Académique Documents
Professionnel Documents
Culture Documents
Project Plan
Project Code: MDMS09
Document Code: MDMS09-PP <version 1.3>
The group:
To Viet Anh, Team leader
Tran Cong Phan Vinh, Member
Dao Duy Thanh, Member
Vu Minh Phong, Member
Le Gia Cuong, Member
RECORD OF CHANGE
M Project risks
A Project Communication
SIGNATURE PAGE
Project Manager
Project Manager
TABLE OF CONTENTS
1. INTRODUCTION........................................................................................6
2. PROJECT ORGANIZATION........................................................................7
3. PROJECT RISKS........................................................................................8
4.1. Software.............................................................................................9
4.2. Hardware............................................................................................9
4.3. Others infrastructures..........................................................................9
6. PROJECT SCHEDULE...............................................................................11
7. PROJECT COMMUNICATION...................................................................12
PM Project Manager
TL Team Leader
DV Developer
TP Test Plan
TC Test Case
SC Source Code
CM Configuration Management
CI Configuration Item
1. INTRODUCTION
Project start date: Sep 7th 2009 Expected end date: Sep 28th 2009
1.2.1. Constraints
Table2: Constraints
No Description Type2
1 The interface of MDMS should be simple enough for users to be able to use it Product
easily after using the system for no more than 10 minutes.
2 The size of database must be large enough to store information which increases Product
when used.
4 The software must be run from .exe file extension (in Windows version). Product
1
1 man-month equals 25 man-day
2
These are type normally: staff, budget, equipment, schedule, infrastructure, business, ...
Table3: Assumptions
No Description Type3
1 Communication available between members and teacher through mobile phone Business
and email.
2. PROJECT ORGANIZATION
3
These are type normally: staff, budget, equipment, schedule, infrastructure, business, ...
1 Tô Việt Anh PM Sep 7th 2009 Sep 28th 2009 2 hours per day
2 Đào Duy Thanh DV1 Sep 18th 2009 Sep 19th 2009 2 hours per day
3 Trần Công Phan Vinh DV2 Sep 18th 2009 Sep 19th 2009 2 hours per day
4 Tô Việt Anh DV3 Sep 18th 2009 Sep 19th 2009 2 hours per day
5 Lê Gia Cường Designer 1 Sep 15th 2009 Sep 17th 2009 2 hours per day
6 Vũ Minh Phong Designer 2 Sep 15th 2009 Sep 17th 2009 2 hours per day
th th
7 Vũ Minh Phong Analyst 1 Sep 14 2009 Sep 14 2009 2 hours per day
8 Lê Gia Cường Analyst 2 Sep 14th 2009 Sep 14th 2009 2 hours per day
9 Đào Duy Thanh Tester 1 Sep 18th 2009 Sep 23th 2009 2 hours per day
10 Trần Công Phan Vinh Tester 2 Sep 18th 2009 Sep 23th 2009 2 hours per day
11 Vũ Minh Phong Tester 3 Sep 18th 2009 Sep 23th 2009 2 hours per day
3. PROJECT RISKS
Table5: Project Risks
Risk Description Probability Impact Trigger Status Mitigation Plan Contingency Plan
- Time constraints High Serious N/A Open 1. More work from team 1. Extend schedule of
are 2 weeks, which members. requirement phase.
is too short. The
project may not 2. Frequent relaxing is 2. Reduce time of the
finish on time. needed. not yet necessary phase.
Requirement Medium Tolerable Teacher Open Team members need to A requirement plan
changes: New ideas gives generate ideas at first stage. needs to be seriously
may turn up during more considered first.
project advices
development. Some about the
can change the project
whole structure of
the project
Compatibility: Mac High Tolerable When Close a future version for different N/A
OS, UNIX and deliver the OS is planned
Linux users may not product to
run the application the users
due to the fact that
the program is
written in VS on
Windows
People: the team High Serious N/A Close the team needs constant N/A
consists of 5 guidance from the instructors
inexperienced in
software project
members
4
Fill here any note about working time as % of total effort or how many hours per day or per week.
4.1. Software
4.2. Hardware
Laptops and desktop computers are needed for designing, coding and testing.
5.2. Milestones
5
Table7: Project milestones
No Milestone Milestone date Objectives, Notes
3 Project Plan Submit Sep 11th Group’s review, approval and Submit
5
This table and other tables in this project plan may be referred to appendixes. It’s permitted to replace tables by text but this
information in table should be required.
6
This table and other tables in this project plan may be referred to appendixes. It’s permitted to replace tables by text but this
information in table should be required.
- Project Topic, Documents must be approved by all members of the team. All team are free to
raise ideas and opinions.
- Communication is via mobile phone, instant messengers, emails as well as face-to-face
- Meetings for progress reports are held twice a week. If serious problems occur, unplanned
meetings are held.
- The team receives frequent supervising from project leader and subject lecturer.
7.4. Others
N/A