating a
longer payback period. The attractiveness of the project would further increase if the
KPLC tariff increased from the current 2.36 KES/kWh, e.g., at 4 KES/kWh, the return
on equity is around 21,4%.
There no significant difference in terms of attractiveness when considering the global
return for both the BOO company and the tea factories, or the BOO company alone.
This situation results from the little saving on diesel costs actually supported by the four
KTDA factories.
In all events, it would seem that the attractiveness of the project would be marginally
improved with a more attractive financial package but the impact on the cash flow
would be very significant as it would result in a positive cash flow.
The investment cost of 2,966 $/kW could be decreased if the tea factories take the
responsibility to do part of the civil work or at least the excavation work.
The RoE would be more significantly improved by getting a good CO2 price. This
would be possible on the VER market, as buyers are willing to pay for a higher price if
social benefits can be added to the avoiding CO2 emission. Given these characteristics
the BOO should seek for partnership with VER buyers or with consultancy who, in
return from the sell of VER will carry out in partnership with the tea factories part of the
remaining development activities and other services.
On the technical side, the project is technically simple but would require some
management skills to operate the resulting power systems. The loss of revenue due to
current interruptions in power supply resulting in lower quality tea and the fact that this
is less likely to happen once the SHP power plant is in place will be an indirect benefit
of the Gura Small Hydro power project, which is not computed in the RoE.
As a conclusion, the four KTDA tea factories should be interested to develop the Gura
SHP project, being alone as single developer or in association with a private developer
as the required equity is quite high (~3 M$ in the baseline scenario) compare with their
actual cumulated assets of 14 M$ for the 4 Tea factories.
8 ANNEXES